Advanced Soil Products

Needs

Planning Design

Construction
 Project Data

 Generator weight: 400 KN

 Area: 3.82m x 10.65m = 40.68 m2

 Depth: 20 cms

 Volume: 8.14 m3

 Superficial load: 9.8 KM/m2

 Total stabilizer used: 7 Lt

 Total Cemento used: 445 kg

 Material Mix per m3:

 - Rock ¾” 510 kg,

 -Rock 3/8” 485 kg,

 -Sand 1/8” 1,200 Kg

 - Cement 53 Kg

 - Water: 150 Lt

 - SoilBinder 750 ml
Pillars of Success

Fast delivery to
In Situ Materials
user

Cement usage Environmentally


reduction safe
Construction Process
Construction Process
Construction Process
Final Results
Final Results