Appendix C

Gantt Chart

VIEWNaVS: Visually Impaired Electronic Wearable Navigational System using TensorFlow

Month September October November December January February


Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Duration
Task Point-Person Start Date End Date
(days)
I. Preparation Phase
A Research Problem All 9/3/2018 9/14/2018 12 Days
B Interview and Gathering Information All 9/172018 9/27/2018 11 Days
C Preparation and Proposal Defense All 9/28/2018 10/11/2018 14 Days
D Further Interview and Research All 10/12/2018 10/21/2018 10 Days
II. Design Phase
E Purchasing of Materials All 10/27/2018 12/8/2018 43 Days
F Construction of the Vest All 11/5/2018 11/15/2018 10 Days
G Integration of Materials to the Vest Calamba 11/12/2018 11/29/2018 18 Days
G.1 Integration of the PixyCam2 and Web Camera Calamba 11/12/2018 11/18/2018 7 Days
G2. Integration of the Arduino Uno and Ultrasonic Sensors Calamba 11/12/2018 11/18/2018 7 Days
G.3 Integration of the Rpi 3 Calamba 11/12/2018 11/18/2018 7 Days
G.4 Integration of the GSM and GPS Module Modelo 11/19/2018 11/26/2018 7 Days

G.5 Integration of the speaker unit and the power supply unit Calamba 11/26/2018 11/29/2018 4 Days

III. Development Stage


H Components Programming Quizo 11/12/2018 12/22/2018 40 Days
H.1 Programming the Rpi 3 Quizo 11/12/2018 12/2/2018 20 Days
H.2 Programming the Arduino Uno Quizo 12/2/2018 12/22/2018 20 Days
I Android Programming Modelo 11/26/2018 12/29/2018 33 Days
I.1 Android App GUI Programming Modelo 11/26/2018 12/11/2018 15 Days
I.2 Android App Functionality Programming Modelo 12/12/2018 12/29/2018 18 Days
J Initial Testing All 12/28/2018 12/30/2018 2 Days
K Troubleshooting All 12/28/2018 1/15/2019 18 Days
L Final Testing All 1/16/2019 1/18/2019 2 Days
M Technical Defense All 1/19/2019 1/22/2019 3 Days
V. Evaluation Stage
N Evaluation of the Overall Design All 1/27/2018 2/26/2018 30 Days
O Final Documentation All 2/4/2019 2/24/2019 20 Days
P Final Defense All 2/26/2019 2/29/2019 3 Day