DASHBOARDS
Project Overview
% Complete
Status Period :
7 Dec 2018 – 30 Jan 2019
70%
Progres Project Pengadaan Storage BNI Direct di DC & DRC
Baseline Schedule Actual Schedule
100%
91%
73%
70%
66% 66%
46% 45%
34%
11% 12%
8%
5%
2% 3%
1% 1%
W2 W3 W4 W1 W2 W3 W4 W5 W1 W2
Dec'18 Jan'19 Feb'19
Staffing Summary
Resource Name Effective Date Assigned or Reports to Role Description
Released
PT. Metrocom Global Solusi
Aulia Rachman 7 Dec 2018 Assigned PMO Head Project Manager
Ricky Anthony 7 Dec 2018 Assigned PM Co PM
Sahatma Siallagan 7 Dec 2018 Assigned PM Technical Lead
Sambas Albana 7 Dec 2018 Assigned PM DC Facilies
Youke I 7 Dec 2018 Assigned PM System Engineer
Wisnu H 7 Dec 2018 Assigned PM System Engineer
Frans F 7 Dec 2018 Assigned PM Project Admin
Risk Register
Risk Impact Owner Mitigation
Issue Register
Issue Impact Owner Resolution Status
Project Activities
Activities Planned Actual Status Explanation
Finish Date Finish Date
Initiation
SPK Released 7 Dec 2018 7 Dec 2018 Done
Executing
2 Feb 2019 15 Jan 2019 Done
Power On Storage DC Slipi
31 Jan 2019 16 Jan 2019 Done
Install Cable
Install & Configure Hardware 2 Feb 2019 15 Jan 2019 Done
Closing