Professional Documents
Culture Documents
MIDTERM
2. What is the recommended management strategy if a project stakeholder has high power
but low interest? (3.45 p)
A) Monitor
B) Keep satisfied
C) Manage closely
D) Keep informed
3. Which of the following is the best action if you realize that the project will be completed two
weeks ahead of the expected due date? (3.45 p)
C) It is the iterative process of increasing the level of detail in plans as greater amounts of
information become available.
10. As a project manager, which of the following stakeholders will you want to know most?
(3.45 p)
A) The stakeholder who is not interested in implementing the product of the project.
B) The department manager who will use the product of the project, and who is known to be
resistant to change.
C) The project sponsor, with whom you have worked before for a long time.
D) A team member who is going to leave the company next week.
12. Which of the following methods cannot be used for prioritizing the requirements? (3.45 p)
A) RACI Matrix
B) Kano Model
C) MosCoW Analysis
D) Paired Comparison Analysis
14. Which of the following is not an advantage of recording the lessons learned information
continuously during the project? (3.45 p)
17. Which of the following activities will not be performed during the kickoff meeting? (3.45 p)
18. Which function/unit required for maximise interaction relations between University and
industy? (3.45 p)
A) SMEs
B) Mini academy unit
C) Technology transfer office
D) International relations unit
E) Commercial chambers
19. Which of the following best describes how a project charter would help the project
manager? (3.45 p)
A) It lists the activities.
B) It lists the names of all team members.
C) It gives the project manager authority.
D) It describes the history of similar projects.
20. Which of the following is not an advantage of using a time-boxed meeting? (3.45 p)
A) It increases flexibility.
B) It improves focus.
C) It encourages prioritization
D) It becomes less likely that the meeting interferes with another work.
21. The work breakdown structure can best be thought of as an effective aid for______
communications. (3.45 p)
A) Team
B) Project manager
C) Customer
D) Stakeholder
22. When would one use a milestone chart instead of a bar chart? (3.45 p)
A) The technical experts know that the system has at least one defect.
B) Consecutive measurements are taken. One observes that the system failed to respond
only at one, single measurement.
C) The technical expert realizes that one single defect creates most of the problems.
D) Only one, single project team member has the required skill.