Sayyed Engineers Limited Project Charter (2023)

Project Summary SEL/QMS/ORS


Project Name To reduce Monthly Rejection of Lumps & sweep Depatment Plastic
Project Manager Rizwan Ishaq (plastic Section incharge) Sign
Coach Athar Mahmood (Factory Manager) Sign
Sponsor Rizwan Ishaq Phone
Start Date 1/2/2023 Target End Date 12/10/2023

Project Details
Project Description To reduce monthly rejection of lumps (0.40to 0.35%)& sweep (0.25 to 0.20%)

Lumps are generated from Molding Machines & Extruders due to nozzle blockage,color change ,mold change,material change
Problem Statement and machine stoppages. Recycle Material also is a cause of nozzle blockage leading to generation of Lumps. Sweep is generated
from Crushers .

Lumps & sweep are rejected materials .Less Lumps & sweep rejection will save money, Productivity will be increased by reducing
Business Case
the down time of machines & defects of production.
Process and Process
Injection Molding, Mr. Rizwan Ishaq.
Owner
Scope Process Scope (Lumps) Start of Process Raw material received from Plastic Store
End of Process Semi Finished Goods submitted to store
Process Scope (Sweep) Start of Process Runner received at Crusher (Start of Crushing/Grinding)
End of Process Regrind of the Runner (End of Crushing/Grinding)

Project Scope Includes All molding machines and Extruders & Crushers

Excludes N/A
Goals and Metrics
Project Goal Metric/CTQ Baseline Current Goal Entitlement
To Reduce monthly Lumps %(percentage) 0.45% 0.40% 0.35% 0.30%
To Reduce monthly Sweep %(percentage) 0.30% 0.25% 0.20% 0.18%
Project Planning

Customer Benefits Cost saving. Less defects being produced & Less defects reaching to next step of Assembly

Team Members Riaz Ahmed, M.Iqbal,Maqbool Ahmed, Akbar Shah, Mushtaq Ahmed, Ashraf Ali, Nobahar Khan, Nasir Malik

Support Required Spare Nozzles, Flanges, Sprue bush etc fromTool Room . Recycle material Quality be improved

Risks/Constraints Frequent nozzle blockage due to regrind material. And large number of mold changes due to less no of machines

By (expected) Completed by (actual)


Define the project PC-01 Define objective of the project 1/2/2023 1/1/2023

Gather Data, Measure


Gather data of 2021 year & Measure 12/3/2023 3/14/2023
(ist Quarter) PC-02

Analyse the data which machines are producing more lumps


Analyze Data
& sweep & why. Gather suggessions from team members & 10/6/2023
(2nd Quarter) PC-03
machine operators

Improve Improve the process to reduce rejection level of lumps &


6/9/2023
(3rd Quarter) PC-04 sweep

Control
Standardize the implemented suggestions 10/12/2023
(4 th Quarter) PC-05