Professional Documents
Culture Documents
BY
I confirm that the work reported in this proposal was carried out by the candidate under my
supervision.
Thanks to all my friends and classmates for staying and supporting me till the end.
ACKNOWLEDGEMENT
My utmost sincere gratitude goes to the almighty GOD for his unending love and care
throughout the entire period. Also, for the good health and enabling to learn and have
knowledge to be able to accomplish the task.
My dear parents also had a very huge role in supporting me morally, spiritually and financially
in order to successfully complete the proposed trade project in time and without any fatigue. My
siblings’ efforts won’t go unappreciated this is due to their restless support and sacrifice in
terms of time and financial support.
Mr. Mathenge also had a very phenomenal effect in his guidance in our preparation for the write
up of the proposed trade project. His words of inspiration and direction will not go unnoticed.
To my friends and colleagues and other protocol for their enormous mutual support in the
completion of the project. Their ideas and encouragement and their useful criticism made my
project even more success. May almighty GOD bless you abundantly?
ABSTRACT
The proposed office is a story building which will have both a ram and stairs that will help
both disable and able people access the office on their own. According to space our current
offices are also very small which is squeezed with all the office facilities and some are kept
due to insufficient space hence requires enlargement. The newly proposed block will allow that
since it will be a two-story building. It will allow the principal and their deputies to have their
own offices and wash rooms in addition with wresting room for the principal.
The current office also has a low angle of elevation which allows too much heat during high
temperatures hence the office holders working under uncontrolled temperatures. Therefore,
the proposed office will have the standard angle of elevation which is required to control the
temperature. The office will also have standard windows that allow sufficient light to pass
through and light the room during the day to avoid use of power during the day which is
costly and expensive. Since the current administration block is having gullshet irons which
transmit heat will be replaced by tiles which don’t allows heat to pass through. The proposed
structure also has lighting arrestors which is good during lightening and helps to control
thunderstorm that may cause death to human beings and interferences with the structure itself
hence renovation which is very expensive.
Contents
DECLARATION..................................................................................................................................................2
DEDICATION.....................................................................................................................................................3
ACKNOWLEDGEMENT....................................................................................................................................4
ABSTRACT.........................................................................................................................................................5
1.0 CHATER ONE: INTRODUCTION..............................................................................................................9
1.1BACKGROUND INFORMATION................................................................................................................9
1.1 PROBLEM STATEMENT..................................................................................................................10
1.2 PROJECT OBJECTIVES....................................................................................................................11
1.3 PROJECT OBJECTIVES.............................................................................................................................12
1.4 LIST OF ACRONYMS AND ABBREVIATIOS USED............................................................................13
2.0 CHAPTER TWO..........................................................................................................................................14
LITERATURE REVIEW...................................................................................................................................14
3.0 CHAPTER THREE: METHODOLOGY.....................................................................................................15
3.1 SURVEY......................................................................................................................................................15
3.1.1Reconnaissance Survey..............................................................................................................................15
3.1.2 Chain survey..............................................................................................................................................17
3.1.2 Leveling.....................................................................................................................................................17
3.1.3 Contouring.................................................................................................................................................17
3.1.4 LEVELLING: FIELD SURVEY DATA .................................................................................................18
CONTOUR A........................................................................................................................................................19
CONTOUR B.........................................................................................................................................................19
3.1.5 SOIL MECHANIC....................................................................................................................................20
SOIL INVESTIGATION...................................................................................................................................20
3.1.6 PAVEMENT AND DRAINAGE DESIGN..............................................................................................25
3.1.6.1 PAVEMENT DESIGN...........................................................................................................................25
3.1.6.2 DRAINAGE WORK..............................................................................................................................25
3.1.6.2 Floor.......................................................................................................................................................26
3.1.6.3 Windows.................................................................................................................................................26
3.1.6.4 Ventilation..............................................................................................................................................27
3.1.6.5 Ceiling....................................................................................................................................................27
3.1.6.6 Maintenance...........................................................................................................................................27
3.1.6.7 Reception................................................................................................................................................27
3.1.6.8 Balcony...................................................................................................................................................27
3.1.7.1 Lightening..............................................................................................................................................28
3.1.7.2 Hygiene..................................................................................................................................................28
3.1.7.3 Safety Measures.....................................................................................................................................28
3.2.0 ARCHITECTURAL DESIGN AND DRAWINGS..................................................................................29
3.2.1 MEASUREMENTS..................................................................................................................................30
3.2.2 BILL OF QUANTITIES...........................................................................................................................42
3.3.0 SITE ORGANIZATION AND ADMINISTRATION..............................................................................59
3.3.1 Introduction...............................................................................................................................................59
3.3.2 Site layout and planning............................................................................................................................59
3.3.4 Safety.........................................................................................................................................................59
3.3.5 Site accessibility........................................................................................................................................60
3.3.6 Security......................................................................................................................................................60
3.3.7 Information signs.......................................................................................................................................60
3.3.8 Offices.......................................................................................................................................................60
3.3.9 Water supply and sanitation......................................................................................................................60
3.3.9.1 Storage and site cleaning........................................................................................................................60
3.3.9.2 SCHEDULE OF WORK........................................................................................................................61
3.4 REFERENCE...............................................................................................................................................64
1.0 CHATER ONE: INTRODUCTION
1.1BACKGROUND INFORMATION
It is due to the rising of population in the college, there has been need improving
all l the facility to accommodate the fast growing development. The current
available administration block could no longer accommodate or serve the rapid
rising of population, hence need for creation of single block, well-design
administration block unlike the old scattered on
10
1.2 PROJECT OBJECTIVES
The main and major goal of the project is to test the students ‘process and
ability to apply their gained knowledge after three years of studying
diploma in building technology into real world. Both theoretical and
practical knowledge is needed to be put into in order for the success of the
trade project
To make detailed drawings and specifications of the proposed parking structure.
11
1.3 PROJECT OBJECTIVES
The main and major goal of the project is to test student prowess and ability to apply
their gained knowledge after three years of studying diploma in architecture into real
world. Both theoretical and practical knowledge is needed to put into action in order for
the success.
12
1.4 LIST OF ACRONYMS AND ABBREVIATIOS USED
LL: liquid limit
PL: plasticity limit
PM: plasticity modulus
ML: millimeter
WT: weight
%: percentage
NO: number/order
No: number/units
Dia: diameter
Hr.: hour
Deg c: degrees centigrade
STN: station
BS: back sight
FS: foresight
RL: reduced level
LS: linear shrinkage
MC: moisture content
CBR: California bearing ratio
OMC: optimum moisture content
13
2.0 CHAPTER TWO
LITERATURE REVIEW
INTRODUCTION
Generally, Administration Block requires a large area of floor space. Engineering
consideration tend to be the primary drivers for the solution of this type of structure
construction. Due to the population in the country and globally there is need to improve
infrastructure both to accommodate the rising population and to develop facilities into the
current modern design.
The Kenya vision 2030 which is in line with the MDGs, is the national long-term
development blue-print that aims to transform Kenya into a newly industrializing, middle-
income country providing a high quality of life to all its citizens by 2030 in a clean and secure
environment.
Among the pillars of the vision is deploying world class infrastructure and facilities. The
government of Kenya started an initiative to achieve the vision.
2030 documents and sensitization of people of Kenya are done by partners of Kenya in vision
2030. This was done to ensure that Kenyans understood the vision, goals, and the expected
outcome in order to own the process and implement the medium-term plans and vision 2030.
14
3.0 CHAPTER THREE: METHODOLOGY
3.1 SURVEY
I adopted grid method as the method of taking survey points and also during coming up of
contours. This is because it is easy and most comprehensive considering the availability of
survey equipment’s which had to be shared in groups.
Survey had to be carried out in order to;
Conduct the necessary field survey work to determine the best alignment.
Carry out engineering survey on the chosen alignment in order to obtain data for the
design of horizontal and vertical alignment.
3.1.1Reconnaissance Survey
This activity was carried out on forth of October 2020 by a team which included:
i. The cavities carried out included:
ii. Site selection
iii. Marking of obstacles
iv. Noting of obstacles
v. Pre-existing features identification
vi. Running the survey lines
vii. Site selection
15
i. Marking of obstacles
Being selected as the team leader I lead my team to sight to be able to identify obstacles that
may hinder the process of survey work.
v. Taking notes
All my team member’s each had to take note on the procedures. The materials needed were
Field book
Pencil
Tape measure
Ranging rods
Dumpy level
Staff
Pegs
16
Challenges faced
Misunderstanding among the colleagues since some of them are not familiar with the
survey method used.
Early tiresomeness among colleagues hence lack of constructions.
Unfavorable weather condition hot sun and strong winds.
Lack of experience in reading dumpy level among members hence taking a lot of time.
3.1.2 Leveling
The grids were established on the day of chaining this was 20m by 20m.they were marked
using wooden pegs. During level the dumpy level was used to take readings on leveling staff
at each point on grid. An assumed datum of 1200m was used to calculate reduced levels all
20points.the field level was taken as in table 1.
3.1.3 Contouring
After reducing the levels on each of the grid points at the intersection the levels were then put
into excel format in systematic manner to help in coming up the contours using AutoCAD.
17
3.1.4 LEVELLING: FIELD SURVEY DATA .
£ £F.
B.S= S=
2.64 1.8
4 54
18
Out of the results obtained from the field survey. Leveling is to be achieved through cut and fill
technique regarding the contour map obtained.
Lowest R.L
=1800.790
Difference in reduced levels
=1801.461-
1800.790
=0.671
No of contours to be drawn
=5
1st-1800.500
2nd-11800.600
3rd--1800.700
CONTOUR A
POINT1:
1800.500-1800.790
=0.29
1782.245-1787.970=0.275
(0.29/0.671) (9.00)=3.88
CONTOUR B
1800.600-1801.790
=1.19
19
3.1.5 SOIL MECHANIC
SOIL INVESTIGATION
This is aimed at determining the characteristics of the soil at the proposed site in order to carry
out soil test.
Samples are taken from various parts of the site in order to get the correct data to be used in
design which is used in geotechnology laboratory.
Soil sampling was done from different trial pits. The tools used include;
i. Two spades.
ii. Tamping rod
iii. Moisture bags.
20
Apparatus;
Riffle box
Weighing balance
Assorted sieve sizes.
Pan.
Procedure;
i. The sample is passed through the rifle box to obtain the required quantity.
ii. Weigh the sample to be sieved.
iii. The sample is soaked in a solution containing 2grms of sodium hexameter phosphate
for 24hrs.it is then washed and left to dry.
iv. The sieves are then assembled in descending order.
v. The dry sample is placed on top most sieve followed by shaking of the sieves.
vi. The weights of retained samples through each sieve size is taken.
vii. A graph of percentage retain against sieve size is plotted and then checked ageist
speciation given.
b) Plasticity index
The purpose of this test is to determine the plasticity of fine soil.
Apparatus
Casagrande.
Grove
Wash bottle.
Glass plate.
Weigh balance.
Palette knifes
Pestle and mortar.
Trough
Receiver
Sieve-425 um
21
Procedure
Sample is crushed using pestle and mortar and then passed though the sieve,
Water is added to the sample on the sieve and mixed thoroughly using pellet knife on
the glass plate to form a uniform paste.
A portion of the collected material is placed in the Casagrande which is then grooved
leaving a gap at the center.
The sample in the Casagrande is then heat with the specified number of blows till the
grouped portions meet.
A portion of the wet sample for each number if blows is taken for a moisture
determination.
For shrinkage limit the sample is heat though 25blows then placed in 140ml long trough
and air dried for 24hrs.the length of dried sample is measured for the shrinkage limit
determination.
For plastic limit the sample of 50th blow is used after drying to make rolls that are used
in moisture content determination.
The higher the number of blows the lesser the amount of moisture thus soil is added to
the wet sample on the glass plate with proper mixing.
A graph of moisture content against the number of blows is then plotted to determine
liquid limit.
Purpose: to determine optimum moisture content maximum dry density of the soil.
Apparatus
i. Sieve 20
ii. Mould, base plate and collar
iii. Measuring cylinder
iv. Rammer (2.5kg for field)
v. Weighing balance
vi. Straight edge chisel
vii. Mixing plate
22
Procedure
2500g of the sample passed through sieve 20 is weighed.
Using the measuring cylinder, the lowest amount of water is added to the sample the
mixed to achieve homogeneous product.
2.5rama s used with the Sample placed in 3 layers with 27 blows in each layer.
The collar is then removed from the mould and excess material trimmed using straight
edge.
The sample is then weighed plus the mould and the base.
A portion of the compacted sample is taken for moisture content determination.
The above process is required with different amount of water till the optimum moisture
content is achieved.
23
Apparatus
i. Mixing plate.
ii. Mould, base plate and collar.
iii. Weighing balance.
iv. Measuring cylinder.
v. Spacer disc
vi. Swell disc.
Procedure
Using the obtained proctor result, weigh the dry sample and measure the amount of
water then mix to obtain a wet material.
Take a portion of the wet material for moisture content determination.
From the proctor result calculation, weigh the required material to be mould.
For dynamic method, three moulds are used placing the material in 3 layers compacting
each layer with 62 blows for the first mould, 25blows for the 2nd and 10 blows for the
last mould.
In static method, the wet material is placed in CBR mould then using a jack, the
material is compressed in the mould.
Placing a swell disc on top of the mould, the initial swell readings are taken.
Place the mould in water for 4 days in case of neat materials.
After soaking the final swell readings are taken.
The mould is left to drain then placed on CBR penetration machine penetrating the top
and bottom. The penetration readings are taken at intervals of 0.25 up to 5.00.
To obtain the strength, the values at 2.50mm and 5.00mm are multiplied by the ring factor
for both the top and bottom then average.
24
3.1.6 PAVEMENT AND DRAINAGE DESIGN
Design factors
Climate factors.
Traffic
Drainage
25
Manning roughness coefficient
The rainfall intensity obtained from the meteorological department of Kenya is 120mm per
hour
3.1.6.2 Floor
Mastic asphalt should be provided to reduce the penetration of water to the floor of building.
Sand screed 15mm thick
Floor finish are made terrazzo in 1:3 mix
3.1.6.3 Windows
Steel casement windows clear glass and obscure
Stairs
Reinforcement concrete mix 1:2:4
Tread - 250mm
26
Rise – 150mm
Waist – 150 mm
Baluster – 10000mm
Landing -1200mm
3.1.6.4 Ventilation
Building has enough windows which are well position in direction to allow sufficient
natural light to entire
There are also natural ventilation in sense of a permanent ventilation (PV)
3.1.6.5 Ceiling
Suspended type at ceiling 12mm thick Celotex.
Boards and 50x50 soft wood branding T&G
3.1.6.6 Maintenance
Maintenance of the building is given top priority so that the building functions in accordance
with the approved standards. The responsibility is handed over to specialized groups.
3.1.6.7 Reception
A reception and information counter attended by trained and experienced personnel is placed
near the main entrance.
3.1.6.8 Balcony
An extravagantly specious balcony with atmosphere of comfort and convenience makes the
difference. The flood of light from the panel glass surrounding brings high quality to the
balcony.
27
3.1.7.1 Lightening
Lighting arrangements are fixed in the entire building and are designed to ensure functional
excellence.
3.1.7.2 Hygiene
The Administration block is cleaned and organized for efficiency. Scientific and hygienic
methods are used in working and for the washing of the entire Administration block.
28
3.2.0 ARCHITECTURAL DESIGN AND DRAWINGS
29
3.2.1 MEASUREMENTS
30
T D S DESCRIPTION
SUBSTRUCTURE
ALL PROVISIONAL
L W
33.299 25.00
Add allowances
2/0.20 2/20
33.69 25.04
2/1.00 2/1.00
35.69 27.04
35.69 Clear site of all bushes and shrubs including small trees and bush on
site.
27.04
2.Excavation of top soil(m2)
L W
33.29 25.00
34.69 26.04
31
34.69 Excavate vegetation soft top soil 200mm depth and deposit 2km away
from site.
26.04
Trench excavation
2 =116.50 0.60
1.05
1.05
Concrete building
Width =0.60
32
Length =116.5
L *h
2 116.5 116.5*0.20
L w h
7. Foundation Walling
L W
116.5 1.20
1.15
33
1.15 0.80
400mm thick natural stone foundation well bedrock and jointed CSM
14 and ditto.
1.15
8.Sides of foundation wall
0.80
Protect sides of excavation by plucking and strutting protects sides of
excavation by from water by boiling and pumping.
9.Laying of hardcore
L w
33.299 25.00
Treatment
L W
33.29 25.00
34
33.29 Dpm(m2)
25.00 500 gauge dpm on stone dust blinding and BRC mash size A142 ,in
slab CSM 1:4
2 33.29
Formwork (Lm)
2 25.00
Sawn formwork to sides of slab 100mm * 175mm high
Slab( m2)
Dpc(Lm)
Plinth
-height of concrete-100mm
12mm thick CSM 1:4 to plinth proper and apply of black bituminous
paint to rendered surfaces.
35
T1bars (Lm)into Kgs
L W
33.29 25.00
33.29 25.10
33.29 2500
12mm2 twisted bars and spaces blocks *0.888 to change into Kgs.
T10bars(lm)
33.29+1
0.888
=37.49+1
=37.50
33.29+1
0.02
=166.75
36
Width
No of short distance
25.00+0.04=25.04 + 1
0.02
=1253 numbers
600mm(0.6m)
150.36
37
Reinforcement(kgs)
Formwork ( lm)
L W
33.29 0.02
=10.40
Roof construction
2/10.40 Rafters
75mm*50mm rafters
38
Purlins(lm)
Gutter(lm)
2/1 100mm diameter downpipe fabricated from gauge 24 plain sheet fixed
to wall with holder bolts .Allow for painting and fair finishing to
satisfaction of the architect.
Sawn neck
Extra over for gauge 24 swan necks of 100mm long and prepare and
apply 3 coats of oil paint.
Shoe (No)
Extra over downpipe shoe 100mm long and prepare and apply 3 coal
of oil paint to external surfaces 100mm girth.
2/1
39
DOORS(No 35)
FRAME(LM)
Architrave(lm)
Quatrant(lm)
2700*2=5400
1000
6400mm
45mm *38mm architrave nailed to timber door frame with two labour
and 25mm*25mm cypress quadrant fillet nailed to timber frame.
Hinges (pairs)
40
Windows
ELEMENT NO. 01
SUBSTRUCTURE
A Excavation 510 SM
Clear site of all grass, bushes and
small trees grab up their roots
and remove all arising debris as
directed on site.
41
top soil average 200mm deep
and cart away
C Excavate trenches for strip 120 CM
foundation not exceeding 1.5
meters from reduced level
D Excavate for column base not 92 CM
exceeding
1.mm from reduced level
E Backfilling 100 CM
Return, fill and rum selected
excavated materials around
foundations
23 CM
A Columns
25 CM
B Ring beams
320 SM
C Sides and soffits of beams
290 SM
D Vertical sides of Columns
43
986 KG
E 8mm diameter bars
2890 KG
F 16mm ditto
WALLING
42 SM 1500
C Ditto internal walling
ELEMENT NO.4
Covering
Carpentry
Roofing (continued)
Carried to collection
Carried to collection
COLLECTIONS
FROM ABOVE
47
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
ELEMENT NO.5
DOORS
Galvanized Mild Steel casement
doors Fabricate, deliver and
install heavy duty grill members,
purpose made steel casement
doors to comply with BS
990,obtained from approved
manufacturer primed with red
oxide primer before delivery to
site complete with
100mmx50mmx3mm frame,
hinges,
handles, catches assembled and
fixed to openings including
cutting and pinning lugs to
concrete or block work surround
and bedding frame in cement and
sand(1;4) to architects approval
A 1200mmx2800mm 1 NO
Purpose made steel cement
glazed panel door standard Z
B 1500mmx2800mm 2 NO
Timber Doors
Flush Doors as BS 459 part 2;
48
C 45mm Thick solid core flush 13 NO
door size
900mmx2100mm overall
Rot cypress or other equal and
approved
Carried to collection
COLLECTIONS
FROM BW/8
FROM ABOVE
WINDOWS
Glazing
4 SM
K 4mm thick clear glass sheet in
panes 0.501.0m
Carried to collection
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
WINDOWS (continued)
FINISHES
B Walls 678 SM
C Walls 525 SM
Backings
53
Internal Wall Finishes
CEILING FINISHES
Soft board
Cornice
Carried to collection
COLLECTION
FROM BW/12
FROM ABOVE
55
SUMMARY
DESCRIPTION PAGE
SUBSTRUCTURE BW/3
RC BW/4
SUPERSTRUCTURE
BW/5
WALLING
ROOFING BW/7
CONSTRUCTION
AND
RAIN WATER
DISPOSAL BW/10
DOORS BW/12
WINDOWS BW/14
FINISHES
TOTALS FOR
BUILDING
WORKS CARRIED
TO
GRAND SUMMARY
GRAND SUMMARY
56
ITEM DESCRIPTION AMOUNT
GRAND SUMMARY
1. BUILDERS WORK
3.3.1 Introduction
57
The site organization and administration is per the project direction and guidelines
Site work plan and material storage, the site space has to be able to accommodate office,
material storage, working areas and general circulation areas.
3.3.4 Safety
Fire prevention; fire extinguishers should be installed on the site immediately on the site as
construction commences.
Medical services; first aid kit is very important and should be kept in safety office to be used
in case of an emergency.
Construction safety gear ; the contractor should ensure that he supplies his employees at the
construction site with basic attires including safety boots, hard hat, gloves and ear muffs.
3.3.6 Security
The entrance guard should be provided with a booth to watch all the movements in site
There should be enough lightings in site and security lights to allow for easy monitoring.
58
Hoarding should be done all around the site to prevent unwanted access to the site and provide
safety of workers and machines.
3.3.8 Offices
The offices should be closed together and close to the site the offices include job office,
constructor’s office they may be temporary offices.
59
Site organization 1 day
A gauge of four comprising of three unskilled and one
skilled labor who will be supervising the cleaning of site
which will include; cutting trees, grabbing up their roots
2
and burning the wastes.
1 day
3 Excavation of top soil
Done by using excavators and back actors and disposed
by a dumper. A depth of 150mm thick. Materials will be 3 days
excavated and deposited 3 km from site.
4
Site offices and services 2 days
Construction of site huts and offices will be done
5 manually by 4 skilled labors and eight unskilled labors.
Water is available on site. 8 days
6
Setting out
The setting out of the building will be done using a 3 days
Theodolite operated by one skilled assisted by two
unskilled labors.
60
7 Excavation of foundation trenches
One skilled for supervision and seven unskilled 7 days
labors who will be digging the trench.
8 2 days
Plunking and strutting
Work to be done by one skilled for supervising two
9
unskilled labors.
1 day
10
Removal of general water
Dewatering will be done by two skilled and two 2 days
11 unskilled labor
Foundation concrete
Concreting in the foundation will be executed by
one skilled and five unskilled workers.
Backfilling
Done by ten workers all-round the building
Concrete in column
Executed by one skilled and two unskilled labors
61
16 Foundation walling
Done by one skilled and five unskilled workers 5 days
17
Hardcore treatment 3 days
Done by six unskilled and one skilled labor
18 1 day
Anti-termite treatment
19 Carried out by two skilled and assisted by two 1 day
unskilled labors
20 2 days
Dpm laying
21 Done by five unskilled and one skilled workers
5 days
Screed
22 Done by two skilled and five unskilled.
2 days
Floor finish
Executed by eight unskilled and three workers
pg. 62
3.4 REFERENCE
The codes which were adopted for the design work include.
The BS8110 for concrete work
The standard method of measurement (SMM)
Research was also included
The price quotation used in the BQ was obtained from standard prices of
building materials.
pg. 63