TRS-HS-COS-0021
Revision History
Joal Roaquin /
Simon Horner Brian Spraker
Lijo Abraham
00 06-Jan-2022 Initial Document
Table of Contents
Acronyms and Abbreviations ........................................................................................................................................................... 3
Definitions .......................................................................................................................................................................................... 3
1 Purpose ..................................................................................................................................................................................... 4
2 Scope.......................................................................................................................................................................................... 4
3 Requirements ........................................................................................................................................................................... 4
3.1 Temporary Works..................................................................................................................................................................................4
5 References............................................................................................................................................................................... 10
5.1 Resources .............................................................................................................................................................................................10
5.2 Forms and Templates .........................................................................................................................................................................10
5.3 Supporting Documents.......................................................................................................................................................................11
6 Appendices .............................................................................................................................................................................. 11
Term Expansion
TW Temporary Works
Definitions
Term Definition
Parts of a construction project that are needed to enable the permanent works to be
built. Usually the TW are removed after use (e.g. access scaffolds, props, shoring,
Temporary Works excavation support, falsework and formwork). Sometimes the TW is incorporated into the
permanent works (e.g. haul road foundations, crane or piling platforms may be used for
hard standing or road foundations)
Individual designated to ensure that temporary works is allocated and carried out in a
Temporary Works Coordinator manner that does not create unacceptable risk of harm to workers or members of the
public.
A list set out in a table containing all identified temporary works item associated with the
Temporary Works Register
project.
1 Purpose
The purpose of this section is to introduce minimum H&S specifications for temporary works. These specifications
are intended to provide consultants, contractors and sub-contractors with guidance and information for defining,
planning and incorporating temporary works arrangements on construction sites.
2 Scope
This procedure applies to work activities and employees under the control of TRSDC, contractors, sub-contractors
and consultants.
3 Requirements
3.1 Temporary Works
• Contractors shall have defined temporary works policy and procedures describing how the risks and
hazards associated with Temporary Works are identified, classified and controlled. Procedures shall be in
accordance with the requirements of BS 5975:2008 and its updates.
• All temporary works shall be designed and checked, in accordance with Contractor's own procedures and
where required, by independent third parties.
• The Contractor’s (and their supply chain) temporary works shall be properly checked and approved at each
phase by the Contractors appointed temporary works coordinator and shall therefore be presented for
check/approval in good time.
• The Contractor’s Temporary Works Coordinator, shall check all the temporary works designed or erected
by their sub–Contractors and supply chain.
• The Contractor’s Project Manager shall be the default temporary works coordinator until such time as they
appoint a Temporary Works Coordinator. The Contractor’s Project Manager is responsible for appointing
the Temporary Works Coordinator in writing.
4 Execution of Requirements
Temporary Works (TW) are defined as all works required for execution, completion, maintenance and/or demolition
of permanent works, (including temporary stress states of permanent works) and which will normally be removed
from the site on completion.
Examples include:
The TWC is responsible for ensuring that the Contractor's procedures for the control of temporary works are
implemented on site. The TWC is not normally the designer, but is responsible for ensuring that a suitable temporary
works design is prepared, checked and implemented on site in accordance with the relevant drawings and
specification.
The principal activities of the TWC are listed in Clause 7.2.5 of BS5975:2008. On some projects, particularly smaller
jobs involving lower risk temporary works, it may be appropriate for the TWC and designer roles to be carried out
by the same person, provided that he/she is competent to carry out each of the roles.
The TWC for a project shall be formally appointed and have adequate authority to carry out his/her tasks, including
stopping the work if it is not satisfactory. It is essential that those selected to act as TWC are competent with relevant
up-to-date training, and experience and qualifications appropriate to the complexity of the project. Ideally a TWC
would:
• Relevant experience
• Formal TWC training
• Professional qualifications TWCs shall have the competence and authority to be effective
4.2.2 Responsibilities
• Prepare company procedures for the design, checking, erection, inspection, use, and dismantling of
temporary works.
• Assess and appoint specialist temporary works suppliers and designers as required.
• Ensure that the temporary works are designed, checked, certified and implemented in accordance with
the approved procedures, appropriate to the classification.
• Classify and register all packages of temporary works and compile the Temporary Works Register (TWR).
• Prepare detailed design briefs for each item of temporary works when required by the temporary works
classification.
• Ensure concept, design, risk assessment and checking are carried out in accordance with the design brief.
• Establish and implement an inspection regime for all temporary works with the temporary works
designer to ensure that they remain suitable and fit for purpose.
• Submit checked temporary works design drawings and calculations for approval.
• Produce method statements for the erection, use and dismantling of the temporary works.
• Inspect the completed temporary works to confirm when a structure can be loaded and unloaded. Issue
permits to load and unload.
• Where appropriate, ensure that copies of the design, design check and test certificates as well as permits
to load/strike are issued and registered.
• Ensure that loads from temporary works and temporary loads, such as plant and materials are accepted
by the permanent works designers.
• Ensure that method statements for the erection, use and dismantling of the TW are prepared and
communicated to all those involved in the operation.
4.4.2 The TWC shall ensure that an adequate design brief is provided to the designer and design checker of the
temporary works.
4.5.2 Temporary works designers include; the manufacturers and suppliers of proprietary temporary works
equipment and those working in a contractor's temporary works department or office. Temporary works
designs are sometimes categorised to indicate the complexity/simplicity of the specific temporary works
structure and the potential risk. See below for an example:
• Standard scaffold
• Formwork less than 1.2m high
• Hoarding and fencing up to 1.2m high
• Simple propping schemes – 1 or 2 props
• Internal hoarding systems and temporary partitions not subject to wind loading
• Shallow excavations less than 1.2m deep/high
• Falsework up to 3m high
• Formwork for columns and walls up to 3m high
• More complex propping schemes – multiple props at single level
• Needling of structures up to 2 storeys high
• Excavations up to 3m deep/high
• Net systems not fixed to robust primary members
• Hoarding and fencing up to 3m high
• Simple designed scaffold
• Temporary roofs
4.5.3 In practice, even relatively simple temporary works may require careful consideration in their design,
construction, commissioning, inspection and loading. An apparently simple temporary works job could lead to
failure and even to fatalities if it is not competently executed. The choice of the appropriate temporary works
solution, including the use of “standard solutions,” is discussed in Clause 9.4 of BS5975: 2008. A “standard
solution” is an arrangement for which the basic design work has already been carried out and is presented in a
tabular or similar form, and for which no further calculations are required.
• Design concept
• Strength and structural adequacy (including foundations and lateral stability)
• Compliance with the design brief.
4.6.2 The design check shall be carried out by an independent competent person(s) . The ability and independence
of the checker shall be greater where the temporary works are more complex or where new ideas are
incorporated. Recommendations for various categories of design check are given in Table 1 of BS5975:2008,
reproduced below:
• Suitable verification of correct erection of the temporary works and someone overseeing and co-
ordinating the whole process
4.7.2 Smaller contractors may not have anyone sufficiently experienced to plan effectively all but the most simple
temporary works. There shall be clear evidence that appropriate external expertise has been engaged. This
includes obtaining the services of a suitably competent TWC and temporary works designer to ensure
temporary works are effectively designed, constructed, inspected, loaded and managed. On some projects,
particularly smaller jobs involving low risk temporary works, it may be appropriate for the TWC and designer
roles to be carried out by the same person.
4.8 Temporary Works Design Principles and the Consequences and Causes of Failure
4.8.1 Design principles
In order to ensure the strength and stability of any temporary works structure, there are 3 fundamental aspects
that need to be considered which can be simplified as follows:
• Foundations – the ability of the ground to carry the loads transmitted from the temporary works
structure without failure or excessive deformation or settlement.
• Structural integrity – the ability of the temporary works structure itself to carry and transmit loads to
the ground via the foundations without failure of the structural elements, including fixings and
connections (e.g. by buckling, bending, shear, tension, torsion), and without excessive deflection.
• Stability – the ability of the temporary works structure to withstand horizontal or lateral loading without
sway, overturning or sliding failure (stability may be inherent in the temporary works structure itself or
provided by the permanent works).
Failure to adequately design, construct and maintain temporary works can lead to:
• Risk of single/multiple fatalities and serious injuries to workers and members of the public
• Significant financial and commercial risks to contractors, sub-contractors, designers, suppliers, and to
TRSDC.
• Overloading of temporary works, i.e. failure to control loading or lack of awareness of the capacity of
the equipment (e.g. acrow props)
5 References
5.1 Resources
Australian Government
External reference
Safety and Compensation Council; List of National Codes of Practice/Standards
European Union
External reference
European Agency for Safety and Health at Work
United Kingdom
6 Appendices
N/A