Site Selection and

Preparation

www.sistema.bio
What will we learn?
This training will present the essential knowledge about:

• Where to install a biodigester?


• The area required for the installation.
• What do we need to prepare prior to an
installation?

 Followed up by a session of Questions an Answers!

www.sistema.bio
How do I select the position of the
digester?

www.sistema.bio
www.sistema.bio
Optimal location of the biogas system on the farm

30 m
to kitchen
Close to
animal dung

Distance to kitchen is the Biodigester


most important factor location
Close to water

 Biodigester can be located up to 50m from Near to


the biogas point of use. farm land
 For anything from 50m to 500m specific And crops
technical solutions might be required
Ex.: biogas pump

www.sistema.bio
on sloping ground
DOs and DONT’s

NOT across a slope


Manual digging Reinforce loose soil NO support wall
with masonry walls

On a slope make
a terrace first…

NOT in the way of


NOT under trees
people and animals
NOT close to trees
…then dig the pit
www.sistema.bio
Constructed Pit

www.sistema.bio
Configuration of Gas line for site selection
The closer the digester is from the gas point of use:
• The easier and faster is the installation of the gas line;
• The higher is the biogas flow.

It is important to consider that a gas line post must be install to


support the gas line every 8 to 10 meters.

The slope of the gas line will have to be 10%: 1 meter vertical slope Minimum
every 10 meters. 1 meter

 Make sure to install the


biodigester where the gas line
will not disturb the way of
vehicles or animals!

Maximum Maximum
10 meters 10 meters

www.sistema.bio
Optimal location of the biogas system on the farm

It is very helpful to sketch the farm


configuration before confirming
the location of installation!
It must include positions of the
following element and distances
between them:
• kitchen
• water source
• dung source
• agriculture field
• digester
• biofertilizer tank
• gas line

www.sistema.bio
Do I have enough space for the
digester?

www.sistema.bio
www.sistema.bio
Land Requirements
Land requirement for standard installation of the
Reactor, Feeder Tank and Biofertilizer Tank

Length

Walking / Working Space


Areal view of a Sistema 6

Biofertilizer
Reactor
Feeder
Width

Tank

Tank

Walking / Working Space

Areal view of a Sistema 20


www.sistema.bio
Land Requirement for Sistema Digester
Different options of configuration
Configuration 1
Biofertilizer tank
aligned Configuration 2
Biofertilizer tank
non-aligned Configuration 3
Biofertilizer tank located
at another location

www.sistema.bio
Land Requirement for Sistema Digester
Configuration 1

www.sistema.bio
Land Requirement for Sistema Digester
Configuration 2

www.sistema.bio
Land Requirement for Sistema Digester
Configuration 3

www.sistema.bio
www.sistema.bio
Confirm and set the selected
biodigester position

www.sistema.bio
www.sistema.bio
Location & Excavation
Get your family’s
consent on the location
of digester and bio
fertilizer tank
In case the soil is very loose, re-
inforce the pit with masonry walls

The site markings for the pit must be


A good pit will allow
provided by Sistema.bio technician Excavate the pit according to the exact
a good installation!
dimensions provided by Sistema.bio
www.sistema.bio
www.sistema.bio
What else do I need to prepare
before the installation day?

www.sistema.bio
www.sistema.bio
Sistema 6
Material Preparation before Installation
Prepare cow dung to
Prepare 0.7 times the do the initial feeding
digester size of Water to be of the digester on the
filled in the digester on the day of installation: 10
day of installation. times the daily feeding
Ex.: Sistema 6 = 0.7 * 6 = with cow dung.
3.6 m3 or 3600 liters. Ex.: Sistema 6 = 10 *
40L = 400L or 20*
20L buckets

Prepare 1 metal/concrete/
hardwood poles every 8 to 10
meters between the biodigester
and the biogas point of use
(min 3 m long) to support the Prepare cement, sand and
gas pipeline on the day of ballast to permanently fix
installation the poles into the ground
on the day of installation
www.sistema.bio
Exercise!

www.sistema.bio
www.sistema.bio
What are the requirements for the following farm?

1. Farm configuration as shown on the right.


2. You are Installing a Sistema 8.

a. What maximum distance can I consider


between the biodigester and the biogas
Distance:
point of use? 15 meters

b. What area will you require?


Sistema 8
c. What do you need to prepare for the day
of installation?

www.sistema.bio
Answers
Max 10 Max 10
a. 30 meters is a good distance! 50m would be meters meters
the maximum!

b. 8 by 4 meters in configuration 2.

c. The farmer will have to provide:


1. 2 Posts: one for the filter, one between the
kitchen and the biogas post. The gas line
will then be fixed to the house.
Post
2. Cement, sand and ballast to set the posts
into the ground.
2. Sistema 8: 8 * 0.7 = 5.6 m3 Water to fill Post
the reactor on installation day.
3. 10 * daily feeding = 10 * 60 liters = 600
liters of manure loading for first feeding
(30 buckets)
4. The farmer will have to prepare the Pit for
digester AND biofertilizer tank.

www.sistema.bio
THANK YOU
FOR YOUR
ATTENTION!
Copyright © 2019 Sistema.bio. All rights reserved.

Now let’s www.sistema.bio

discuss and
answer Sistema.bio | Sistema Biobolsa

Questions!