You are on page 1of 135
4 NAM MO 2 POWER COMPANY LIMITED $ et? y 88, Nongbeuk-Tay village, Sikhottabong district, Vientiane Capital, Lao PDR NAM MO 2 HYDROPOWER PROJECT - LAO PDR BASIC DESIGN VOLUME V - PART 1 SPECIFICATION OF CIVIL WORK SCI CONSULTING JOINT STOCK COMPANY | 3rd Floor, Tower C, Golden Pala ing, Me Tri Road, Me Tri Ward, | Nam Tu Lie Noi, Viet Nam | —$$—$———— = ‘ NAM SAM 3 POWER COMPANY LIMITED | ey 88, Nongbeuk-Tay village, Sikhottabong district, Vientiane Capital, Lao PDR NAM MO 2 HYDROPOWER PROJECT- LAO PDR BASIC DESIGN VOLUME V - PART 1 SPECIFICATION OF CIVIL WORK TECHNICAL MANAGER : DESIGN MANAGER SCI JOINT STOCK COMPANY ‘SCI CONSULTING JOINT __STOCK COMPANY HA NOI- VIET NAM, 07-2023 Basic Design Nam Mo 2 Hydropower Project General informations iC DESIGN DOCUMENT LIST. 1 ‘Summary report 2 | Volume I Main report 3 | Volume II Design criteria 4 Volume III - Part 1 Drawings of Civil works Drawings of Hydro-Mechanical (HM) and Electro- 5 | Volume Il - Part 2 Mechanical (EM) tavinnecnts 6 Volume IV.1 - Part 1 Appendix - Hydraulic calculation of il works: 7 Volume IV.1 - Part 2 Appendix - Stability calculation of Civil works 8 Volume IV.1 - Part 3 Appendix - Structure analysis of Civil works 9 __| Volume IV.1 - Part 4 Appendix - HM and EM equipments calculation 10. | | Volume IV.2 - Part 1 Appendix - Report on Topography survey I1__| Volume IV.2-Part2 _| Appendix - Topography maps 12__| Volume IV.3-Part1 _| Appendix - Report on Hydrology and Meteorology study 7 ‘Appendix - Report on Reservoir Sedimentation and 13 Volume IV.3 - Part 2 Backwater calculation 14_|VolumeIV4 ‘Appendix - Report on Hydropower calculation 15 | Volume IV.5-Part 1 | Appendix - Report on Geology investigation 16 | Volume IV.5-Part2 | Appendix - Geology drawings . ‘Appendix - Driling cores, borehole logs and testing results 17 Volume IV.5 - Part 3 in the boreholes 18 Volume IV.5 - Part 4 Appendix - Report on geophysical investigation _| 19 Volume IV.5 - Part 5 Appendix - Testing results in Lab 20 Volume IV.6 Appendix - Report on Hydraulic model experiment 21 | Volume 1V.7 “Appendix - Report on Seismic Hazard Assessment 23 Volume V - Part 2 Specification of Earth and Rockfill dam . Specification of Hydro-Mechanical and Electro- 24 | Volume V - Part 3 Mechanical Equipment 25 Volume VI Reservoir operating procedure Estimating downstream inundation in case of flood 26 Volume VII dis .e and dam break SCI Design Manager | Technical Manager 4 I Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project _ General informations INVOLVED PERSON IN THE BASIC DESIGN Deputy General Director of SCI Group - General 1 | Pham Van Nghia Menage Deputy General Director of SCI Group - Advisor 2 |YuAnMinh of HM and EM equiments design 3 | Nguyen Tai Son Deputy Director of SCI PMC - Advisor of Civil work design 4 | Hoang The Vinh Deputy Director of SCI PMC - Design manager 3 | Ngo Vu An Deputy Director of SCI PMC - Technical manager 6 | Ngo Duy Manh Design leader of Main dam and Auxiliary dam 7 | Phan Van Huan Design leader of Spillway and Waterway 8 | Nguyen Thi Dieu Chinh Design leader of Powerhouse and Monitoring equipments 9 | Tran Minh Khoi Design leader of Construction organization 10 | Vu Duy Hung Design leader of Civil work structure 11 | Pham Van Cuu Design leader of Electrical equipments 12 | Do Manh Cuong Design leader of HM and EM equipments 13. | Nguyen Do Nhat Senior engineer of Topographic survey 14 | Tran Van Vi Senior engineer of Geological investigation 15 | Bui Van Thom. Expert of Seismic hazard assessment 16 | Le Van Nghi Team leader of Hydraulic model experiment 17 | Doan Thi Minh Yen Team leader of Estimating downstream inundation in case of flood discharge and dam break 18 | Dau Trung Kien Senior engineer of Hydrology and Meteorology study 19 | Tran Kim Chau Expert of PMF flood estimation 20 | Hoang Xuan Chien Expert of Hydropower calculation S C I Design Manager Technical Manager Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work TABLE OF CONTENTS CHAPTER 1. GENERAL 1.1, DEFINITIONS....... 1.2, SCOPE OF WORKS. 1.2.1. General . 12.2. Discoveries during construction 1.3. TRADE NAME 1.4, ACCORDANCE OF MATERIAL WITH TECHNICAL FEATURES 1.5, STANDARDS...... 6. TESTING AND TESTING EQUIPMENTS. 1.7, TEMPORARY WORKS FOR CONSTRUCTION... 1.8, AUXILIARY WORKS AND CAMPS 1.9. POWER, WATER AND COMMUNICATION FOR CONSTRUCTION 1.10, SURVEYING OF EPC CONTRACTOR 1.10.1, Scope of work 1.10.2. Material and tool 1.10.3. Implement the surveying. 1.11, SAFETY IN CONSTRUCTIOI CHAPTER 2. EXCAVATION OF OVERGROUND SOIL AND ROCK. 2.1. GENERAL 2.2. GENERAL REGULATION. 2.2.1. Dispose and storage soil and rock from excavation work 2.2.2. Minimize the affects to the outside of excavation area. 2.2.3. Drainage work during excavation process . 2.2.4. Safety in construction. 2.2.5. Limit the excavation boundary .. 2.2.6. Allowable errors in the overground excavation wor 2.2.7. Clear surface 2.2.8. Inspection of excavation work of soil and rock 2.3. EXCAVATION OF SOIL. 23.1. Protect surface at the excavation area.. 2.3.2. Rainwater drainage system on slope 2.3.3. Excessive volume of excavation boundary 2.4. EXCAVATION OF ROCK 2.4.1, Excavation methods and protection of rock slope 2.4.2. Excavate rock in the areas with surface after excavation are not surface of conerete structure . 2-4 2.4.3. Excavation of rock in the areas with rock surface after excavation is concrete base 2-4 2.4.4, Faults and joint treatment 2-5 S C Design Manager Technical Manager 1 Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work 2.4.5. Excessive volume of rock .. 2.5, OVERGROUND EXPLOSION. 25.1. General requirement. 2.5.2. Affix explosion... 2.5.3. Blasting work for mining at quarry. 2.5.4. Safety technique in explosion CHAPTER 3. UNDERGROUND EXCAVATION WORK.. 3.1. GENERAL .. 3.1.1. Scope of work . 2. Safety in construction process. MATERIAL, EQUIPMENT AND SERVICE SYSTEM. General Ventilation system, Lighting system... ‘Communication system Drainage system. Fire regulations. 3. UNDERGROUND EXCAVATION.. 1. General... 2. Investigation drilling... 3.3. Site testing for blastin, 4, Underground explosioi 3.3.5. Excess excavation 3.3.6. Checking work. 3.3.7. Inspection work. CHAPTER 4. SLOPE PROTECTION AND SLOPE CONSOLIDATION WORK 4.1, GENERAL. 4.2, GRASS PLANTING... 4.3, ROCK GUTTER... 4.4. ROCK WALL 4.5. GABION SUPPOR’ 4.5.1. Scope of work 4.5.2. Implementation 4.6. ROCK ANCHO! 46.1. 4.6.2. 4.6.3. Drilling and installing anchor 4.6.4. Grouting into the borehole of rock anchot 4.6.5. Protection again corrosion .. 4.6.6. Rock anchor testing work 4.6.7. Quality inspection and acceptance work. 4,7, SHOTCRETE OF EXCAVATED ROCK SURFACE... 47.1. Scope of work... S C Design Manager Technical Manager 2 Hoang The Vinh Ngo Vu An & SRRDSE 3. 3. 3. 3. 3.2, 3. 3. 3. 3 3. 3. 3. 3.: Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work 4.7.2. Materials and devices 4.73. Implementation... 4.7.4. Experimental work and indicators 4.7.5. Construction safety . 48. TEMPORARY REINFORCED STEEL ARCH 48.1. General 4.8.2. Applicable standards 4.8.3. Material . 4.8.4, Implementation CHAPTER 5. GROUTING.. 5.1 5.11 5.1.2. Applicable standard. 5.2. MATERIALS AND EQUIPMENTS, 5.2.1. Mortar for grouting .. 5.2.2. Drilling equipment 5.2.3, Grouting equipment 5.3. CARRYING OUT GROUTING WORK. 5.3.1. Drilling work. se 5.3.2. Water pressing work 5.3.3. Grouting work. CHAPTER 6. ROAD CONSTRUCTIO! 6.1. GENERAL .. . 6.1.1. Scope of work .... 6.1.2. Applicable standard. 6.2, MATERIAL! 6.2.1. Roadbed.. 6.2.2. Gravel foundation 6.2.3. Asphalt concret 6.3. IMPLEMENTATION... 6.3.1, Road foundation construction... 6.3.2. Construction of aggregate base course.. 6.3.3. Construction of asphalt concrete lining CHAPTER 7. BACK FILLING. 7.1. SCOPE OF WORK... 7.2. MATERIAL AND EQUIPMENTS .. 7.2.1. Material . 7.2.2. Equipments. 7.3. IMPLEMENTATION... 7.3.1. Foundation backfill of concrete structure . 7.3.2. Backfill of roadbed and switchyard. 7.3.3. Embankment of cofferdam. CHAPTER 8. REINFORCEMENT INSTALLATION S CI Design Manager Technical Manager 3 Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V- Part 1: Specification of Civil Work 8.1, GENERAL 8.1.1, Scope of work .. 8.1.2, Applicable standard 8.2. MATERIAL wens 8.2.1. Reinforcement and pre-stressed reinforcement 8.2.2. Hole forming pipe for prestressed reinforcement 8.2.3. Lubricant in the tube where the prestressed reinforcement is placed 8.3. IMPLEMENTATION 8.3.1. General. 8.3.2, Cut and bend steel rebar... 8.3.3. Rebar welding .. 8.3.4, Rebar splicin; 8.3.5. Place pipe containing prestressed reinforcement. 8.3.6. Processing prestressed rebar . 8.3.7. Transportation and installation of rebar. 8.4. PRESTRESSED REBAR TENSIONING DEVICE. CHAPTER 9. CONCRETE PRODUCTION AND CONSTRUCTION. 9.1, GENERAL 9.1.1. Scope of work .. 9.1.2. Applicable standards 9.2. CONCRETE PRODUCTION MATERIAL 9.21. Cement. 9.2.2. Additives... 9.2.3. Water for conerete.. 9.2.4. Sand for concrete. 9.2.5. Crushed stone for concret - PARTICLE SIZE 25 + 50MM. ~ PARTICLE SIZE 12.5 + 25MM — PARTICLE SIZE 4,75 + 12.5MM 7 - PARTICLE SIZE SMALLER THAN 4.75MM 9.3. PRODUCTION OF CONCRETE MIX 93.1. General ern 9.3.2. Technical requirement of concrete mixture 9.3.3. Quantitative and mixing concrete . 9.3.4. Temperature of concrete mixture, 93.5. Notes. - 9.4. TRANSPORTING CONCRETE MIXTURE, 9-7 9.4.1. Transporting the concrete mix from the place of mixing to the place of pouring 9-7 9.4.2. Put the concrete mixture into the pouring block... 9.5. FORMWORK FOR CONCRETE 9.5.1. General. 9.5.2. Material su . 9.5.3. Structure and processing of formwork S C Design Manager Technical Manager Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work 9.5.4. Sliding formwork... 9-10 9.5.5. Formwork of water tunnel. 9-10 9.5.6. Erection of formwork and bracing. 9-11 9.5.7. Dismantling formwork. 9.6. CONCRETING OF CONVENTIONAL STRUCTURE 9.6.1. Surface preparation work 9.6.2. Acceptance work of pouring blocks. 9.6.3. Some limitations when pouring concrete. 9.64, Leveling, compacting the concrete...... 9.6.5. Temporary stop time for casting concrete.... 9.6.6. Construction joint 9.6.7. Thermal expansion joint... 9.68. Note... . 9-20 9.7. POURING CONCRETE OF COLUMN, WALL, BEAM AND FLOOR SLABS9-20 9.7.1. Pouring concrete of column and wall or pillar of frame 9-20 9.7.2. Pouring concrete of beam and floor slabs... 9-21 9.7.3. Construction joint when pouring concrete of column, wall, beam and floor slab 9-21 9.7.4, Note... . 9.8. POURING CONCRETE PHASE 2. . . 9.9. CONCRETING HORIZONTAL TUNNEL, VERTICAL SHAFT... 9.9.1, ‘Transporting tunnel concrete into the pouring block. 9.9.2. Implementation .. 9.10, PRECAST CONCRETE CONSTRUCTION 9.10.1. General . 9.10.2. Applied standard 9.10.3. Material 9.10.4. Implementation 9.10.5. Allowable deviation... 9.11, TREATMENT THE DEFECT OF CONCRETE. ses 9.12. CONCRETE CURING AND CONCRETE PROTECTION... 9.13, MEASURE THE TEMPERATURE OF THE CONCRETE POURING BLOCK 9-26 9.14, CONTROL TEMPERATURE OF CONCRETE MIXTURE AND CONCRETE9-27 9.15, FINISHING THE CONCRETE SURFACE. . 9.16, CHECKING QUALITY OF CONCRETE AND ACCEPTANCE 9.16.1. Checking quality of conerete ... . 9.16.2, Acceptance... CHAPTER 10. STEEL STRUCTURE. 10.1, GENERAL .. Scope of work . 9-22 10.2, MATERIALS 10.3, IMLEMENTATION 10.3.1. Processing in workshop S C | Design Manager Technical Manager 5 | Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work 10.3.2. Transportation .. . 10.3.3. Storage. 10.3.4. Assembly 10.4. INSPECTION AND ACCEPTANCE. CHAPTER 11, PAVING AND PLASTERING WORK. 11.1, GENERAL 1L.L.1. Scope of work .. 11.1.2. Standard, 11.2. IMPLEMENTATION 11.2.1. Constructing brick. 11.2.2. Floor paving . 11.2.3. Plasterin; CHAPTER 12. PAINTING WORK 12.1, GENERAL 12.2, MATERIAL... 12.3, IMPLEMENTATION 10-2 --- 10-2 10-2 10-3 1-1 11-1 11-1 Al-1 11-1 112 11-2 12-1 12-1 12-1 12.3.1. General regulation 12-1 12.3.2. Oil paint on metal surface .. 12-2 12.3.3. Oil paint on wooden surface .. 12-2 12-2 12-2 12.2 12.2 13-1 13-1 13-1 12.3.4. Water-based paint on plaster and concrete surfaces. 12.3.5. Finishing wooden surfaces with varnishes 12.3.6. Floor paint. 12.3.7. Acid resistant paint.. CHAPTER 13. DOORS AND WINDOWS. 13.1. GENERAL .. 7 13.2. MATERIAL AND CONSTRUCT 10} 13.2.1. Steel hollow door 13.2.2. Steel door frame 13.2.3. Roller sliding door ... 13.2.4. Doors, windows and aluminum frames 13.2.5. Wooden door... 13.2.6. Glass for doorway CHAPTER 14. OTHER ARCHITECTURE WORK. 14.1. GENERAL .. . 14.2. MATERIAL AND CONSTRUCI T ‘ON 14.2.1. The floor with space underneath 14.2.2. Aluminum ceiling panels .., 14.2.3. Drainage hopper in floor and roof decl 14.2.4. Drainage pipe of floor and roof. 14.2.5. Rotation shutter curtain... CHAPTER 15. MONITORING EQUIPME! 15.1. GENERAL... 15.2. REQUIREMENT OF THE MON TORING EQUIPMENT C Design Manager Technical Manager 6 Hoang The Vinh Ngo Vu An 13-1 Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work LIST OF TABLES Table 1-1. Testing standards of materials and construction quality .. Table 3-1. Permissible content of emission gas in underground construction. Table 4-1. Aggregate distribution table for shotconcrete .. Table 5-1. Content of components in stable clay cement mortar... 5-8 Table 6-1. Allowable deviation in comparison with design of aggregate gradation and asphalt content for mixture. Table 6-2. Allowable deviation for geometric characteristics of asphalt concrete road surface .. oo 6-10 Table 6-3. Standard table of acceptance te test for the flatness of asphalt concrete pavement . - 6-10 Table 6-4. Acceptance standard for two points along centre of road ... Table 8-1. Deviation dimension of processed steel bar Table 8-2, Permissible deviation for welds. Table 8-3, Reinforcement splicing for concrete with different grades . Table 8-4. Allowed error of installed steel rod... Table 9-1. Allowable deviation for installed formwork and bracing... Table 9-2. Minimum strength of concrete to take down for load bearing formwork 9-13 Table 9-3. Table of permissible deviations of concrete structures .... 9-30, Table 9-4. Table of permissible deviation for prestressed reinforced concrete structures . 9-31 Design Manager Technical Manager Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work CHAPTER 1. GENERAL 1.1. DEFINITIONS "Project" means Nam Mo 2 Hydropower Project; “Works” means Construction works of Nam Mo 2 Hydropower Project; "Contract" means an BPC contract between the Employer and the general contractor; "Employer" is an agency, organization or individual that owns capital, borrows capital or is assigned to directly manage and use capital to invest in Nam Mo 2 Hydropower Project; "EPC General Contractor" is the main contractor responsible for the Design - Procurement, supply of equipment - Construction, equipment installation of Nam Mo 2 Hydropower Project; "Consultant" is a Project Management Consulting Unit, Supervising Consultant of the Employer; "Principal works" or "Major constructions" are works whose damage ot destruction will directly affect the normal operation of the head works and the system of post-focal works, making them unable to fulfill the designed tasks, including: main dam, auxiliary dam, spillway, intake, headrace tunnel, vertical shaft, pressure tunnel, powerhouse, switch yard, transmission line; "Secondary works" means are works whose damage or destruction has little effect on the normal operation of the focal works and the system, and can be recovered in a short time, including but not limited to: Diversion works, quarries, retaining walls downstream of powerhouse, long-lasting excavated slopes, slope consolidation and shore protection structures, operation road (access road) systems; "Temporary works" means the works used only during the construction or repair of a long-term work during the exploitation period, including but not limited to: Inlet and outlet channel of diversion tunnel, coffer dams, construction road systems; "Auxiliaries works" are temporary works that establish the servicing facilities for built the main works as well as temporary works; "Camps, public works" is the residential areas, working houses of EPC General Contractor / Subcontractors and Employer / Consultant as well as the works for the public activities of people of parties involved in construction; "Design documents" are all or specific parts of the approved Basic Design, Detailed Design of Nam Mo 2 Hydropower Project; "Equipment" means tools, machines that erected to the main works; S Cl Design Manager Technical Manager a Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work 1.2. 1.2.1. — "Construction equipment" means all equipment, machinery, vehicles ... required to serve the construction work, work completion and repair of any errors; — "Goods" are equipments, materials, workshops and temporary works, daily: life appliances or any of the above categories, purchased by EPC General Contractor for the construction of works; — "Materials" means things or all types (not equipment) in order to create or create a part of a work, including those provided only in terms of materials (if any) provided under the Contract; SCOPE OF WORKS General Main works are executed according to contract with Employer including these but not limit: = Contruct the auxiliary area and camp — Contruct the main dam, saddle dam (auxiliary dam) and spillway — Contruct and install the equipments for spillway — Contruct and install equipments on the waterway include intake, headrace tunnel, vertical shaft, pressure tunnel — Contruct and install the equipments for diversion work — Contruct and install the equipments for powerhouse — Contruct and install the equipments for switchyard — Contruct the access and construction road systems in the site includes access road is used during construction, etc. = Contruct the auxiliary tunnel of headrace tunnel, vertical shaft and pressure tunnel This specification shows only technical requirements for Contruct main works and auxiliary works to serve construction (auxiliary tunnel, construction road). The works does not show in this document needs carry out according to rules in relevant drawings and existing standard and normal. Required technical are shown in this documents applied for construction of powerhouse, switchyard, intake, headrace tunnel, vertical tunnel, pressure tunnel, auxiliary tunnel, spillway, diversion works (diversion tunnel, upstream and downstream coffer dam), access roads, construction roads in the site and auxiliary area, temporary camp, Constructing the Earth-Rock Fill Main Dam and Earth- Rock Fill Saddle Dam will be guided in separate specification. EPC General Contractor must make and submit to Consultant the management procedures of the laboratory as: organization, equipment, testing contents, acceptance criteria, testing monthly reports, EPC General Contractor must make and submit to Consultant the management procedures of the batching plants as: organization, equipment at the batching S Cl Design Manager Technical Manager Lo Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work 1.2.2. 1.3, 14. 15. 1.6. plant (probes, wattmeter), control the implementations, acceptance criteria, monthly reports on concrete delivery, delivery ticket... EPC General Contractor must make and submit to Consultant the technical procedures as: conerete pouring, concrete curing, treatment of concrete defects. Discoveries during construction If any thing is historic or significant value discovered random during construction at the site, then it will be Lao P.D.R’s properties. EPC General Contractor must inform immediately to Employer about these and solve these problems under instructions of Employer. If there is appeared bones which not be forecasted before, then EPC General Contractor and Employer will determine each other to ensure timeline and suitable for local habits. Expense for movement will be paid to EPC General Contractor by Employer. TRADE NAME Unless otherwise specifically stated, any trade name stated in this specification or in drawings does not mean that this trade name will be the sole using one. The things stated in this Specification for guide about standard, quality, grade, and type of finishing specified for use. These products have been manufactured in accordance with the Code of Quality and Type. Similar products are manufactured by other manufacturers which meet to the specified quality could be proposed the EPC General Contractor and agree by Consultant before use. ACCORDANCE OF MATERIAL WITH TECHNICAL FEATURES All material to make up parts of permanent works must be new and suitable for “Specifications.” While characteristic of any material is not defined in the material table then this material is suitable for regulation as other material agreed by Consultant too. STANDARDS This Specification is shown for performance styles of Contruction of works suitable with standards in Lao and American. During performance, replacing proposed standards (if any) needed submit to Consultant by EPC General Contractor for agreement and not allow to apply until receive the Consultant acceptance. ‘TESTING AND TESTING EQUIPMENTS, EPC General Contractor will install equipments in the test laboratory at the site to implement the tests according to defines in the design and requirements of Consultants, suit for this Specification. Testing and checking will be implemented not only in laboratory but also at the site. It should implement immediately for Consultant’s requirements. While there is a doubt about test result, Consultant will require testing to quality. Consultant is who exposing last conclusions about test results. Employer will pay CI Design Manager Technical Manager 1a S Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V- Part 1: Specification of Civil Work == expense of tests. If there are any technical errors according to conclusions of Consultant, depending on test result to control then EPC General Contractor should pay for errors and tests Testing standards of materials and construction quality of Nam Mo 2 Hydropower Project are ASTM and CRD, including but not limited to Table 1.1 below: Table 1-1. Ley tent sie Is and construction sa os Solt testing 1_| Humidity ASTM D2216 (2 | Yield limit ASTM D4318 3_| Gradation ASTM D2487 | ASTM D698 4 | Standard compacted rE IsEG] | 5_| Density ASTM D2980 6 | Permeability ‘ASTM D2434 7_| Site density ASTM D1556 B_| Reinforced Steel testing 1_| Tensile and bending ASTM A370 | Material of mortar and concrete I | Cement and mineral additive L_| Density, fineness Fenrir 2 | Standard water volume, setting | ASTM C184 time, volumetric stability ‘ASTM C187 3_ | Humidity | ASTM C188 4 | Content lost when baked ‘SIM Cee 5 Benting and compressing SIM GL 6 | Index of activity intensity ASTM C1240 1 | Aggregate of mortar and concrete (1_| Gradation ASTM C136 (2 | Humidity ASTM C566 | , . ASTM C127 | 2 | Density Volumetric mass ‘ASTM C128 4 | Loose density, porosity ‘ASTM C29 5_| Organic impurity content ‘ASTM C40 6 Content of dust, mud, clay and ASTMCH7 lumps ASTM C142 ASTM C131 7 | Los Angeles Abrasion ‘ASTM C535 The content of long grain, flat [8 | grain ASTM D4791 Cl Design Manager Technical Manager La S Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work Intensity and softening 9 coefficient of original rock ASTM D2938 TIT | Mortar and conerete testing 1_| Slump ASTM C143 2 | Vebe stiffness, density ‘ASTM C1170 Temperature of concrete 3 | Temper ASTM C1064 4 | Volumetric mass ASTM C138 [5 | Water and mortar separation ‘ASTM C232 6 | Air content in concrete mixture ASTM C231 7_ | Setting time ASTM C403 ASTM C39 8 Compressive strength aoe 9. | Elastic Modulus ‘ASTM C469 10 | Tensile strength ‘ASTM C496 11__ Direct tensile strength CRD C64 ASTM C1585 Permeabil 12 | Permeability CR 13 | Concrete mixture flowability ASTM C1437 14 | Initial setting time ‘ASTM C807 15 | Conerete mixture mobility ASTM C939 1.7. TEMPORARY WORKS FOR CONSTRUCTION Temporary works for construction are works used for main works construction purpose only. Afier main works completed, the temporary works will be disposed or maintenanced, repaired to serve the Project Generation in later phase ‘Temporary works include but not limit these item below: — Cofferdam as earth-rock fill structure = Construction roads = Other temporary works Arrangement diagram, main structure, and consequence construction auxiliary works for construction, and relevant problems are shown in design. 1.8. AUXILIARY WORKS AND CAMPS Employer approves size of auxiliary works and camps. Auxiliary and camps will be implement under package. Supervision of construction and checking upon delivery auxiliary works and camps are implemented as bellow: = Auxiliary works: Consultant accept for size of works only, do not accept the detail of works. EPC General Contractor will take responsibility for the quality of auxiliary works. S C I Design Manager Technical Manager Ls Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V- Part 1: Specification of Civil Work 1.9, — Temporary camps: based on approved size, EPC General Contractor executes and the Employer accept and pay based on fact. Consultant does not check and accept the camps of EPC General Contractor. Contructing the auxiliary works and camps must be suite with approved General Construction Layout. Since completed the works, whole of auxiliary works built by EPC General Contractor, except parts are assigned and specific guide will be disposed out of site and hand over all material of them to Employer. EPC General Contractor should ensure safety for affected areas of auxiliary works and restore the natural drainage. POWER, WATER AND COMMUNICATION FOR CONSTRUCTION EPC General Contractor will contruet the power transmission line and substation for construction (including the medium and low voltage system) and take responsibility for this system. EPC General Contractor will contruct the water system for construction and lives in the site and take responsibility this system. EPC General Contractor will co-operate with communication supplier in Lao or Vietnam to build a post office in the construction area. Since completed the Project, whole of power, water supply system (except specific guided parts) will be taken off the site. 1.10. SURVEYING OF EPC CONTRACTOR 1.10.1.Scope of work Employer will hand over to EPC General Contractor the Construction Benchmarks in site. Since received the Construction Benchmarks, EPC General Contractor must take responsibility for saving and maintenance them during construction and use them for surveying. The EPC General Contractor can build additional Construction Benchmarks if necessary. Since completed the Project, EPC General Contractor must hand over these Benchmarks (and additional benchmarks if any) to Employer. 1.10.2.Material and tools EPC General Contractor will supply, maintain, and operate the equipments, tools, and materials suitably for accurately surveying. 1.10.3.Implement the surveying — All surveying will be recorded on the relevant drawing or map and site book according to Consultant's guide and agreement. Republishing drawings and maps is apart of work of EPC General Contractor in the required place. S CI Design Manager Technical Manager Ls Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work Consultant has a right to do check surveying and, degree of accurate, benchmarks and calculating and suitable for design. EPC General Contractor will maintain professional records of all measures at the site, relevant calculations, handwritings, drawings, maps, etc and ready to submit to Consultant based on the requirements. Surveying works at the site or in the office may be added or modified based on the Consultant requirments. Required accurate of triangle control grid * Average closing deviation is not over: 5s * Maximum closing deviation is not over: 10s Required accurate of traverse grid * Allowed closing deviation: 1/3000 * Allowed distance deviation: 1/5000 Required accurate of level grid = Allowed deviation of distance per one kilometer: 1mm. * Allowed closing deviation of measuring forward and backward is 105 (mm) (S is cummulative distance of level calculation parts by kilometer). Allowed deviation of general structures * Plan of location 220mm * Elevation :+20mm Allowed deviation of center defining of inclined tunnel excavation is + 25mm. Allowed deviation of center defining of horizontal tunnel and vertical shaft * Plan of location :+10mm = Elevation :+10mm Allowed deviation of anchor in rock = Location 2 150mm Allowed deviation of consolidation drilling holes, curtain drilling holes, drainage drilling holes: = Location :+£200mm * Depth of drilling holes: + 100mm. Allowed deviation of access road * Location of centerline: 50mm. = Elevation 225mm = Regular deviation :10mm/3m Allowed deviation of bottom elevation of open drainage structures is + 35mm, but not allow the inverted slope at any where. Allowed deviation of bottom elevation of underground drainage structures is 25mm, but not allow the inverted slope at any where. S C I Design Manager Technical Manager i Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work 1.11, SAFETY IN CONSTRUCTION EPC General Contractor should comply the Vietnam standars bellow to ensure required safety in construction: — QCVN 18:2014/BXD “National technical regulation on Safety in Construction” — TCVN 3985:1999 “Acoustics - Allowable noise levels at workplace” — TCVN 4086:1985 “Electrical safety in construction- General requirements” — TCVN 3254:1989 “Fire safety - General requirements” — TCVN 3255:1986 “Explosion safety- General requirements” — TCVN 3146:1986 “Electric welding works - General safety requirements” — TCVN 4245:1986 “Working safety and hy gienes in axetylene and oxygen production and utilization for metal-procesing” — TCVN 3147:1990 “Safety code for loading and unloading works - General requyrements” ~ TCVN 2293:1978 “Wood processing - General safety requirements” — TCVN 2292:1978 “Painting works - General safety requirements” — TCVN 5585:1991 “Diving work - Safety requirements” — TCVN 4744:1989 “Safety requirements in mechanical bases” — TCVN 4586:1997 “Industrial explosion material — Require safety about maintenance, transport and use” = QPVN2-1975 “Safety method rule of pressured cylinder” — TCVN 4244:1986 “Code for the safe technique for crane ~ equipment” — TCVN 5863:1995 “Lifting appliances - Safety requirements for installations and use” EPC General Contractor can be implemented additional methods to ensure safety work in construction which be suitable with construction equipments/technologies if neccesary. EPC General Contractor will be responsibility in contruction safety in any case. S C I Design Manager Technical Manager Le Hoang The Vink Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work CHAPTER 2. EXCAVATION OF OVERGROUND SOIL AND ROCK 2.1. GENERAL EPC General Contractor will execute the work of excavation of overground soil and rock of main constructions in the specified area is shown in the drawing. 2.2. GENERAL REGULATION 2.2.1. Dispose and storage soil and rock from excavation work Excavated soil and rock is transported to the category and storage area, and is specified in design. Maximize excavated rock in the IA; IIB zone at the foundation that is not weathered soil to backfill the foundation of powerhouse, slopes support, and builds in the auxiliary area and crushed into aggregate for conerete. Other part including IB layer is used to fill the cofferdam, and access road, making base of gravel and sand storage area, yard and internal road in the auxiliary area, camps of building and installation. Soil is taken from excavation and quarry which do not contain gravel is used to fill cofferdam and construction road. Therefore, the design of the construction organization methods of excavation of soil and rock is always must consider in the best way for ensuring requirement making the maximize soil and rock from foundation and disposal cover at the quarry. Dispose and storage of soil and rock in the disposal and storage area is stipulated as follow: — Excavated soil and rock at the quarry and foundation is disposed to disposal area shown in the drawing. That will make a ground can use for storage area of rock. = Atthe disposal area, soil and rock are poured from lower to upper to make a ground of disposal area and gradually raise the elevation of the ground. At the disposal area, itis necessary to set bulldozer to level soil and rock in the area. ‘There must not pour soil and rock into disposal area by free fall on the slope from higher elevation to lower elevation. There must not pour rock and soil to storage area or fresh rock into disposal area. After disposing to designed elevation and section, carries out storage soil and rock. The work of dispose and storage soil and rock are conducted at the same time. 2.2.2. Minimize the affects to the outside of excavation area Design of construction organization methods for excavation of soil and rock must minimize the affects to the outside of excavation area to reduce the bad impact to the environment and keep natural stability of slopes. 2.2.3. Drainage work during excavation process Drainage work during excavation must be mentioned in design of construction organization methods of construction drawing to ensure safety for excavated slopes when drainage system is not completed and protect surface of excavated slope. Design Manager Technical Manager 21 SCI Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work 2.2.4. 2.2.5. 2.2.6. 2.2.7. Before excavating foundation, it is necessary to make drainage system and then remove the layer of soil containing vegetation and transporting to storage area. Safety in construction In the document of design of construction organization methods must mention to safety measures during construction according to current stipulations. Safety technique during blasting work must follow the stipulations that are shown in the “item 2.5.4” in this document, EPC General Contractor takes responsibility for safety during construction process and do not depend on the agreement of Consultant about construction drawings of excavation of soil and rock. jit the excavation boundary Excavation work of soil and rock must implement according to shape, border, slope, steps as shown in the Designed drawings. In the boundary of excavation, all of loose soil and rock that could make a slide must move out of excavation boundary. Allowable errors in the overground excavation work Allowable errors in the excavation work is stipulated for each region as below: = On the soil or rock slope is not foundation of concrete structure (except slope and bottom of tailrace) can excavate over or do not reach to the boundary shown in the drawing below 30 cm but not over 50% excavated surface when measure for checking along any cross section in the excavation area beyond the excavation boundary. — Excavated surface (slope and bottom) of tailrace canal can be excavated excessively to 10cm and missing not over 30cm compared with border in the drawing. However, it is not over 30% excavated surface when measure checking along any cross section in the excavation area beyond the excavation boundary. — On the excavated rock slope (slope and bottom) is concrete surface or for supporting must excavate according to border that shown in the designed drawing. Excessive border is not over 15cm compared with design border. At the excavation point in the rock zone is excessive then must be backfilled by concrete. Number of cliffs is not over two cliffs per one square meter of surface and height of cliff is not over 1Sem. Clear surface Excavated surface must be cleared, making smooth edge and transport all excavated material out of the surface, make dry surface before pouring fixed materials above. Foundation surface for concrete structure must be cleared of loose soil and rock, broken rock in the cracks, soil, sand, silt, etc. Design Manager Technical Manager 22 S | Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work 2.2.8. 2.3. 2.3.1, 2.3.2. 23.3. 2.4. 2.4.1. Inspection of excavation work of soil and rock The inspection of excavation volume of soil and rock is implemented according to current stipulation of construction quality management and agreement in the contract. Foundation is made dry and have the approval of acceptance board before continued pouring concrete during 24h. If this duration is overdue, it is necessary to check and conduct the inspection again. For foundation inspection, as-built documents must be submitted to Employer. In the inspection minute, the conclusion of geological specialists about suitable for design drawings must be presented. Technique inspection about foundation preparation quality is in the survey system and the execution of works as designed and in compliance with the requirements of this specification. EXCAVATION OF SOIL Protect surface at the excavation area To avoid surface of excavation is soft, heavy equipments as bulldozer, excavator should not operated in the distance about 30 cm from excavated border or lowest elevation in the excavation area by machine. Slopes of foundation remain during frequent generating duration of powerhouse must be protected to avoid the affects of rain and weathering in not later than 15 days after excavating slope. Clay slopes must be covered by grass slab with thickness of 0.2m. Rainwater drainage system on slope Excavation slopes after inspection will be constructed the rainwater drainage system on the slopes, ditch at the toe and grows grass to protect surface. The work of rainwater drainage system contruction and grows grass on the slopes needs to implement immediately after excavation level between berms is completed. Excessive volume of excavation boundary Excavation items that exceed the allowable limit stated in “item 2.2.6” will have to be repaired. EXCAVATION OF ROCK Excavation methods and protection of rock slope During construction process, the work of removal of weathered soil is conducted by using bulldozer, excavator, and truck to transport disposed soil to disposal area according to design stipulations. Excavation work of foundation in the hard rock strata is implemented according to these methods: — Big blasting, diameter of borehole up to 105mm. — Small blasting, diameter of borehole up to 56mm. Design Manager Technical Manager 23 S | Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work 2.4.2, 2.4.3, — Edge blasting, with diameter of borehole up to 105mm, and spacing of hole are 0.7m. — Cleared by pick hammer Forms of hole and schedule of blasting is designed to meet the requirements: — Minimize the crack and loose material in the excavation surface ~ Excessive volume is as the lowest as possibly. To prevent the slope erosion is caused by rain at the upper edge of slope and intermediate berms need to make drainage ditch and consolidate by stones paving. During construction period, rock slopes must be covered by wire mesh and is anchored in the rock mass to prevent rock falling. Excavate rock in the areas with surface after excavation are not surface of concrete structure Areas where the surface after excavation is not a concrete foundation includes the slope of the dam foundation pit and the slope of the downstream scour hole, the tailrace of powerhouse, the entrance portal area to the auxiliary tunnels. — Entrance to auxiliary tunnels: From the outer part of the tunnel portal area to the section adjacent to the tunnel portal, which is excavated by big blasting to the excavation boundary on the design drawings. The slope above the tunnel portal is excavated into 2 layer, the rock layer above the tunnel portal is excavated by big blasting, the protective excavation layer at the tunnel portal with thickness of 2m and is excavated by small blasting. — The slope of the dam foundation pit, the slope of scour hole in the downstream, the tailrace of powerhouse which is not the foundation of the conerete work will be excavated by big blasting, the bore hole diameter is Jess than 105mm to the excavation boundary on the design drawing for layers IIA, IIB but must conduct edge blasting. Particularly in areas with slopes less than 1:1, the rock layer of 2m close to the excavation boundary must be carried out by small blasting, Excavation in layers IB, IA2 is excavated by small blasting within 2m above the excavation boundary. Excavation of rock in the areas with rock surface after excavation is concrete base With horizontal or incline with slope coefficient of 1:1: — Implement excavation at least is two layer when depth of rock stratum higher than 2m. In there, the last layer (contain layers above slopes) is protection layer with depth not smaller than 2m. — Excavated layers above protection layer are excavated by big blasting. — Protection layer is excavated in two step: Upper step is blasting with small boreholes (small blasting). However, the distance from bottom of borehole to excavation boundary must be less than 30cm. Lower step (remaining rock Design Manager Technical Manager 2-4 S | Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work 2.4.4, 2.4.5. 2.5. 2.5.1. layer near surface foundation) is excavated by pick hammer, and does not use blasting. For incline area with slope coefficient greater than 1 — The excavation work is allowable according to big blasting to excavation boundary that shown in the designed drawing for ILA and IIB layers but needs to edge blasting. Faults and joint treatment Faults and joints are on the rock surface of foundation after excavation that is foundation of concrete structure must be expanded excavation to make slope coefficient of 4:1 or more gentle slope along the joints, faults, clear loose rock to the depth that is not smaller twice length of fault, joints. After clear loose rock, faults and joints are backfilled by concrete to elevation of designed foundation. Treatment work must be implemented according to additional Consultant's requirement (if any). Excessive volume of rock Excavation items that exceed the allowable limit stated in “item 2.2.6” have to be repaired. OVERGROUND EXPLOSION General requirement 2.5.1.1. Primary conditions for explosion EPC General Contractor will not be accepted and used any explosion if there is not any permission of competence authority. EPC General Contractor implements relevant stipulations for using and transport explosion material out and in site according to current stipulations about using and explosion material management of Vietnam and Lao. Explosion material has nitro-glycerin must not be used, EPC General Contractor must prepare the specification to monitor and control the blasting and submit to Consultant for aproval before implementation. 25.1.2, Technical standards for overground explosion Excavation work is implemented by preliminary blasting methods. Therefore, it is necessary to implement according to the requirement of TCVN 9161:2012 “Hydraulic structure - Drilling blast holes - methods in design, construction and acceptance” and TCVN 3255:1986 “Explosion safety - General requirements”. The explosion must be implemented according to approved method statement. Blasting construction must follow QCVN 18:2014/BXD “National technical regulation on Safety in Construction”. During excavation of rock foundation’s concrete structures, it must meet the requirement of keeping the rock base and slopes of the constructions depending on the characteristic of difference structures. Design Manager Technical Manager 25 S | Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part I: Specification of Civil Work 1 ‘Headrace and tailrace | Allowable for increasing natural and added joints ; Not allowance for added joints by effects of TM | Concrete structures | tasting, require protection layer. Blasting work is only implemented when blasting log is made and approved by competent authorities. Blasting log must be executed according to regulations and technical requirements. 2.5.1.3. Regulations for blasting work of foundation Before blasting for IB and IA zone, must implement pilot blasting. Pilot blasting is implemented for optimum mesh blasting and to reduce volume of oversize rock, estimate parameter of edge blasting, and spacing of blasting need to implement according to regulations and technical requirements, Excavation of rock and soil of construction grade II must excavate according to steps with height not over 10m, Distance to design boundary is 2m, then conduct edge drilling with small boreholes. Excavation of soil and rock after explosion is conducted according to design requirement for foundation and must be accepted by the acceptance board after clearing the ground, This work need to be completed before implement other works. Borcholes for edge are set on a plan along length of slope and parallel to each other, estimated by professional drill equipments. Errors of boreholes compared with edge in the plan are not over 1.Sem for Im length of borehole. To protect the edge, explosion holes are drilled far from the edge with the distance equal 15 time of diameter of mine and has volume less than number of explosive holes that far from the edge. ‘The explosive charge in the hole must be very carefully, do not compress and throw charge equipments on the primer bag. Prohibit the use of clumps or combustible materials to plug mine holes. Length of charge hole is according to design blasting log. Length of charge can choose by 25 time of diameter of mine, In the narrow foundation, length can increasing to 30 + 35 time of diameter of mine. After exploding, if there are some mute explosion holes then the commander let implement treatment immediately by exploding auxiliary explosion hole that are drilled parallel and 30cm far from explosion hole. Commander recommends number and location of auxiliary explosion holes. To estimate direction of auxiliary drill hole may be taken material of charge a segment with a length not over 20cm from the inlet of borehole. When making blasting log, need base on feature of specified rock, methods, feature of dynamite using to calculate safety distance between people and equipments from explosion area. For existing construction or equipments that cannot move to other location, it is necessary to have a method to protect this constructions and equipments, or recalculation, reduce the quantity of dynamite Design Manager Technical Manager 26 SCI Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work to ensure for constructions and equipments. When making the explosion blasting log, it need to calculate safety radius of vibrating and airwave and distance of throw of rocks to peoples and equipments. To calculate safety distance from vibrating position during explosion, this formula can be used: Rake VO (m) In which: — Ke: Coefficient depends on properties of rock foundation. + Monolithic rock: K=3 + Jointed rock: K=5 +Gravel mixed Rock: K=7 — a1: coefficient depends on indicator of affected explosion “‘n”: +Ifns0.5 then 01.2 +Ifn=1.0 then o=1.0 +f n=2.0 then o=0.8 — Q Dynamite volume (kg) To ensure safety during calculate the splash distance of rock by explosion,take safety radius Ra(m) can be taken as following table: 200 300 350 100 150, 250 2.0 200 400 500 100 200 350 4.0 300 500 700 150 250 500 6.0 300 600 800 | 150 300 550 Calculation of the safety distance take into account affects of airwave can use this formula: Ras=ks YQ (m) In which: — ks: coefficient depends on conditions of distribution, capacity of explosion, level of damage (while Q<10.000 kg can choose k= 50+150). While choose safety distance, it needs to select the biggest value in the calculation of safety distances of vibrating, and airwave, and the splash of rock. The blasting log is calculated and it is not smaller to these values: — Affix explosion: Rat 2300m — Explosion in small hole: Rat2200m — Explosion in big hole: Rat2200m Design Manager Technical Manager 27 SCI Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work To ensure the safety for dynamite storages, detonator storage according to specific stipulation of current safety regulation for building, maintain, and dynamite using. When explosion near concrete structures or grouted cement area, if the distance from explosion area to this place is smaller than 30m then it is necessary ti have an agreement to Employer. Before explosion, it needs check the safety conditions depends on rate of relevant weight, distance is applied for vibration test. General rule for integrity guarantee of concrete structure is critical velocity of particle or details of concrete structure can refer experience values and velocity do not over these values as following: 0.25 0.50 1.00 1.50 2.50 2.5.2. Design Manager | ‘Technical Manager 28 S | Hoang The Vinh Ngo Vu An | 4.00 If the explosion near earth cofferdam then ensure that the velocity of particle do not over 5 cm/sec. Commander of blasting work and authorized persons will check the blasting performance. To continue blasting, it need to invite surveyor to check the suitable of work to design or blasting log. Result of test must be recorded in the daily construction daily log. Check the blasting work: — After finishing the drilling work, it must measure depth and diameter, and location of borehole according to plan and section. — Checking the result after blasting, pay special attention to areas where mute mines are suspected as well as areas where explosive rock has collapsed — During excavation process, soft rock and soil need to estimate percentage of oversize rock to require treatment as well as check the foundation surface and slope. Afier excavating all the explosive soil, the as-built diagram must be drawn. Affix explosion During blasting to excavate foundation or mine material, there are some rock which have oversize. Therefore, to explosive this big rock, we can use affix explosion method to reduce cost of drilling. — Affix explosions must be flat, and should locate at the flat surface, or hollow position of rock block to reach the maximum exposure. Basic Design Nam Mo 2 Hydropower Project Volume V - Part 2.5.3. 2.5.4, Specification of Civil Work — If using the explosion as plaster material then it must make boxes form in elastic cover and fixed at the specified rock. Using clay soil to cover outer surface of mine. — When exploding, must calculate volume of dynamite enough to break the rock and the particle with the shortest splash distance. — When blasting, rock fragments can have long splash distance, so special attention to calculate the amount of explosives to ensure absolute safety for peoples and equipments. Blasting work for mining at quarry Blasting work for mining at quarry use mainly explosion method with borehole diameter of 105. Base on equipments, transportation for each explosion time, and calculation volume of dynamite for each time to ensure safety according to regulations on safety in blasting work. Mining sequence must follow the regulations of the mining design agency. Quality of blasting work at the quarry must satisfy these conditions: — Explosive soil and rock on layers must be compact, the number of splashes should be minimal, and the transportation route should not be entangled. — The slopes are not convex and there are no hanging stones — Foundation of layer must be explosive, volume of explosion rock must be minimize. = Volume of soil and rock of a layer must enough to ensure for an excavator working continuously during 5 days. Safety technique in explosion The blasting work is conducted according to the requirements of QCVN 18:2014/BXD “National technical regulation on Safety in Construction”, TCVN 9161:2012 “Hydraulic structure - Drilling blast holes, method in design, construction and acceptance” and TCVN 3255:1986 “Explosion safety- General requirements”. The execution of explosion must follow approval method statements. Blasting works can only be carried out when the construction design has been agreed with the Employer, the main designer B and the Contractor according to regulations. Itis strictly forbidden to use clay as a filling in the charged boreholes. Before exploding, there must shut down electricity in work area that impact to explosion. Move peoples and machines to safety place. Communicate exploding time to units, offices working in the building area, drill, and blast unit. Units and officials conduct work at construction sites and executing units for blasting work must notify the time of explosion. During preparation of explosion, it need to communicate to all constractors in the construction area before 24h. Design Manager Technical Manager 2-9 S | Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work Estimate dangerous area of effect of explosion in the method statement and put a dangerous board. Before explosion, must make a signal for explosion notification 3 times when before 15 minutes, 10 minutes, and 5 minutes. This signal must notify for everyone and must have a guardian. Human is not allowed to go to dangerous area at the all access roads to explosion area. During construction process, must usually check the stability of slope, wall of foundation. When slope have a risk of unstable, slope support must be apllied immediately. In addition, usually check the implementation of approval method statements. All of people when work with industrial explosion material must not smoke, and do not allow explosion materials to be impacted, and not drag, push, through boxes has explosion material. Do not strain or cut conductor wire of electricity detonator. Do not use anything to poke the detonator. All technical staffs, worker and relevant people to explosion material and explosion work must be educated and trained, examined according to regulation of Goverment. Miner who do not meet the requirement in the regular examination ot extraordinary examination will be suspended the allowable of mineworker certification. After 02 months, this miner is allowed to attend the examination again. If they still do not meet requirement, their mineworker certification will be withdrawed. When there is some change in the form of explosion, mineworker must be trained about that changed item, After examination and meet the requirement, their certification will be added a new item from the training. After taking a break from the blasting job for more than 1 year, mine worker must be re-examined his knowledge before doing his job. If they meet the requirements, they can continue to do the blasting work. All of worker serve work of explosion must be trained by leader about features and properties of industrial explosion material. When unit uses new industrial explosion material, they also be trained as above. After meeting the requirement, trained person must sign in the book. When using ammonite dynamite as plaster lump, with soft paper cover, if the dynamite is cumulus, use the hands to squeeze it out. Prohibit the use of explosives that have been moistened beyond the standard When making the blasting log, it needs to absolute compliance the regulations about blasting — Diagram of borehole arrangement, quantity and depth of borehole, volume of dynamite fill up each borehole, explosive name and means, material for explosion hole, fill up length and sequence for detonation. — Dangerous radius of detonation is calculated based on splash distance of rock particle for man and machines. Design Manager Technical Manager 2-10 S I Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work — Hidden location of mineworker and other during explosion process — Place to set guard station during explosion process During the time of charging, it just allows responsible people get in the mine area. Everyone who is not involved in the mine charging work must go out the dangerous area or to hidden safety place as guide of guardians and supervision of mine commander. After charging, all of mine charger man must move out of the dangerous area. Only miners are allowed to stay to connect the blasting network and then move to safety place and starting explosion follow the command of mine commander. After explosion process, check the mine area. If it is safety then notify all clear. If detecting (or suspecting) mute mines then need to treat immediately or if this mine cannot be treated immediately, then put a sign board beside mute mine holes. After that, mute mine holes will be treated according to regulation under Commander’s guide. Where mute mines are located, do not do anything else that is not related to the disposal of mute mines. All these events must record in the daily construction book. After exploding to disposal of mute mine, mineworker must check very carefully exploded rock to collect all explosion material of mute mine that bursting. Then allow for implementation of other next works but still have to watch carefully for detection of remained explosion material. Design Manager Technical Manager 211 S | Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume ¥ - Part 1: Specification of Civil Work 3.1. 3.11. 3.1.2. 3.2. 3.2.1. CHAPTER 3. UNDERGROUND EXCAVATION WORK GENERAL Scope of work EPC General Contractor will carry out underground excavation work at places is specified in Design Document. The volume of this work is specified in Design Document. Underground excavation work will include the horizontal, incline and vertical excavation. This works will be done at following areas: — Auxiliary tunnels. — Headrace tunnel, Pressure tunnel and vertical shaft. The total volume of Underground excavation work are relatively great, excavating sections are small, space for construction is narrow and working alignment is long ‘The above works will be applied the Specification as follow. Underground consolidation works are presented in “Chapter 4: Slope protection and slope consolidation work”, installation of reinforced steel, lining steel, tunnel conerete are presented in “Chapter 8: Reinforcement installation” and “Chapter 9: Concrete production and construction” of this “Specifications”. Safety in construction process In construction organization of excavation and underground consolidation, it must ensure safety in construction according to the existing regulations. EPC General Contractor have responsibility for safety in construction process and do not depend on the agreement to Consultant about construction drawing. MATERIAL, EQUIPMENT AND SERVICE SYSTEM General All materials and members, that are fixed in the construction must be new, must follow the relevant regulations in “Specifications” and is accepted by Consultant. All material, equipment, and member are used in Underground excavation work according to requirement of Specifications but which isn’t fixed in the construction, it may be new or used based on the choosen of EPC General Contractor but must have the agreement of Consultant. Air compression or diesel dynamic machine can be used for different works of Underground excavation. When diesel dynamics are operated, EPC General Contractor must ensure provide essential equipment to remove harmful gas as machine’s operating or the BPC General Contractor shall require the Diesel Equipment Supplier for tunnel to demonstrate that the equipment will comply with the requirements of the applicable safety standards as prescribed, Design Manager Technical Manager 3-1 SCI Hoang The Vinh Ngo Vu An Basic Design Nam Mo 2 Hydropower Project Volume V - Part 1: Specification of Civil Work _ a If exhaust system of diesel dynamic is not enough, Consultant can require suspend operation of diesel dynamic or makes necessary methods to repair that system and EPC General Contractor must follow that decision of Consultant. 3.2.2. Ventilation system EPC General Contractor will supplies, installing, maintaining and operate ventilation system. Capacity of system provide enough fresh air in tunnel during work time. ‘Ventilation system may be supplied by constrained method or other combination, including local ventilation. The system must ensure to be enough for all machines, which may be operate, in the underground. Before installing, ventilation system design must be agreed by Consultant, The ventilation system at construction must ensure the following requirements: — 3.0m*/minute fresh air/one person at underground construction. — 3.0m*/minute fresh air/IKW capacity of diesel installed machine or operation equipment at underground construction, taking into account the simultaneous working factor of different equipments. The ventilation system must be arranged so that air is recirculated and as close as possible to the work area, the ventilation pipes must be kept in an airtight condition (no leaks). Oxygen concentration in air is not lower than 17% in volume at underground construction. Dust concentration in air is lower than 1Smg/m? at underground construction, For different types of emissions, the permissible concentration in underground works are listed in Table 3.1. Table 3-1. Permissible content of emission gas in unde ind construction. Dioxide carbon 5000 15000 Monoxide carbon 50 100 Oxide nitric 25 35 Oxide nitrous 3 5 Hydro sulfate 10 15 (Note: Ippm = lom* air/m? volume) Average speed of air in all excavating place is not lower than 0.15mvs. At all time, average temperature with average humidity at underground construction is not higher than 30°C. — Air temperature at all working place is not higher than 32°C. SCI Design Manager Hoang The Vinh Technical Manager Ngo Vu An

You might also like