Professional Documents
Culture Documents
CON 2013.module 4
CON 2013.module 4
managing,
Scheduling and
Jobsite
Planning II
Module 4: Create Project
Schedule
1
Project Managing, Scheduling and Jobsite Planning II
Module 3 Review
Cost Management
PMBOK-Figure 7-1:Project
Cost Management Overview
Project
Budget
Cost
Baseline
Cost
Estimate
Management Project
Cost Baseline
Reserve Budget
Module 4 Agenda
Project Time Management Overview
Estimate Estimate
Plan Time Define Sequence Develop Control
Activity Activity
Management Activities Activities Schedule Schedule
Resources Duration
PMBOK-Figure 6-1:Project
Time Management Overview
PMBOK-Figure 6-17:Project
Time Management Overview
Fundamentals of Scheduling
WBS
Work Package
Activity
Fundamentals of Scheduling
The WBS is a hierarchical decomposition of the total scope of
work to be carried out by the project team to accomplish the
project objectives and create the required deliverables.
The WBS organizes and defines the total scope of the
project, and represents the work specified in the current
approved project scope statement.
Fundamentals of Scheduling
The planned work is contained within the lowest level of WBS
components, which are called work packages.
A work package can be used to group the activities where
work is scheduled and estimated, monitored, and controlled.
In the context of the WBS, work refers to work products or
deliverables that are the result of activity and not to the
activity itself.
Activity is a distinct, scheduled portion of work performed
during the course of a project.
MODULE 4- Create Project Schedule 14
Project Managing, Scheduling and Jobsite Planning II
Fundamentals of Scheduling
Activity Relationships
•Finish to Start (FS)
•Start to Start (SS)
•Finish to Finish (FF)
•Start to Finish (SF)
MODULE 4- Create Project Schedule 16
Project Managing, Scheduling and Jobsite Planning II
Fundamentals of Scheduling
Dependency Determination
• Mandatory
• Discretionary
• External
• Internal
MODULE 4- Create Project Schedule 17
Project Managing, Scheduling and Jobsite Planning II
Fundamentals of Scheduling
Mandatory dependencies are those that are legally or
contractually required or inherent in the nature of the work.
Discretionary dependencies are sometimes referred to as
preferred logic, preferential logic, or soft logic. Discretionary
dependencies are established based on knowledge of best
practices within a particular application area or some unusual
aspect of the project where a specific sequence is desired,
even though there may be other acceptable sequences.
Fundamentals of Scheduling
External dependencies involve a relationship between
project activities and non-project activities.
Internal dependencies involve a precedence relationship
between project activities and are generally inside the project
team’s control.
Fundamentals of Scheduling
Leads & Lags
A lead is the amount of time whereby a successor activity can be advanced
with respect to a predecessor activity.
A lag is the amount of time whereby a successor activity will be delayed with
respect to a predecessor activity.
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 21
Project Managing, Scheduling and Jobsite Planning II
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 22
Project Managing, Scheduling and Jobsite Planning II
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 23
Project Managing, Scheduling and Jobsite Planning II
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 24
Project Managing, Scheduling and Jobsite Planning II
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 25
Project Managing, Scheduling and Jobsite Planning II
Scope of Activities
• Activities must:
– Be described as a separate function such as “formwork for footings”
– Have a labor crew, with attributable crew hours for the activity
– Have a specific duration attached
– Be able to be monitored by comparing planned duration with actual
duration
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 26
Project Managing, Scheduling and Jobsite Planning II
Sequence of Activities
• Sequence types:
– Finish to Start
• Second activity does not start until first is completed
– Start to Start
• Two activities begin at the same time
– Finish to Finish
• Two activities completed at the same time despite differing durations
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 27
FIGURE 12–1
Example Sequence
Comparison
Delmar/Cengage Learning
Duration of Activities
• Activity duration:
– Must be relative to labor hours in the estimate
– Should relate to quantity of work
– Should consider weather concerns
– Should consider item delivery
– May be affected by subcontractor involvement
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 30
Project Managing, Scheduling and Jobsite Planning II
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 31
Project Managing, Scheduling and Jobsite Planning II
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 32
FIGURE 12–3 Schedule Data
Delmar/Cengage Learning
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 34
Project Managing, Scheduling and Jobsite Planning II
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 35
Project Managing, Scheduling and Jobsite Planning II
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 36
Project Managing, Scheduling and Jobsite Planning II
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 37
Project Managing, Scheduling and Jobsite Planning II
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 38
Project Managing, Scheduling and Jobsite Planning II
Cost Account
Analysis
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 39
Project Managing, Scheduling and Jobsite Planning II
Cost Control
Spreadsheet
Summary
• Control of time and cost
– Most important tasks of field management
– Project plan:
• Method for project construction
– Schedule:
• Communications tool of project plan
– Cost control:
• Compares estimated and actual cost
MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 42
Project Managing, Scheduling and Jobsite Planning II
Review
Project Time management processes?
Next Module
Project time and cost control