You are on page 1of 46

Project

managing,
Scheduling and
Jobsite
Planning II
Module 4: Create Project
Schedule
1
Project Managing, Scheduling and Jobsite Planning II

Module 3 Review
 Cost Management

 Cost Estimating & Budgeting

 Project Budget Components

MODULE 4- Create Project Schedule 2


Project Managing, Scheduling and Jobsite Planning II

PMBOK-Figure 7-1:Project
Cost Management Overview

MODULE 4- Create Project Schedule 3


Project Managing, Scheduling and Jobsite Planning II

Project Budget Components

MODULE 4- Create Project Schedule 4


Project Managing, Scheduling and Jobsite Planning II

Cost Baseline & Project Budget

MODULE 4- Create Project Schedule 5


Project Managing, Scheduling and Jobsite Planning II

Project
Budget
Cost
Baseline
Cost
Estimate

MODULE 4- Create Project Schedule 6


Project Managing, Scheduling and Jobsite Planning II

Cost Contingency Cost


Estimate Reserve Baseline

Management Project
Cost Baseline
Reserve Budget

MODULE 4- Create Project Schedule 7


Project Managing, Scheduling and Jobsite Planning II

Module 4 Agenda
 Project Time Management Overview

 Create Project Schedule

 Construction Project Schedule

 Cost Control Overview

MODULE 4- Create Project Schedule 8


Project Managing, Scheduling and Jobsite Planning II

Project Time Management Overview


• Project Time Management includes the processes required to
manage the timely completion of the project.

Estimate Estimate
Plan Time Define Sequence Develop Control
Activity Activity
Management Activities Activities Schedule Schedule
Resources Duration

MODULE 4- Create Project Schedule 9


Project Managing, Scheduling and Jobsite Planning II

PMBOK-Figure 6-1:Project
Time Management Overview

MODULE 4- Create Project Schedule 10


Project Managing, Scheduling and Jobsite Planning II

PMBOK-Figure 6-17:Project
Time Management Overview

MODULE 4- Create Project Schedule 11


Project Managing, Scheduling and Jobsite Planning II

Fundamentals of Scheduling

WBS

Work Package

Activity

MODULE 4- Create Project Schedule 12


Project Managing, Scheduling and Jobsite Planning II

Fundamentals of Scheduling
The WBS is a hierarchical decomposition of the total scope of
work to be carried out by the project team to accomplish the
project objectives and create the required deliverables.
The WBS organizes and defines the total scope of the
project, and represents the work specified in the current
approved project scope statement.

MODULE 4- Create Project Schedule 13


Project Managing, Scheduling and Jobsite Planning II

Fundamentals of Scheduling
The planned work is contained within the lowest level of WBS
components, which are called work packages.
A work package can be used to group the activities where
work is scheduled and estimated, monitored, and controlled.
In the context of the WBS, work refers to work products or
deliverables that are the result of activity and not to the
activity itself.
Activity is a distinct, scheduled portion of work performed
during the course of a project.
MODULE 4- Create Project Schedule 14
Project Managing, Scheduling and Jobsite Planning II

MODULE 4- Create Project Schedule 15


Project Managing, Scheduling and Jobsite Planning II

Fundamentals of Scheduling

Activity Relationships
•Finish to Start (FS)
•Start to Start (SS)
•Finish to Finish (FF)
•Start to Finish (SF)
MODULE 4- Create Project Schedule 16
Project Managing, Scheduling and Jobsite Planning II

Fundamentals of Scheduling

Dependency Determination
• Mandatory
• Discretionary
• External
• Internal
MODULE 4- Create Project Schedule 17
Project Managing, Scheduling and Jobsite Planning II

Fundamentals of Scheduling
Mandatory dependencies are those that are legally or
contractually required or inherent in the nature of the work.
Discretionary dependencies are sometimes referred to as
preferred logic, preferential logic, or soft logic. Discretionary
dependencies are established based on knowledge of best
practices within a particular application area or some unusual
aspect of the project where a specific sequence is desired,
even though there may be other acceptable sequences.

MODULE 4- Create Project Schedule 18


Project Managing, Scheduling and Jobsite Planning II

Fundamentals of Scheduling
External dependencies involve a relationship between
project activities and non-project activities.
Internal dependencies involve a precedence relationship
between project activities and are generally inside the project
team’s control.

MODULE 4- Create Project Schedule 19


Project Managing, Scheduling and Jobsite Planning II

Fundamentals of Scheduling
Leads & Lags
 A lead is the amount of time whereby a successor activity can be advanced
with respect to a predecessor activity.
 A lag is the amount of time whereby a successor activity will be delayed with
respect to a predecessor activity.

MODULE 4- Create Project Schedule 20


Project Managing, Scheduling and Jobsite Planning II

Introduction to construction project schedule&cost


• Project duration and cost
– Major project parameters
– Contractor controls
• Means of monitoring control effectiveness
– Construction scheduling
– Computerized cost control accounting

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 21
Project Managing, Scheduling and Jobsite Planning II

Project Duration Control


• Owner’s date for project completion
– Establishes project parameters and maximum duration
– Rarely has a direct relationship to actual time needed
– Based on owner’s need for the facility
• Not expected construction duration

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 22
Project Managing, Scheduling and Jobsite Planning II

Project Duration Control


• Owner’s date for project completion
– A school project will be required to be completed in July or August, allowing
time for equipment move-in so that the facility can be in operation in early
September at the start of the school year.
– A retailer will want its facility completed in late summer to be able to stock
goods and train personnel prior to the holiday retail season.
– These completion dates establish a maximum construction duration, but
the contractor may be able to complete the facility prior to the completion
date.

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 23
Project Managing, Scheduling and Jobsite Planning II

Project Duration Control (cont’d.)


• Project plan considerations:
– Activities, duration, and sequencing
– Interrelationship of subcontract activities
– Equipment requirements
– Utilization of subcontractors
– Field management personnel, crew size, and project staffing of
craftspeople

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 24
Project Managing, Scheduling and Jobsite Planning II

Project Duration Control (cont’d.)


– Anticipated material delivery dates
– Weather planning: anticipated lost days, weather protection
– Anticipation of delays: other contracts, labor strikes, and owner-based
changes
– Alternative solutions to sequencing

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 25
Project Managing, Scheduling and Jobsite Planning II

Scope of Activities
• Activities must:
– Be described as a separate function such as “formwork for footings”
– Have a labor crew, with attributable crew hours for the activity
– Have a specific duration attached
– Be able to be monitored by comparing planned duration with actual
duration

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 26
Project Managing, Scheduling and Jobsite Planning II

Sequence of Activities
• Sequence types:
– Finish to Start
• Second activity does not start until first is completed
– Start to Start
• Two activities begin at the same time
– Finish to Finish
• Two activities completed at the same time despite differing durations

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 27
FIGURE 12–1
Example Sequence
Comparison
Delmar/Cengage Learning

Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 28


FIGURE 12–2 Example
Sequence Cost
Comparison
Delmar/Cengage Learning

Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 29


Project Managing, Scheduling and Jobsite Planning II

Duration of Activities
• Activity duration:
– Must be relative to labor hours in the estimate
– Should relate to quantity of work
– Should consider weather concerns
– Should consider item delivery
– May be affected by subcontractor involvement

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 30
Project Managing, Scheduling and Jobsite Planning II

The Project Schedule


• Manifestation of the project plan
– Written or graphical depiction
• Communication tool to share project plan
– Many forms
• bar charts, Gantt charts
• Network charts
– Method varies depending on target

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 31
Project Managing, Scheduling and Jobsite Planning II

The Project Schedule (cont’d.)


• Majority are done with scheduling or project management software
– Full scheduling software
• Calculates critical path
• Considers dependencies of predecessors
– Updating is necessary
• Periodic basis
• Variety of methods

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 32
FIGURE 12–3 Schedule Data
Delmar/Cengage Learning

Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 33


Project Managing, Scheduling and Jobsite Planning II

Project Cost Control


• Actual cost versus estimated cost comparison during the project
– Accurate measure of success
– Opportunity to adjust factors involved
• Computer software programs
– Variety available
• Cost accounting and control

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 34
Project Managing, Scheduling and Jobsite Planning II

Project Cost Control


• Cost control can range from a simple collection of costs for labor,
material, equipment, and subcontractors, organized in projects or
subprojects, to detailed compilation and analysis for every work activity.
• The overhead cost of cost control increases as the detailed collection
and expected reporting detail increases. Therefore, contractors need to
determine how much information they want from their cost systems,
according to their managers and the needs of their risk partners, such as
banks and bonding companies, and compare this to the staff costs to
compile this information.
• Cost control involves construction expertise from construction engineers
or project controls specialists as well as accounting staff.

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 35
Project Managing, Scheduling and Jobsite Planning II

Project Cost Control (cont’d.)


• Cost control can:
– Determine profitability
– Determine the source of overruns
– Compare actual to estimated costs
– Use comparison data for historical data
– Use analysis of problems for “lessons learned” that can be applied to future
work
– Compare costs to baseline estimate

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 36
Project Managing, Scheduling and Jobsite Planning II

Realistic Cost Control Activities


• Major concerns:
– Ensuring cost control accounts are of proper scope
– Relating crew assignment directly to cost control activity
– Results can be used as historical cost data
– Field personnel should realize the purpose

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 37
Project Managing, Scheduling and Jobsite Planning II

Realistic Cost Control Activities (cont’d.)


– Comparison of actual and estimated cost should be done immediately
– Feedback system should be in place
– Thank crews when tasks are accomplished under estimated cost
– Encourage crews when costs are over the estimate

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 38
Project Managing, Scheduling and Jobsite Planning II

Cost Account
Analysis

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 39
Project Managing, Scheduling and Jobsite Planning II

Time & Material


Sheet

MODULE 4- Create Project Schedule 40


Project Managing, Scheduling and Jobsite Planning II

Cost Control
Spreadsheet

MODULE 4- Create Project Schedule 41


Project Managing, Scheduling and Jobsite Planning II

Summary
• Control of time and cost
– Most important tasks of field management
– Project plan:
• Method for project construction
– Schedule:
• Communications tool of project plan
– Cost control:
• Compares estimated and actual cost

MODULE 4- Create Project Schedule Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 42
Project Managing, Scheduling and Jobsite Planning II

Review
 Project Time management processes?

 How to create project schedule?

 Construction Project Schedule?

 Importance of Cost control?

MODULE 4- Create Project Schedule 43


Project Managing, Scheduling and Jobsite Planning II

Topic for Oral Presentation


 Define all activities delivered by all sub-contractors needed for
each phase of a typical project:
 For each phase of project, list all the subcontractors

 Define activities that are delivered by subcontractors

MODULE 4- Create Project Schedule 44


Project Managing, Scheduling and Jobsite Planning II

Next Module
 Project time and cost control

MODULE 4- Create Project Schedule 45


Project Managing, Scheduling and Jobsite Planning II

Thank you for your Attention

MODULE 4- Create Project Schedule 46

You might also like