Basic EOQ Model

Data
D= 6000 (Demand /year)
K= $ 115.00 (Setup cost)
h= $ 4.20 (unit holding cost)
p= $ 7.50 (unit shortage cost)
L= 9.00 (lead time in days)
WD = 250.00 (working days per year)

Decision
Q= 1000 (before solver - set Q=1000)
Result
Reorder Point 216.00

Annual Setup Cost $ 690.00


Annual Holding Cost $ 2,100.00
Total Variable Cost $ 2,790.00
Basic EOQ Model

Data
D= 6000 (Demand /year)
K= $ 115.00 (Setup cost)
h= $ 4.20 (unit holding cost)
p= $ 7.50 (unit shortage cost)
L= 9.00 (lead time in days)
WD = 250.00 (working days per year)

Decision
Q= 573.21150421 (after solver - GRG Nonlinear method)
Result
Reorder Point 216.00

Annual Setup Cost $ 1,203.74


Annual Holding Cost $ 1,203.74
Total Variable Cost $ 2,407.49
Basic EOQ Model

Data
D= 6000 (Demand /year)
K= $ 115.00 (Setup cost)
h= $ 4.20 (unit holding cost)
p= $ 7.50 (unit shortage cost)
L= 9.00 (lead time in days)
WD = 250.00 (working days per year)

Decision
Q= 573.21150422 Optimal Q formula: SQRT(2KD/h)
Result
Reorder Point 216.00

Annual Setup Cost $ 1,203.74


Annual Holding Cost $ 1,203.74
Total Variable Cost $ 2,407.49