construction period to mitigate the environmental impact and ensure compliance with any
requirements of any environmental statements and/or environmental impact assessment and
ensuring compliance with any planning conditions relating to the design and construction of the
site.
The Bidder shall prepare project specific draft of Health and Safety Management Plan and
procedures, and HSE Policy which shall, among others, demonstrate Bidder’s commitment to the
highest standards of personal and general safety during design, construction, commissioning and
operation of the Plant to ensure the safety of all workers and the public. Providing of historical
health and safety records in form of LTIFR (Lost-Time Injury Frequency Rate), Fatal Accident
Rate (FAR) and Total Recordable Case Frequency (TRCF) for the last five (5) years is required.
Provision of documentation/reports covering all fatality cases is required for the same period of
time.
The project specific draft Health and Safety Management Plan and procedures, including all
specific Health and Safety requirements shall follow recommendations as set out by the national
Health and Safety legislative framework, as well as international best practice. The Health and
Safety Management Plan and procedures shall consider the most recent national and OSHA
standards (as published on https://www.osha.gov/law-regs.html).
The Project Company shall prepare and maintain a Health and Safety Management Plan and
procedures separately for the construction period including commissioning, and the operation
period, including a description and analysis of the main health and safety risks and the measures
to be taken to minimize the risk of worker’s and public safety.
The following requirements shall be addressed in the Health and Safety Management Plan, and
procedures as a minimum: