This document provides a status update of precast production as of January 31, 2024 for the TSWREI School and College Bachupally project. It details the agreed and cast quantities for various building elements across five levels - plinth, ground, first, second, and terrace. As of the report date, 677 pieces had been cast against an agreed total of 1690, leaving 1013 pieces still due to be cast. Walls had the highest agreed quantity at 843 pieces but 209 were still outstanding, while beams, columns, staircases and hollow core slabs all had significant quantities still to be cast.
This document provides a status update of precast production as of January 31, 2024 for the TSWREI School and College Bachupally project. It details the agreed and cast quantities for various building elements across five levels - plinth, ground, first, second, and terrace. As of the report date, 677 pieces had been cast against an agreed total of 1690, leaving 1013 pieces still due to be cast. Walls had the highest agreed quantity at 843 pieces but 209 were still outstanding, while beams, columns, staircases and hollow core slabs all had significant quantities still to be cast.
This document provides a status update of precast production as of January 31, 2024 for the TSWREI School and College Bachupally project. It details the agreed and cast quantities for various building elements across five levels - plinth, ground, first, second, and terrace. As of the report date, 677 pieces had been cast against an agreed total of 1690, leaving 1013 pieces still due to be cast. Walls had the highest agreed quantity at 843 pieces but 209 were still outstanding, while beams, columns, staircases and hollow core slabs all had significant quantities still to be cast.
Precast Project of TSWREI SCHOOL AND COLLEGE BACHUPALLY
PRECAST PRODUCTION STATUS AS ON 31.01.2024
Sl No. ELEMENTS AGT.QTY CASTED DUE 1 PLINTH LEVEL a. WALLS 168 168 0 b. COLUMNS 22 22 0 c. BEAMS 21 21 0 2 GROUND FLOOR a. WALLS 162 154 8 b. COLUMNS 22 0 22 c. BEAMS 48 0 48 d. STAIR CASE 3 0 3 e. HCS 191 0 191 3 FIRST FLOOR a. WALLS 189 170 19 b. COLUMNS 18 0 18 c. BEAMS 48 0 48 d. STAIR CASE 3 0 3 e. HCS 189 0 189 4 SECOND FLOOR a. WALLS 193 142 51 b. COLUMNS 18 0 18 c. BEAMS 48 0 48 d. STAIR CASE 3 0 3 e. HCS 189 0 189 5 TERRACE a. PARAPET WAL 89 0 89 b. MUMTY WALLS 42 0 42 c. COLUMNS 18 0 18 d. STAIR CASE 3 0 3 e. BEAMS 3 0 3 f. HCS 0 0 0 GRAND TOTALS ITEM CASTING QNTY CASTED DUE a. WALLS 843 634 209 b. BEAMS 168 21 147 c. COLUMNS 98 22 76 d. STAIR CASE 12 0 12 e. HCS 569 0 569 TOTAL 1690 677 1013
Note : ABOVE INFORMATION IS PURELY FOR ANALYSIS
PURPOSE ONLY ,ABOVE DATA IS NOT OFFICIAL STATEMENT OF NAC OR ANY ORGANIZATION*** Data sent by U Sachin ,PMC,NAC,Field Engi