Precast Project of TSWREI SCHOOL AND COLLEGE BACHUPALLY

PRECAST PRODUCTION STATUS AS ON 31.01.2024


Sl No. ELEMENTS AGT.QTY CASTED DUE
1 PLINTH LEVEL
a. WALLS 168 168 0
b. COLUMNS 22 22 0
c. BEAMS 21 21 0
2 GROUND FLOOR
a. WALLS 162 154 8
b. COLUMNS 22 0 22
c. BEAMS 48 0 48
d. STAIR CASE 3 0 3
e. HCS 191 0 191
3 FIRST FLOOR
a. WALLS 189 170 19
b. COLUMNS 18 0 18
c. BEAMS 48 0 48
d. STAIR CASE 3 0 3
e. HCS 189 0 189
4 SECOND FLOOR
a. WALLS 193 142 51
b. COLUMNS 18 0 18
c. BEAMS 48 0 48
d. STAIR CASE 3 0 3
e. HCS 189 0 189
5 TERRACE
a. PARAPET WAL 89 0 89
b. MUMTY WALLS 42 0 42
c. COLUMNS 18 0 18
d. STAIR CASE 3 0 3
e. BEAMS 3 0 3
f. HCS 0 0 0
GRAND TOTALS
ITEM CASTING QNTY CASTED DUE
a. WALLS 843 634 209
b. BEAMS 168 21 147
c. COLUMNS 98 22 76
d. STAIR CASE 12 0 12
e. HCS 569 0 569
TOTAL 1690 677 1013

Note : ABOVE INFORMATION IS PURELY FOR ANALYSIS


PURPOSE ONLY ,ABOVE DATA IS NOT OFFICIAL
STATEMENT OF NAC OR ANY ORGANIZATION***
Data sent by U Sachin ,PMC,NAC,Field Engi