You are on page 1of 1

Method statement for LSC

Electrical Duration, Duration,


# Activity Equipment, tools required Manpower HSE SPV Electrical SPV Helper
technician days hrs
1 Open PTW, put isolation according LOTO procedure 1 1 1 0.25 2
2 Carry out toolbox talk meeting 6 1 1 2 3 0.0625 0.5
3 Open covers of concrete cable trenches, cable trays, etc. Portable crane 3 1 1 1 1 1 8
Preparation for excavation, includes removing growls and
4 Shovels 6 1 1 2 3 1 8
secure them for mixing with soil.
Shovels, Mattock, Crowbar,
5 Manually excavation cable trench 75 meters 6 1 1 2 3 6 48
Polyethylene plastic sheet 80 meters
6 Cables pulling preparation, includes conduit installation Hand tools, drill bit, electrical drill 3 1 1 1 1 2 16
7 Cables pulling Fishing cable 6 1 1 2 3 3 24
8 Installation of MCBs, DIN rails, terminal blocks, etc. Hand tools 3 1 1 2 1 8
9 Cable glands installation Hand tools 3 1 1 2 3 24
10 Check cables wires insulation before termination Insulation meter 3 1 1 2 0.5 4
11 Cable wires termination Hand tools 3 1 1 2 2 16
12 Check conductivity of cable PE wires Microohm resistance meter 3 1 1 2 0.5 4
13 Check cables wires insulation after termination Insulation meter 3 1 1 2 0.5 4
14 Functional test 3 1 1 2 0.5 4
15 Close covers of concrete cable trenches, cable trays, etc. Portable crane 3 1 1 1 1 1 8
16 Backfill cable trenches Shovels 6 1 1 2 3 2 16

17 Growls will be restored back in few month after backfilling Shovels 6 1 1 2 3 2 16

Total 26.3125 210.5

Caterpillar: Confidential Green


#

You might also like