38.534hrs.=
4.817days
Overall Cumulative Rainfall up-to-date
Delays and Disruption for September, October November and December 2023
Month. Day Date Start End Duration
September Instruction 003 contractor was instructed to halt works on pad 4 days
casting on 22/09/2023 to 26th /09/2023 due sub surface water
Total 4 days
October UCE EXAMINATIONS
17.10.2023 Tuesday 8:00am 2:00pm 8 hrs
19.10.2023 Thursday 8:00am 2:00pm 8 hrs
20.10.2023 Friday 8:00am 2:00pm 8 hrs
Total rain 24 hrs = 3days
7days
Overall Cumulative days for delays up-to-date
summary of rainfall, Delays and Disruption for September, October, November and
December 2023.
summary of rainfall, Delays and Disruption