APPENDIX TO AGREEMENT
Hooloomann & Associates Ltd
APPENDIX TO AGREEMENT
The following information must be completed before the tender is submitted.
Sub-Clause
Documents forming the Contract
Listed in the order of priority 1.1.1
Document Document
(delete if not applicable) Identification
(a) The Agreement Section 2.1
(b) The Letter of Acceptance and Annexes Section 2.3
(c) The addenda (if any)
(d) Particular Conditions Section 3.2
(e) General Conditions Section 3.1
(f) The Specification Section 4.0
(g) The Drawings As listed in Section 5.1
(h) The Contractor’s Offer Section 2.3
(i) The bill of quantities Section 6.0
(j) The Schedules and any other
documents forming part of the Contract
Time for Completion 1.1.9 189 Calendar days
Law of the Contract 1.4 Law of the Republic of Mauritius
Language 1.5 English
Provision of Site 2.1 On the Commencement
Date
Authorised person 3.1 OGA (Mauritius) Ltd, 14,
Edouard Laurent Street, Port
Louis, Mauritius
Name and address of Employer’s Representative (if 3.2 ARUP of 2 Gardens of Bagatelle -
known) Bagatelle Office Park, Bagatelle;
Hooloomann & Associates Ltd
of 90, St Jean Road, Quatre
Bornes, Mauritius; GMF Ltd of
Avenue Victoria, Quatre Bornes,
Mauritius.
M:\Bella Casa\Tender Document - Jan 2018\Editable\Tender Document - Bella Casa.docx Page 1 of 3
Hooloomann & Associates Ltd
Sub-
Clause
Performance security (if any):
Amount 4.4 Ten (10%) of the accepted
Contract amount
Form 4.4 Section 3.2 Annex A
Requirements for Contractor’s Design (if 5.1 Not applicable
any)
Programme:
Time for submission 7.2 Within 14 Days of the
Commencement Date.
Form of programme 7.2 Not applicable
Amount payable due to failure 7.4 0.30% of the sum stated in the
To complete agreement per day or part
thereof up to a maximum of 10%
of sum stated in the Agreement
Period for notifying defects 9.1 365 days calculated from the
& 11.5 date stated in the notice under
Sub-Clause 8.2
Variation Procedures
Daywork rates 10.2 Not applicable
Valuation of the works 11.1 Lump Sum
Percentage of value of Materials 11.2 Materials - 80%
and Plant Plant – 0%
Percentage of retention 11.3 5%
Currency of payment 11.7 Mauritian Rupees
Insurances: 14.1
M:\Bella Casa\Tender Document - Jan 2018\Editable\Tender Document - Bella Casa.docx Page 2 of 3
Hooloomann & Associates Ltd
Type of cover Amount of cover Insuring Party
The Works, The sum stated in the
Materials, Plant and Agreement plus 15% Contractor
fees
Contractor’s Full replacement cost. Contractor
Equipment
Third Party-injury to
persons and damage MUR5,000,000 Contractor
to property
__________________
Workers Contractor
__________________ __________________
Other cover
__________________ __________________
M:\Bella Casa\Tender Document - Jan 2018\Editable\Tender Document - Bella Casa.docx Page 3 of 3