PROJECT: CONSTRUCTION OF COMMERCIAL BUILDING

LOCATION: BACOLOD CITY, NEGROS OCCIDENTAL

ITEM NO: D.VII.c DESCRIPTION: Elevator


QUANTITY: 1 lot

MATERIALS
NO DESCRIPTION QTY UNIT UNIT COST SUB-TOTAL

1 Machineroomless Elevator Assembly 1 unit 4,025,000.00 ₱ 4,025,000.00


complete with Shaf Rails, Fittings,
Accessories, Interior Finishes,
UPS, and Safety Features
2 Electrical Works 1 lot 172,500.00 ₱ 172,500.00
3 Consumables 1 lot 34,500.00 ₱ 34,500.00

A. TOTAL MATERIAL COST ₱ 4,232,000.00

LABOR
NO DESCRIPTION QTY UNIT UNIT COST SUB-TOTAL

1 Labor for Installation 1 lot 2,161,006.77 ₱ 2,161,006.77

B. TOTAL LABOR COST ₱ 2,161,006.77

EQUIPMENT
NO DESCRIPTION QTY UNIT UNIT COST SUB-TOTAL

C. TOTAL EQUIPMENT COST ₱ -

TOTAL COSTS
D. TOTAL DIRECT COST A+B+C ₱ 6,393,006.77
E. OCM 8% of D. ₱ 511,440.54
F. PROFIT 8% of D. ₱ 511,440.54
G. TOTAL DIRECT & INDIRECT COST ₱ 7,415,887.85
H. TAX 7% of G. ₱ 519,112.15
I. TOTAL COST ₱ 7,935,000.00