You are on page 1of 39

CONTRACT NAME: PROPOSED FOUR-STOREY RESIDENTIAL BUILDING WITH

ROOF DECK
CONTRACT LOCATION: BRGY. 55-A BARIT PANDAN LAOAG CITY, ILOCOS NORTE

DETAILED ESTIMATE

ITEM NUMBER: 1
DESCRIPTION: PERMITS AND CLEARANCE
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Permits and Clearance 1 lot 80,000.00 ₱80,000.00
Sub - total: ₱80,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Sub - total: ₱3,000.00
Total Direct Cost: ₱83,000.00

ITEM NUMBER: 2
DESCRIPTION: PROJECT BILLBOARD/SIGN BOARD
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Project Billboard/Sign Board 1 lot 3,000.00 ₱3,000.00
Sub - total: ₱3,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 1 1000 ₱1,000.00
Foreman 1 1 700 ₱700.00
Labor 2 1 450 ₱900.00
Sub - total: ₱2,600.00
Total Direct Cost: ₱5,600.00

ITEM NUMBER: 3
DESCRIPTION: CLEARING AND GRUBBING
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Backhoe w/ Breaker 1 3 1,998.00 ₱5,994.00
Bulldozer 1 3 3,379.00 ₱10,137.00
Truck 1 3 1,420.00 ₱4,260.00
Sub - total: ₱20,391.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
₱0.00
Sub - total: ₱0.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Operators 3 3 650 ₱5,850.00
Labor 3 3 450 ₱4,050.00
Sub - total: ₱12,900.00
Total Direct Cost: ₱33,291.00
ITEM NUMBER: 4
DESCRIPTION: EXCAVATION
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Backhoe w/ Breaker 2 3 1,998.00 ₱11,998.00
Bulldozer D6 2 3 3,379.00 ₱20,274.00
Payloader 2 3 1,733.00 ₱10,398.00
Sub - total: ₱42,660.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
₱0.00
Sub - total: ₱0.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Operators 3 3 650 ₱5,850.00
Labor 3 3 450 ₱4,050.00
Sub - total: ₱12,900.00
Total Direct Cost: ₱55,560.00

ITEM NUMBER: 5
DESCRIPTION: EMBANKMENT (BACKFILL AND GRAVEL BEDDING)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Vibratory Plate Compactor 2 3 1,300.00 ₱7,800.00
Water Pump 1 3 680.00 ₱2,040.00
Sub - total: ₱9,840.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Embankment 619.76 cu.m 250.00 ₱154,940.00
Backfill Gravel Bedding 305.24 cu.m 650.00 ₱198,406.00
Sub - total: ₱353,346.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Operators 3 3 650 ₱5,850.00
Labor 3 3 450 ₱4,050.00
Sub - total: ₱12,900.00
Total Direct Cost: ₱376,086.00
ITEM NUMBER: 6
DESCRIPTION: CONCRETE WORKS (COLUMN FOOTING)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 2 2 1,318.00 ₱5,272.00
Portable Concrete Vibrator 4 2 600.00 ₱4,800.00
Water Pump 2 2 680.00 ₱2,720.00
Sub - total: ₱12,792.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 313 bags 280.00 ₱87,640.00
Vol. of sand 18 cu.m 1,150.00 ₱20,700.00
Vol. of gravel 35 cu.m 1,930.00 ₱67,550.00
Sub - total: ₱175,890.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 650 ₱3,900.00
Labor 5 2 450 ₱4,500.00
Foreman 1 2 700 ₱1,400.00
Skilled 5 2 600 ₱6,000.00
Sub - total: ₱17,800.00
Total Direct Cost: ₱206,482.00
ITEM NUMBER: 7
DESCRIPTION: CONCRETE WORKS (WALL FOOTING)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 2 2 1,318.00 ₱5,272.00
Portable Concrete Vibrator 4 2 600.00 ₱4,800.00
Water Pump 2 2 680.00 ₱2,720.00
Sub - total: ₱12,792.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 67 bags 280.00 ₱3,360.00
Vol. of sand 3.68 cu.m 1,150.00 ₱1,150.00
Vol. of gravel 7.35 cu.m 1,930.00 ₱3,860.00
Sub - total: ₱8,370.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱29,266.00

ITEM NUMBER: 8
DESCRIPTION: CONCRETE WORKS (COLUMN, GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 70 bags 280.00 ₱19,600.00
Vol. of sand 4 cu.m 1,150.00 ₱4,600.00
Vol. of gravel 8 cu.m 1,930.00 ₱15,440.00
Sub - total: ₱39,640.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱60,536.00

ITEM NUMBER: 9
DESCRIPTION: CONCRETE WORKS (COLUMN, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 70 bags 280.00 ₱19,600.00
Vol. of sand 4 cu.m 1,150.00 ₱4,600.00
Vol. of gravel 8 cu.m 1,930.00 ₱15,440.00
Sub - total: ₱39,640.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱60,536.00

ITEM NUMBER: 10
DESCRIPTION: CONCRETE WORKS (COLUMN, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 70 bags 280.00 ₱19,600.00
Vol. of sand 4 cu.m 1,150.00 ₱4,600.00
Vol. of gravel 8 cu.m 1,930.00 ₱15,440.00
Sub - total: ₱39,640.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱60,536.00

ITEM NUMBER: 11
DESCRIPTION: CONCRETE WORKS (COLUMN, FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 55 bags 280.00 ₱14,840.00
Vol. of sand 3 cu.m 1,150.00 ₱3,450.00
Vol. of gravel 6 cu.m 1,930.00 ₱11,580.00
Sub - total: ₱29,870.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱50,766.00
ITEM NUMBER: 12
DESCRIPTION: CONCRETE WORKS (GRADE BEAM)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 64 bags 280.00 ₱17,920.00
Vol. of sand 4 cu.m 1,150.00 ₱4,600.00
Vol. of gravel 8 cu.m 1,930.00 ₱15,440.00
Sub - total: ₱37,960.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱58,856.00

ITEM NUMBER: 13
DESCRIPTION: CONCRETE WORKS (BEAM, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 93 bags 280.00 ₱26,040.00
Vol. of sand 6 cu.m 1,150.00 ₱6,900.00
Vol. of gravel 11 cu.m 1,930.00 ₱21,230.00
Sub - total: ₱54,170.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱75,066.00

ITEM NUMBER: 14
DESCRIPTION: CONCRETE WORKS (BEAM, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 93 bags 280.00 ₱26,040.00
Vol. of sand 6 cu.m 1,150.00 ₱6,900.00
Vol. of gravel 11 cu.m 1,930.00 ₱21,230.00
Sub - total: ₱54,170.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱75,066.00

ITEM NUMBER: 15
DESCRIPTION: CONCRETE WORKS (FOURTH, ROOF DECK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 93 bags 280.00 ₱26,040.00
Vol. of sand 6 cu.m 1,150.00 ₱6,900.00
Vol. of gravel 11 cu.m 1,930.00 ₱21,230.00
Sub - total: ₱54,170.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱75,066.00

ITEM NUMBER: 16
DESCRIPTION: CONCRETE WORKS (BEAM, ROOF DECK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 80 bags 280.00 ₱22,400.00
Vol. of sand 5 cu.m 1,150.00 ₱5,750.00
Vol. of gravel 9 cu.m 1,930.00 ₱17,370.00
Sub - total: ₱45,520.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱66,416.00
ITEM NUMBER: 17
DESCRIPTION: CONCRETE WORKS (SLAB, GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 108 bags 280.00 ₱30,240.00
Vol. of sand 6 cu.m 1,150.00 ₱6,900.00
Vol. of gravel 12 cu.m 1,930.00 ₱23,160.00
Sub - total: ₱60,300.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱81,196.00

ITEM NUMBER: 18
DESCRIPTION: CONCRETE WORKS (SLAB, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 108 bags 280.00 ₱30,240.00
Vol. of sand 6 cu.m 1,150.00 ₱6,900.00
Vol. of gravel 12 cu.m 1,930.00 ₱23,160.00
Sub - total: ₱60,300.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱81,196.00

ITEM NUMBER: 19
DESCRIPTION: CONCRETE WORKS (SLAB, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 108 bags 280.00 ₱30,240.00
Vol. of sand 6 cu.m 1,150.00 ₱6,900.00
Vol. of gravel 12 cu.m 1,930.00 ₱23,160.00
Sub - total: ₱60,300.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱81,196.00

ITEM NUMBER: 20
DESCRIPTION: CONCRETE WORKS (SLAB, FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 108 bags 280.00 ₱30,240.00
Vol. of sand 6 cu.m 1,150.00 ₱6,900.00
Vol. of gravel 12 cu.m 1,930.00 ₱23,160.00
Sub - total: ₱60,300.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱81,196.00

ITEM NUMBER: 21
DESCRIPTION: CONCRETE WORKS (SLAB, ROOF DECK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 108 bags 280.00 ₱30,240.00
Vol. of sand 6 cu.m 1,150.00 ₱6,900.00
Vol. of gravel 12 cu.m 1,930.00 ₱23,160.00
Sub - total: ₱60,300.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱81,196.00
ITEM NUMBER: 22
DESCRIPTION: CONCRETE WORKS (STAIRS, GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 6 bags 280.00 ₱1,680.00
Vol. of sand 1 cu.m 1,150.00 ₱1,150.00
Vol. of gravel 1 cu.m 1,930.00 ₱1,930.00
Sub - total: ₱4,760.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱25,656.00

ITEM NUMBER: 23
DESCRIPTION: CONCRETE WORKS (STAIRS, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 6 bags 280.00 ₱1,680.00
Vol. of sand 1 cu.m 1,150.00 ₱1,150.00
Vol. of gravel 1 cu.m 1,930.00 ₱1,930.00
Sub - total: ₱4,760.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱25,656.00

ITEM NUMBER: 24
DESCRIPTION: CONCRETE WORKS (STAIRS, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 6 bags 280.00 ₱1,680.00
Vol. of sand 1 cu.m 1,150.00 ₱1,150.00
Vol. of gravel 1 cu.m 1,930.00 ₱1,930.00
Sub - total: ₱4,760.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱25,656.00

ITEM NUMBER: 25
DESCRIPTION: CONCRETE WORKS (STAIRS, FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 6 bags 280.00 ₱1,680.00
Vol. of sand 1 cu.m 1,150.00 ₱1,150.00
Vol. of gravel 1 cu.m 1,930.00 ₱1,930.00
Sub - total: ₱4,760.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱25,656.00

ITEM NUMBER: 26
DESCRIPTION: MASONRY WORKS (GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 6 1,318.00 ₱7,908.00
Sub - total: ₱7,908.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
6" CHB 1405 pcs 18.00 ₱25,290.00
4" CHB 1032 pcs 12.00 ₱12,384.00
# of cement 258 bags 280.00 ₱72,240.00
Vol. of sand 24 cu.m 1,150.00 ₱27,600.00
12mm dia. x 6m 368 pcs 305.00 ₱112,240.00
Tie wire #16 17 kg 100.00 ₱1,700.00
Sub - total: ₱249,754.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 6 1000 ₱6,000.00
Foreman 1 6 650 ₱3,900.00
Mason 5 6 500 ₱15,000.00
Helper 5 6 400 ₱12,000.00
Sub - total: ₱36,900.00
Total Direct Cost: ₱294,562.00
ITEM NUMBER: 27
DESCRIPTION: MASONRY WORKS (SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 6 1,318.00 ₱7,908.00
Sub - total: ₱7,908.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
6" CHB 1434 pcs 18.00 ₱25,812.00
4" CHB 1032 pcs 12.00 ₱12,384.00
# of cement 170 bags 280.00 ₱47,600.00
Vol. of sand 23 cu.m 1,150.00 ₱26,450.00
12mm dia. x 6m 366 pcs 305.00 ₱111,630.00
Tie wire #16 17 kg 100.00 ₱1,700.00
Sub - total: ₱223,876.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 6 1000 ₱6,000.00
Foreman 1 6 650 ₱3,900.00
Mason 5 6 500 ₱15,000.00
Helper 5 6 400 ₱12,000.00
Sub - total: ₱36,900.00
Total Direct Cost: ₱268,684.00

ITEM NUMBER: 28
DESCRIPTION: MASONRY WORKS (THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 6 1,318.00 ₱7,908.00
Sub - total: ₱7,908.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
6" CHB 1434 pcs 18.00 ₱25,812.00
4" CHB 1032 pcs 12.00 ₱12,384.00
# of cement 170 bags 280.00 ₱47,600.00
Vol. of sand 23 cu.m 1,150.00 ₱26,450.00
12mm dia. x 6m 366 pcs 305.00 ₱111,630.00
Tie wire #16 17 kg 100.00 ₱1,700.00
Sub - total: ₱223,876.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 6 1000 ₱6,000.00
Foreman 1 6 650 ₱3,900.00
Mason 5 6 500 ₱15,000.00
Helper 5 6 400 ₱12,000.00
Sub - total: ₱36,900.00
Total Direct Cost: ₱268,684.00
ITEM NUMBER: 29
DESCRIPTION: MASONRY WORKS (FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 6 1,318.00 ₱7,908.00
Sub - total: ₱7,908.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
6" CHB 1434 pcs 18.00 ₱25,812.00
4" CHB 1032 pcs 12.00 ₱12,384.00
# of cement 170 bags 280.00 ₱47,600.00
Vol. of sand 23 cu.m 1,150.00 ₱26,450.00
12mm dia. x 6m 366 pcs 305.00 ₱111,630.00
Tie wire #16 17 kg 100.00 ₱1,700.00
Sub - total: ₱223,876.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 6 1000 ₱6,000.00
Foreman 1 6 650 ₱3,900.00
Mason 5 6 500 ₱15,000.00
Helper 5 6 400 ₱12,000.00
Sub - total: ₱36,900.00
Total Direct Cost: ₱268,684.00

ITEM NUMBER: 30
DESCRIPTION: RSB WORKS (COLUMN FOOTING)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
16mm dia. x 6m 103 pcs 540.00 ₱55,620.00
Tie wire #16 5 kg 100.00 ₱500.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱56,520.00

C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱89,735.00

ITEM NUMBER: 31
DESCRIPTION: RSB WORKS (WALL FOOTING)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
12mm dia. x 6m 28 pcs 300.00 ₱8,400.00
Tie wire #16 2 kg 100.00 ₱200.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱9,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱42,215.00

ITEM NUMBER: 32
DESCRIPTION: RSB WORKS (GRADE BEAM)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
16mm dia. x 6m 96 pcs 540.00 ₱51,840.00
Tie wire #16 12 kg 100.00 ₱1,200.00
10mm dia. x 6m (Stirrups) 612 pcs 215.00 ₱131,580.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱185,020.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱218,235.00

ITEM NUMBER: 33
DESCRIPTION: RSB WORKS (BEAM, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
16mm dia. x 6m 116 pcs 540.00 ₱62,640.00
Tie wire #16 14 kg 100.00 ₱1,400.00
10mm dia. x 6m (Stirrups) 735 pcs 215.00 ₱158,025.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱222,465.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱255,680.00

ITEM NUMBER: 34
DESCRIPTION: RSB WORKS (BEAM, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
16mm dia. x 6m 116 pcs 540.00 ₱62,640.00
Tie wire #16 14 kg 100.00 ₱1,400.00
10mm dia. x 6m (Stirrups) 735 pcs 215.00 ₱158,025.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱222,465.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱255,680.00
ITEM NUMBER: 35
DESCRIPTION: RSB WORKS (BEAM, FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
16mm dia. x 6m 116 pcs 540.00 ₱62,640.00
Tie wire #16 14 kg 100.00 ₱1,400.00
10mm dia. x 6m (Stirrups) 735 pcs 215.00 ₱158,025.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱222,465.00

C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱255,680.00

ITEM NUMBER: 36
DESCRIPTION: RSB WORKS (BEAM, ROOF DECK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
16mm dia. x 6m 116 pcs 540.00 ₱62,640.00
Tie wire #16 14 kg 100.00 ₱1,400.00
10mm dia. x 6m (Stirrups) 735 pcs 215.00 ₱158,025.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱222,465.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱255,680.00

ITEM NUMBER: 37
DESCRIPTION: RSB WORKS (COLUMN, GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
16mm dia. x 6m 96 pcs 540.00 ₱51,840.00
Tie wire #16 4 kg 100.00 ₱400.00
10mm dia. x 6m (Stirrups) 104 pcs 215.00 ₱22,360.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱75,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱108,215.00

ITEM NUMBER: 38
DESCRIPTION: RSB WORKS (COLUMN, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
16mm dia. x 6m 96 pcs 540.00 ₱51,840.00
Tie wire #16 4 kg 100.00 ₱400.00
10mm dia. x 6m (Stirrups) 104 pcs 215.00 ₱22,360.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱75,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱108,215.00

ITEM NUMBER: 39
DESCRIPTION: RSB WORKS (COLUMN, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
16mm dia. x 6m 96 pcs 540.00 ₱51,840.00
Tie wire #16 4 kg 100.00 ₱400.00
10mm dia. x 6m (Stirrups) 104 pcs 215.00 ₱22,360.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱75,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱108,215.00

ITEM NUMBER: 40
DESCRIPTION: RSB WORKS (COLUMN, FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
16mm dia. x 6m 96 pcs 540.00 ₱51,840.00
Tie wire #16 4 kg 100.00 ₱400.00
10mm dia. x 6m (Stirrups) 104 pcs 215.00 ₱22,360.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱75,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱108,215.00

ITEM NUMBER: 41
DESCRIPTION: RSB WORKS (SLAB, GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
10mm dia. x 6m 106 pcs 215.00 ₱22,790.00
Tie wire #16 4 kg 100.00 ₱400.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱23,590.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱56,805.00

ITEM NUMBER: 42
DESCRIPTION: RSB WORKS (SLAB, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
10mm dia. x 6m 212 pcs 215.00 ₱45,580.00
Tie wire #16 14 kg 100.00 ₱1,400.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱47,380.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱80,595.00
ITEM NUMBER: 43
DESCRIPTION: RSB WORKS (SLAB, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
10mm dia. x 6m 212 pcs 215.00 ₱45,580.00
Tie wire #16 14 kg 100.00 ₱1,400.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱47,380.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱80,595.00

ITEM NUMBER: 44
DESCRIPTION: RSB WORKS (SLAB, FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
10mm dia. x 6m 212 pcs 215.00 ₱45,580.00
Tie wire #16 14 kg 100.00 ₱1,400.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱47,380.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱80,595.00

ITEM NUMBER: 45
DESCRIPTION: RSB WORKS (SLAB, ROOF DECK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
10mm dia. x 6m 212 pcs 215.00 ₱45,580.00
Tie wire #16 14 kg 100.00 ₱1,400.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱47,380.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled (Installation) 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱80,595.00

ITEM NUMBER: 46
DESCRIPTION: RSB WORKS (STAIRS, GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
12mm dia. x 6m 28 pcs 305.00 ₱8,540.00
10mm dia. x 6m 36 pcs 215.00 ₱7,740.00
Tie wire #16 4 kg 100.00 ₱400.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱17,080.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Skilled (Installation) 5 3 500 ₱7,500.00
Sub - total: ₱17,700.00
Total Direct Cost: ₱38,495.00

ITEM NUMBER: 47
DESCRIPTION: RSB WORKS (STAIRS, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
12mm dia. x 6m 28 pcs 305.00 ₱8,540.00
10mm dia. x 6m 36 pcs 215.00 ₱7,740.00
Tie wire #16 4 kg 100.00 ₱400.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱17,080.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Skilled (Installation) 5 3 500 ₱7,500.00
Sub - total: ₱17,700.00
Total Direct Cost: ₱38,495.00

ITEM NUMBER: 48
DESCRIPTION: RSB WORKS (STAIRS, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
12mm dia. x 6m 28 pcs 305.00 ₱8,540.00
10mm dia. x 6m 36 pcs 215.00 ₱7,740.00
Tie wire #16 4 kg 100.00 ₱400.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱17,080.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Skilled (Installation) 5 3 500 ₱7,500.00
Sub - total: ₱17,700.00
Total Direct Cost: ₱38,495.00

ITEM NUMBER: 49
DESCRIPTION: RSB WORKS (STAIRS, FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 5 321.00 ₱1,605.00
Bar Bender 1 5 422.00 ₱2,110.00
Sub - total: ₱3,715.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
12mm dia. x 6m 28 pcs 305.00 ₱8,540.00
10mm dia. x 6m 36 pcs 215.00 ₱7,740.00
Tie wire #16 4 kg 100.00 ₱400.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱17,080.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Skilled (Installation) 5 3 500 ₱7,500.00
Sub - total: ₱17,700.00
Total Direct Cost: ₱38,495.00
ITEM NUMBER: 50
DESCRIPTION: TILING WORKS (GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Portable Tile Cutter 1 2 1,200.00 ₱2,400.00
Sub - total: ₱2,400.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
60 x 60 glazed floor tiles 157 pcs 210.00 ₱32,970.00
30 x 60 glazed floor tiles 271 pcs 122.00 ₱33,062.00
30 x 30 unglazed floor tiles 361 pcs 52.00 ₱18,772.00
Cement Mortar 12 bags 280.00 ₱3,360.00
White Cement 66 kg 650.00 ₱42,900.00
Adhesive 15 bags 350.00 ₱5,250.00
Cutting Blade 1 pcs 250.00 ₱250.00
Sub - total: ₱136,564.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Foreman 1 2 650 ₱1,300.00
Laborer 5 2 350 ₱3,500.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱11,800.00
Total Direct Cost: ₱150,764.00
ITEM NUMBER: 51
DESCRIPTION: TILING WORKS (SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Portable Tile Cutter 1 2 1,200.00 ₱2,400.00
Sub - total: ₱2,400.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
60 x 60 glazed floor tiles 157 pcs 210.00 ₱32,970.00
30 x 60 glazed floor tiles 271 pcs 122.00 ₱33,062.00
30 x 30 unglazed floor tiles 361 pcs 52.00 ₱18,772.00
Cement Mortar 12 bags 280.00 ₱3,360.00
White Cement 66 kg 650.00 ₱42,900.00
Adhesive 15 bags 350.00 ₱5,250.00
Cutting Blade 1 pcs 250.00 ₱250.00
Sub - total: ₱136,564.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Foreman 1 2 650 ₱1,300.00
Laborer 5 2 350 ₱3,500.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱11,800.00
Total Direct Cost: ₱150,764.00

ITEM NUMBER: 52
DESCRIPTION: TILING WORKS (THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Portable Tile Cutter 1 2 1,200.00 ₱2,400.00
Sub - total: ₱2,400.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
60 x 60 glazed floor tiles 157 pcs 210.00 ₱32,970.00
30 x 60 glazed floor tiles 271 pcs 122.00 ₱33,062.00
30 x 30 unglazed floor tiles 361 pcs 52.00 ₱18,772.00
Cement Mortar 12 bags 280.00 ₱3,360.00
White Cement 66 kg 650.00 ₱42,900.00
Adhesive 15 bags 350.00 ₱5,250.00
Cutting Blade 1 pcs 250.00 ₱250.00
Sub - total: ₱136,564.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Foreman 1 2 650 ₱1,300.00
Laborer 5 2 350 ₱3,500.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱11,800.00
Total Direct Cost: ₱150,764.00

ITEM NUMBER: 53
DESCRIPTION: TILING WORKS (FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Portable Tile Cutter 1 2 1,200.00 ₱2,400.00
Sub - total: ₱2,400.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
60 x 60 glazed floor tiles 157 pcs 210.00 ₱32,970.00
30 x 60 glazed floor tiles 271 pcs 122.00 ₱33,062.00
30 x 30 unglazed floor tiles 361 pcs 52.00 ₱18,772.00
Cement Mortar 12 bags 280.00 ₱3,360.00
White Cement 66 kg 650.00 ₱42,900.00
Adhesive 15 bags 350.00 ₱5,250.00
Cutting Blade 1 pcs 250.00 ₱250.00
Sub - total: ₱136,564.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Foreman 1 2 650 ₱1,300.00
Laborer 5 2 350 ₱3,500.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱11,800.00
Total Direct Cost: ₱150,764.00

ITEM NUMBER: 54
DESCRIPTION: PAINTING WORKS (GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Acrylic Concrete Primer Sealer 13 gallons 800.00 ₱10,400.00
Acrylic Semi-Gloss Latex Paint 13 gallons 800.00 ₱10,400.00
Acrylic Topcoat 13 gallons 800.00 ₱10,400.00
Paint Roller Set 10 pcs 150.00 ₱1,500.00
Sub - total: ₱32,700.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Painter 5 3 400 ₱6,000.00
Sub - total: ₱9,000.00
Total Direct Cost: ₱41,700.00

ITEM NUMBER: 55
DESCRIPTION: PAINTING WORKS (GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Acrylic Concrete Primer Sealer 13 gallons 800.00 ₱10,400.00
Acrylic Semi-Gloss Latex Paint 13 gallons 800.00 ₱10,400.00
Acrylic Topcoat 13 gallons 800.00 ₱10,400.00
Paint Roller Set 10 pcs 150.00 ₱1,500.00
Sub - total: ₱32,700.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Painter 5 3 400 ₱6,000.00
Sub - total: ₱9,000.00
Total Direct Cost: ₱41,700.00

ITEM NUMBER: 56
DESCRIPTION: PAINTING WORKS (THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Acrylic Concrete Primer Sealer 13 gallons 800.00 ₱10,400.00
Acrylic Semi-Gloss Latex Paint 13 gallons 800.00 ₱10,400.00
Acrylic Topcoat 13 gallons 800.00 ₱10,400.00
Paint Roller Set 10 pcs 150.00 ₱1,500.00
Sub - total: ₱32,700.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Painter 5 3 400 ₱6,000.00
Sub - total: ₱9,000.00
Total Direct Cost: ₱41,700.00

ITEM NUMBER: 57
DESCRIPTION: PAINTING WORKS (FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Acrylic Concrete Primer Sealer 13 gallons 800.00 ₱10,400.00
Acrylic Semi-Gloss Latex Paint 13 gallons 800.00 ₱10,400.00
Acrylic Topcoat 13 gallons 800.00 ₱10,400.00
Paint Roller Set 10 pcs 150.00 ₱1,500.00
Sub - total: ₱32,700.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Painter 5 3 400 ₱6,000.00
Sub - total: ₱9,000.00
Total Direct Cost: ₱41,700.00

ITEM NUMBER: 58
DESCRIPTION: FORMWORKS (TIE BEAM)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Cutting Machine 1 3 2,000.00 ₱6,000.00
Sub - total: ₱6,000.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Lumber 2in x 3in x 8ft 99 pcs 132.00 ₱13,068.00
Phenolic Plywood 3/4in 28 sheet(s) 1,180.00 ₱33,040.00
#2 1/2 CW Nails 2 kg 100.00 ₱200.00
#1 Finishing Nails 1 kg 160.00 ₱160.00
Sub - total: ₱46,468.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱69,418.00

ITEM NUMBER: 59
DESCRIPTION: FORMWORKS (BEAM, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Cutting Machine 1 3 2,000.00 ₱6,000.00
Sub - total: ₱6,000.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Lumber 2in x 3in x 8ft 784 pcs 132.00 ₱103,488.00
Phenolic Plywood 3/4in 112 sheet(s) 1,180.00 ₱132,160.00
#2 1/2 CW Nails 20 kg 100.00 ₱2,000.00
#1 Finishing Nails 10 kg 160.00 ₱1,600.00
Sub - total: ₱239,248.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱262,198.00

ITEM NUMBER: 60
DESCRIPTION: FORMWORKS (BEAM, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Cutting Machine 1 3 2,000.00 ₱6,000.00
Sub - total: ₱6,000.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Lumber 2in x 3in x 8ft 784 pcs 132.00 ₱103,488.00
Phenolic Plywood 3/4in 112 sheet(s) 1,180.00 ₱132,160.00
#2 1/2 CW Nails 20 kg 100.00 ₱2,000.00
#1 Finishing Nails 10 kg 160.00 ₱1,600.00
Sub - total: ₱239,248.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱262,198.00

ITEM NUMBER: 61
DESCRIPTION: FORMWORKS (BEAM, FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Cutting Machine 1 3 2,000.00 ₱6,000.00
Sub - total: ₱6,000.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Lumber 2in x 3in x 8ft 784 pcs 132.00 ₱103,488.00
Phenolic Plywood 3/4in 112 sheet(s) 1,180.00 ₱132,160.00
#2 1/2 CW Nails 20 kg 100.00 ₱2,000.00
#1 Finishing Nails 10 kg 160.00 ₱1,600.00
Sub - total: ₱239,248.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱262,198.00
ITEM NUMBER: 62
DESCRIPTION: FORMWORKS (BEAM, ROOF DECK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Cutting Machine 1 3 2,000.00 ₱6,000.00
Sub - total: ₱6,000.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Lumber 2in x 3in x 8ft 784 pcs 132.00 ₱103,488.00
Phenolic Plywood 3/4in 112 sheet(s) 1,180.00 ₱132,160.00
#2 1/2 CW Nails 20 kg 100.00 ₱2,000.00
#1 Finishing Nails 10 kg 160.00 ₱1,600.00
Sub - total: ₱239,248.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱262,198.00

ITEM NUMBER: 63
DESCRIPTION: FORMWORKS (COLUMN, GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Cutting Machine 1 3 2,000.00 ₱6,000.00
Sub - total: ₱6,000.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Lumber 2in x 3in x 10ft 176 pcs 165.00 ₱29,040.00
Phenolic Plywood 3/4in 30 sheet(s) 1,180.00 ₱35,400.00
#2 1/2 CW Nails 6 kg 100.00 ₱600.00
#1 Finishing Nails 3 kg 160.00 ₱480.00
Sub - total: ₱65,520.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱88,470.00

ITEM NUMBER: 64
DESCRIPTION: FORMWORKS (COLUMN, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Cutting Machine 1 3 2,000.00 ₱6,000.00
Sub - total: ₱6,000.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Lumber 2in x 3in x 10ft 176 pcs 165.00 ₱29,040.00
Phenolic Plywood 3/4in 30 sheet(s) 1,180.00 ₱35,400.00
#2 1/2 CW Nails 6 kg 100.00 ₱600.00
#1 Finishing Nails 3 kg 160.00 ₱480.00
Sub - total: ₱65,520.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱88,470.00

ITEM NUMBER: 65
DESCRIPTION: FORMWORKS (COLUMN, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Cutting Machine 1 3 2,000.00 ₱6,000.00
Sub - total: ₱6,000.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Lumber 2in x 3in x 10ft 176 pcs 165.00 ₱29,040.00
Phenolic Plywood 3/4in 30 sheet(s) 1,180.00 ₱35,400.00
#2 1/2 CW Nails 6 kg 100.00 ₱600.00
#1 Finishing Nails 3 kg 160.00 ₱480.00
Sub - total: ₱65,520.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱88,470.00

ITEM NUMBER: 66
DESCRIPTION: FORMWORKS (COLUMN, FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Cutting Machine 1 3 2,000.00 ₱6,000.00
Sub - total: ₱6,000.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Lumber 2in x 3in x 10ft 176 pcs 165.00 ₱29,040.00
Phenolic Plywood 3/4in 30 sheet(s) 1,180.00 ₱35,400.00
#2 1/2 CW Nails 6 kg 100.00 ₱600.00
#1 Finishing Nails 3 kg 160.00 ₱480.00
Sub - total: ₱65,520.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱88,470.00

ITEM NUMBER: 67
DESCRIPTION: SCAFFOLDINGS (COLUMN, GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft (vertical) 168 pcs 132.00 ₱22,176.00
2in x 2in x 8ft (hori & braces)1181 pcs 88.00 ₱103,928.00
#4 CW Nails 33 kg 100.00 ₱3,300.00
Sub - total: ₱129,404.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱146,354.00

ITEM NUMBER: 68
DESCRIPTION: SCAFFOLDINGS (COLUMN, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft (vertical) 168 pcs 132.00 ₱22,176.00
2in x 2in x 8ft (hori & braces)1181 pcs 88.00 ₱103,928.00
#4 CW Nails 33 kg 100.00 ₱3,300.00
Sub - total: ₱129,404.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱146,354.00

ITEM NUMBER: 69
DESCRIPTION: SCAFFOLDINGS (COLUMN, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft (vertical) 168 pcs 132.00 ₱22,176.00
2in x 2in x 8ft (hori & braces)1181 pcs 88.00 ₱103,928.00
#4 CW Nails 33 kg 100.00 ₱3,300.00
Sub - total: ₱129,404.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱146,354.00

ITEM NUMBER: 70
DESCRIPTION: SCAFFOLDINGS (COLUMN, FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft (vertical) 168 pcs 132.00 ₱22,176.00
2in x 2in x 8ft (hori & braces)1181 pcs 88.00 ₱103,928.00
#4 CW Nails 33 kg 100.00 ₱3,300.00
Sub - total: ₱129,404.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱146,354.00

ITEM NUMBER: 71
DESCRIPTION: SCAFFOLDINGS (BEAM, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft (vertical) 368 pcs 132.00 ₱48,576.00
2in x 2in x 8ft (hori) 430 pcs 88.00 ₱37,840.00
#4 CW Nails 20 kg 100.00 ₱2,000.00
Sub - total: ₱88,416.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱105,366.00

ITEM NUMBER: 72
DESCRIPTION: SCAFFOLDINGS (BEAM, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft (vertical) 368 pcs 132.00 ₱48,576.00
2in x 2in x 8ft (hori) 430 pcs 88.00 ₱37,840.00
#4 CW Nails 20 kg 100.00 ₱2,000.00
Sub - total: ₱88,416.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱105,366.00
ITEM NUMBER: 73
DESCRIPTION: SCAFFOLDINGS (FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft (vertical) 368 pcs 132.00 ₱48,576.00
2in x 2in x 8ft (hori) 430 pcs 88.00 ₱37,840.00
#4 CW Nails 20 kg 100.00 ₱2,000.00
Sub - total: ₱88,416.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱105,366.00

ITEM NUMBER: 74
DESCRIPTION: SCAFFOLDINGS (BEAM, ROOF DECK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft (vertical) 368 pcs 132.00 ₱48,576.00
2in x 2in x 8ft (hori) 430 pcs 88.00 ₱37,840.00
#4 CW Nails 20 kg 100.00 ₱2,000.00
Sub - total: ₱88,416.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱105,366.00

ITEM NUMBER: 75
DESCRIPTION: SCAFFOLDINGS (FLOORING, SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft 410 pcs 132.00 ₱54,120.00
#4 CW Nails 10 kg 100.00 ₱1,000.00
Sub - total: ₱55,120.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱72,070.00

ITEM NUMBER: 76
DESCRIPTION: SCAFFOLDINGS (FLOORING, THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft 410 pcs 132.00 ₱54,120.00
#4 CW Nails 10 kg 100.00 ₱1,000.00
Sub - total: ₱55,120.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱72,070.00

ITEM NUMBER: 77
DESCRIPTION: SCAFFOLDINGS (FLOORING, FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft 410 pcs 132.00 ₱54,120.00
#4 CW Nails 10 kg 100.00 ₱1,000.00
Sub - total: ₱55,120.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱72,070.00

ITEM NUMBER: 78
DESCRIPTION: SCAFFOLDINGS (FLOORING, ROOF DECK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
LUMBER:
2in x 3in x 8ft 410 pcs 132.00 ₱54,120.00
#4 CW Nails 10 kg 100.00 ₱1,000.00
Sub - total: ₱55,120.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Carpenter 5 3 450 ₱6,750.00
Sub - total: ₱16,950.00
Total Direct Cost: ₱72,070.00

ITEM NUMBER: 79
DESCRIPTION: ELECTRICAL WORKS (GROUND FLOOR) (LUMP SUM)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Electrical Works 120 sq.m 850.00 ₱102,000.00
Sub - total: ₱102,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Electrical Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Sub - total: ₱17,000.00
Total Direct Cost: ₱119,000.00
ITEM NUMBER: 80
DESCRIPTION: ELECTRICAL WORKS (SECOND FLOOR) (LUMP SUM)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Electrical Works 120 sq.m 850.00 ₱102,000.00
Sub - total: ₱102,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Electrical Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Sub - total: ₱17,000.00
Total Direct Cost: ₱119,000.00

ITEM NUMBER: 81
DESCRIPTION: ELECTRICAL WORKS (THIRD FLOOR) (LUMP SUM)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Electrical Works 120 sq.m 850.00 ₱102,000.00
Sub - total: ₱102,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Electrical Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Sub - total: ₱17,000.00
Total Direct Cost: ₱119,000.00
ITEM NUMBER: 82
DESCRIPTION: ELECTRICAL WORKS (FOURTH FLOOR) (LUMP SUM)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Electrical Works 120 sq.m 850.00 ₱102,000.00
Sub - total: ₱102,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Electrical Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Sub - total: ₱17,000.00
Total Direct Cost: ₱119,000.00

ITEM NUMBER: 83
DESCRIPTION: PLUMBING WORKS (GROUND FLOOR) (LUMP SUM)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Plumbing Works 13.72 sq.m 10,000.00 ₱137,200.00
Sub - total: ₱137,200.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Master Plumber 1 1 1000 ₱1,000.00
Foreman 1 1 650 ₱650.00
Laborer 5 1 350 ₱1,750.00
Sub - total: ₱3,400.00
Total Direct Cost: ₱277,800.00

ITEM NUMBER: 84
DESCRIPTION: PLUMBING WORKS (SECOND FLOOR) (LUMP SUM)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Plumbing Works 13.72 sq.m 10,000.00 ₱137,200.00
Sub - total: ₱137,200.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Master Plumber 1 1 1000 ₱1,000.00
Foreman 1 1 650 ₱650.00
Laborer 5 1 350 ₱1,750.00
Sub - total: ₱3,400.00
Total Direct Cost: ₱277,800.00

ITEM NUMBER: 85
DESCRIPTION: PLUMBING WORKS (THIRD FLOOR) (LUMP SUM)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Plumbing Works 13.72 sq.m 10,000.00 ₱137,200.00
Sub - total: ₱137,200.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Master Plumber 1 1 1000 ₱1,000.00
Foreman 1 1 650 ₱650.00
Laborer 5 1 350 ₱1,750.00
Sub - total: ₱3,400.00
Total Direct Cost: ₱277,800.00

ITEM NUMBER: 86
DESCRIPTION: PLUMBING WORKS (FOURTH FLOOR) (LUMP
SUM) A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Plumbing Works 13.72 sq.m 10,000.00 ₱137,200.00
Sub - total: ₱137,200.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Master Plumber 1 1 1000 ₱1,000.00
Foreman 1 1 650 ₱650.00
Laborer 5 1 350 ₱1,750.00
Sub - total: ₱3,400.00
Total Direct Cost: ₱277,800.00

ITEM NUMBER: 87
DESCRIPTION: DOORS (GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Panel Door 5 pcs 6,500.00 ₱32,500.00
PVC Sliding Door 2 pcs 2,725.00 ₱5,450.00
Door Knob 7 pcs 350.00 ₱2,450.00
Sub - total: ₱40,400.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 1 1000 ₱1,000.00
Skilled 5 1 500 ₱2,500.00
Sub - total: ₱3,500.00
Total Direct Cost: ₱43,900.00

ITEM NUMBER: 88
DESCRIPTION: DOORS (SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Panel Door 4 pcs 6,500.00 ₱26,000.00
PVC Sliding Door 2 pcs 2,725.00 ₱5,450.00
Door Knob 6 pcs 350.00 ₱2,100.00
Sub - total: ₱33,550.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 1 1000 ₱1,000.00
Skilled 5 1 500 ₱2,500.00
Sub - total: ₱3,500.00
Total Direct Cost: ₱37,050.00

ITEM NUMBER: 89
DESCRIPTION: DOORS (THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Panel Door 4 pcs 6,500.00 ₱26,000.00
PVC Sliding Door 2 pcs 2,725.00 ₱5,450.00
Door Knob 6 pcs 350.00 ₱2,100.00
Sub - total: ₱33,550.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 1 1000 ₱1,000.00
Skilled 5 1 500 ₱2,500.00
Sub - total: ₱3,500.00
Total Direct Cost: ₱37,050.00

ITEM NUMBER: 90
DESCRIPTION: DOORS (FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Panel Door 4 pcs 6,500.00 ₱26,000.00
PVC Sliding Door 2 pcs 2,725.00 ₱5,450.00
Door Knob 6 pcs 350.00 ₱2,100.00
Sub - total: ₱33,550.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 1 1000 ₱1,000.00
Skilled 5 1 500 ₱2,500.00
Sub - total: ₱3,500.00
Total Direct Cost: ₱37,050.00

ITEM NUMBER: 91
DESCRIPTION: WINDOWS (GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Fixed Window (1.22mx0.61m) 1.49 sq.m 510.00 ₱759.90
Sliding Window (1.22mx1.8m) 8.78 sq.m 6,206.00 ₱54,488.68
Fixed Window (1.22mx1m) 2.44 sq.m 510.00 ₱1,244.40
Fixed Window (1.83mx0.915m) 3.35 sq.m 510.00 ₱1,708.50
Fixed Window (0.61mx1.8m) 2.2 sq.m 510.00 ₱1,122.00
Fixed Window (0.61mx0.41m) 0.5 sq.m 510.00 ₱255.00
Sub - total: ₱59,578.48
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 1 1000 ₱1,000.00
Skilled 5 1 500 ₱2,500.00
Sub - total: ₱3,500.00
Total Direct Cost: ₱63,078.48

ITEM NUMBER: 92
DESCRIPTION: WINDOWS (SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Fixed Window (2mx3m) 6 sq.m 510.00 ₱3,060.00
Sliding Window (1.22mx1.8m) 8.78 sq.m 6,206.00 ₱54,488.68
Fixed Window (1.22mx1m) 2.44 sq.m 510.00 ₱1,244.40
Fixed Window (1.83mx0.915m) 3.35 sq.m 510.00 ₱1,708.50
Fixed Window (0.61mx1.8m) 2.2 sq.m 510.00 ₱1,122.00
Fixed Window (0.61mx0.41m) 0.5 sq.m 510.00 ₱255.00.00
Sub - total: ₱61,878.58
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 1 1000 ₱1,000.00
Skilled 5 1 500 ₱2,500.00
Sub - total: ₱3,500.00
Total Direct Cost: ₱65,378.58

ITEM NUMBER: 93
DESCRIPTION: WINDOWS (THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Fixed Window (2mx3m) 6 sq.m 510.00 ₱3,060.00
Sliding Window (1.22mx1.8m) 8.78 sq.m 6,206.00 ₱54,488.68
Fixed Window (1.22mx1m) 2.44 sq.m 510.00 ₱1,244.40
Fixed Window (1.83mx0.915m) 3.35 sq.m 510.00 ₱1,708.50
Fixed Window (0.61mx1.8m) 2.2 sq.m 510.00 ₱1,122.00
Fixed Window (0.61mx0.41m) 0.5 sq.m 510.00 ₱255.00.00
Sub - total: ₱61,878.58
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 1 1000 ₱1,000.00
Skilled 5 1 500 ₱2,500.00
Sub - total: ₱3,500.00
Total Direct Cost: ₱65,378.58

ITEM NUMBER: 94
DESCRIPTION: WINDOWS (FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Fixed Window (2mx3m) 6 sq.m 510.00 ₱3,060.00
Sliding Window (1.22mx1.8m) 8.78 sq.m 6,206.00 ₱54,488.68
Fixed Window (1.22mx1m) 2.44 sq.m 510.00 ₱1,244.40
Fixed Window (1.83mx0.915m) 3.35 sq.m 510.00 ₱1,708.50
Fixed Window (0.61mx1.8m) 2.2 sq.m 510.00 ₱1,122.00
Fixed Window (0.61mx0.41m) 0.5 sq.m 510.00 ₱255.00.00
Sub - total: ₱61,878.58
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 1 1000 ₱1,000.00
Skilled 5 1 500 ₱2,500.00
Sub - total: ₱3,500.00
Total Direct Cost: ₱65,378.58

ITEM NUMBER: 95
DESCRIPTION: EXCAVATION (SEPTIC TANK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Backhoe w/ Breaker 1 1 1,998.00 ₱1,998.00
Bulldozer D6 1 1 3,379.00 ₱3,379.00
Payloader 1 1 1,733.00 ₱1,733.00
Sub - total: ₱7,110.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
₱0.00
Sub - total: ₱0.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 1 1000 ₱1,000.00
Operators 3 1 450 ₱1,350.00
Labor 3 1 350 ₱1,050.00
Sub - total: ₱3,400.00
Total Direct Cost: ₱10,510.00

ITEM NUMBER: 96
DESCRIPTION: CONCRETE WORKS (SEPTIC TANK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Portable Concrete Vibrator 2 2 600.00 ₱2,400.00
Water Pump 1 2 680.00 ₱1,360.00
Sub - total: ₱6,396.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
# of cement 6 bags 280.00 ₱1,680.00
Vol. of sand 1 cu.m 1,150.00 ₱1,150.00
Vol. of gravel 1 cu.m 1,930.00 ₱1,930.00
Sub - total: ₱4,760.00

C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Operators 3 2 450 ₱2,700.00
Labor 5 2 350 ₱3,500.00
Foreman 1 2 650 ₱1,300.00
Skilled 5 2 500 ₱5,000.00
Sub - total: ₱14,500.00
Total Direct Cost: ₱25,656.00

ITEM NUMBER: 97
DESCRIPTION: MASONRY WORKS (SEPTIC TANK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Concrete Mixer 1 2 1,318.00 ₱2,636.00
Sub - total: ₱2,636.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
4" CHB 258 pcs 12.00 ₱3,096.00
MORTAR:
# of cement 11 bags 280.00 ₱3,080.00
Vol. of sand 1 cu.m 1,150.00 ₱1,150.00
PLASTERING:
# of cement 6 bags 280.00 ₱1,680.00
Vol. of sand 1 cu.m 1,150.00 ₱1,150.00
Sub - total: ₱10,156.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Foreman 1 2 650 ₱1,300.00
Mason 5 2 500 ₱5,000.00
Helper 5 2 400 ₱4,000.00
Sub - total: ₱12,300.00
Total Direct Cost: ₱25,092.00

ITEM NUMBER: 98
DESCRIPTION: RSB WORKS (SEPTIC TANK)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
Bar Cutter 1 2 321.00 ₱642.00
Bar Bender 1 2 422.00 ₱844.00
Sub - total: ₱1,486.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
12mm dia. x 6m 15 pcs 305.00 ₱4,575.00
Tie wire #16 1 kg 100.00 ₱100.00
Cutting Blade 1 pcs 400.00 ₱400.00
Sub - total: ₱5,075.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 2 1000 ₱2,000.00
Foreman 1 2 650 ₱1,300.00
Laborer 5 2 350 ₱3,500.00
Skilled (Installation) 5 2 500 ₱5,000.00
Sub - total: ₱11,800.00
Total Direct Cost: ₱18,361.00

ITEM NUMBER: 99
DESCRIPTION: CEILING (GROUND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Gypsum Board (4'x8'x12mm) 41 pcs 650.00 ₱26,650.00
Screw 1716 pcs 4.00 ₱6,864.00
Furring Channel 19mmx50mmx5.0m 59 pcs 234.00 ₱13,806.00
Carrying Channel 12mmx38mmx5.0m 42 pcs 108.00 ₱4,536.00
Wall Angle 25mmx25mmx3.0m 30 pcs 155.00 ₱4,650.00
W-Clip 109 pcs 3.00 ₱327.00
Blind Rivet 1/8x3/8 (4-4) 360 pcs 5.00 ₱1,800.00
Sub - total: ₱58,633.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Skilled 5 3 500 ₱7,500.00
Sub - total: ₱17,700.00
Total Direct Cost: ₱76,333.00
ITEM NUMBER: 100
DESCRIPTION: CEILING (SECOND FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Gypsum Board (4'x8'x12mm) 41 pcs 650.00 ₱26,650.00
Screw 1716 pcs 4.00 ₱6,864.00
Furring Channel 19mmx50mmx5.0m 59 pcs 234.00 ₱13,806.00
Carrying Channel 12mmx38mmx5.0m 42 pcs 108.00 ₱4,536.00
Wall Angle 25mmx25mmx3.0m 30 pcs 155.00 ₱4,650.00
W-Clip 109 pcs 3.00 ₱327.00
Blind Rivet 1/8x3/8 (4-4) 360 pcs 5.00 ₱1,800.00
Sub - total: ₱58,633.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Skilled 5 3 500 ₱7,500.00
Sub - total: ₱17,700.00
Total Direct Cost: ₱76,333.00

ITEM NUMBER: 101


DESCRIPTION: CEILING (THIRD FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Gypsum Board (4'x8'x12mm) 41 pcs 650.00 ₱26,650.00
Screw 1716 pcs 4.00 ₱6,864.00
Furring Channel 19mmx50mmx5.0m 59 pcs 234.00 ₱13,806.00
Carrying Channel 12mmx38mmx5.0m 42 pcs 108.00 ₱4,536.00
Wall Angle 25mmx25mmx3.0m 30 pcs 155.00 ₱4,650.00
W-Clip 109 pcs 3.00 ₱327.00
Blind Rivet 1/8x3/8 (4-4) 360 pcs 5.00 ₱1,800.00
Sub - total: ₱58,633.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Skilled 5 3 500 ₱7,500.00
Sub - total: ₱17,700.00
Total Direct Cost: ₱76,333.00

ITEM NUMBER: 102


DESCRIPTION: CEILING (FOURTH FLOOR)
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Gypsum Board (4'x8'x12mm) 41 pcs 650.00 ₱26,650.00
Screw 1716 pcs 4.00 ₱6,864.00
Furring Channel 19mmx50mmx5.0m 59 pcs 234.00 ₱13,806.00
Carrying Channel 12mmx38mmx5.0m 42 pcs 108.00 ₱4,536.00
Wall Angle 25mmx25mmx3.0m 30 pcs 155.00 ₱4,650.00
W-Clip 109 pcs 3.00 ₱327.00
Blind Rivet 1/8x3/8 (4-4) 360 pcs 5.00 ₱1,800.00
Sub - total: ₱58,633.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 3 1000 ₱3,000.00
Foreman 1 3 650 ₱1,950.00
Laborer 5 3 350 ₱5,250.00
Skilled 5 3 500 ₱7,500.00
Sub - total: ₱17,700.00
Total Direct Cost: ₱76,333.00

ITEM NUMBER: 103


DESCRIPTION: RAILINGS STAIR
A. EQUIPMENT
Name of Capacity No. of Units No. of Day/s Daily Rate Total Cost (Php)
₱0.00
Sub - total: ₱0.00
B. MATERIALS
Name and Specification Quantity Unit Unit Cost Total Cost (Php)
Customized Wrought Iron Railings 12 sq.m 5,000.00 ₱60,000.00
Sub - total: ₱60,000.00
C. LABOR
Designation No. of Personel/s No. of Day/s Unit Cost Total Cost (Php)
Civil Engineer 1 5 1000 ₱5,000.00
Foreman 1 5 650 ₱3,250.00
Laborer 5 5 350 ₱8,750.00
Skilled 5 5 500 ₱12,500.00
Sub - total: ₱29,500.00
Total Direct Cost: ₱89,500.00
PROGRAM OF WORKS (DETAILED ESTIMATE)
SUMMARY
LUMP SUM:
UNIT COST FLOOR AREA NUMBER OF FLOOR TOTAL
2
₱17,550.00 120 m 5 ₱10,530,000.00

EQUIPMENT RENTAL COST:


PART A EARTHWORKS ₱58,671.00
PART B FOUNDATION ₱20,222.00
PART C GROUND FLOOR ₱73,270.00
PART D SECOND FLOOR ₱62,752.00
PART E THIRD FLOOR ₱62,752.00
PART F FOURTH FLOOR ₱62,752.00
PART G ROOF DECK ₱26,222.00
TOTAL: ₱366,641.00
MATERIAL COST:
PART A EARTHWORKS ₱168,050.00
PART B FOUNDATION ₱264,840.00
PART C GROUND FLOOR ₱1,536,562.48
PART D SECOND FLOOR ₱1,899,904.58
PART E THIRD FLOOR ₱1,899,904.58
PART F FOURTH FLOOR ₱1,890,134.58
PART G ROOF DECK ₱758,449.00
TOTAL: ₱8,417,845.22
LABOR COST:
PART A EARTHWORKS ₱39,350.00
PART B FOUNDATION ₱88,000.00
PART C GROUND FLOOR ₱363,825.00
PART D SECOND FLOOR ₱359,125.00
PART E THIRD FLOOR ₱359,125.00
PART F FOURTH FLOOR ₱359,125.00
PART G ROOF DECK ₱138,850.00
TOTAL: ₱1,707,400.00
TOTAL DIRECT COST: ₱10,491,886.22

DIFFERENCE (LUMP SUM & DETAILED ESTIMATE)


LUMP SUM – DETAILED ESTIMATE = DIFFERENCE
₱10,530,000.00 - ₱10,491,886.22 = ₱38,113.78