therewith, and with all other Change Orders that have already
become binding upon the Contractor under this GC Clause 63,
would be to increase or decrease the Contract Prive ay original
set forth in the Contract Agreement by more than fifleen percent
(15%), the Contractor may give a written notice of objection
thereto prior to furnishing the’ Change Proposal as aforesaid I!
the Employer accepts the Contractor's objection, the Employer
shall withdraw the proposed Change and shall aotity the
Contractor in writing thereof.
The Contractor's failure to so object shall neither affect its right
to object to any subsequent requested Changes or
herein, nor affect its right to take into account, when making such
or decrense in
subsequent objection, the percentage increas
the Contract Price that any Change not objected to by the
Contractor represents
63.2.6 Upon receipt of the Change Proposal, the Employer and the
Contractor shall mutually agree upon all matters therein
contained, Within fourteen (14) days after such agreement, the
Employer shall, if it intends to proceed with the Change, issue the
Contractor with a Change Order.
If the Employer is unable (o reach a decision within fourteen (14)
days, it shall notily the Contractor with details of when the
Contractor can expect a decision
If the Employer decides not to proceed with the Change tor
whatever reason, it shall, within the said period of fourteen (141)
days, notify the’ Contractor accordingly. Under such
circumstances, the Contractor shall be entitled to reimbursement