Proper task
delegation
2 Crane preparation Malfunction crane Property Crane Lifting STOP work SHO
damage inspection & Supervisor authority Lifting
certification Spilt kit standby supervisor
Crane Manual Crane at crane Lifting
checklist operator Foreman
Daily routine
inspection
before start
work
3 Pre-sling of rigging Damage lifting Personnel To Inspect the Supervisor Unsure lifting
equipment gear injury lifting gear prior to Foreman gear are Supervisor
Property use Riggers inspected Foreman
damage Workleader Use Impact
Competent lifting Gloves
team are engage
Discard Damage
Lifting Gear
JOB HAZARD ANALYSIS (JHA) WORKSHEET
Improper Manual Body Injury Posture, lifting & Supervisor First Aid Kit Supervisor
Handling stability technique Foreman TBM Foreman
Use mechanical Workleader PJSM
device whenever Riggers
necessary.
Sufficient
manpower
Avoid twisting
motion.
Identify Load
Weight
Buddy System
Slip, trip and fall Personnel Housekeeping area Supervisor Workplace Supervisor
injury Ensure safety boot Foreman inspection SHO
sole in good Riggers
condition Workleader
Avoid short-cut
step.
Sharp Edges Hands and Identified & cover Supervisor Close supervision SHO
finger injury any of sharp edge Foreman by supervisor Supervisor
Body Injury Remove Signalman Proactive Foreman
protruding Crane intervention Rigger
material/ sharp Operator First aid kit at First Aider
edges Riggers jobsite
Workleader Use impact Glove
enter jobsite
Sharp Edges Hands and Identified & cover Supervisor Close supervision SHO
finger injury any of sharp edge Foreman by supervisor Supervisor
Body Injury Remove Signalman Proactive Foreman
protruding Crane intervention Rigger
material/ sharp Operator First aid kit at First Aider
edges Riggers jobsite
Workleader Use impact Glove
JOB HAZARD ANALYSIS (JHA) WORKSHEET
Sharp Edges Hands and Identified & cover Supervisor Close supervision SHO
Pinch Point finger injury any of sharp edge Foreman by supervisor Supervisor
Body Injury Remove Proactive Foreman
protruding Riggers intervention Rigger
material/ sharp Workleader First aid kit at First Aider
edges jobsite
Use impact Glove
Improper Manual Body Injury Posture, lifting & Supervisor First Aid Kit Supervisor
Handling stability technique Foreman TBM Foreman
Use mechanical Workleader PJSM
device whenever Riggers
necessary.
Sufficient
manpower
Avoid twisting
motion.
Identify Load
Weight
Buddy System
JOB HAZARD ANALYSIS (JHA) WORKSHEET
Slip, trip and fall Personnel Housekeeping area Supervisor Workplace Supervisor
injury Ensure safety boot Foreman inspection SHO
sole in good Riggers
condition Workleader
Avoid short-cut
step.
Sharp Edges Hands and Identified & cover Supervisor Close supervision SHO
finger injury any of sharp edge Foreman by supervisor Supervisor
Body Injury Remove Signalman Proactive Foreman
protruding Crane intervention Rigger
material/ sharp Operator First aid kit at First Aider
edges Riggers jobsite
Workleader Use impact Glove
JOB HAZARD ANALYSIS (JHA) WORKSHEET
REVIEWED BY APPROVED BY
NAME NAME
DATE DATE
Name (S) Designation Signature Signature Signature Signature Signature Signature Signature Name (S) Designation Signature Signature Signature Signature Signature Signature Signature