Professional Documents
Culture Documents
Waste Clearance
SAUDI SALCO
Persons at Risk (Groups) Risk Assessor Appointment Tel. No. Description of Task or Activity
A – SALCO employees Ahmad Ali Khan H&S Manager 0506219441 Removal of rubbish generated by One
B – Contractors/Sub contractors Direct activities
C – Tenants
D – Members of the public
Hazard/Risk Groups at Severity Probability Risk Level Existing Controls Risk Level Additional Controls Required Risk Level Actioned by
Risk before with with added
Controls Controls Controls
Severity C = Catastrophic, Cr = Critical, S = Serious, M = Minor, Probability N = Negligible, F = Frequent, P = Probable, O = Occasional, R = Remote, I = Improbable,
Risk T = Tolerable, L = Low, M = Medium, H = High, N = Intolerable
Page 1
Safety Risk Assessment
Waste Clearance
SAUDI SALCO
Hazard/Risk Groups at Severity Probability Risk Level Existing Controls Risk Level Additional Controls Required Risk Level Actioned by
Risk before with with added
Controls Controls Controls
Severity C = Catastrophic, Cr = Critical, S = Serious, M = Minor, Probability N = Negligible, F = Frequent, P = Probable, O = Occasional, R = Remote, I = Improbable,
Risk T = Tolerable, L = Low, M = Medium, H = High, N = Intolerable
Page 2
Safety Risk Assessment
Waste Clearance
SAUDI SALCO
Severity C = Catastrophic, Cr = Critical, S = Serious, M = Minor, Probability N = Negligible, F = Frequent, P = Probable, O = Occasional, R = Remote, I = Improbable,
Risk T = Tolerable, L = Low, M = Medium, H = High, N = Intolerable
Page 3
Safety Risk Assessment
Waste Clearance
SAUDI SALCO
Contingency Plan
Item No
1 Unauthorised entry to working area. 1) Aggressive behaviour / damage to access equipment 1) Work would cease. Unauthorised visitors asked to leave One
Violence and aggression / public access Direct supervisor informed. Emergency services called if
to restricted work area required.
2) Lone working procedure in place.
2 Electricity failure / flood / pipe 1) Severance of services / lighting failure. 1) Work would cease and client would be informed by One
leak / striking cable / pipework Direct Supervisor so remedial work can be carried out in
order for the work to re-start.
Lighting failure / water in
premises / electrocution
3 Poor communication / lack of contact 1) Poor standard of work / low customer satisfaction / 1) One Direct supervisor to keep all parties informed of work
between direct labour and sub- violent and aggressive behaviour from customer procedures and standards, H&S inspections to take place.
contractors
Poor standards / work being carried out
in an inappropriate manner
4 Disturbance of asbestos containing 1) Lack of appropriate asbestos information supplied 1) Implement emergency asbestos procedure.
materials for the property / task
Exposure to asbestos related illness 2) Failure to comply with asbestos procedures
Severity C = Catastrophic, Cr = Critical, S = Serious, M = Minor, Probability N = Negligible, F = Frequent, P = Probable, O = Occasional, R = Remote, I = Improbable,
Risk T = Tolerable, L = Low, M = Medium, H = High, N = Intolerable
Page 4