PLANT PRODUCTION

Construction of 6 Lane with Access Controlled Greenfield Highway from km 26.000 to km 97.000, MH/KN Border (Badadal) to Maradgi S Andola section of NH–150C
Project
(Package-II of Akkalkot to KN/TS Border section) on Hybrid Annuity Mode under Bharatmala Pariyojna.
Client National Highways Authority of India

Independent Engineer M/s. K & J Projects Private Limited in Joint Venture with TPF Engineering Pvt. Ltd. & in association with SEG Engineering Services Private

Concessionaire Akkalkot Highways Private Limited


EPC Contractor M/s PNC Infratech Limited

Batching Plant: 01 PNC CP 30. 78+300 RHS CAMP-02 DATE - 07-02-2024

Grade of Structure Qty of Concrete


Sl. No. Name of Agency SIDE Type of Structure Structure Component Remarks
Concrete Chainage (m3)

1 M-15 RIYA ENTERPRISES 73+561 TO 73+580 LHS CLOSING TOE WALL WALL IST LIFT 11.00

2 M-35 P.R. CONSTRUCTION 91+835 LHS SVUP WALL 2ND LIFT A1 & A2 27.50

3 M-30 GODAWARI PLANT 79+520 U-TROUGH RAFT BOTTOM HAUNCH A1 & A2 SIDE 1.00

ASHOK
4 M-15 85+450 RHS PIPE UTILITY DUCT CRADLE CONCRETE 6.00
SHIVSHANKARRAPPA

5 M-15 SHIVKUMAR 73+580 TO 73+600 RHS TOE WALL IST LIFT 16.00

6 M-15 G.G.M CONSTRUCTION 87+610 TO 87+590 RHS TOE WALL 2ND LIFT 10.00

7 M-15 KANHA CONSTRUCTION 78+530 TO 78+510 LHS TOE WALL PCC 8.80

8 M-30 ALPHA CONSTRUCTION 73+697 RHS BOX CULVERT WALL A1 , 2ND LIFT 7.50

9 M-35 SHARAVAN ENTERPRISES 78+300 RHS RE PANNEL RE PANNEL 12.00


Batching Plant: 02 SBPL VENUS CP30 PLANT 71+100 RHS

1 SUWARNA BUILDCON 70+530 RHS Nil

WMM/CTGSB Plant: 03 PNC WMM PLANT : 78+300 RHS CAMP-02

MEDIAN & TOE SIDE PATCH (R1 & R2) WMM


1 WMM PNC 94+100 TO 94+290 LHS LAYING
Ist LAYER
812.400 MT
2 WMM PNC 94+120 TO 94+270 RHS MEDIAN SIDE PATCH (R1) WMM Ist LAYER LAYING

Batching Plant: 04 APPOLO CP 30 78+300 RHS CAMP-02

1 M-30 PNC 78+300 RHS (2*2) SEGMENT BOX CASTING- 05 CUSHION (0.2) 18.00

TOTAL QUANTITY 117.80 CUM.