You are on page 1of 1

GENERAL NOTES: CAST IN PLACE REINFORCED CONCRETE (CONTINUED): STEEL JOIST: DELEGATED DESIGN NOTES:

1. ALL MATERIALS, CONSTRUCTION, AND DETAILS SHALL CONFORM WITH THE FOLLOWING: 18. OWNER SHALL HIRE A MATERIALS TESTING LABORATORY TO CAST AND TEST CONCRETE CYLINDERS. ALL TESTING SHALL BE IN ACCORDANCE 1. DESIGN, FABRICATION, AND ERECTION SHALL CONFORM TO THE CURRENT EDITION OF ''STEEL JOIST INSTITUTE SPECIFICATIONS''. 1. ENGINEERING DESIGN, DETAILING, AND COORDINATION OF DELEGATED DESIGN ITEMS ARE DELEGATED TO THE CONTRACTOR PER THE
PLANS AND SPECIFICATIONS WITH ACI 318. RESULTS OF CYLINDER TESTS SHALL BE SUBMITTED TO THE ARCHITECT AND ENGINEER. CONCRETE TEST REPORTS SHALL SPECIFICATIONS AND CRITERIA INDICATED ON THE DRAWINGS. THE PRIMARY BASE BUILDING STRUCTURE HAS BEEN DESIGNED AS INDICATED
CODE AS SPECIFIED IN DESIGN DATA STATE THE FOLLOWING INFORMATION: 2. JOIST MANUFACTURER SHALL BE A MEMBER OF THE SJI (STEEL JOIST INSTITUTE). HEREIN TO ACCEPT THE DELEGATED DESIGN ITEMS. THE CONTRACTOR SHALL COORDINATE THE WORK OF THE DELEGATED DESIGNERS WITH
A. LOCATION ON PROJECT WHERE THE CONCRETE IS USED EACH OTHER AND THE PRIMARY BASE BUILDING STRUCTURE. IT IS SUGGESTED THAT DESIGN CRITERIA, LOAD PATHS, AND ATTACHMENT
2. THE GENERAL CONTRACTOR AND SUBCONTRACTORS SHALL BE FAMILIAR WITH THE ENTIRE SET OF CONSTRUCTION DOCUMENTS B. 7 DAY COMPRESSIVE STRENGTH 3. CONTRACTOR SHALL ELECTRONICALLY SUBMIT STEEL JOIST SHOP DRAWINGS FOR APPROVAL PRIOR TO FABRICATION. CONTRACTOR SHALL SCHEMES PROPOSED BY THE DELEGATED DESIGNER BE SUBMITTED FOR REVIEW BY THE ARCHITECT FOR COMPATIBILITY OF THE BASE
(ARCHITECTURAL, CIVIL, MECHANICAL, ELECTRICAL, PLUMBING, STRUCTURAL, ETC.) IN ORDER TO PROVIDE ALL CONSTRUCTION AND MATERIALS C. 28 DAY COMPRESSIVE STRENGTH REVIEW AND STAMP ALL SHOP DRAWINGS BEFORE SUBMITTING TO THE ARCHITECT. BUILDING DESIGN PRIOR TO FINAL DESIGN AND DETAILING OF THE DELEGATED DESIGN PACKAGE.
FOR THIS PROJECT. D. AIR CONTENT
E. SLUMP 4. PROVIDE SJI STANDARD BRIDGING AS REQUIRED BY DESIGN. JOIST BRIDGING IS A REPRESENTATION FOR GENERAL INFORMATION PURPOSES 2. STRUCTURAL SYSTEMS SHALL BE DESIGNED FOR THE DELEGATED DESIGN PERFORMANCE CRITERIA DEFLECTION LIMITS NOTED ON THIS SHEET 181 N. Broadway Ave
3. THE CONTRACTOR SHALL REFER TO OTHER DRAWINGS CONTAINED IN THE CONSTRUCTION DOCUMENTS FOR ADDITIONAL SPECIFIED MEMBERS, F. AMOUNT OF WATER ADDED ON JOB SITE ONLY. JOIST SUPPLIER SHALL BE RESPONSIBLE FOR DESIGNING BRIDGING. AND TO LIMIT BUILDING MOVEMENTS TO LESS THAN THE VALUES INDICATED IN THE COORDINATION WITH OTHER TRADES AND BUILDING Milwaukee, WI 53202
DIMENSIONS, ELEVATIONS, DETAILS, OPENINGS, INSERTS, SLEEVES, DEPRESSIONS, ETC. NOT SHOWN ON THE STRUCTURAL DRAWINGS, G. MIX USED SYSTEMS NOTES ON S002. 414.278.6060
REQUIRED TO CONSTRUCT THIS PROJECT. 5. DO NOT CUT OR DRILL THROUGH ANY JOIST. www.pierceengineers.com
19. CONCRETE TEST REPORTS SHALL DIRECTLY STATE WHETHER OR NOT THE TEST RESULT COMPLIES WITH THE CONSTRUCTION DOCUMENTS 3. DOCUMENTS FOR DELEGATED DESIGN ITEMS SHALL BE STAMPED BY A QUALIFIED, PROFESSIONAL ENGINEER LICENSED IN THE STATE IN WHICH PE Project: 230647
4. DETAILS SHOWN ON STRUCTURAL DRAWINGS SHALL BE APPLICABLE TO ALL PORTIONS OF THE CONTRACT DOCUMENTS UNLESS NOTED AND SPECIFICATIONS. 6. ALL CONCENTRATED LOADS SHALL BE APPLIED AT A JOIST PANEL POINT UNLESS SPECIFICALLY NOTED OTHERWISE. PROVIDE ANGLE TO PANEL THE PROJECT IS LOCATED. THE CONTRACTOR SHALL FORWARD THE REVIEWED DOCUMENTS TO THE ARCHITECT AND/OR ENGINEER OF RECORD
OTHERWISE. POINT PER DETAILS WHERE CONCENTRATED LOADS DO NOT OCCUR AT PANEL POINT. WITH A NOTATION INDICATING THAT THE DELEGATED DESIGN DOCUMENTS HAVE BEEN REVIEWED AND BEEN FOUND TO BE IN GENERAL
20. CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIR OF ANY IRREGULARITIES OR DEFECTS IN CONCRETE SLABS (CRACKS, BUMPS, FLOOR CONFORMANCE TO THE DESIGN OF THE BUILDING.
5. NOTES AND DETAILS ON DRAWINGS SHALL TAKE PRECEDENCE OVER GENERAL STRUCTURAL NOTES AND TYPICAL DETAILS. CURLING, ETC.) BEFORE ANY FLOOR FINISHES ARE APPLIED. 7. JOIST MANUFACTURER SHALL VERIFY ALL MEPF EQUIPMENT, DISTRIBUTION SYSTEMS, AND BUILDING EQUIPMENT WEIGHTS, SIZES, AND
LOCATIONS PRIOR TO PREPARING SHOP DRAWINGS AND FABRICATING MATERIALS. CONTRACTOR TO COORDINATE ANY CHANGES w/ JOIST 4. DELEGATED DESIGN ITEMS INCLUDE ANY ITEMS NOT EXPLICITLY NOTED ON THE STRUCTURAL DRAWINGS, INCLUDING BUT NOT LIMITED TO:
6. DO NOT SCALE PLANS. 21. CONFORM TO ACI 117 FOR CONCRETE TOLERANCES. SUPPLIER AND STRUCTURAL ENGINEER.
PRIMARY BASE BUILDING STRUCTURAL ELEMENTS
7. IN NO CASE SHALL STRUCTURAL ALTERATIONS OR WORK AFFECTING A STRUCTURAL MEMBER BE MADE UNLESS APPROVED BY THE 22. CONFORM TO ACI 306.1 FOR COLD WEATHER CONCRETE PLACEMENT. 8. DESIGN JOIST AND BRIDGING TO RESIST A NET WIND UPLIFT LOAD COMBINATION 0.6DL+0.6WL. "WL" AS INDICATED IN THE GENERAL NOTES • SHORING AND/OR UNDERPINNING OF EXISTING STRUCTURES
STRUCTURAL ENGINEER. DESIGN DATA. USE "DL" = 7 PSF. • LOAD-BEARING COLD FORMED METAL FRAMING AND CONNECTIONS

8. IT IS SOLELY THE CONTRACTOR'S RESPONSIBILITY TO DETERMINE AND PROVIDE FOR THE CONSTRUCTION MEANS, METHODS, TECHNIQUES,
23. CONFORM TO ACI 305.1 FOR HOT WEATHER CONCRETE PLACEMENT.
9. PROVIDE CAMBER IN JOIST AS RECOMMENDED BY SJI SPECIFICATIONS.


OPEN WEB STEEL JOISTS AND JOISTS GIRDERS
PRE-ENGINEERED ROOF/FLOOR OPENING FRAMES REVISIONS:
SEQUENCES, AND PROCEDURES REQUIRED TO COMPLETE THE STRUCTURE IN ACCORDANCE WITH THE CONTRACT DOCUMENTS. THIS POST-INSTALLED ANCHORS TO CONCRETE AND MASONRY: OTHER ITEMS SUPPORTED BY PRIMARY STRUCTURE (SECONDARY MEMBERS)
DATE ISSUE
INCLUDES, BUT IS NOT LIMITED TO: SHORING, UNDERPINNING, TEMPORARY BRACING, ETC. SAFETY PRECAUTIONS AND PROGRAMS IN 1. POST INSTALLED ANCHORS SHALL BE: EXPANSION, ADHESIVE, OR SCREW ANCHORS AS SPECIFIED, UNLESS NOTED OTHERWISE. 10. JOIST MANUFACTURER SHALL PROVIDE SPECIAL SEATS IN ACCORDANCE WITH SJI FOR JOISTS SLOPING MORE THAN 1/4" PER FOOT. • NON-LOAD-BEARING COLD FORMED METAL FRAMING AND CONNECTIONS
CONNECTION WITH THE WORK AS REQUIRED TO ENSURE THE SAFETY OF THE BUILDING AND WORKMEN ARE THE SOLE RESPONSIBILITY OF THE • STAIRS, RAILINGS, HANDRAILS, GUARDRAIL, LADDERS, ETC. – REFER TO STAIR DELEGATE DESIGN NOTES
CONTRACTOR. THE BASE BUILDING PRIMARY STRUCTURAL FRAME IS DESIGNED FOR THE FINAL, COMPLETED CONDITION AS INDICATED 2. EXPANSION ANCHORS (SEE NOTES BELOW FOR SUBSTITUTIONS): 11. JOIST SUPPLIER SHALL COORDINATE THEIR WORK WITH THE STEEL SUPPLIER ON THE PROJECT. • BOLLARDS, GUARDRAILS, TRAFFIC CONTROL DEVICES
HEREIN. LOADS IMPOSED ON THE BUILDING STRUCTURE DURING THE COURSE OF CONSTRUCTION SHALL BE CONFIRMED BY THE CONTRACTOR A. FOR CONCRETE: • CLADDING SYSTEMS AND COMPONENTS, INCLUDING SUPPLEMENTAL SUPPORT, WHERE REQUIRED
AND THE CONTRACTOR’S ENGINEER AS PART OF THE MEANS AND METHODS OF CONSTRUCTION. CARE SHALL BE GIVEN BY THE CONTRACTOR a. HILTI KWIK BOLT TZ. 12. DO NOT RUN JOIST BRIDGING THROUGH ANY DECK OPENINGS. JOIST SUPPLIER SHALL REVIEW AND PROVIDE ALTERNATE LOCATION FOR • FURNITURE, FIXTURES, AND OTHER MISCELLANEOUS ARCHITECTURAL FABRICATIONS
AND THE CONTRACTOR’S ENGINEER TO CONSIDER THE PRESENT STATE OF THE STRUCTURE AT THE TIME OF LOADING, INCLUDING AGE- B. FOR SOLID GROUTED CONCRETE MASONRY: BRIDGING ALONG JOIST SPAN AS REQUIRED. • SITE, UTILITY, PLAZA, AND LANDSCAPE ITEMS
DEPENDENT STRENGTH OF THE STRUCTURAL ELEMENTS AND THE NATURE OF ALL LOADS IMPOSED. a. HILTI KWIK BOLT TZ. • SUPPORTS, BRACING, ATTACHMENTS, AND SUBFRAMING FOR SUPPORT OF OTHER TRADES AND BUILDING COMPONENTS. REFER TO
13. JOIST SHALL BE FIELD ATTACHED w/ A MINIMUM OF LISTED VALUES, UNLESS NOTED OTHERWISE ON PLAN DETAILS: MODIFICATIONS FOR COORDINATION WITH OTHER TRADES NOTES.
9. CONSTRUCTION DOCUMENTS SHOW DIMENSIONS AND ELEVATIONS TO SIGNIFICANT WORKING POINTS (COLUMN CENTERLINES, OUTSIDE FACE 3. ADHESIVE ANCHORS (SEE NOTES BELOW FOR SUBSTITUTIONS): A. K-SERIES JOISTS - (2)-1/8" FILLET WELDS x 2 1/2" LONG EACH SIDE OF JOIST SEAT,OR BOLTED w/ (2)-1/2" DIA BOLTS IN SLOTTED HOLES
OF WALLS, TOP OF FRAMING MEMBERS, ETC.) MATERIAL SUPPLIERS AND DESIGNERS ARE RESPONSIBLE FOR ALL OTHER INFORMATION IN A. FOR CONCRETE: PARALLEL TO JOIST AT COLUMNS. 5. DELEGATED DESIGN SUBMITTALS PERTAINING TO FOUNDATIONS AND OTHER GEOTECHNICAL ELEMENTS SHALL BE REVIEWED BY THE
ORDER TO DETAIL/FABRICATE THEIR WORK. CONTACT THE ARCHITECT WITH ANY DISCREPANCIES. a. HILTI HIT RE 500 V3 EPOXY ADHESIVE ANCHOR SYSTEM WITH HAS THREADED ROD, THREADED ROD OR REBAR WHERE GEOTECHNICAL ENGINEER OF RECORD.
SPECIFIED METAL DECK:
10. IN THE EVENT OF ANY DISCREPANCIES BETWEEN THE STRUCTURAL DRAWINGS AND ANY OTHER PLANS, THE CONTRACTOR SHALL BRING THE b. HILTI HIT-HY 200 ADHESIVE ANCHOR SYSTEM WITH HAS THREADED ROD, THREADED ROD OR REBAR WHERE SPECIFIED. 1. DECK, ACCESSORIES, AND ATTACHMENTS SHALL CONFORM WITH THE CURRENT EDITION OF ''STEEL DECK INSTITUTE SPECIFICATIONS''. 6. ENGINEERING AND SYSTEMS REQUIRED BY THE CONTRACTOR TO SUPPORT CONSTRUCTION REMAIN THE PREROGATIVE AND RESPONSIBILITY
DISCREPANCY TO THE ARCHITECT'S ATTENTION IMMEDIATELY, IN WRITING. B. SOLID GROUTED CONCRETE MASONRY: OF THE CONTRACTOR. REFER TO GENERAL NOTES.
a. HILTI HIT-HY 270 ADHESIVE ANCHOR SYSTEM WITH HAS THREADED ROD, THREADED ROD OR REBAR WHERE SPECIFIED. 2. ALL ROOF DECK SHALL BE PAINTED, EXCEPT DECK EXPOSED TO WEATHER WHICH SHALL BE GALVANIZED. ALL FLOOR DECK SHALL BE GALVANIZED.
11. NO PROVISIONS HAVE BEEN MADE IN THE DESIGN OF THIS STRUCTURE FOR FUTURE EXPANSION, UNLESS SPECIFICALLY NOTED ON PLAN. C. HOLLOW OR MULTI-WYTHE MASONRY: COORDINATION WITH OTHER TRADES:
a. HILTI HIT-HY 70 ADHESIVE ANCHOR SYSTEM WITH HAS THREADED ROD OR THREADED ROD WITH SCREEN TUBES. 3. AT CHANGE IN DECK DIRECTION, PROVIDE A 20 GAUGE x 9'' WIDE CONTINUOUS PLATE. PROVIDE SAME PLATE AT ALL RIDGES, VALLEYS, AND HIPS BENT TO 1. SUPPORT, SUBFRAMING, BRACING, AND ATTACHMENTS TO PRIMARY BASE BUILDING STRUCTURE FOR ALL NONSTRUCTURAL BUILDING
12. ALL EXISTING STRUCTURES, INCLUDING EXISTING FOUNDATION SYSTEMS AND UNDERGROUND ELEMENTS, SHALL BE COMPLETELY REMOVED. MATCH PROFILE OF ROOF. COMPONENTS, INCLUDING ARCHITECTURAL, MECHANICAL, ELECTRICAL, PLUMBING, AND FIRE PROTECTION ELEMENTS SHALL BE DESIGNED AND NOTICE TO BIDDERS
EXISTING SUBSURFACE ELEMENTS MAY REMAIN IF APPROVED BY THE GEOTECHNICAL ENGINEER IN CONSULTATION WITH THE STRUCTURAL 4. SCREW ANCHORS (SEE NOTES BELOW FOR SUBSTITUTIONS): DETAILED BY THE MANUFACTURER, SUPPLIER, OR CONTRACTOR FURNISHING THOSE COMPONENTS. CONNECTIONS AND SUPPORTED LOADS TO BIDDERS SHALL REVIEW ALL DRAWINGS AND
ENGINEER AND THE EXISTING MATERIALS ARE PREPARED AS DIRECTED BY THE GEOTECHNICAL ENGINEER TO ACHIEVE THE PERFORMANCE A. FOR CONCRETE: COLD FORMED METAL FRAMING: STRUCTURAL MEMBERS SHALL BE SUBMITTED TO THE ARCHITECT FOR REVIEW. RESPONSIBILITY FOR THE PERFORMANCE OF THE SUPPLIED SPECIFICATION SECTIONS TO DETERMINE THE IMPACT OF
CHARACTERISTICS INDICATED IN THE GEOTECHNICAL REPORT. a. HILTI KWIK HUS EZ 1. CONTRACTOR SHALL ELECTRONICALLY SUBMIT COLD-FORMED SHOP DRAWINGS WITH STRUCTURAL CALCULATIONS STAMPED BY A SYSTEM AND ASSOCIATED CONNECTIONS SHALL REMAIN THAT OF THE PARTY FURNISHING THE DESIGN AND DETAILING. OTHER SECTIONS OF WORK ON THEIR OWN WORK
B. SOLID GROUTED CONCRETE MASONRY: PROFESSIONAL ENGINEER REGISTERED IN THE STATE IN WHICH THE PROJECT IS LOCATED TO THE ARCHITECT AND ENGINEER FOR APPROVAL.
CONTRACTOR SHALL REVIEW AND STAMP ALL SHOP DRAWINGS BEFORE SUBMITTING TO THE ARCHITECT. 2. THE CONTRACTOR SHALL COORDINATE THE WORK OF ALL TRADES CONNECTING TO, REQUESTING OPENINGS IN, PENETRATIONS THROUGH, OR © 2023 ABACUS ARCHITECTS, INC.
FOUNDATION AND EARTHWORK: a. HILTI KWIK HUS EZ
1. FOUNDATION DESIGN IS BASED ON THE SUBSURFACE EXPLORATION AND RECOMMENDATIONS OF THE BORINGS PERFORMED BY: ITEMS EMBEDDED WITHIN STRUCTURAL ELEMENTS, OR OTHERWISE IMPACTING THE BASE BUILDING STRUCTURE. UPON COMPLETION OF
5. WHEN INSTALLING POST INSTALLED ANCHORS: 2. SHOP DRAWING SUBMISSIONS SHALL INCLUDE THE FOLLOWING INFORMATION: COORDINATION AND DESIGN, FULLY COORDINATED PLANS SHALL BE SUBMITTED FOR REVIEW AND APPROVAL BY THE STRUCTURAL ENGINEER
MILLER ENGINEERS & SCIENTISTS A. THE MANUFACTURER'S PRINTED INSTALLATION INSTRUCTIONS AND CURRENT ICC-ES REPORT SHALL BE FOLLOWED. A. THE NAME, ADDRESS, PHONE NUMBER, AND FAX NUMBER OF THE SUPPLIER OF RECORD PRIOR TO FABRICATION AND INSTALLATION. THIS INCLUDES BUT IS NOT LIMITED TO SLEEVES, CONDUITS, CABLES, PIPES,
5308 SOUTH 12th STREET B. DO NOT DAMAGE EXISTING REINFORCING, POST TENSIONED CABLES OR OTHER EMBEDDED ITEMS. B. ALL DESIGN LOADS ELECTRICAL BOXES, CAST-IN ATTACHMENTS, POST-INSTALLED ANCHORS, ETC. REFER TO TYPICAL DETAILS CONTAINED HEREIN FOR
SHEBOYGAN, WI 53081 C. WHEN INSTALLING IN CONCRETE: C. PLANS AND ELEVATIONS KEYING IN ALL SECTION REINFORCEMENT REQUIRED TO ACCOMMODATE REQUESTED MODIFICATIONS TO THE PRIMARY BASE BUILDING STRUCTURE. UPON REVIEW,
JOB NO. 20689-001 a. THE MINIMUM CONCRETE DESIGN COMPRESSIVE STRENGTH SHALL MATCH THE COMPRESSIVE STRENGTHS NOTED IN THE D. CONNECTION DETAILS SPECIFYING ALL FASTENER TYPES, QUANTITY, AND LOCATIONS ADDITIONAL OR ALTERNATIVE MODIFICATIONS MAY BE REQUIRED AT THE DISCRETION AND DIRECTION OF THE STRUCTURAL ENGINEERING OF

1135A MICHIGAN AVE. SHEBOYGAN, WI 53081 (920) 452-4444 │ 640 N VEL R. PHILIPS AVE, SUITE 210, MILWAUKEE, WI 53203
DATED MAY 23, 2023 CONCRETE NOTES SECTION. E. ALL REQUIRED BRIDGING, BRACING, AND OTHER COLD FORMED COMPONENTS RECORD.
b. FOR POST INSTALLED ADHESIVE ANCHORS, THE CONCRETE SHALL HAVE A MINIMUM AGE OF 21 DAYS AT THE TIME OF
2. THE CONTRACTOR AND THE OWNER'S TESTING AGENT SHALL CONFIRM INSTALLATION AND CONSTRUCTION OF FOUNDATIONS IS COMPLETED IN INSTALLATION. ANCHORS INSTALLED IN CONCRETE LESS THAN 21 DAYS OLD SHALL BE TESTED IN ACCORDANCE WITH ACI 355.4 3. ALL COLD-FORMED MEMBERS SPECIFIED ON THE CONSTRUCTION DOCUMENTS ARE MINIMUM SIZES. COLD-FORMED DESIGNER TO VERIFY ALL 3. PENETRATIONS THROUGH, CONNECTIONS TO, AND ITEMS EMBEDDED WITHIN STRUCTURAL MEMBERS SHALL NOT NEGATIVELY IMPACT THE
CONFORMANCE WITH THE RECOMMENDATIONS OF THE GEOTECHNICAL REPORT. TO VERIFY PERFORMANCE. SIZES. PERFORMANCE OF THE BASE BUILDING STRUCTURE.
c. FOR POST INSTALLED ADHESIVE ANCHORS, THE CONCRETE TEMPERATURE AT THE TIME OF INSTALLATION SHALL BE AT LEAST
3. CENTER PIERS AND FOUNDATIONS UNDER COLUMN / WALL CENTERLINES UNLESS NOTED OTHERWISE. 50-DEGREES FAHRENHEIT. 4. REFER TO MATERIAL STRENGTHS FOR COLD-FORMED METAL FRAMING YIELD STRESS (Fy). 4. CONTRACTOR SHALL COORDINATE THE WORK OF ALL TRADES, INCLUDING AS-BUILT CONDITIONS IMPACTING DESIGN AND COORDINATION.
D. ADHESIVE USED IN AN ADHESIVE ANCHOR SYSTEM SHALL BE STORED AT THE SERVICE TEMPERATURE RANGE RECOMMENDED BY THE ADJACENCIES OF ITEMS PLANNED OR INSTALLED IN OR ON STRUCTURE SHALL BE IDENTIFIED AND CONSIDERED BY EACH TRADE FOR THE
4. BACKFILL AT WALLS SHALL BE PROVIDED PER THE RECOMMENDATIONS OF THE GEOTECH. BACKFILL SIMULTANEOUSLY ON BOTH SIDE OF MANUFACTURER. 5. ALL COLD-FORMED MEMBERS SHALL BE GALVANIZED. IMPACT OF SUCH ADJACENCIES TO THEIR SYSTEMS. VERIFY ALL MECHANICAL EQUIPMENT, WEIGHTS, SIZES, AND LOCATIONS PRIOR TO
FOUNDATION AND STEM WALLS. E. ANCHORS TO BE INSTALLED IN ADHESIVE SHALL BE CLEAN, OIL FREE AND FREE OF RUST, PAINT OR OTHER COATINGS. PREPARING SHOP DRAWINGS AND FABRICATING MATERIALS. COORDINATE ANY REQUIRED REVISIONS TO THE BASE BUILDING STRUCTURE WITH
F. ADHESIVE ANCHORS SHALL BE SECURELY PLACED TO PREVENT DISPLACEMENT OR DISTURBANCE WHILE THE ADHESIVE CURES. IF AN 6. DESIGN, SUPPLY, AND INSTALL ANY HOT-ROLLED OR COLD-ROLLED SECTION NEEDED TO PROVIDE A COMPLETE EXTERIOR CLADDING SYSTEM. THE STRUCTURAL ENGINEER.
5. EARTH RETENTION AND UNDERPINNING SYSTEMS, TEMPORARY OR PERMANENT, SHALL BE PROVIDED BY THE CONTRACTOR AND THE ANCHOR IS DISPLACED OR DISTURBED BEFORE A FULL ADHESIVE CURE IT SHALL BE CONSIDERED DAMAGED AND REPLACED AT THE
CONTRACTOR'S ENGINEER AS AN ELEMENT OF THE MEANS AND METHODS OF CONSTRUCTION. CONTRACTOR'S EXPENSE. 7. REFER TO DEFLECTION LIMIT CRITERIA FOR ALL COLD-FORMED FRAMING DEFLECTION REQUIREMENTS. 5. MISCELLANEOUS ELEMENTS SUCH AS SHELF ANGLES, LINTELS, SUPPORTS FOR CURTAIN WALLS OR MASONRY, AND EDGE ANGLES AT OPENINGS
G. UNLESS NOTED OTHERWISE, ANCHORS SHALL BE INSTALLED PERPENDICULAR TO THE SUPPORTING SURFACE. AND PERIMETER CONDITIONS ARE INTENDED TO SUPPORT AND BE COORDINATED WITH MATERIALS FURNISHED BY OTHER TRADES. THESE

HAPPY LANE, SHEBOYGAN FALLS, WI 53085


6. SUBGRADES SHALL BE PREPARED PER THE GEOTECHNICAL RECOMMENDATIONS. TOP OF FOOTING ELEVATIONS SHOWN ON THESE H. INSTALL ANCHORS TO ACCOMMODATE THE STANDARD HOLE SIZE IN THE SUPPORTED STEEL MEMBER. THE HOLE DIAMETER THROUGH 8. ALL WELDING SHALL BE AWS D1.3. WELDERS SHALL BE CERTIFIED FOR THE THICKNESS OF MATERIAL BEING WELDED. MATERIALS ARE INTENDED TO BE FIELD ATTACHED TO MEET THE TOLERANCES REQUIRED BY OTHER TRADES, WHICH MAY BE MORE STRINGENT

OOSTBURG STATE BANK


CONSTRUCTION DOCUMENTS REPRESENT MINIMUM FOOTING DEPTHS FOR FROST PROTECTION AND ESTIMATES OF REQUIRED BEARING DEPTH THE SUPPORTED STEEL MEMBER SHALL BE 1/16" LARGER THAN THE ANCHOR UNLESS NOTED OTHERWISE. USE PLATE WASHERS WITH A THAN THE TOLERANCES SPECIFIED BY THE RELEVANT CODE OF STANDARD PRACTICE FOR THE SUPPORTING ELEMENTS. THE CONTRACTOR
BASED ON THE RECOMMENDATIONS OF THE GEOTECHNICAL REPORT. THE ON-SITE GEOTECHNICAL ENGINEER SHALL ENSURE FOUNDATION STANDARD SIZE HOLE WELDED TO STEEL MEMBERS WHERE OVERSIZED HOLES MUST BE USED THROUGH THE STEEL MEMBER, UNO. 9. SCREW PENETRATION THROUGH JOINED MATERIALS SHALL NOT BE LESS THAN THREE EXPOSED SCREW THREADS. REFER TO INSTALLATION SHALL COORDINATE THE WORK OF ALL TRADES AND COORDINATE THE INSTALLATION OF SUPPORTING ELEMENTS TO COMPLY WITH THE
AND SLAB-ON-GROUND SYSTEMS ARE FOUNDED ON COMPETENT MATERIAL TO ACHIEVE THE DESIGN VALUES INDICATED ON THESE I. HOLES SHALL BE DRILLED AND INSTALLED PER THE MANUFACTURER'S PRINTED INSTALLATION INSTRUCTIONS AS OUTLINED IN THE ICC- INSTRUCTIONS OF THE SCREW MANUFACTURER AND/OR ASTM C-954 FOR MINIMUM SPACING AND EDGE DISTANCE AND TORQUE REQUIREMENTS. TOLERANCE CRITERIA REQUIRED FOR INSTALLATION OF MATERIALS BY OTHER TRADES.
CONSTRUCTION DOCUMENTS AND IN THE GEOTECHNICAL REPORT. AT THE GEOTECHNICAL ENGINEER'S DIRECTION, EXCAVATIONS MAY BE ES REPORT. WHERE APPLICABLE, INSTALLATION SHALL ALSO FOLLOW PROPER CLEANING PROCEDURE AS INDICATED IN THE
NEED TO BE EXTENDED TO FIND COMPETENT MATERIALS OR ADDITIONAL SUBGRADE PREPARATIONS MAY BE REQUIRED. MANUFACTURER'S PRINTED INSTALLATION INSTRUCTION AS OUTLINED IN THE ICC-ES REPORT. HOLES SHALL BE DRILLED WITH A 10. INSTALL CONTINUOUS TRACKS SIZED TO MATCH STUDS. ALIGN TRACKS ACCURATELY TO LAYOUT AT BASE AND TOPS OF STUDS. SECURE 6. UNDERGROUND
ROTARY IMPACT HAMMER DRILL OR ROCK DRILL, DO NOT CORE DRILL HOLES. TRACKS AS RECOMMENDED BY STUD MANUFACTURER FOR TYPE OF CONSTRUCTION INVOLVED, EXCEPT DO NOT EXCEED 24'' o/c SPACING FOR A. THE INFLUENCE AREA OF A FOOTING OR MAT SHALL BE DEFINED AS THE FRUSTUM OF SOIL LOCATED BELOW THE FOOTING OR MAT
POWDER-DRIVEN FASTENERS, OR 16'' o/c FOR OTHER TYPES OF ATTACHMENT. PROVIDE FASTENERS AT CORNERS AND END OF TRACKS. HAVING A 1:1 (HORIZONTAL:VERTICAL) SLOPE EMANATING FROM THE FOOTING OR MAT EDGE, OR AS DEFINED BY THE GEOTECHNICAL

NEW BUILDING FOR:


7. ALL EXTERIOR FOUNDATIONS SHALL BE CAST AT LEAST FROST DEPTH BELOW ADJACENT FINISH EXTERIOR GRADE. FOOTINGS SHALL BE CAST
AT LEAST MINIMUM BEARING DEPTH BELOW ADJACENT FINAL GRADE OR FINISHED FLOOR ELEVATION. REFER TO SOIL DESIGN VALUES. 6. ALL PERSONNEL INSTALLING ANCHORS SHALL BE TRAINED AND CERTIFIED BY THE ANCHORING SYSTEM MANUFACTURER. CONTRACTOR SHALL ENGINEER OF RECORD.

ISSUE DATE: 11/13/2023


SUBMIT VALID CERTIFICATION FROM THE MANUFACTURER ON ALL PERSONNEL. ALL PERSONNEL INSTALLING ADHESIVE ANCHORS IN A 11. WHERE SPLICING OF TRACK IS NECESSARY BETWEEN STUD SPACINGS, PROVIDE A PIECE OF STUD PLACED BETWEEN ADJACENT TRACKS AND
FASTENED BY WELD OR SCREW TO EACH SIDE OF THE TRACK EACH END.

BID SET
8. REFER TO GEOTECHNICAL AND/OR ENVIRONMENTAL REPORT FOR REMEDIATION OF SOILS THAT ARE NOT SUITABLE FOR BEARING BELOW HORIZONTAL, OVERHEAD OR UPWARDLY INCLINED CONDITION SHALL BE TRAINED AND CERTIFIED BY THE ACI/CRSI ADHESIVE ANCHOR B. PIPES, CONDUITS, AND BURIED ITEMS SHALL NOT BE PLACED WITHIN THE INFLUENCE AREA OF ADJACENT FOOTINGS OR MATS.
FOOTINGS OR SLABS, OR SOILS THAT REQUIRE REMOVAL DUE TO CONTAMINATION. INSTALLER CERTIFICATION PROGRAM FOR SUCH APPLICATIONS.
12. AT NON-LOAD BEARING WALLS, PROVIDE A SLIP TRACK AT TOP OF WALL. C. ALL STRUCTURES (eg. TRIPLE BASINS, GREASE TRAPS, ETC.) SHALL NOT BE INSTALLED WITHIN THE INFLUENCE AREA OF ADJACENT
9. ENGINEERED FILL MATERIALS OR LEAN CONCRETE SHALL BE PROVIDED AND INSTALLED PER THE GEOTECHNICAL ENGINEER'S 7. POST INSTALLED ANCHORS SHALL ONLY BE USED WHERE SPECIFIED ON THE DRAWINGS. CONTRACTOR SHALL OBTAIN APPROVAL FROM FOOTINGS OR MATS UNLESS THE STRUCTURE IS DESIGNED BY THE MANUFACTURER FOR INCREASED SURCHARGE LOAD APPLIED BY
RECOMMENDATIONS. STRUCTURAL ENGINEER OF RECORD PRIOR TO USING POST INSTALLED ANCHORS FOR MISSING OR MISPLACED CAST IN PLACE ANCHORS. ONLY 13. FASTENING OF COMPONENTS SHALL BE WITH SELF-DRILLING SCREWS OR BY WELDING. SCREWS AND WELDS SHALL BE SUFFICIENT SIZE TO THE ADJACENT FOUNDATION AND HAS BEEN REVIEWED AND APPROVED BY THE STRUCTURAL ENGINEER OF RECORD OR THE
USE SPECIFIC TYPE OF ANCHOR (EXPANSION, ADHESIVE, SCREW) WHERE INDICATED. DO NOT SUBSTITUTE ANCHOR TYPES WITHOUT WRITTEN ENSURE THE STRENGTH OF THE CONNECTION. GEOTECHNICAL ENGINEER OF RECORD.
10. FOUNDATIONS SHALL NOT BE INSTALLED ON FROZEN SUBGRADE. APPROVAL FROM SEOR.
14. ALL WELDS SHALL BE TOUCHED UP WITH ZINC-RICH PAINT. D. ITEMS TO BE BURIED IN IMPROVED SOILS SHALL BE REVIEWED AND APPROVED BY THE GROUND IMPROVEMENT DELEGATED DESIGN
8. SUBSTITUTION REQUESTS FOR PRODUCTS OTHER THAN THOSE LISTED ABOVE SHALL BE SUBMITTED TO THE ENGINEER WITH CALCULATIONS ENGINEER AND THE GEOTECHNICAL ENGINEER OF RECORD
CAST IN PLACE REINFORCED CONCRETE: THAT ARE PREPARED AND SEALED BY A STRUCTURAL ENGINEER REGISTERED IN THE STATE WHERE THE PROJECT IS LOCATED (PER THE 15. INSTALL COLD-FORMED FRAMING MEMBERS IN ACCORDANCE WITH MANUFACTURERS PRINTED OR WRITTEN INSTRUCTIONS AND
1. CONCRETE WORK SHALL CONFORM TO REFERENCED EDITION OF ACI 318 "BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE" AND DELEGATED DESIGN NOTES) SHOWING THAT THE SUBSTITUTED PRODUCT WILL ACHIEVE AN EQUIVALENT CAPACITY USING THE APPROPRIATE RECOMMENDATIONS UNLESS NOTED OTHERWISE. 7. CONCRETE ELEMENTS
ACI 302 "GUIDE FOR CONCRETE FLOOR AND SLAB CONSTRUCTION". DESIGN PROCEDURE REQUIRED BY THE BUILDING CODE. PRODUCT ICC-ES CODE REPORTS SHALL BE INCLUDED WITH THE SUBMITTAL PACKAGE. A. REFER TO TYPICAL CONCRETE SLAB PENETRATION AND CONDUIT PLACEMENT CRITERIA DETAIL.
THE PROPOSED SUBSTITUTION(S) SHALL MEET THE MOST RECENTLY PUBLISHED ACI 355.2 OR ACI 355.4. 16. FIELD CUTTING OF COLD-FORMED MEMBERS SHALL BE BY SAW OR SHEAR. TORCH CUTTING IS NOT PERMITTED.
2. CONTRACTOR SHALL ELECTRONICALLY SUBMIT STEEL REBAR SHOP DRAWINGS FOR APPROVAL PRIOR TO CONSTRUCTION. CONTRACTOR B. GROUPS OF ADJACENT OPENINGS REQUIRE SPECIAL CONSIDERATION AND MAY BE IMPERMISSIBLE. EARLY COORDINATION OF
SHALL REVIEW AND STAMP ALL SHOP DRAWINGS BEFORE SUBMITTING TO THE ARCHITECT. 17. TEMPORARY BRACING OF COLD-FORMED MEMBERS SHALL BE PROVIDED AND REMAIN IN PLACE UNTIL WORK IS PERMANENTLY STABILIZED. ALL CLUSTERED PENETRATIONS WITH THE STRUCTURAL ENGINEER OF RECORD IS HIGHLY RECOMMENDED.
STRUCTURAL STEEL:
BRACING REQUIRED SHALL BE DESIGNED AND SUPPLIED BY THE COLD-FORMED CONTRACTOR.
1. DESIGN, FABRICATION, AND ERECTION SHALL CONFORM TO AISC (AMERICAN INSTITUTE OF STEEL CONSTRUCTION) ''STEEL CONSTRUCTION
3. REFER TO REINFORCEMENT DEVELOPMENT AND LAP SPLICE SCHEDULE FOR LAP SPLICES (Lst) AND DEVELOPMENT LENGTH (Ld) IN 8. STEEL ELEMENTS
MANUAL''. EDITION AS SPECIFIED BY CODE.
REINFORCING STEEL. 18. AT LOCATIONS REQUIRING WELDING OF OR TO METAL STUDS, MINIMUM STUD THICKNESS SHALL BE 16 GA. A. ALL PENETRATIONS INDICATED HEREIN SHALL BE CONFIRMED BY THE CONTRACTOR THROUGH COORDINATION WITH THE
SUBCONTRACTORS AND DELEGATED DESIGN ENGINEERS. SUBMIT ALL REQUIRED PENETRATIONS FOR REVIEW AND APPROVAL
2. STEEL DETAILING AND CONNECTIONS SHALL CONFORM TO THE REQUIREMENTS OF AISC 360 ''SPECIFICATIONS FOR STRUCTURAL STEEL
4. ALL LAPS IN REINFORCING STEEL SHALL BE CLASS ''B'' LAP SPLICES UNLESS OTHERWISE NOTED. AT CONSTRUCTION JOINTS, CONTINUOUS SUBSEQUENT TO FINAL COORDINATION OF BUILDING SYSTEMS.
BUILDINGS". EDITION AS SPECIFIED BY CODE, ALLOWABLE STRESS DESIGN. DELEGATED DESIGN STAIR NOTES:
BARS SHALL BE LAP SPLICED WITH A CLASS "B" LAP. ALL OTHER BARS EXTENDING THRU THE JOINT SHALL BE FULLY DEVELOPED (Ld OR Ldh AS 1. STAIRS NOT DETAILED ON THE DRAWINGS ARE DELEGATED TO THE CONTRACTOR FOR DESIGN. REFER TO THE ARCHITECTURAL DRAWINGS AND
ILLUSTRATED OR NOTED) EACH SIDE OF JOINT, UNO. B. FIELD-CUTTING SHALL NOT BE PERMITTED WITHOUT PRIOR APPROVAL BY THE STRUCTURAL ENGINEER OF RECORD.
3. BEAM AND GIRDER CONNECTIONS SHALL BE DETAILED AS NOTED ON PLANS AND DETAILS. PROJECT SPECIFICATIONS FOR ADDITIONAL PERFORMANCE CRITERIA AND FINISHING REQUIREMENTS. THE BASE BUILDING STRUCTURE HAS
BEEN DESIGNED FOR SUPPORT OF STAIRS AS INDICATED HEREIN.
5. ALL HOOKS IN REINFORCING STEEL SHALL BE STANDARD HOOKS, UNO. 9. METAL DECK
4. SUBSTITUTION REQUESTS FOR CONNECTIONS SHALL BE SUBMITTED TO THE STRUCTURAL ENGINEER WITH CALCULATIONS THAT ARE PREPARED
A. ATTACHING OR HANGING ANY LOADS FROM METAL ROOF DECK WILL NOT BE ACCEPTED WITHOUT WRITTEN APPROVAL FROM THE
AND SEALED BY A REGISTERED STRUCTURAL ENGINEER SHOWING THAT THE SUBSTITUTED CONNECTION WILL ACHIEVE AN EQUIVALENT 2. STAIRS, HANDRAILS, AND GUARDRAILS SHALL BE DELEGATED DESIGN BY THE STEEL SUPPLIER. CONNECTIONS INTO SURROUNDING STRUCTURE
6. PROVIDE THE FOLLOWING CLEAR COVER DISTANCES FOR REINFORCEMENT IN CONCRETE UNLESS NOTED OTHERWISE: STRUCTURAL ENGINEER.
CAPACITY USING THE APPROPRIATE DESIGN PROCEDURE REQUIRED BY THE BUILDING CODE. SHALL BE APPROVED BY STRUCTURAL ENGINEER. CALCULATIONS OF ALL STAIR COMPONENTS MUST BE SUPPLIED WITH STAIR SHOP DRAWINGS
AND STAMPED BY THE PROFESSIONAL ENGINEER IN RESPONSIBLE CHARGE, IN THE STATE IN WHICH THE PROJECT IS LOCATED.
CONCRETE CAST AGAINST AND PERMANENTLY EXPOSED TO EARTH: 3" B. COMPOSITE FLOOR DECK HANGER LOADS SHALL NOT EXCEED 60 POUNDS PER HANGER. IN ADDITION, LOADS ON HANGERS SHALL BE
5. STRUCTURAL STEEL AND CONNECTIONS EXPOSED TO WEATHER OR CORROSIVE ENVIRONMENTS SHALL BE GALVANIZED OR COATED PER THE
DISTRIBUTED IN SUCH A MANNER THAT THE TRIBUTARY LOADS FROM EACH HANGER SHALL NOT EXCEED 5 POUNDS PER SQUARE FOOT.
REQUIREMENTS OF AISC 360. 3. REFER TO ARCHITECTURAL DRAWINGS FOR STAIR FRAMING AND CONFIGURATION.
CONCRETE EXPOSED TO EARTH OR WEATHER:
NO. 6 THROUGH NO. 18 BARS 2" C. CONDUIT AND PIPING MAY NOT BE EMBEDDED IN COMPOSITE DECK SLABS.
6. WELDING SHALL BE PERFORMED BY CERTIFIED WELDERS HOLDING CURRENT AWS CERTIFICATES IN THE TYPES OF WELDING SPECIFIED ON THE 4. LANDING BEAMS AND ANY ADDITIONAL SUPPORTS BEYOND WHAT IS SHOWN IN THE CONTRACT DOCUMENTS INCLUDING ADDITIONAL
NO. 5 BAR AND SMALLER 1 1/2" CONSTRUCTION DOCUMENTS. FOUNDATIONS, IF REQUIRED, SHALL BE DESIGNED AND PROVIDED BY THE STAIR SUPPLIER.
D. VERIFY ALL MECHANICAL EQUIPMENT WEIGHTS, SIZES, & LOCATIONS PRIOR TO PREPARING SHOP DRAWINGS & FABRICATING
CONCRETE NOT EXPOSED TO WEATHER OR IN CONTACT WITH GROUND: MATERIALS. CONTRACTOR TO COORDINATE ANY CHANGES w/ STRUCTURAL ENGINEER..
7. ALL STEEL BEAMS SHALL BE FABRICATED WITH THE NATURAL CAMBER (WITHIN MILL TOLERANCE) IN THE UPWARD VERTICAL DIRECTION. 5. DESIGN LOADS:
WALLS, JOISTS: NO. 11 BAR AND SMALLER 1"
BEAMS AND COLUMNS 1 1/2" E. REFER TO TYPICAL DETAILS FOR FRAMING AROUND FLOOR AND ROOF OPENINGS. COORDINATE SIZE, LOCATION, & QUANTITY OF STEEL
8. PROVIDE 3/16'' CAP PLATE AT THE ENDS OF ALL EXPOSED TUBE AND PIPE MEMBERS, UNLESS NOTED OTHERWISE. A. STAIR LIVE LOAD SHALL BE 100 PSF, NON-REDUCIBLE.
FRAMES WITH MECHANICAL CONTRACTOR ON PROJECT.
7. CALCIUM CHLORIDE OR ADMIXTURES CONTAINING CALCIUM CHLORIDE ARE NOT PERMITTED IN ANY CONCRETE MIX. 9. PROVIDE STIFFENER PLATES ON BOTH SIDES OF BEAM WEBS AT ALL CONCENTRATED LOADS ABOVE AND BELOW A BEAM. UNLESS NOTED B. STAIR CONSTRUCTION SHALL BE:
F. NO METAL ROOF DECK OPENINGS SHALL BE CUT UNLESS AUTHORIZED AND/OR DIRECTED BY THE STRUCTURAL ENGINEER. WHEN
OTHERWISE, FRAME THE LARGEST BEAM OVER COLUMNS AT BEAM TO BEAM INTERSECTIONS.
8. CONTRACTOR SHALL USE SMOOTH FORMS FOR EXPOSED CONCRETE SURFACES. ANY CONCRETE SURFACE REPAIRS SHALL BE PERFORMED a. METAL PAN WITH 2” NORMAL WEIGHT CONCRETE FILL ON TREADS AND INTERMEDIATE LANDINGS, HAVING A TOTAL AVERAGE DEAD
OPENINGS ARE REQUIRED, THE FOLLOWING RECOMMENDATIONS APPLY: DRAWN BY: PE
BY THE CONTRACTOR AS REQUIRED. REPAIR AND PATCH DEFECTIVE AREAS WITH PROPRIETARY PATCHING COMPOUND IMMEDIATELY AFTER 6" OPENING OR LESS (ONE RIB REMOVED) - NO REINFORCING REQUIRED
10. SPLICES SHALL BE ALLOWED ONLY AT LOCATIONS INDICATED ON THE STRUCTURAL DRAWINGS, UNLESS APPROVED BY THE STRUCTURAL LOAD OF NOT MORE THAN 50 PSF.
REMOVAL OF FORMS. 6" TO 8" OPENING (ONE RIB REMOVED) - 18 GA. REINFORCING PLATE, SCREWED TO ADJACENT RIBS,
ENGINEER. UNLESS NOTED OTHERWISE, FRAME THE LARGEST BEAM OVER COLUMNS AT BEAM TO BEAM INTERSECTIONS.
6. CONNECTIONS TO BASE BUILDING STRUCTURE
PROVIDED BY STEEL SUPPLIER. CHECKED BY: PE
9. PROVIDE A 3/4'' CHAMFER ON EXPOSED CORNERS OF CONCRETE UNLESS NOTED OTHERWISE. TOP SURFACE OF WALLS SHALL BE FINISHED 8" TO 12" OPENING (TWO RIBS REMOVED) - 16 GA. REINFORCING PLATE, SCREWED TO ADJACENT RIBS,
11. CONTRACTOR SHALL ELECTRONICALLY SUBMIT STEEL SHOP DRAWINGS FOR APPROVAL PRIOR TO FABRICATION. CONTRACTOR SHALL REVIEW
SMOOTH, UNLESS NOTED OTHERWISE. PROVIDED BY STEEL SUPPLIER.
AND STAMP ALL SHOP DRAWINGS BEFORE SUBMITTING TO THE ARCHITECT. A. CONNECTION OF STAIRS TO THE BASE BUILDING STRUCTURE SHALL BE DESIGNED AND SUPPLIED BY THE STAIR SUPPLIER SUBJECT TO THE
OPENINGS OVER 12" STEEL ANGLE FRAME, AS SHOWN ON THE STEEL DETAIL DRAWINGS
CONDITIONS INDICATED HEREIN AND COORDINATED WITH ALL OTHER TRADES AND SUBCONSULTANTS. SIGNED AND SEALED STAIR
10. CONTRACTOR SHALL PROVIDE SUITABLE WIRE SPACERS, CHAIRS, TIES, ETC FOR SUPPORTING REINFORCING STEEL IN THE PROPER POSITION - ARE REQUIRED, PROVIDED BY STEEL SUPPLIER.
12. THE STRUCTURE IS STABLE ONLY IN ITS COMPLETED FORM. CONTRACTOR SHALL DETERMINE, FURNISH AND INSTALL ANY TEMPORARY BRACING DESIGNS, INCLUDING CONNECTION LOCATIONS AND LOADS, SHALL BE PROVIDED PRIOR TO OR CONCURRENT WITH THE REVIEW OF SHOP
WHILE PLACING CONCRETE. OR GUYS REQUIRED TO ERECT STEEL MEMBERS. TEMPORARY BRACING SHALL BE LEFT IN PLACE UNTIL THE PERMANENT STRUCTURE IS IN
PLACE AND SECURE.
DRAWINGS FOR THE SUPPORTING BASE BUILDINGS STRUCTURAL ELEMENTS. CONNECTION CALCULATIONS SHALL INCLUDE CONSIDERATION
OF ALL LOCAL EFFECTS IMPOSED ON THE SUPPORTING MEMBERS.
10. MOVEMENT ACCOMMODATION BY BUILDING COMPONENTS. GENERAL NOTES
11. PROVIDE 1/2'' EXPANSION JOINT MATERIAL AT INTERIOR LOCATIONS WHERE SLABS ABUT WALLS, COLUMNS, AND OTHER VERTICAL SURFACES A. BUILDING COMPONENTS SUPPORTED ON THE BASE BUILDING STRUCTURE, SUCH AS CLADDING SYSTEMS, PARTITIONS WALLS,
UNLESS NOTED OTHERWISE. OPERABLE PARTITIONS, ETC., SHALL BE DESIGNED AND DETAILED TO ACCOMMODATE STRUCTURAL MOVEMENTS INDICATED BELOW:
13. STRUCTURAL STEEL FRAMING SHALL BE TRUE AND PLUMB BEFORE CONNECTIONS ARE FINALLY BOLTED OR WELDED. B. CONNECTIONS FOR INTERMEDIATE LANDINGS ARE ASSUMED TO BE MADE AT THE FAR END OF THE STAIR STRINGER OPPOSITE THE
CONNECTION AT THE FLOOR LEVELS, UNLESS NOTED OTHERWISE. IT IS SUGGESTED THAT ALTERNATE SUPPORT LOCATIONS BE
12. TIME BETWEEN CONCRETE BATCHING AND PLACEMENT SHALL BE IN ACCORDANCE WITH ASTM C94. B. VERTICAL MOVEMENTS
14. ANY HOLES, CUTS, OR COPING FIELD CUT INTO STEEL MUST BE VERIFIED WITH THE STRUCTURAL ENGINEER PRIOR TO WORK. CONTRACTOR SUBMITTED FOR REVIEW PRIOR TO COMPLETION OF THE STAIR SHOP DRAWINGS.
a. FLEXIBLE CLADDING SYSTEMS: 1/2"

S
SHALL COORDINATE ALL HOLES REQUIRED BY OTHERS WITH THE STRUCTURAL ENGINEER.
13. ADDITION OF JOBSITE WATER TO CONCRETE SHALL BE PER ASTM C94. b. BRITTLE CLADDING SYSTEMS: 3/8”
C. ALL LOADS APPLIED TO BASE BUILDING SHALL BE ATTACHED SUCH THAT ROTATION OF THE BASE BUILDING STEEL FRAMING IS RESTRAINED,
c. INTERIOR PARTITION DIFFERENTIAL MOVEMENT BETWEEN FLOORS: 1 1/2"
15. THE STEEL SUPPLIER SHALL COORDINATE HIS WORK WITH OTHER DELEGATED DESIGN COMPONENTS (i.e. STEEL JOISTS, PRECAST CONCRETE, UNLESS NOTED OTHERWISE. PROVIDE CONCENTRIC CONNECTIONS WHERE POSSIBLE, OR DESIGN AND PROVIDE KICKERS OR OTHER
14. ALL CONCRETE SLABS SHALL BE CURED PER ACI 308.1 RECOMMENDATIONS. d. OPERABLE PARTITIONS HUNG FROM ABOVE: 2 1/2”
STEEL STAIR COMPONENTS, ETC.). MEANS OF RESTRAINT IF NECESSARY.
15. CONTROL JOINTS SHALL BE PLACED IN CONVENTIONAL SLAB ON GROUND WITHIN 24 HOURS OF INITIAL POUR. REFER TO PLAN NOTES FOR C. HORIZONTAL MOVEMENTS

001
16. ALL BEAMS TO BE PLACED WITH POSITIVE CAMBER (INCLUDING NATURAL BEAM CAMBER) UPWARD. STRUCTURAL ENGINEER RECOMMENDS
ADDITIONAL INFO. a. CLADDING SYSTEMS – IN-PLANE: H/400
CONTRACTOR PERFORM A PRE-POUR SURVEY OF THE FRAMING TO ENSURE CAMBERS ARE WITHIN TOLERANCE. COORDINATE ALL INFORMATION
b. CLADDING SYSTEMS – OUT-OF-PLANE: L/240
PRIOR TO CONCRETE POUR WITH STRUCTURAL ENGINEER.
16. WELDING OF REINFORCING STEEL SHALL NOT BE PERMITTED FOR NONWELDABLE REBAR NOR WITHOUT THE CONSENT OF THE STRUCTURAL
ENGINEER 17. STEEL SUPPLIER SHALL VERIFY ALL MEPF EQUIPMENT, DISTRIBUTION SYSTEMS, AND BUILDING EQUIPMENT WEIGHTS, SIZES, AND LOCATIONS
PRIOR TO PREPARING SHOP DRAWINGS AND FABRICATING MATERIALS. CONTRACTOR TO COORDINATE ANY CHANGES w/ STEEL SUPPLIER AND
17. DOWELS FOR SUCCESSIVE WORK SHALL BE SECURELY FASTENED IN CORRECT POSITION BEFORE PLACING CONCRETE. THE STICKING OF STRUCTURAL ENGINEER.
DOWELS AFTER PLACING CONCRETE SHALL NOT BE PERMITTED.
18. PROVIDE SUPPORT AT COLUMNS AS REQUIRED FOR DECK SUPPORT. PROVIDE L2x2x3/16 MINIMUM.
PROJ. NO. 2023-50

You might also like