Contents
1 INTRODUCTION.....................................................................................................3
2 SCOPE: ..................................................................................................................3
3 SAFETY:.................................................................................................................3
3.1 Potential Hazards and Risks:...............................................................................................3
3.2 Environmental Hazards and Risks:......................................................................................5
3.3 General Safety Requirements:.............................................................................................6
4 RESPONSIBILITIES:..............................................................................................6
4.1 Project Director: ...................................................................................................................7
4.2 Construction Manager Tunnel:.............................................................................................7
4.3 Project Engineer Tunnel: .....................................................................................................7
5 ABBREVIATIONS: .................................................................................................7
6 REFERENCES: ......................................................................................................8
6.1 Specifications.......................................................................................................................8
6.2 Project Procedures ..............................................................................................................8
6.3 Project Work Method Statements ........................................................................................8
6.4 Drawings ..............................................................................................................................8
8 ATTACHMENTS...................................................................................................13
1 INTRODUCTION
This document sets out the Work Method Statement for the installation of Rock Bolting for
stabilization of excavated slopes and tunnel surfaces in order to carry out the works in
planned and systematic manner.
2 SCOPE
To set out the requirements for rock bolting on the Chenani- Nashri Tunnel Project to meet
all the contract requirements and LIN standards for work operation, safety, quality and
environmental compliance .This includes the following.
i. Drilling
ii. Grouting
iii. Installation rock bolts
iv. Testing rock bolts
3 SAFETY
Rock bolting work shall be undertaken in accordance with this document, the contract
requirements, approved Leighton Safety WMS and any specific job safety analysis
conducted prior to commencement of work. The general hazards and risks and their
controls are as follows
Controls:
3.1.6 Electrocution:
i. Provisions of 30mA ELCB (Earth Leakage Circuit Breaker) in all DBs
ii. Proper earthling of all DGs
iii. All electrical equipment inspected and tagged by authorised electricians
iv. Use LOTO
v. Avoid standing in water while using electrical tools
3.1.10 Fire:
i. Certified Fire Extinguishers
ii. Obtain Hot Work Permit
iii. Housekeeping
iv. Proper fuel storage
Controls:
3.2.1 Poor Communication:
i. Proper induction for all personnel
ii. Pre-start briefs, TBTs
iii. JSEA and HSE Verification checklist developed, communicated and monitored
iv. Coordination of the communication
v. Appropriate signage for each location
3.2.3 Emissions:
i. Regular maintenance of all equipment
ii. Quarterly monitoring of exhaust emissions
4 RESPONSIBILITIES
i. The WMS shall be followed by all personnel involved in the rock bolting activity. This WMS
may be adjusted to suit adverse site conditions subject to approval of LIN Construction
Manager.
ii. Action may be delegated, but responsibilities shall not be delegated.
iii. Use of word ‘shall’ with in this document indicates a mandatory requirement.
iv. Use of word ‘should’ within this document indicates a preferred requirement.
v. Detailed responsibilities are set out in:
- ITPs
- JSEAs
- HSEVCs
5 ABBREVIATIONS:
6 REFERENCES:
6.1 Specifications
Refer Attachment 1 List of References.
6.4 Drawings
Refer Attachment 2 Drawings.
7.1 Methodology
7.1.2 Installation
i. Rock Bolts:
- Rock Bolting shall be carried out as shown on the design drawings.
- Jumbo shall drill the boreholes for all rock bolts to the depths as per requirement/ design.
- Borehole shall be flushed / cleaned of drill cuttings and debris by flushing with high
pressure compressed air and water, jumbo will continuing to drill additional rock bolts /
rock anchors.
ii. PG Bolts:
- The hole is drilled as per the lengths as shown in the drawings.
- The bar is inserted into the hole with the grout hoses. The collar is blocked and the hole
is grouted.
- Post tensioning shall be done 8 to 12 hours after the grouting by tightening the nut of the
grouted rock bolt after installation of anchor plate. This force shall be applied by a
calibrated torque wrench.
- After the installation of the bolts a force of approximately 20KN shall be applied at the
anchor plate to tighten the nut and bolt
iii. SN Bolts:
- The hole is drilled as per the lengths as shown in the drawings.
- The grout hose shall be placed at the full depth of the drill hole and thereafter gravity in
association with internal pressure will therefore allow the grout tube/grout hose to
withdraw as the grout is pumped inside. The bolt is then driven / pushed into the hole
and shall be allowed to set for at least 8 to12 hrs.
- Post tensioning shall be done 8 to 12 hours after the grouting by tightening the nut of the
grouted rock bolt after installation of anchor plate.
- Boreholes for the rock bolts shall be drilled to the depths as required. The boreholes
shall be cleaned of all drill cuttings, sludge and debris.
- The installation of rock bolts shall be done not later than two hours after drilling of the
boreholes.
- The installation system for Swellex rock bolts consists of a high pressure water pump
coupled with an inflation chuck that is pushed over the bolt’s head bushing to conduct
the water flow from the pump to the inside of the bolt.
- The water pumps used for this operation are high pressure pumps that can rapidly and
safely deliver the 300 bars constant pressure specified for a perfect installation. The
inflation chuck is a safe and simple system that grips and injects the water inside the of
the Swellex bolt.
- Once the inflation is completed, the pressure is released manually, or automatically, like
with the electric and hydraulic versions of the pump.
- Swellex Pump PSP 240/300 shall be used. The rock bolt shall be drained after inflation.
Rock Bolts
Progressing Face
Round length as
Zone B Zone A (Max 30) per Support Class
Rock Bolts
Progressing Face
Round length as
Zone B Zone A (Max 20) per Support Class
8 ATTACHMENTS
ATTACHMENT 1 LIST OF REFERENCES
ATTACHMENT 2 DRAWINGS
ATTACHMENT 3 CHECKLISTS
ATTACHMENT 4 ITP & CHECKLISTS
ATTACHMENT 5 EQUIPMENT LIST
ATTACHMENT 6 RISK ASSESSMENT
ATTACHMENT 7 JSEA & CHECKLISTS
ATTACHMENT 8 HSE CHANGE REQUEST FORM WITH RESIDUAL RISK > 6
ATTACHMENTS
Applicable Specifications
As per section 6.1 Specifications, the following are applicable to this WMS:
i. IS Code:8112:1989 Cement Specification
ii. IS Code 9103:1999 Admixture Specification
iii. ISRM: Doc. 2 or IS 11309 Rock Bolting
Attachment 2 Drawings
Applicable Drawings
As per section 6.4 Drawings, the following are applicable to this WMS:
(Please refer to the latest revision of the drawings)
Tunnel
Heading
Tunnel Meter (TM)
Round Number
Installed Support :
General Information:
Valid RESS No.
Deformation tolerance mm
Round length m
I1007-OPR-FM-020A(2)
I1007 - CHENANI-NASHRI TUNNEL PROJECT
Sheet No. :
Tunnel
Heading
From Tunnel Meter (TM)
To Tunnel Meter (TM)
Round No.
General
Rock Class
Deformation Tolerance (d) mm
Round Length of Excavation m
Max/Min Ring Closure Distance m
Reference Drawings
Note : Indicate any changes to designed support system in the table below
Remarks:
I1007-OPR-FM-020B(2)
I1007 - CHENANI-NASHRI TUNNEL PROJECT
Sheet No.:
RBI-
ROCK BOLT / SOIL NAIL INSTALLATION REPORT TunName-
Heading-
Portal Drawing no
Slope Instruction no
Sketch: Remarks:
SIGNATURE :
SIGNATURE :
I1007-OPR-FM-014B(2)
Chenani-Nashri Tunnel Project Rock Bolting
WMS No.: I1007-LIN-OPR-WMS-TL-0003 (6)
3 Material
4 Rock Bolting
5 Post Grouting
Installation of Bearing Plates & Nuts IS 15026 & Contract doc 4.6.2.1
5.1 Visual Inspection During Installation I1007-OPR-FM-020A W Tunnel Engineer
etc vol III
5.3 Compressive Strength Test Visual Inspection IS 516/Contract Document 5 cubes every week As per QC manual for material R QC Engineer
*H = HOLD (Don't Proceed to next activity unless cleared exclusively) R = REVIEW (Work may proceed but the verification record to be given for review) Contractor = Leighton Contractors (India) Pvt. Ltd. W = Witness
I1007-LIN-QAM-ITP-TL-0003(5)
ROCK BOLT TEST
DATA SHEET
TEST RESULTS :
Displacement at Maximum Pull Force :- mm
Remarks:
SIGNATURE : SIGNATURE :
I1007-QAM-FM-TL-0003B(3)
Chenani-Nashri Tunnel Project Rock Bolting
WMS No.: I1007-LIN-OPR-WMS-TL-0003 (6)
ATTACHMENT-5
Tunnel Excavation
(Drilling, Blasting,
S. No Equipment Make Model Description Remarks
Mucking and
Deposition)
1 Additional Cement Silo 100ton
4 Bar Bending
5 Bar Cutting
10 Container 20 20 Ft
11 Container 40 40 Ft
15 Dozer Cat D6
16 Dozer Cat D5
Page 1 of 2
Leighton Contractors (India) Pvt Ltdeighton Contractors (India) Pvt Ltd
ATTACHMENT-5
Tunnel Excavation
(Drilling, Blasting,
S. No Equipment Make Model Description Remarks
Mucking and
Deposition)
31 Light Tower IR 1000w x 4
42 Rescue Container
Page 2 of 2
Chenani-Nashri Tunnel Project Rock Bolting
WMS No.: I1007-LIN-OPR-WMS-TL-0003 (6)
Cause of
People/ Adverse Effect / Type
Ctrl Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental L1 S1 RFN ** Mitigating Controls L2 S2 RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
Moderate/ Acceptable
Provide proper benching and/or sloping techniques. Must BOCW Act'96
Collapse of excavation walls Serious injury / fatality 3 4 12 E&A 2 4 8 with review JSEA
include adequate safe access/egress BOCW Central Rules'101
required
Operator,
Personnel trained in signalling, spotters in place visible to all
Helper of the
personnel, stop whistles,
drilling m/c,
Reverse alarm on all mobile equipment, Motor Vehicle Act'88
Rock Bolting Other Operatives
Pre-start checks of all mobile equipment, Moderate/ Acceptable
& workers working
Struck by machinery Serious injury / fatality 3 4 12 E&A Competency assessment of the operators, 2 4 8 with review JSEA BOCW Act'96
nearby,
Limit the speed of any vehicles in the work area to 10km/h, required
Job Supervisors,
No personnel to be in front of drill m/c, BOCW Central Rules'98
Adequate lighting.
Authorised personnel only to be in the work area
Personal Injury,
Usage of eye protection and proper hygiene practices,all the BOCW Act'96
Flying projectiles and air borne Eye irritation / injury/ Skin
3 3 9 A&P worker will be provided with proper PPE 2 2 4 Tolerable
particles irritation
experienced and certified driller, good work practices, BOCW Central Rules'99
Wet drilling,
Dust eye injury, lung damage 3 3 9 E&P 2 3 6 JSEA
Wear dust mask/respirator, eye protection
Moderate/ Acceptable
Install barriers, guards, BOCW Act'96
Pinch points Injury to persons 3 3 9 E&A 2 3 6 with review JSEA
Identify and communicate in Tool Box Talks BOCW Central Rules'102
required
Dust supression,
Speed Limit,
Suffocation,Community Permit to Excavate – I1007-HSE-FM-
Minimise topsoil stripping during windy condition,
Nuisance Dust health, 3 2 6 E&A 2 2 4 Tolerable 036A
Staging land clearance activities to keep total area cleared to
Air protection Act'1986
minimum,
Cover stockpiles,
Frequency Severity Risk Factor Number (RFN) Residual Risk Number (RRN) * Prepare Job Safety Analysis and Safety Verification
1: Unlikely/Improbable 1: Negligible 1-2: Trivial/Acceptable 1-2: Trivial/Acceptable Checklist when RRN is > 6
2: Remote 2: Slight 3-5: Tolerable 3-5: Tolerable ** Prepare Safety Verification Checklist when RFN is > 6.
3: Quite Possible/Occasional 3: Moderate 6-9: Moderate/Acceptable with Review 6-9: Moderate/Acceptable with Review L1 Likelihood as is
4: Likely/Probable 4: Critical/High 10-15: Substantial 10-15: Substantial L2 Likelihood with mitigating controls in place
5: Very Likely/Frequent 5: Catastrophic/Very High 16-25: Intolerable/Unacceptable 16-25: Intolerable/Unacceptable S1 Severity as is
S2 Severity with mitigating controls in place
Mitigating Controls Control Type Hierarchy
Select controls based on the Control Type Hierarchy. EL - Elimination BEST
Remember: Multiple controls will provide assurance S - Substitution
for best results. E - Engineering
A - Administrative
P - PPE WORST
JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED (Eg. Remove overhead cable or ACTION BY/RECORD
(Eg. Set Up Crane) (Eg. Electrocution from 11Kv Cables) isolate/sheath overhead or monitor with spotter) Training PPE Needs (Eg. Supervisor)
1. Ensure jumbo is set on stable ground, to be checked by operator and
Tunnel Foreman.
Tunnel Engineer/Foreman – Competency
2. Competency Assessment of the Operators,
Assessment of Operators, Take-5
1. Set Up Jumbo Tipping of machinery on unstable ground 3. Pre-start checks of the machine,
4. Demarcate operational area.
Operator – Prestart Checks (daily)
5. Erect No Entry Signs.
6. Jumbo movements controlled by a banksman
1. Task specific briefings.
2. Experienced / certified operators /foreman / banksman.
Tunnel Engineer/Foreman – Take-5, TBT,
3. All personnel to have undergone induction training, use of self rescuer,
Pre-start brief,
4. Separate route for pedestrians and vehicles,
Being struck by moving machinery
5. All moving vehicle shall have the reverse horn (working),
TM(Traffic Management) Supervisor – all
6. Adequate area lights at the work area, access routes,
traffic management issues, signs etc
7. On job training (as per the training needs and matrix) for all the
associated persons.
1. Task specific briefings.
2. Experienced / certified operators /foreman / banksman.
Tunnel Engineer/Foreman – Take-5, TBT,
3. All personnel to have undergone induction training, use of self rescuer,
Pre-start brief,
4. Separate route for pedestrians and vehicles,
2. Drilling Rock Bolt Holes Being Struck by Machinery
5. All moving vehicle shall have the reverse horn (working),
TM(Traffic Management) Supervisor – all
6. Adequate area lights at the work area, access routes,
traffic management issues, signs etc
7. On job training (as per the training needs and matrix) for all the
associated persons.
1. Demarcate operational area.
2. Noise monitoring to establish control zone.
3. Awareness of operational parameters of Jumbo. Safety officer / Tunnel Foreman – gas,
4. Dust monitoring/ gas monitoring. noise testing record, Take-5, HAZID,
Noise/Dust/Explosive Gas 5. Efficient and maintained ventilation system.
6. Wet drilling
7. Task Specific Briefings. Training in use of Specific PPE such as
respirators,
8. PPEs - Mandatory PPE plus eye protection/dust masks
1. Only approved work access appliances to be used
2. No over-reaching, wearing of safety harness
Tunnel Engineer /Foreman.
3. Installation of Rock Bolt Fall from Height 3. Safety Inspections
Inspection/Installation record
4. Mandatory PPE plus safety harness/dust masks/eye
protection/disposable coveralls/rubber gloves/gauntlets
1. Task specific briefings.
2. Training in use of specific PPE such as safety harness Safety Officer/Tunnel Foreman. Briefing
Dust/chippings
3. Briefing on use of chemicals with regard to MSDS and COSHH Record. Briefings by Suppliers
regulations
1. Mixing use of chemicals under supervision of materials
Chemical Burns Safety Officer. PPE receipt
engineer/technical
Dec 2010 Page 2 of 3 I1007-HSE-FM-001B(0)
Leighton Contractors (India) Pvt Ltd
PROJECT: Chenani-Nashri Tunnel Project, Jammu & Kashmir Responsible Person : Tunnel Engineer
JSEA No.: JSEA/TUN/013 Frequency of Inpection : Weekly
Activity : Rock Bolting HSEVC No: 2 Date: 5/02/2011
Action Taken Action Closed
ITEMS TO BE CHECKED
(indicated by tick) ACTION REQUIRED (indicated by tick)
(Taken from JSEA)
Yes No Yes No
Set Up Jumbo
1. Ensure jumbo is set on stable ground, to be checked by operator
and Tunnel Foreman.
2. Competency Assessment of the Operators,
3. Pre-start checks of the machine,
4. Demarcate operational area.
5. Erect No Entry Signs.
6. Jumbo movements controlled by a banksman
7. Task specific briefings.
8. Experienced / certified operators /foreman / banksman.
9. All personnel to have undergone induction training, use of self
rescuer,
10. Separate route for pedestrians and vehicles,
11. All moving vehicle shall have the reverse horn (working),
12. Adequate area lights at the work area, access routes,
13. On job training (as per the training needs and matrix) for all the
associated persons.
Excavation
Manual Handling
Initiator: Date:
Other Materials
C: Hazard Identification
E: Risk Assessment
Overall Risk Level after Change (Intolerable, Substantial, Moderate, Tolerable, Acceptable)
Attach Risk Assessment to back of form
If change is Moderate to Intolerable, Initiator must update Risk Register
8. Does the modification required approval from Original Equipment Manufacturer? Yes / No / NR
9. Does the modification have an impact to other parties or supporting documents? Yes / No / NR
G: Approval
Name Signature Date Accept / Reject
Department Manager
Project Manager
Comments:
H: Actions
Action Who needs to be informed Date Responsibility
E. Review
Review Date: