Professional Documents
Culture Documents
METHOD STATEMENT
AND DESIGN FOR SECANT PILE
CONTENTS
1.0 Introduction............................................................................................................................................. 2
2.0 Secant Pile Wall....................................................................................................................................... 3
1 Programme............................................................................................................................................. 5
2 Document References............................................................................................................................... 5
3 Personnel and Competencies...................................................................................................................... 5
4 Plant and Equipment................................................................................................................................. 6
5 Main Material Requirements........................................................................................................................ 6
6 Setting Out / Survey.................................................................................................................................. 6
7 Emergency Arrangements........................................................................................................................... 7
8 Other Associated Plan............................................................................................................................... 7
9 Health & Safety Controls............................................................................................................................. 7
10 Environmental Controls.............................................................................................................................. 7
11 Quality Controls........................................................................................................................................ 7
12 Monitoring and Review............................................................................................................................... 8
Method Statement Review / Risk Assessment Review.................................................................................8
(Append additional copies for any subsequent changes)..............................................................................8
Appendix B.................................................................................................................................................... 9
QHSE Risk Assessment................................................................................................................................ 9
Appendix C.................................................................................................................................................. 10
Drawings..................................................................................................................................................... 10
1 Introduction
This document explains in detail the Method Statement & Design for Secant Pile wall showing system for
circular pits.
Trial trenches by Main Contractor to locate all the underground services. The main
contractor shall take care for the location of services passing very close to the shoring
system.
Mobilization of piling equipment to the existing ground by Shoring Contractor.
Installation of guide wall for construction of Secant pile wall by shoring contractor
Installation of Capping beam by Main Contractor
Dewatering system to be made operational by the Showing Contractor before encountering
water.
Excavation to final level by Main Contractor.
1.2 General
A secant pile wall shoring system is proposed as shown below:
The existing ground level on site is at +5.50 m. General excavation and leveling of the site
will be made to prepare the working platform level.
The primary piles are un-reinforced piles. The characteristic strength of concrete for all piles
shall be 20/N / mm2., The secondary piles are reinforced pile with concrete strength 40 N/
mm2.
The piles shall be installed by over cutting the piles installed on the previous day by 200mm.
The c/c distance between the piles after installation shall be 800 mm for 1000 mm diameter
piles.
ensure good quality and contamination free concrete. The concrete will be removed before
setting and chipped to cut off level for the installation of capping beam.
2.3 MATERIALS
Concrete - Piles : Grade 20 / 20 (OPC) – Primary Piles
Grade 40/20 (OPC) – Secondary Piles
Appendix A
Appendix B
Appendix C
Drawings