"Community Support Projects (public facilities/spaces)" According to Schedule

below is approximately 11 days


3-Baseline Plan of Work to Complete a Community Support Projects (public facilities/spaces)

PROJECT NAME DURATION PROJECT START DATE PROJECT END DATE


Rehibiltation of (public facilities/spaces) 11 Days 16-02-24 26-02-24
INSTALLATION OF WATER TANKS
Done by Eng.Essam Alhayek
DAY WED THU FRI SAT SUN MON TUE WED THU FRI
Category

16-02-24

17-02-24

18-02-24

19-02-24

20-02-24

21-02-24

22-02-24

23-02-24

24-02-24

25-02-24
Task ID
Task

Task Start
Task Description Duration Date
End Date

Supply and in Casting reinforced concrete base "1.5*1.5*0.2"with


sanitation Work 3 16-02-24 18-02-24
1

X X X
steel mesh 10mm 1 bar every 25 cm
Supply and install a horizantal pllastic septic tank with a capacity of
sanitation Work 3 17-02-24 19-02-24 X X X
2

1000 litter 3 layer Part 1


Supply and install a horizantal pllastic septic tank with a capacity of
sanitation Work 3 19-02-24 21-02-24
3

X X X
1000 litter 3 layer Part 1.2
Supply and install a horizantal pllastic septic tank with a capacity of
Closing Project 3 22-02-24 24-02-24 X X X
4

1000 litter 3 layer Part 1.3


Connecting the existing llatrinre outlet with the new installed holding
aluminum work 1 25-02-24 25-02-24
5

X
tank
hedule

OJECT END DATE

26-02-24