Professional Documents
Culture Documents
LNG Operations
The det ails provided in this doc ument are relevant to c argo
Please c lic k on the headings to go to the par tic ular topic. You c an
retur n bac k to this page by c lic king on the symbol ( ) provided in the
page fo oter.
Index
• Coo l i n g D ow n
• L a you t D ra w i n g
• Pre p a ra t i o n
• Monitoring
G a s Tra n s p o r t (N o 96)
Te ch n i g a z (M AR K I I I) a n d I H I -S PB (I MO B -t y p e)
M os s
• Coo l d ow n a n d I n su l a t i o n S p a ce s
Coo l i n g D ow n
LNG is supplied from the ter minal to the liquid manifold c onnec tion. It is
fed into the c argo tanks via c o oling spray r ings loc ated inside each tank
vapor dome. The gas produc ed in the c argo tanks f lows into the vapor
header via the baf f les at the top of the vapor dome and is then free
f lowed to the ter minal via the vapor crossover and the vapor manifold.
If the ter minal is unable to handle the volume of gas being produc ed, the
f low rate of LNG liquid will have to be reduc ed to prevent a r ise in tank
hour s, preferably with the c ool down rate at bet ween -10 OC to -12 OC per
hour.
Lower spray r ing with small bore noz zles (diameter: 3/8 ”)
N oz z l e
Ca rg o ta n k
numbers
N o 1 Tank: 6
N o 2 Tank: 9
N o 3 Tank: 9
N o 4 Tank: 8
Coo l i n g D ow n Ca rg o Ta n k s
Upper sprayer r ing with large bore noz zles (diameter: 3/4”)
N oz z l e
Ca rg o ta n k
numbers
N o 1 Tank: 9
N o 2 Tank: 14
N o 3 Tank: 14
N o 4 Tank: 13
S p ra y N oz z l e
S p ra y N oz z l e
P re p a ra t i o n
operation.
domes opened.
(Normally larger sprayer nozzles on the upper spray ring are used, unless
the nitrogen production system is unable to cope with the rate of cool
down, the smaller nozzles on the lower spray ring may be used instead).
relevant valves are opened and (Using the Control System) the set point
on the Primary Insulation Supply control is set to 5.0 mbar and pressure
The set point on the Secondar y Insulation Supply control is set to 6.0
mbar and pressure reading checked to be taken from the primar y header.
7. Using the Control System the set points of the insulation spaces exhaust
control valves is set as follows: Secondar y Exhaust 6.5 mbar, Primar y
11. Cargo tank 1 to 4 spray hydraulic valves at the vapor domes opened.
valves being par tially open to restrict flow and hence initial boil- of f and
pressure rise.
13. Tank pressures closely monitored and when conditions stabilize, the tank
spray control valves further opened to increase flow. If the temperature
cool down rate is too high, the spray control valves adjusted by throttling in
15. However as the operation gets under way the amount of gas generated
is a distinct possibility.
are required:
ii. Using the Control System, the set point of both HD c ompressor s
vane c ontrol valves are adjusted to the required value.
inc reased and ensured to maint ain positive pres sure in supply line.
19. When the cargo tanks bottom temperature reaches -100 OC the spray
control bypass valves are opened to maintain the same cool down rate.
20. When all tanks have attained the required temperature (i.e -100 OC at top,
manifold double shut valves and all c argo tanks loading valves.
the temperature of the tank bottoms are close to -160 OC with a few
centimeters of liquid at tank bottoms.
22. The cargo tanks stripping/spray header valves are lef t opened to allow
the lines to warm up to the ambient air temperature before closing them.
25. Using the Control System the set point on the Primary Insulation Supply
control is set to 3.0 mbar and the Secondary Insulation Supply control is set
to 4.0 mbar. pressure reading checked to be taken from the primary header.
26. Using the Control System the set points of the insulation spaces exhaust
Monitoring
Matter Re q u i re d va l ues
Optimum LNG liquid f low rate 10 0 m 3/ hr with a pressure of 5 bar
G a s Tra n s po r t (N o 96)
The temperature reading of the ther moc ouples on the tr ipod mast,
membranes and insulation spac es are monitored dur ing c ool down and
eac h t ank has temperature s of -10 0 OC at the top and -13 0 OC at the
Tech n i g a z (M AR K I I I) a n d I H I -S PB (I M O B -t y p e)
of -13 0 OC or lower. Nor mally from design point of view, it is ac c ept able
M os s
Coo l d ow n a n d I n su l a t i o n S p a ces
Dur ing c ool down the volume of nitrogen in the pr imar y insulation
be nec essar y to chec k the nitrogen supply f low to the pr imar y and
If the demand of nitrogen is greater than the produc tion of the t wo (2)
Nitrogen produc tion unit s, the pressure in the pr imar y insulation may fall
below atmospher ic and the c ontrol of the outlet valve from the Nitrogen
storage tank end of the inlet valve to the pr imar y insulations will have to
supply line.
If the pressure in the primar y insulations were to fall below - 30 mbar g the
c o oling down would have to be slowed down. This ef fect will c ontinue
until af ter the tanks have been c o oled and loading has st ar ted due to the
mbar and the sec ondar y insulation spac es pressure to 3 mbar pr ior to
These initial pressures ease the demand on the nitrogen produc tion