Professional Documents
Culture Documents
1 – Create Order
We might need some items for a Maintenance order for which no stock is kept.
So these are non-stock items and are only procured only when they are needed,
and are consumed immediately.
Take example of the BOM we created before.
IH03 will display the structure of the cube, where we have an equipment, which
has a number of materials as components.
Create a Maintenance order = IW31
Order Type = PM02
Equipment = equipment form the BOM
Plan Plant = 1000
Press Enter
Components Tab:
As we need to change / replace some component, and for the purpose of this
exercise we are considering this item to be non-stock item. The component
could be readily available in the mkt or it could be a part which rarely needs
replacement so no stock is kept.
Component = give the component needed, and the qty
Press Enter
System asks for Item Category (this defines if the item is a stock or a non-stock
item).
Item Category = N (non-stock)
Release the order to update the plan cost.
PR now needs to be converted into PO, or we can create a PO directly with the
PR
3 – Convert PR to PO
PO Create = ME21N
On the item line enter the PR number in Purchase Req column, and press enter.
SAP will copy the data from PR to the PO, Now complete the PO with the
Vendor number etc.
The component will be directly consumed to the PM Order, and stock quantity
will not change.
Display the order in IW32 and check the costs, the actual cost for the
component will now be posted.
Process as per normal to confirm the order in IW41, and the remaining
processes of technical completion, variance posting, settlement and business
completion.