Subcontracting Process in SAP
MM
1. Create subcontracting Info record (Optional) – T Code – ME11
2. Create subcontracting PO with item category L – T Code – ME21N
Steps: ME21N —> Enter Item Category L –>, Material (End Product), PO Quantity, Delivery
Date, Net Price, Plant –> Click on Item Details –> Tab Material Data — >Components, select
Explode BOM –> Click on Components button –> Enter the sub components –> Go back &
Save.
Note: Components can be exploded through BOM (T Code CS01) or components can be given
manually also.
3. Create Transfer Posting with Movement Type 541 to issue the sub components to the vendor T
Code -ME2O/ MIGO
4. Goods Receipt for finished product – T Code -MIGO
Note: During goods receipt, final product will be received with movement type 101 and
components will be consumed automatically with 543 movement type
5. Invoice Receipt for the services performed – T Code – MIRO
Accounting entries for subcontracting: Example: Components cost is 100 INR,
Subcontracting Charges are 40 INR
There will be no account entries at transfer posting 541.
Accounting entries at the time of Goods Receipt 101 (&543) : Finished goods will be
received with 101 and the Components will be consumed with Movement type 543.
(BSX) Stock A/c of Assembly – 140 Dr
(BSV) Change in Subcontracting Stock -140 Cr
(FRL) Subcontracting Charges – 40 Dr
(WRX) GR/IR Clearing A/c – 40 Cr
(BSX) Stock A/c of Components – 100 Cr
(GBB-VBO) Consumption A/c of Components – 100 Dr
Steps of Subcontracting Process in SAP
Let’s start with discussing the steps that are involved in the subcontracting process in SAP. They
are summarized below:
You order the end product using a subcontract order. The components that the vendor needs to
manufacture the end product are specified in the subcontract order.
The components are posted to the stock of materials provided to the vendor. The components are
then supplied to the vendor.
The vendor performs its service and delivers the ordered material (the end product). The
consumption of the components is posted.
If, after the goods receipt has been posted, the vendor informs you that a larger or smaller quantity
of the components was actually consumed than planned in the purchase order, you must make an
adjustment.
The vendor charges for his or her service. The invoice is posted.
Diagram of Subcontracting Process in SAP
Prerequisites
A material BOM needs to be created before any subcontracting order can be placed. The bill of
materials (BOM) is a formally structured list of the components that make up a product. The list
contains the object number of each component, together with the quantity and unit of measure.
Subcontracting Requisition
The subcontracting requisition lists the finished material that is to be procured in a subcontract
item. Against each subcontracted item the system copies the material components that are to be
provided to the vendor from the bill of material (BOM). The bill of material refers to the end
product that the vendor will deliver.
The requisition for subcontracting must contain the item category ‘L’ which is used for
subcontracting in the SAP system.
Subcontracting Purchase Order
Subcontracting materials are sent to vendors for processing finished products. A subcontracting
purchase order is placed by converting the subcontracting requisition into a purchase order. The
system will generate a purchase order number internally.
The rates quoted by the vendor for labour charges are mentioned in the purchase order line items.
If a purchase info record has been maintained, the service charges are defaulted into the purchase
order.
Provision of Components to Vendor for Processing
To receive material against the purchase order, SIM cards and packaging materials need to be
issued to the subcontractor. The materials that are provided to the subcontractor are managed as
stock provided to a vendor. The provision is a transfer posting from the unrestricted use stock to
the stock of material provided to a vendor.
The SIM cards supplier will be instructed to deliver the raw material at the subcontractor’s
premises. When the subcontractor receives the raw SIM cards at his premises, he will inform the
client and a goods receipt will be posted with reference to the purchase order increasing the
subcontractor stock in the system. If the material is already available in the client own stock, it
will be issued from the unrestricted use stock to the vendor. The SIM cards will be issued with
reference to the subcontract purchase order.
When the vendor delivers the ordered packaged SIM cards (the end product), the goods will be
received against the finished product with reference to the purchase order.
At the time of receipt, the raw materials for each order item will be determined and the system
will create a goods issue accounting entry item for each raw material. As a result, the material
document will consists of the following items:
Goods receipt items for the packaged SIM cards (end product) supplied by the vendor.
Goods issue items for the SIM cards (components).
The goods receipt will be valuated at the subcontract price plus the value of the SIM cards
consumed.
Subcontracting Invoice
Invoices will be entered in the system against the purchase order. The vendor will be billed only
for items delivered. At the time of invoice receipt a liability is created against the vendor. The
liability created will only be of the amount charged by the vendor for processing and does not
include the material component value.
Example of Subcontracting Process in SAP
Create a Subcontracting Purchase Order
To create a subcontracting purchase order, start the transaction ME21N or navigate to
the following path in SAP menu: Logistics→ Materials Management→ Purchasing→ Purchase
Order→ Create (ME21N).
SAP Menu Path to ME21N
Transaction
In ME21N transaction, you need to select a Document Type and provide a Vendor as shown on
the below screenshot:
Create a Subcontracting Purchase Order – Select a Document Type and Provide a Vendor
In the Item Overview screen, you need to use Item Category ‘L’ which is used for subcontracting
documents. Also, you need to provide Material, Quantity, Delivery Date, Plant, and Price.
Enter Information about Items of Subcontracting Order
Now, click Explode BOM button to open the below screen, where you provide your
components to the subcontractor.
Components of Subcontracted Product
If there are any additional charges required, you input them in the Conditions tab as shown on
the screenshot below. Finally, you save the subcontracting purchase order.
Pricing Conditions in a Subcontracting Purchase Order
Create a Transfer Posting
Use transaction MIGO to provide components to the subcontractor. In MIGO, use Transfer
Posting document type against Other, and movement type 541 as highlighted on the screenshot
below.
Create a Transfer Posting in MIGO Transaction
In the Item Overview Screen, you need to provide Material, Quantity, Plant, and Storage
Location. If the material is managed with batches, a batch number will be shown as well.
Item Overview Screen of Transfer Posting
Now, click on Detail Data button.
Detail Data Button
It will open the screenshot shown below. Here in the highlighted box you provide the number of
your subcontractor.
Enter
the Number of Subcontractor
Next, click on Check button to check whether the document is OK. Finally, click on Post button
to post the document.
Check and Post Material Document
Now, when the subcontractor returned the materials after performing the work you need to enter
the received finished material back into the SAP system by using the transaction MIGO.
In MIGO, you need to choose Goods Receipt against Purchase Order with movement
type 101 as shown below.
Goods Receipt in Transaction MIGO
Now, press to display the components provided to the subcontractor for the
finished material as shown on the screenshots below.
Display Components Provided to the
Subcontractor Com
ponents Provided to the Subcontractor
Next, click OK checkboxes as shown below. The first line corresponds to the goods receipt of
the final product, whereas the second two lines correspond to the issue of components which you
provided to the subcontractor earlier. The good receipt and the goods issue will be done
simultaneously by the SAP system.
Click OK
Checkboxes
Finally, it is necessary to click Post button to save the document.
Click Post Button to Save Transfer Posting
Now, let’s display the document that we have just created. It can also be done through
via MIGO transaction. Start it and select Display against Material Document while inputting
the document number as shown below and click Enter.
Display Material
Document (Transfer Posting)
Please note the movement types used: 101 for Goods Receipt and 543 for Issue of Components.
Items of Material Document
It is also possible to see accounting documents that were automatically generated by the SAP
system during posting of material movements. To do it, click on Doc. Info button.
Doc. Info Tab
Next, click on FI Documents button to display FI document created for goods receipt and
goods issue.
Click FI
Documents Button
The system will open a window with the list of documents in accounting. Double click
on Accounting Document.
List of Documents in Accounting
Finally, you will see the accounting document created for goods receipt and goods issue.
SAP
FI Document Corresponding to Transfer Posting
Post Invoice Receipt
The next step of subcontracting process in SAP is to do posting of invoice receipt against the
purchase order using the transaction MIRO.
Start MIRO Transaction
On the start screen of MIRO choose Invoice transaction, enter Invoice Date and Purchase Order
number and click Enter on the keyboard.
MIRO Transaction: Enter Incoming
Invoice
Next, provide Amount in the box to balance the amount of service provided.
MIRO
Transaction: Enter Details and Amount
Click on Simulate button which will notify you of any errors. If none, a green light will turn on
near Balancefield and the SAP system will show you accounting document which will be
created.
Click Simulate Button
The Results of Simulation of Invoice Posting
Finally, click on Post button to save the invoice receipt (IR).
Post Invoice Receipt