Professional Documents
Culture Documents
Section 9.1.1.4 Temporary speed warning balise groups (TSW’s); second paragraph is
replaced with the following content:
The balise group for a temporary speed restriction (TSR) shall be positioned at the Warning TSR
sign in the normal direction being protected but may be moved up to 30 m beyond the TSR
Warning sign if required.
Section 9.1.1.4 Temporary speed warning balise groups (TSW’s); fourth paragraph is
replaced with the following content:
The TSW balise group shall not be located closer than 10 m from any other balise on the same
track.
Section 9.1.1.4 Temporary speed warning balise groups (TSW’s); add the following final
paragraph:
Where a guard rail or other object is encountered in the four foot, the TSW balise group should be
relocated. As a simplified requirement, the balise shall not be any closer than 10 m from guard
rails, point's equipment or any large objects (containing metal) in the four foot.
The entire contents of Section 9.1.2 Balise installation is replaced with the following
content:
• Vortok (or the approved alternative) on-sleeper spreader beam (eClip or FastClip)
• Vortok (or the approved alternative) between-sleeper universal mount spreader beam (for
example, for TSW or where the normative balise permanent mounting methods are
impractical due to the infrastructure constraints)
Balises shall be secured in a manner that allows repeated removal and re-fixing using tools, by
authorised personnel. This should be done without damaging the integrity of the anchor or the
balise or the structural integrity of the sleeper/slab.
Balise mounting brackets, fixings, spacers, spreader beams and associated cabling shall:
The AMS project for the installation of the ETCS Level 1 LS equipment has carried out a life cycle
analysis in consultation with maintenance. The following order of preference for balise mounting
is required for the AMS project works:
i. Vortok on-sleeper spreader beam (eClip or FastClip) for concrete sleepers and slab track
ii. Direct fixing for timber sleepers, where guard rails are installed or on slab track where the
Vortok on sleeper spreader beam cannot be used
iii. Vortok between sleeper universal mount spreader beams is to be used where the on-sleeper
spreader beam or direct fixing is not possible
Replace the heading and the entire contents of Section 9.1.2.1 Direct fixing with the
following content:
Vortok (or the approved alternative) on-sleeper spreader beam mounted balises shall be fitted in
accordance with drawing M05-569.
Replace the heading and the entire contents of Section 9.1.2.2 Spreader beam installation
with the following content:
Direct fixed balises shall be mounted on a rubber mounting pad, refer to drawing M05-500 for
manufacturing details.
Note: Rigid balise spacer mounts used with direct fixing are not preferred and should
not be installed except where required to bring the balise up to within the required
vertical design limits.
Balise mounting anchor holes shall be protected by fitting a flush mounted, plastic slotted plug
when the balise has been removed for track maintenance.
For concrete strata, direct fixed mounted balises shall be fitted in accordance with drawing
M05-502.
Where balises are to be direct fixed to concrete, two flush mount M10 female 316 grade stainless
steel anchors shall be fitted into the concrete and two Class 70 316 grade stainless steel M10
bolts.
Balise fixing points shall be located along the centre line of the sleeper in accordance with
methods approved by TfNSW.
Cup washers and thread-retaining/anti-galling fluid shall be used to secure parallel thread bolts in
place.
Timber sleepers
For timber strata, direct fixed mounted balises shall be fitted in accordance with drawing
M05-501.
The balise shall be fixed using two galvanised steel coach screws of 12 mm diameter and at least
150 mm in length together with 316 grade stainless steel cup washers.
In order to ease future removal of steel coach screws in timber, lanolin grease or other approved
environmentally friendly product shall be used for lubrication in a pre-drilled hole before insertion
of the screw.
Heavily degraded timber sleepers shall not be used for balise installation and should be
considered for replacement. Where the timber degradation is not structural (surface degradation
only) and it is not practical to replace the sleeper, a chemical anchor may be considered generally
in accordance with the installation procedure detailed on drawing M05-502. When drilling a timber
sleeper for a chemical anchor, undercut the hole to ensure that the chemical (resin) plug cannot
be easily pulled out of the sleeper.
Add new Section 9.1.2.3 after Section 9.1.2.2 with the following content:
Vortok (or the approved alternative) universal beam mounted balises shall be fitted in accordance
with drawing M05-548.
The use of a universal spreader beam for a permanent balise installation is not permitted where
any other approved permanent method can be used to mount the balise and relocation is not
practical.
Section 9.1.3.1 General; first and second paragraphs are replaced with the following
content;
Balises shall be positioned clear of a DTRS train radio Transponder and a DPU in accordance
with Design Principles ESG 100.31.
• Occupies the required placement of a balise, shift the affected balise or the balise group one
sleeper increment in accordance with the permitted window of tolerance. If movement by one
sleeper is not possible, the balise/balise group shall not be installed until the DTRS train
radio transponder has been relocated.
• Is within the exclusion zone from a balise, the DTRS train radio transponder shall be
relocated.
The contents of Section 9.1.3.2 Balise alignment is replaced with the following content:
Balises shall be positioned and aligned in accordance with specification drawing M05-503.
Balises shall be mounted transversally to the rails, unless there is existing infrastructure in the
four foot, such as guard rails or check rails and so on require a longitudinal mount.
Drawing M05-545 details the longitudinal mounting method. The transverse mounting
arrangement is shown on drawing M05-501 or drawing M05-502.
Balises at guard rails shall be shall be fitted in accordance with drawing M05-558.
The contents of Section 9.1.4.2 Balise location ID is replaced with the following content:
Balise location ID plates shall be affixed to the sleeper or concrete slab adjacent to each balise in
accordance with drawing M05-544.
Section 9.1.5 Temporary speed warning (TSW) balise ID; second paragraph the drawing
number M05-546 is replaced with the following drawing number:
M05-565
Section 9.1.6 Big metal mass; second paragraph is replaced with the following content:
Authorisation:
Signature
Position Lead Signals and Lead Signals and A/Chief Engineer Director
Control Systems Control Systems Network Standards
Engineer Engineer and Services
Engineering Specification
SPG 0706
INSTALLATION OF TRACKSIDE
EQUIPMENT
Version 2.3
Disclaimer
This document was prepared for use on the RailCorp Network only.
RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be
sufficient to ensure safe systems or work or operation. It is the document user’s sole responsibility to ensure that the
copy of the document it is viewing is the current version of the document as in use by RailCorp.
RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes
any liability which arises in any manner by the use of this document.
Copyright
The information in this document is protected by Copyright and no part of this document may be reproduced, altered,
stored or transmitted by any person without the prior consent of RailCorp.
Document control
Version Date Summary of change
1.0 30 August 2006 Version 1.0 of this Specification replaced
Specification No SC 00 47 00 00 SP - Installation
of Trackside Equipment Version 2.6 of 12 July
2005.
1.1 20 March 2007 Amend 7.2.1 to delete last paragraph and move to
new section 7.4 (Identification of Points) with
additional details
1.2 18 June 2007 New paragraph added to end of Section 5 re:
trainstops out of use.
1.3 26 February 2009 Level Crossing requirements transferred to Level
Crossing Specifications SPG 0723 and SPG
0724.
Section on signal post foundations transferred
across to Specification SPG 0705.
Minor changes all sections.
Focusing of LED & Incandescent colour lights
moved to Appendix.
Section 2.1.4 revised for safe access to ladders
and landings.
Section 2.2.2.1 added last paragraph.
Section 2.2.2.6 Other Considerations, re-written.
Added Section 2.2.3 Protective Barriers.
Section 2.3 main red datum height corrected.
Section 2.4 corrected foundation bolt sizes.
Moved information on signal gantry cages from
Section 3.2 across to SPG1571.
Section 3.4 has been moved and is now section
15.4 ‘Subsidiary Signals, Horizontal and Vertical
Shunt Signals’.
Section 4.1 Guards Indicator. Information copied
in from SPG 0705.
Section 5 Buffer Stop Lights. Information copied in
from SPG 0705.
Section 6 revised.
Section 7 Train Stops. Information copied in from
SPG 0705.
Section 8 Track circuits. Information copied in
from SPG 0705.
Added Section 9.1 Points.
Deleted first paragraph in sect 9.4
Insulated Joint stagger was 2m. Refer to revised
sketch 0706/003.
Added Guards Indicator Sketch 0706/005.
Added last 3 paragraphs of Section 10.
Added Section 11, Notice Boards.
1.4 3-Mar-09 New Section 2.6 – Cable Distribution Pits; Minor
amendments. Sections: 1.1, 1.2, 1.3, 1.4, 1.5,
1.7.1, 2.1.1, 2.1.2, 2.1.3, 2.1.4, 2.2.1, 2.2.2.1,
2.2.2.5, 2.2.2.6, 2.2.3, 2.2.3.1, 2.2.3.2, 2.4, 2.7,
8.1, 8.2, 9.3.1, 9.4, & 15.1 .
1.5 1-Dec-2009 1.6.2, 2.2.1 & 3: Reference to Structure Gauge
changed to ESC 215
1.6 21-May-2010 Document reformatted to comply with TMA 400
Engineering Publications Manual. Technical
content updated to incorporate requirements re
drilling of rails from Engineering Instruction:
Signalling 06/01. Appendix D ‘Drilling of Switches
© RailCorp Page 2 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
© RailCorp Page 3 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Contents
1 General .....................................................................................................................................7
1.1 Introduction ................................................................................................................7
1.2 Definitions ..................................................................................................................7
1.3 Submissions for Approval..........................................................................................7
1.4 Referenced Documents .............................................................................................7
1.5 Referenced Drawings ................................................................................................8
1.6 Quality of Work ..........................................................................................................8
1.6.1 Fitness for Purpose ....................................................................................8
1.6.2 General.......................................................................................................8
1.7 Locks..........................................................................................................................9
2 Signals......................................................................................................................................9
2.1 General ......................................................................................................................9
2.1.1 Signal Location...........................................................................................9
2.1.2 Signal “Out of Use” Marking .....................................................................10
2.1.3 Security ....................................................................................................10
2.1.4 Ladders and Landings..............................................................................10
2.1.5 Alignment of Incandescent Colour Light Running Signals .......................11
2.2 Signal Installation.....................................................................................................11
2.2.1 Structure Gauge .......................................................................................11
2.2.2 Location of Signals ...................................................................................11
2.2.2.1 Location ....................................................................................11
2.2.2.2 Acceptable Sighting ..................................................................12
2.2.2.3 Sighting Limitations...................................................................12
2.2.2.4 Unacceptable and Undesirable Sighting...................................13
2.2.2.5 Solutions to Unacceptable and Undesirable
Sighting .....................................................................................13
2.2.2.6 Other Considerations ................................................................13
2.2.3 Protective Barriers - General....................................................................14
2.2.3.1 Fall Protection Barrier ...............................................................14
2.2.3.2 Electrical Protection Barrier ......................................................14
2.3 Relative Heights of Signals......................................................................................15
2.4 Signal Foundations ..................................................................................................15
2.5 Ladder Footings.......................................................................................................15
2.6 Cabling Distribution Pit ............................................................................................15
2.7 Tunnel Signal Installation.........................................................................................16
3 Signal Gantries......................................................................................................................16
3.1 Gantry Access Ladders ...........................................................................................17
3.2 Signal Gantry Cages................................................................................................17
3.3 Gantry Walkways and Handrails .............................................................................17
4 Guards Indicators / Warning Lights ....................................................................................17
4.1 Guards indicators.....................................................................................................18
4.2 Warning lights ..........................................................................................................18
5 Buffer Stop Lights.................................................................................................................19
6 Flashing Lights and Horns (Calling Devices).....................................................................19
© RailCorp Page 4 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
7 Train stops.............................................................................................................................19
8 Track Circuits, Traction Bonding and Impedance Bonds.................................................21
8.1 Track Circuits...........................................................................................................21
8.1.1 Bootleg Risers ..........................................................................................21
8.1.2 High Voltage Impulse and Audio Frequency Track Circuits.....................21
8.2 Traction Bonding......................................................................................................22
8.3 Impedance Bonds....................................................................................................22
9 European Train Control System (Automatic Train Protection) Equipment ....................23
9.1 ETCS Balises...........................................................................................................23
9.1.1 General.....................................................................................................23
9.1.1.1 Signal Balise Group ..................................................................23
9.1.1.2 Non-Standard Stopping Locations (at signals) .........................23
9.1.1.3 Station Areas ............................................................................23
9.1.1.4 Temporary Speed Warning Balise Groups (TSW’s).................23
9.1.2 Balise Installation .....................................................................................24
9.1.2.1 Direct Fixing ..............................................................................24
9.1.2.2 Spreader Beam Installation ......................................................25
9.1.3 Balise Installation Constraints ..................................................................25
9.1.3.1 General .....................................................................................25
9.1.3.2 Balise Alignment .......................................................................26
9.1.3.3 Metal Mass................................................................................26
9.1.3.4 Cable Exclusion Zone ...............................................................27
9.1.4 Permanently Fixed Balise Identification ...................................................27
9.1.4.1 Balise ID....................................................................................27
9.1.4.2 Balise Location ID .....................................................................28
9.1.5 Temporary Speed Warning (TSW) Balise ID ...........................................28
9.1.6 Big Metal Mass.........................................................................................29
9.2 ETCS Trackside Junction Box.................................................................................29
9.3 ETCS Tail Cable ......................................................................................................29
10 Points and Ground Frames ..................................................................................................29
10.1 Points .......................................................................................................................29
10.2 Point Indicators ........................................................................................................30
10.3 Point Machines ........................................................................................................30
10.3.1 Electric......................................................................................................30
10.3.2 Pneumatic Mechanisms ...........................................................................30
10.4 Ground Frames........................................................................................................31
10.5 Identification of Points and Catchpoints ..................................................................31
11 Location Cases and Platforms ............................................................................................31
12 Notice Boards and Signage .................................................................................................32
13 Level Crossings ....................................................................................................................32
14 Alignment (focusing) of Level Crossing Signals...............................................................32
Appendix A Drawings.................................................................................................................33
Appendix B Alignment (focusing) of LED Colour Light Running Signals ............................40
Main Signals............................................................................................................................40
Turnout Signals (band of yellow lights) ...................................................................................40
© RailCorp Page 5 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
© RailCorp Page 6 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
1 General
1.1 Introduction
This Specification sets out requirements for the installation of trackside signalling
equipment including signalling related communications equipment.
Requirements for foundations for location cases, telephones, releasing switches etc and
general mounting arrangements for track circuit equipment boxes, tuning units etc are set
out in Specification SPG 0705.
Where a method of fastening or fixing is not specified by this or any other specification
the proposed method of fastening or fixing shall be as nominated by person/s with the
appropriate delegated engineering authority.
1.2 Definitions
AREMA American Railway Engineering and Maintenance of Way Association.
Australian Standard 1657 Fixed platforms, walkways, stairways and ladders – Design,
construction an installation.
Australian Standard 1742 Manual of uniform traffic control devices – Railway crossings
Australian Standard 1743 Road Signs – Specifications
AREMA part 3.2.15 Recommended Design Criteria for Gate Arm Operating Mechanisms
for Highway Grade Crossing Warning Device
AREMA part 14.2.1 Specification for Incandescent Electric Lamps
© RailCorp Page 7 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Quality of materials and workmanship shall also ensure that the necessity for regular
preventative maintenance tasks to retain the safety, reliability and usability of the asset
over its lifetime is minimised.
All relevant Signal Sighting, Mechanical, Site Installation, Layout and/or Structural
Drawings shall be produced in accordance with SPG 0703 and SPG 0711.2 and
approved by persons with delegated engineering authority. Evidence of Inspection,
Testing and Certification of the works shall be provided as set out in SPG 0711.1 to 7.
1.6.2 General
On site drilling, cutting or other machining or grinding of galvanized or zinc plated steel
components will generally not be acceptable. However in those circumstances where
approval is granted, holes drilled as part of the installation process or any other cut,
machined or ground surface shall be left clean, free of corrosion and free of burrs and
shall be cold galvanised prior to the installation of the item.
Generally equipment shall be installed so that it does not infringe within the Structure
Gauge as defined in the Standard Structure Gauge Drawing ESC 215 and referenced in
Specification SPG 0705. A survey using qualified surveyors to applicable RailCorp
Standards shall be required where there is any doubt as to structure gauge clearances
and each time a submission for an infringement waiver is necessary. Note that the size of
the structure gauge envelope will vary according to location, track curvature and track
superelevation and the nature of the type of equipment being installed.
Clearances shall be maintained where tracks converge. Survey for the location of
clearance points to applicable RailCorp Track Standards shall be required using suitably
qualified surveyors.
© RailCorp Page 8 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Where physical limitations force the placement of equipment within the Structure Gauge
envelope or the location of a clearance point is required, details of the proposed location
with the degree of infringement defined and details of options considered, shall be
documented and submitted in accordance with the requirements of and presented to the
RailCorp Chief Engineer Signals for approval.
Any fasteners used shall generally be hot dip galvanised or made from stainless steel.
Zinc plating or similar shall be acceptable on fasteners less than 8mm diameter except
where the fastener is used in a location which is likely to retain moisture.
Note that:
• Self locking nuts (eg nyloc nuts) shall not be used with hot dip galvanised bolts
unless the thread of the bolt is recut with a die nut before the nyloc nut is fitted.
Where this is done, the thread shall be cold galvanised after the nut is fitted.
• An anti-seize product (eg Loctite Anti-seize) shall be used between stainless steel
bolts and stainless steel nuts or inserts.
Bolts used to attach equipment to timber sleepers (or any timber at or close to ground
level) shall be installed such that nuts are located on the top of the sleeper or timber. A
special lock washer shall be installed under the head of the bolt to prevent rotation of the
bolt. The nut shall be secured with “Loctite 242 or equivalent”.
1.7 Locks
Construction locks shall be provided so that all relay rooms, walk-in enclosures, location
cases and trackside equipment can be locked following installation. Sufficient keys for
these locks shall be supplied to permit access for RailCorp’s representatives to carry out
inspection of the progress and quality of the work.
The construction locks will be replaced with RailCorp’s locks during the project
commissioning.
Lock hardware fitted to relay rooms and walk-in enclosures shall be compatible for direct
substitution with RailCorp’s series of security locks.
2 Signals
2.1 General
The longitudinal location of signals shown on signalling plans may be adjusted, with
written approval:-
© RailCorp Page 9 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
And the amended Signalling Plan is approved by the Chief Engineer Signals or his
delegate.
Such adjustments shall be agreed prior to the approval of the Detailed Site Surveys and
the surveying or marking of the signal foundation location or the surveying or marking of
the location of any associated track circuit, train stop, location case or walk-in enclosure
and prior to any construction of cable route in the vicinity.
Alternatively, the signal head may be covered with a purpose made laminated woven or
extruded, heavy duty minimum 0.2mm thick, weatherproof, UV resistant plastic bag
incorporating a large white retro-reflective cross. The bag may be black or white in colour.
The most prominent bag on any signal displaying a cross shall be positioned to ensure
that the cross is displayed in the direction of oncoming traffic.
The cross should consist of two pieces of tape, either self adhesive or sewn on, each
50mm in width and 450mm to 600mm in length.
Similarly any signal which is taken out of use, but not removed, shall be fitted with a
diagonal retro-reflective white cross.
For semaphore signals, the white cross shall be attached across the face of the arm.
Subsidiary signals and horizontal or vertical shunt signals shall be securely covered with
opaque material until brought into use. Lamps shall not be fitted into signals until they are
to be brought into use except that they may be temporarily fitted for the purpose of
testing, which shall comply with the Network Rules (after which they may be left stored
within the lampcase). Lamps shall be removed from any signal which is taken out of use.
For main signals illuminated by LEDs, the printed circuit boards are to remain fitted to the
signals but the face of the signal shall be covered with a suitable opaque cover as
described further above. The white retro-reflective cross shall also be fitted.
2.1.3 Security
Lampcase doors shall be fitted with padlocks and locked immediately the signal is
erected. Refer to dimensional sketch of padlock shown in Specification SPG 1571.
Where it is not possible to install the ladder immediately behind the signal post,
alternative proposals shall be submitted for approval.
© RailCorp Page 10 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
2.2.2.1 Location
Signals shall be located in accordance with the signalling plans and the approved signal
sighting forms provided that the requirements of Section 2.2.1 and the requirements
included in this clause are met.
The centre of the signal post shall be located between 2.2 and 2.5 metres from the
running face of the nearest rail. Exceptions may be approved provided that the
requirements of Section 2.2.1 are met and sighting is not compromised.
Running signals shall be placed to the left of the track in the direction of travel.
Exceptions:-
b) Where the signal is for the “wrong” running direction in bi-directionally signalled
double line track areas only, and all signals are similarly located..
If it is considered necessary to place a signal to the right of the track for any other reason,
the proposal shall be submitted to the Chief Engineer Signals RailCorp for approval, with
full reasons, including as assessment of risks associated with the location. Co-acting
signals on the correct side may be required.
c) Background lighting:- whether road traffic lights, street lights, floodlights will
overpower the signal aspect or tend to mislead the train driver.
d) "Reading through":- whether the driver will be misled by sighting past the signal
to another more obvious signal.
e) That signals on parallel running lines, or at the ends of loops, should generally
be placed opposite one another and stagger along the track should be
minimised. Exceptions may be made where the approach is such that both
signals are visible and there is no possibility of confusion, and as noted below.
© RailCorp Page 11 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
f) Where bi-directional running applies, the possibility of sighting the signal on the
"wrong" road before sighting the correct signal.
• As far as practical, the longest, most continuous sighting of the signal after passing
the signal in the rear.
• Preferably, a minimum of 200 metres sighting distance for speeds to 100 kph and
300 metres for speeds over 100 kph wherever the environment permits.
• A minimum of 6 seconds sighting at line speed. Distances which equate to 6
seconds at various speeds are given in Table 1 (Note: These distances include a
10% speed tolerance, but must be treated as minimum distances)
• Signal sighting distances shall be maximised where signals are widely spaced and
speeds are high. Where related 1 signals are spaced more than 2.5 kilometres
apart, the minimum sighting distances shall not be less than 200m for speeds to
100 kph and 300m for speeds over 100kph.
The maximum reliable sighting distance for a colour light running signal in full sunlight is
usually limited to 500 - 600 metres. A crowded, multicoloured or very bright background
environment will reduce this distance.
It is not necessary that sighting be totally uninterrupted except for the final approach to
the signal (50 metres approximately). However interruptions should be of only short
1
Related means that the indication on one signal will affect the indication on the signal in the rear. Eg
home and distant signals, automatic signals in section.
© RailCorp Page 12 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
duration and in total should not apply for more than 20% of the total sighting distance to
the signal.
A gantry mounted signal will not normally be visible, in daylight, within about 10 - 15
meters of the gantry. If a train is required to pull right up to a gantry mounted signal (eg at
a platform), a co-acting signal will usually be necessary.
a) Local conditions are exceptional and such that it is reasonable to predict that
drivers may have particular difficulty in properly observing and being able to
stop at the signal when required to do so.
b) The signal will not be visible to the driver when the train is stationary at a
platform or when the train is stationary within 15 metres of the signal.
Trains frequently approach a signal with restricted sighting, having received a caution
indication at the previous signal. In order to prevent unnecessary slowing of the train it
would be advantageous to advise the driver before the signal becomes visible, that the
signal has cleared.
The signal is a junction signal and the sighting is such that the driver would be required to
slow the train more than is necessary for the diverging route.
Co-acting and repeater signals shall be provided only in those cases where there is no
alternative method of providing acceptable viewing to the train driver.
• Safe access for drivers to alight and use the signal post telephones. Walkways
shall be provided (and handrails placed for protection on embankments or from
other tracks) whenever this requirement is noted on approved signal sighting
forms. Where walkways are required, the position of access to and from the drivers
cabin shall be taken into account when determining the length of walkway required.
Where the walkway will impact on the track ballast or formation profile, the Chief
Engineer Track &/or the Chief Engineer Bridges & Structures shall be consulted.
• Overhead wiring air gaps. Avoid locating signals such that an electric train stopped
at the signal will span an air gap. Since the last pantograph on an 8 car intercity
electric set is approximately 175 metres from the front of the set, the signal should
be placed at least 200 metres after the air gap, if the air gap is on the approach
side of the signal.
• Where there is likely to be the possibility of a reduction in visibility from sunlight
shining into the lens. If this possibility does exist:-
– hoods shall be increased in cover and length as noted on the signal sighting
sheets.
© RailCorp Page 13 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
• Where there is potential for a person to come into contact with the overhead wiring
or where the standard configuration is considered inadequate to guard against a
particular hazard the need for, additional protective barriers shall be provided in
accordance with Section 2.2.3. All other measurements to avoid the need for a
protective barrier shall be investigated before implementing a protective barrier.
Barrier infill may be constructed of expanded sheet metal with openings typically no
larger than 50mm by 50mm to limit an arm being placed through the infill screen.
Barriers shall be assessed for insulation, bonding and spark-gap bonding requirements.
The protective barrier shall extend at least 1.5 metres ahead of the signal post centre and
at least 1 meter behind the base of the signal ladder.
Where the signal does not incorporate a work landing i.e. only a ladder, the screen shall
extend to the full height of the signal ladder, or higher where required.
Where the signal incorporates a work landing, the screen shall extend to at least 1m
above the deck of the topmost landing.
Where the signal does not incorporate a work landing i.e. only a ladder, the screen shall
extend either, at least 1m above the signal ladder or at least 1.5 meters above the height
of the live wiring, whichever is the lesser distance.
Where a work landing is incorporated into the signal, the screen shall extend either, 2m
above the deck of the topmost landing or at least 1.5 meters above the height of the live
wiring, whichever is the lesser distance.
Full details of any proposed screens, including insulation and bonding shall be submitted
to the Chief Engineer Signals for consideration and approval.
© RailCorp Page 14 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
At crossing loops, the loop starting signal shall be 400 to 500 mm lower than the main
line starting signal and substantially in line with it unless otherwise approved.
For bi-directional running on double line sections, adjacent signals shall be of equal
height.
For double aspect signals the lower main red indication shall be the reference point for
height measurements.
For single aspect signals the main red shall be the reference point for height
measurements.
Signal gantry footings are to comply with Bridges and Structures (Civil) specifications and
requirements.
Foundation bolts shall be not less than 30mm diameter galvanised steel for 140mm OD
signal posts, not less than 24mm diameter galvanised steel for 114mm OD signal posts
and not less than 16mm galvanised steel for dwarf signals.
The top of the foundation shall generally be positioned at rail level. However, where the
cess depth or ballast shoulder exceeds 750mm the top of the foundation may be
positioned not less than 300mm above ground level and the signal post lengthened
accordingly. In some circumstances the top of foundation may be positioned above rail
level where agreed on the Signal Sighting form.
Where more than one ladder is fitted to a signal post, a single concrete pad should be
formed and poured linking all ladders.
Signal gantry access ladder concrete landing/footing pad shall comply with Civil
manufacturing drawing E1-451.
© RailCorp Page 15 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
box. Site Installation Drawings (SPG 0711.2) shall be produced and approved for each
typical installation drawing at each signal.
The signal lampcases shall be clear of the tunnel wall by 20 - 30mm at the closest point
and shall be mounted so that the top red aspect is between 2250 and 2550mm above rail
level. The signal shall be vertical in both planes.
Where the top lampcase of the signal is more than 2 metres above the floor level of either
the tunnel or refuge (if the signal is mounted at the edge of the refuge), a step, platform or
ladder shall be installed to provide maintenance access to the signal.
3 Signal Gantries
Signal gantries shall be provided where indicated by the signalling plans and signal
sighting forms. The gantry shall span the minimum number of tracks consistent with
obtaining clearances between mast and track required by the Standard Structure Gauge
Drawing ESC 215 and the necessity to clear any pathway or roadway adjacent to the
track.
Gantries shall be designed to accommodate dead load from the structure, cages, signals,
walkway and handrails; live loading from maintenance personnel and wind loading
assuming a maximum wind speed of 160 kph and the appropriate terrain category for the
location, plus any construction and temperature loadings. The design (where design
details are not provided) and a Structural Engineer’s certificate specifying that the gantry
is suitable for its intended use, shall be submitted for approval.
Welding to or drilling of the gantry structure after fabrication and erection to attach
signals, signal cages, walkways, handrails, ladders, notice plates, telephones, cable trays
or cables is not permitted.
Either holes and/or brackets for attachment are to be included in the gantry structure
during manufacture or the various items are to be clamped to the gantry.
Signals gantries and all ferrous attachments thereto shall be hot dip galvanised after
fabrication.
Gantry masts shall be vertical in both planes. The gantry beam shall be horizontal and be
either straight or have small positive camber. Masts shall be wedged, shimmed or packed
on foundations to achieve levelling then grouted between foundation and mast foot.
The gantries shall be positioned on the footings to allow a minimum of 25mm of low
shrinkage concrete grout to be installed between the concrete footing and the column
base plate after levelling has been completed. All temporary packing (if used) shall be
removed.
© RailCorp Page 16 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Gantry access ladders shall not exceed 6m in height without an intermediate landing, in
compliance with AS1657 Fixed Platforms, walkways, stairways and ladders.
Cages shall extend down no lower than 2m above the ground level landing and be fitted
with a lockable door panel to restrict unauthorised access. A split door panel is preferred
in lieu of a single door construction, in order to reduce the overall weight and potential for
the door to fall on the user.
Cages shall be installed such that they are vertical in both planes, except that where the
gantry beam is cambered, no compensation is necessary for the angle caused by the
camber unless this exceeds 0.2°.
The cage shall be provided with an access ladder not less than 380 mm wide between
stiles, stile section not less than 50 x 12, rungs not less than 20 mm diameter and rung
spacing not greater than 300 mm.
Where cages are cantilevered from the gantry, the ladder stiles shall extend to the
topmost rail on the gantry handrail. There shall not be less than 175 mm clearance
behind any rung on the ladder to any part of the cage or gantry.
The cage shall be either pre-drilled for lampcase brackets or shall have the brackets
welded in as part of the cage. Similarly the cage shall be pre-drilled for attachment to the
gantry.
Prior approval shall be obtained where it is required to mount indicators on heritage listed
infrastructure.
Guards Indicators and warning lights shall be covered or wrapped in black opaque woven
or re-enforced material until brought into use.
© RailCorp Page 17 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Guards indicator mounting posts may be steel pipe (Minimum75NB) with capped top or
RHS (minimum 75x75x3.2) whichever best matches the particular station architecture.
(Note: On some stations, which are heritage listed, posts that more closely match the
period architecture of the station may be required. The necessity for this is to be
determined in consultation with the Regional Representative)
The post may be bolted to a concrete foundation or cast into a concrete foundation. The
size of foundation shall be such that it can withstand a person swinging on the post
without moving the foundation in the platform.
The underside clearance of the guards indicator lampcase with identification plate shall
be mounted 2400mm above platform level unless otherwise directed.
The post shall be painted the same colour as the station lighting posts.
Cabling to guards indicators shall be run in pipes buried in the platforms or in conduits or
cable ducts in or on station buildings or other structures subject to specific approval.
Exposed conduits or cable ducts shall be made as unobtrusive as possible and painted to
blend with the supporting structure.
Shall be positioned such that they provide an uninterrupted view by the train Guard.
Shall be placed at a height such that they can be maintained with the use of a 2m step
ladder placed behind the yellow safety line on the platform. Refer to Figure 6 in Appendix
A.
Shall not be placed where they will block the driver's or guards observation of any signal.
Refer to Guards Indicator sighting form located in SPG 0711.7 Inspection and Testing of
Signalling - Standard Forms.
Also refer to ESG 100.1 Signal Design Principles - Signals for guidance on locating of
Guards Indicators.
© RailCorp Page 18 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Buffer stop lights shall be positioned at the buffer stop or stop block, with the red light at a
height of 1200 to 1500 mm above rail level.
In areas where trip fitted trains approach the buffer stop a fixed train stop shall be
provided before the buffer stop & the buffer stop light shall be located adjacent to the left
of the fixed train stop.
Where practical, buffer stop lights shall be fitted to a free standing post. A free standing
buffer stop light post shall be constructed to Standard drawing M01-163.
The buffer stop light mounting post shall be capable of supporting a 150kg horizontal load
applied at 1.5m above ground level with deflection of less than 10mm.
The post shall be secured, into the ground or otherwise, so that it is capable of resisting a
pull out force or 250kg plus the above specified horizontal loading without movement.
Where metal buffer stops are provided, any metal work for the buffer stop light shall be
insulated from the buffer stop frame itself or separately mounted and insulated, to avoid
any touch potentials from the buffer stop.
Refer to ESG 100.1 Signal Design Principles - Signals for configuration details.
Where horns are located close to any dwelling, hotel, motel or similar building occupied
during or overnight, the horns shall be silenced between the hours of 2000 and 0600.
If there is any hospital, nursing home or similar in the vicinity, as well as being silenced
overnight, the horns shall be directed away from the establishment.
The calling devices shall be located where indicated on the signalling plan or in the
Particular Specification.
The rotating flashing light shall be equivalent to Hella model 2RL002 03 and horns shall
be equivalent to RVB model 4100-008
The calling devices shall not be mounted in any position which will obscure or reduce the
clarity of any signal indication and if mounted on a location or building roof shall have the
mounting arrangement suitably sealed to prevent any possibility of moisture entry to the
location or building.
Maintenance access shall be provided to calling devices but either the access or the
devices shall be secured to prevent unauthorised access, theft or vandalism.
7 Train stops
Pneumatic or hydraulic train stops shall be cycle tested for a minimum of 20 operations
per hour for 24 hours prior to installation in the track. For hydraulic train stops, this shall
© RailCorp Page 19 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
be followed by a hold clear test of a minimum of 6 hours duration to test the valve and
ram seals. The trip arm shall not move more than 4mm towards the stop position during
this test.
Train stop mounting brackets shall be installed on concrete sleepers in accordance with
Drawings M04-027,028 and shall be mounted parallel to the rail and horizontal.
Train stops attached directly to timber sleepers shall be fixed with 20 mm galvanised
steel coach screws which penetrate the timber for at least 100mm. Flat washers shall be
provided under coach screw heads.
Wet sump JA and JAH type train stops shall be filled with lubricating oil and the
lubricating system primed immediately following installation.
The train stop is to be mounted in the position shown on Drawing 0706/ 004 and the
location of the arm in the raised position is to be tested with a train stop gauge, the
gauging dimensions of which are shown on Drawing 0706/ 005. The relative positions of
signal, train stop and insulated joint (or tuned loop) are shown on Drawings 0706/006 and
007.
The cable entry to the train stop shall be sealed after cable termination with a neutral cure
silicon sealant to prevent moisture entry.
Train stop arms shall be securely fixed down to the sleeper and the return spring
disconnected from the train stop, or the arm shall be removed, until the train stop is
required to be brought into use. Fitting a wedge between arm and arm stop is not
acceptable.
Alternatively a sleeve, secured by bolt or other means may be fitted over the extended
ram shaft (pneumatic or hydraulic) to prevent retraction.
Where a ram shaft is to be held in the extended position for more than 30 days, it shall be
protected against corrosion. The corrosion inhibitor used shall not in any way be
detrimental to the hydraulic or pneumatic seals on the ram or cylinder.
Train stops which have been taken out of use but not removed shall also have the arm
securely fixed down or removed.
The train stop deflection plate shall be secured to the train stop mounting brackets or to
the timber sleeper in advance of the train stop in the normal direction of travel, in
accordance with the relevant drawings.
On tracks signalled for operation in either direction, train stop deflection plates shall be
provided on both ends of the train stop.
Flexible conduit leading to the train stop shall be arranged as specified in Specification
SPG 0705.
If a train stop is not in use and fitted to a running road, a retro-reflective white cross that is
visible to drivers shall be fixed to the cover of the train stop.
© RailCorp Page 20 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Insulated joints in turnouts shall be placed in accordance with the track insulation plans
and will normally be in the least used and/or slowest speed route (usually the turnout
route) whenever possible.
Junctions between rails of different section shall not be used for insulated joints.
Wiring to connect track circuits to both control equipment and to rail shall be as stipulated
in Specification SPG 0707.
Maintenance access shall be made available to tuning units, matching units etc of audio
track circuits and terminal cases of impulse track circuits. Where these are mounted on
the edges of drains or cesses which are likely to be water filled or in which staff cannot
stand, a suitable standing area formed by either filling or by installing a fabricated
platform, shall be provided.
The bootleg riser is used as an interface between the surface mounted rail connecting
cables and the track circuit cables running to the equipment location case or to the relay
room as applicable or between the surface mounted rail connecting cables and the
bonding cables in the cable route.
The bootleg riser is suitable for only for terminating cables of sizes up to 7/1.7 mm. For
larger size bonding cables specific proposals shall be submitted for approval.
Except where site conditions preclude, the bootleg risers shall be installed 2500 mm
(minimum) from the nearest rail face and the top of the terminal box shall be 300 - 400
mm above ground level. Where track centres do not permit this position, the riser shall be
placed centrally between tracks and the top of the box shall be at least 50mm below rail
level.
The posts and trackside equipment shall be installed opposite the applicable IRJ or track
connection position to avoid excessive length on the track connecting cables.
Posts used for mounting high voltage impulse (Jeumont Schneider) and audio frequency
track circuit (CSEE, ML and Westinghouse) trackside equipment and boxes shall be of
sufficient cross section to support the box plus a load of 150kg applied horizontally at the
top of the post (nominally approximately 1metre above ground level) with less than 20mm
© RailCorp Page 21 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
deflection. In addition the post shall have sufficient torsional rigidity to deflect less than 5°
under a torque of 300Nm applied at the top.
The posts shall be secured into the ground so that there will be no movement of the base
of the post with a load of the box plus 150kg applied vertically to the post plus the load of
150kg applied horizontally at the top of the post or with these loads applied individually.
The post shall also withstand a pullout load of at least 250kg.
Incoming cable from location case to box shall be protected by either passing through the
post or by a rigid conduit securely fixed to the post. Cables to the track shall be supported
by clamping to the post to minimise loading on the cable terminations.
Design life of the posts, the method of securing in ground, and conduits and cable
supports shall be a minimum of 25 years.
Cable entries into tuning units shall be sealed to prevent entry of moisture.
Where traction bonds are attached to rails with either stainless steel tapered bolts or
stainless steel cadweld studs, an anti-seize compound (such as ‘Loctite’ 771) shall be
used between the stainless steel nuts and stainless steel bolts/studs. Care shall be taken
to ensure that the anti-seize is not permitted to contaminate the mating surfaces between
cable lug and bush or boss on the rail.
The mating surfaces of cable lugs and of the copper bush in the rail or the cadweld boss
welded to the rail shall be cleaned (with solvents or abrasive products if needed) prior to
assembly.
Size, type, quantity and connection requirements for side lead and neutral conductors to
rails and impedance bonds shall be as specified in Specifications SPG 0707 and SPG
0709.
Side lead and neutral conductor cable terminations shall be accessible for examination
and disconnection with the bond lid or cover in place but shall not be unduly exposed to
damage. Cables shall be mechanically supported to reduce the load on the termination
point and cable lugs.
The side leads to one rail shall be equal in length and configuration to the side leads to
the other rail.
All cable connections to bonds shall be made using stainless steel fastenings. An anti-
seize compound (Loctite 771 or equivalent) shall be applied to the fastenings during
installation. Care shall be taken to ensure that the compound is not permitted to come
between cable lug and bond termination plate.
The mating surfaces of cable lugs and of the impedance bond terminals shall be cleaned
(with solvents or abrasive products if needed) prior to assembly.
© RailCorp Page 22 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
9.1.1 General
ETCS balises are required for spot transmission of ETCS telegrams from trackside to the
train. Balises are generally required at signals, and are positioned in the ‘four foot’ on the
track.
All balises that are installed but are not commissioned shall be prevented from affecting
operating services by muting (either by a metal cover or electronically).
Each balise shall be a reduced (compact) size Class A. Balise mounting shall meet
requirements of Class B in accordance with SRS Subset-036.
Note: Where a DPU is encountered at a signal, the DPU is treated as per an insulated rail
joint.
The balise group for a Temporary Speed Restriction (TSR) shall be positioned at the blue
TSR sign but can be moved up to 30m beyond the TSR blue sign if required.
Balise pairs making up the TSW balise group shall be spaced as close as practical to
each other depending on sleeper spacing, but never closer than 2.5m between the balise
reference marks.
The TSW balise group shall not be located closer than 8m from any other balise on the
same track.
© RailCorp Page 23 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
The TSW balises are to be installed using an approved spreader beam fixing system that
is easily installed and removed using tools.
Balises shall be secured in a manner that allows repeated removal and re-fixing using
tools, by authorised personnel. This is to be done without damaging the integrity of the
anchor or the balise or the structural integrity of the sleeper/slab.
Balise mounting brackets, fixings, spacers, spreader beams, etc and associated cabling
shall be:
Direct fixed balises shall be mounted on a rubber mounting pad, refer to drawing M05-
500 for manufacturing details. Note: rigid balise spacer mounts used with direct fixing are
not preferred and should not be installed except where required to bring the balise up to
within the required vertical design limits.
Refer to fabrication drawing M05-553 for details of the balise drilling template. Alternative
templates may be submitted for review.
Balise mounting anchor holes shall be protected by fitting a flush mounted, plastic slotted
plug when the balise has been removed for track maintenance.
Where balises are to be direct fixed to concrete, two flush mount M10 female 316
stainless steel anchors shall be fitted into the concrete and two 316 Class 70 Stainless
Steel M10 bolts.
Note: Generally, for concrete sleepers use mechanical-set anchors. In the case of slab
track where the concrete is weaker than 40MPa or the strength is unknown or the
concrete is weakened, chemical-set anchors are likely to be required.
Balise fixing points shall be located along the centre line of the sleeper in accordance
with methods approved by RailCorp.
Cup washers and thread-retaining/anti-galling fluid shall be used to secure parallel thread
bolts in place.
© RailCorp Page 24 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
A stainless steel internal star type push-on fix washer or similar product may be used
where it is necessary to keep the bolts captive to the balise during maintenance activities.
Timber Sleepers
The balise shall be fixed using two galvanised steel coach screws of 12mm diameter and
at least 150mm in length together with 316 stainless steel cup washers.
In order to facilitate future removal of steel coach screws in timber, lanolin grease or other
approved environmentally friendly product shall be used for lubrication in the pre-drilled
hole before insertion of screw.
Timber sleepers heavily degraded shall not be used for balise installation and should be
considered for replacement. Where the timber degradation is not structural (surface
degradation only) and it is not practical to replace the sleeper, a chemical anchor may be
considered generally in accordance with the installation procedure detailed on RailCorp
drawing M05-502. Note: When drilling a timber sleeper for a chemical anchor, undercut
the hole to ensure that the chemical (resin) plug cannot be easily pulled out of the
sleeper.
Approval will only be given where it is not possible to direct fix a permanent installation
and relocation is not practical.
The balise shall be secured to the spreader beam with two stainless steel 316 Class 70
M12 bolts and spring washers.
The spreader beam shall incorporate two stainless steel 316 M12 threaded inserts to suit
position of balise fixing holes.
Design life of the spreader beam and method of securing shall be a minimum of 25 years.
9.1.3.1 General
Balises shall be positioned clear of a DTRS Metronet train radio Transponder and a DPU
in accordance with Design Principles ESG 100.31.
• occupies the required placement of a balise, shift the affected balise or the balise
group one sleeper increment in accordance with the permitted window of
tolerance.If movement by one sleeper is not possible, the balise/balise group shall
not be installed until the Metronet train radio transponder has been relocated.
• is within the exclusion zone from a balise, the Metronet train radio transponder
shall be relocated.
For all permanent balise positions where the balise falls foul of a track mounted object,
the following options are to be considered:
© RailCorp Page 25 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
• Relocate the balise, after approval from the Chief Engineer Signals and Control &
Systems,
• Modify the track obstruction, after approval from the both the Chief Engineer
Signals and Control Systems, and the Chief Engineer Track.
• Rails shall not be stored in the four foot within 1m of any balise.
• No more than two rails shall be stored side by side in the four foot.
• Where stored rails overlap one another, the distance shall be less than 8m.
Balises shall be mounted transversally to the rails, unless existing infrastructure in the
four foot, such as guard rails or check rails etc require a longitudinal mount. Refer to
drawing M05-558 for details of longitudinal mounting method.
Vertical Alignment
The Balise Reference Mark (BRM) on the side of the balise shall be positioned between
93mm and 193mm from the top of rail level. This height range is known as the mounting
height constraint. Refer to drawing M05-503 for details.
Balises shall generally be mounted as low as possible within the mounting height
constraints except where the balise is mounted between guard rails in which case the
balise shall be mounted as high as practical within the mounting height constraints.
The top of the balise shall never be higher than the plane of the top of the rail heads.
Horizontal Alignment
The balise shall be positioned centrally to the rails. Refer to drawing M05-503 for details.
Balises shall be aligned centrally in the four foot (parallel to the rails), but should not
laterally exceed +/-15mm with respect to the track centre.
Note: Where necessary due to infrastructure constraints, lateral deviation from track
centre of up to 40mm may be permitted.
A balise shall not be installed where the track curve radius is less than 160mm without
approval from the Chief Engineer Signals and Control Systems.
Where lines converge on each other, balises shall not be installed within 2m of each
others centre line.
Balises should preferably not be located on or adjacent to metal objects in the four foot
unless infrastructure constraints make it unavoidable. These include concrete slab track,
guard rails, concrete derailment plinths, checkrails etc.
© RailCorp Page 26 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
A geographical survey shall be carried out to identify metal mass locations. Once
identified, exclusion zones will be provided and maintained around the balise location
• and the feet of the guard rails are between 440mm and 630mm apart , install the
balise in accordance with drawing M05-558.
• and the feet of the guard rails are less than 630mm apart, the guard rails shall be
cut adjacent each balise and an insulated joint kit installed in accordance with
drawing M05-558.
• and the feet of the guard rails are less than 440mm apart, refer to the Chief
Engineer Signals and Control & Systems for resolution.
Where a balise is to be mounted on or above a concrete slab, the steel reinforcing shall
be at least 210mm below the side BRM. Where the depth of the reinforcing below the
surface of the concrete is unknown, it shall be assumed to be 25mm.
• the plinth shall be cut out and the balise mounted ensuring that the steel reinforcing
and side BRM are kept at least 210mm vertically apart.
• The steel reinforcing in the derailment plinth shall not be located closer than
500mm in the horizontal plane from the top BRM (centre of balise).
All modifications to guard rails, check rails, concrete derailment plinths and the like, shall
be first approved by the Chief Engineer Track, and Chief Engineer Civil.
Note: A concrete derailment plinth may only be removed or cut after approval has been
granted from RailCorp. Where it is unacceptable to leave a gap in a derailment plinth, a
site inspection will be required and an engineering report prepared to assess the hazards
and risk being mitigated by the plinth and provide recommendation for appropriate
mitigations.
Refer to sketch 6 of Appendix A for normative interoperable exclusion limits. Note: Some
balise suppliers may have a less restrictive distance than shown.
Each balise location shall be fitted with a balise location identification (ID) name plate.
Identical information shall be provided on the balise ID name plate and its respective
balise location ID name plate.
Refer to drawings M05-545 for details of the balise ID plates and Signal Design Principles
ESG 100.31 for details on naming convention. Manufacturing material, layout, information
to be shown and lettering of ID plate are outlined in the aforementioned drawings.
9.1.4.1 Balise ID
Balise ID name plates shall be affixed by mechanical means to the balise and should be
able to be removed without damage using tools so that the label from a damaged balise
can be relocated to a new replacement balise of the same model. Where the balise ID
© RailCorp Page 27 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Label is secured to the balise using one or more of the balise hold-down fixings, a star
type push-on washer is essential to secure the fixing bolt.
As well as being provided with its own balise identification plate, each balise shall display
its own manufactures identification label. The manufactures label shall include the
following information as a minimum:
Other traceability information such as, description of product, manufacturing date, expiry
date, batch number etc should be provided where applicable.
For concrete slab track or sleepers, the location ID plate shall be glued and aligned as
per the balise ID plate.
For wooden sleepers, the location ID plate shall be screwed and glued to the sleeper and
aligned as per the balise ID plate.
Each balise in a TSW balise group pair shall be fitted with an identification (ID) plate
manufactured of the same material, have the same form and the same mounting as the
standard Balise ID plate (refer to drawing M05-546 for material and dimensional details).
Each balise in a TSW group shall have a unique balise identifier made up as follows:
• Each TSW balise group pair shall be uniquely numerically identified e.g: 1, 2, 3,
onwards.
• The first balise encountered in the relevant running direction shall be colour coded
blue. The balise position in group identifier for this balise is 0, and identification
plate engraving shall include “First TSW balise in direction of travel” as well as the
position in group letter ‘A’ identifier.
• The second balise encountered in the relevant running direction shall be colour
coded amber (or yellow). Balise position in group identifier for this balise is 1, and
identification plate engraving shall include “Second TSW balise in direction of
travel” as well as the position in group letter ‘B’ identifier.
See example sketch below showing TSW balise group number 1 with position in group
letter ‘A’.
© RailCorp Page 28 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
1A
Balise position in group identifier
TSW balise group pair, letter. Either A or B depending on
unique identifier, eg: whether it is the first or second
1,2,3,4, etc balise in the group.
Note: The colour coding requirements defined above shall be achieved by colour coding
the engraved identification plates i.e. instead of a white background the plate will have a
blue or yellow/amber background, as required.
The ETCS junction box shall be constructed in accordance with drawing M05-504,
cabled/wired in accordance with M05-511 and secured with a Falcon 8 padlock.
The incoming balise trunk cable from the location case shall be typically protected by a
rigid 63mm HD conduit securely fixed to the junction box in-ground post. Stainless steel
bandit strapping is an acceptable method to secure the conduit to the post.
The balise tail cable (enclosed in electrical hose) shall be secured to the junction box in-
ground post with half saddles.
Surface run balise tail cables between the ETCS junction box and balise shall be sleeved
with approved orange flexible electrical hose over the length of the cable to provide
mechanical protection and to improve conspicuity.
10.1 Points
All bolted connections that are not adjustable shall use nyloc nuts.
© RailCorp Page 29 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
All critical elements shall be evidenced as unlikely to fail or shall be provided with
redundancy, eg: double secured pins.
Any work involving drilling switches and stockrails shall be carried out in accordance with
the requirements of appendix ‘D’ Drilling of Switches and Stockrails.
All point machines shall be installed to the standard designs. Where individual set screws
or plain nuts are used, “Loctite 242” or equivalent shall be used. Nyloc nuts are to be
used wherever possible.
If stainless steel bolts are used with stainless steel inserts in the sleeper an anti-seize
compound (Loctite 771 or equivalent) shall be applied to the bolts.
Where a standard layout drawing is not available a design for a suitable layout shall be
prepared and presented for approval.
Connections between the machine and switches shall be to details referenced on the
standard points layout drawing. Where the referenced details are unsuitable, detailed
designs for the connections are to be prepared and submitted for approval. Every effort
shall be made to use or adapt items referenced on the standard layouts.
Protection ramps shall be installed ahead of the electrical detector and rodding as shown
in the standard layout drawings.
Electrical point indicators shall be in accordance with the requirements of Section 2 of this
Specification and the requirements of Specification SPG 0705 for horizontal or vertical
shunt signals.
10.3.1 Electric
All power operated point driving and locking mechanisms used shall be in accordance
with the requirements of Specification SPG 1588.
The switch machine shall be installed so that no part infringes structure gauge except that
the hand throw levers on a dual control machine may infringe when being thrown
between the normal and reverse positions and the crank handle may infringe when
inserted in the switch machine for emergency operation.
Where there is insufficient space to locate the switch machine without some infringement
of structure gauge, the extent of the required infringement shall be submitted for
determination as to whether the proposed infringement can be permitted.
Backdrives shall be provided as shown on the standard layout drawing or where not
available, a design shall be prepared and submitted to RailCorp for approval.
The switch machine cable entry shall be sealed with a neutral cure silicon sealant after
cable termination to prevent moisture entry.
© RailCorp Page 30 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
and rodding shall be installed in accordance with the standard points layout drawing
relevant to the type of turnout and whether it is facing or trailing.
For claw lock or Spherolock operation, motors, claw lock or Spherolock mechanisms, and
detectors & backdrives shall be installed in accordance with the standard points layout
drawing.
All bolts through timber sleepers shall have nuts secured with "Loctite 242" or equivalent.
Protection ramps shall be installed ahead of the electrical detector in the normal direction
of travel.
The layout of ground frame and channel rodding runs, including compensation, if it differs
in any way from the layout shown on Drawing M10-301, shall be drawn up and submitted
for approval.
Tangental type turnouts and large conventional turnouts shall not be fitted with hand
operated ground frames.
‘N’ and ‘R’ letters shall also be provided to indicate the normal and reverse positions.
When concrete bearers are in use, the identification shall be glued to the bearer.
When in-bearers are in use or it is otherwise not possible to fit to the A beam, the
identification shall be provided on the A1 sleeper (the beam preceding the tip of the
blades).
Direct access for maintenance staff shall be provided from the equipment which is
serviced by the location case (eg track circuit units, points machines etc) to the location
case.
• the case and equipment are not separated by a cess or drain which is too deep to
walk through or subject to standing water or flooding.
• the case is not at the foot of a steep embankment.
• the case is not at the top of a steep cutting.
Where necessary, walkways, steps, ladders or bridging over drainage ditches or cesses
shall be provided.
© RailCorp Page 31 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Walkways, steps and landings shall comply with the requirements of AS1657 - Fixed
Ladders and Walkways.
Handrail posts shall be bolted to masonry surfaces with stainless steel "Dynabolt" or
equivalent expanding anchors or stainless steel chemical anchors. The minimum
anchorage depth shall be such that the strength of the anchorage is equal to or
exceeding that of the post.
Handrail posts (where not welded to the structure) shall be bolted to steel structures with
galvanised bolts with spring washers and nuts. The strength of the fastenings shall be
equal to or exceeding that of the post.
The height of the sign shall be not more than 1600mm above the level of the formation.
This height is to ensure that the sign does not become a hazard by being at head height.
Where the formation falls away and the sign would be too low for reasonable driver
visibility, the post height may be increased, but in such cases the lower edge of the sign
must be installed well above head height, which for these purposes shall be taken as
2200mm. In any case the lower edge of the sign shall not be more than 2000mm above
rail height. When these longer posts are required the post size shall be 65mm nominal
bore, and shall extend 600mmm into the ground.
Where these requirements cannot be met due to site constraints and local requirements,
the matter shall be referred to the Chief Engineer Signals for determination.
Signage that requires to be mounted low to clear structure gauge, such as between
tracks, such as Yard Limit, EYL, Shunting Limit boards etc may be located low down on
similar posts. It may be appropriate to lay back the post so that the sign is more easily
readable. Such posts should not protrude above the sign by more than 50mm.
Refer to specification SPG 1210 and drawing M05-066 for sign manufacturing and
mounting requirements.
13 Level Crossings
Refer to Specification SPG 0723 and SPG 0724.
© RailCorp Page 32 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Appendix A Drawings
0706/001 Position - Trainstop Arm Relative to Rail Level
0706/004 Relationship of Signal, Trainstop and Audio Track Circuit Tuned Loop
© RailCorp Page 33 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Figure 2 - Drawing No 0706/001 - Position - Train Stop Arm Relative to Rail Level
© RailCorp Page 34 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
© RailCorp Page 35 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
© RailCorp Page 36 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
© RailCorp Page 37 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Notes:
2) Cable should be top entry and preferably incorporated within the support bracket to
provide mechanical protection.
© RailCorp Page 38 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
© RailCorp Page 39 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Main Signals
The signal shall be focused (aligned) to provide the train driver with optimum sighting of
signal indications.
The final check of signal focus shall be carried out from a train approaching the signal.
This check shall be carried out in daylight, where possible with the sun in front of the
signal. A signed record of this check shall be submitted as part of the quality
documentation.
The alignment shall be carried out in daylight. (If circumstances force initial alignment to
be carried out at night, a follow up check in daylight must be made).
The signal shall be viewed from a distance of approximately 300 metres, or at the
maximum sighting distance, or from the signal in the rear, whichever distance is the
lesser. The signal shall be viewed by a standing person from a position immediately
above the left hand rail.
The person aligning the signal should first approximately align the lampcase to point
towards the viewer and vertically align the lampcase so that the light beam is
approximately horizontal.
Where possible, sighting should be carried out using the green indication as this is
usually the least visible of the indications in daylight due to the colour green being the
closest of the colours to daylight in the colour spectrum.
The lampcase is then to be rotated side to side and the viewer is to indicate the position
of maximum visibility. Lock at the position of maximum visibility. If a focusing ring is fitted
adjust the ring and insert the locking pin.
Finally the lampcase is to be rotated up and down until the viewer indicates the position
of maximum visibility. Again lock at the position of maximum visibility.
Where the approach to the signal is curved, the viewer is then to walk along the track
towards the signal checking the visibility. Some reduction in the intensity of the indication
can be expected on a curved approach as can some obstruction from overhead wiring
structures. Provided the signal is visible for 80% or more of the approach distance, this is
acceptable. There must be unobstructed and clear visibility of the signal indication
between 15 and 50 metres from the signal.
Where maximum sighting distances are 150 metres or greater, it is not necessary for the
viewers eye level to be elevated to driver’s eye level. The vertical spread of the LED
signal will take care of the difference.
Special attention shall be paid to gantry mounted signals. Because they are mounted so
far above the track and need to be angled downwards.
Further requirements associated with conversion of incandescent signals to LED are set
out in SPG 0711.6 Interface Requirements and Procedures for Alterations.
© RailCorp Page 40 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
In yards where trains may stand very close to shunt signals, mounting on a post may
improve visibility. Shunt signal post construction is to comply with drawing M01-168.
© RailCorp Page 41 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
The alignment distances shown assume that there is no other signal, or obstruction,
within that distance. Where there is, the alignment distance should be reduced to the
distance between signals or the distance to the obstruction.
The correct lens shall be selected to achieve best sighting. The spread light type of lens,
which reduces the intensity of the indication, should not be used unless the approach to
the signal is sharply curved and/or the maximum available sighting distance is less than
250 metres.
Drawings:
© RailCorp Page 42 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
© RailCorp Page 43 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
© RailCorp Page 44 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
© RailCorp Page 45 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3
RailCorp Engineering Specification — Signals — Construction Specification
Installation of Trackside Equipment SPG 0706
Drilling of switches and stockrails staff may only be carried out in conformance with the
following requirements (includes competency requirements).
• The centre of the hole must be between 62mm and 72mm above the rail foot
• Holes must not be drilled within 45mm of the switch tip.
Drilling of Stockrails
Stockrails are normally factory drilled to fit the required signalling equipment. Altered
drilling should be carried out to suit the standard drawings of the equipment:
• The centre of the hole is to be 75mm from the bottom of the rail for 60kg/m rail and
68mm from the bottom of the rail for 53kg/m rail.
• For holes up to 22mm diameter the minimum distance between holes (edge to edge)
is 11mm, including tolerances.
• Where required 22mm holes are countersunk on the blade side using a 90 o
countersink bit.
© RailCorp Page 46 of 46
Issued 4 December 2012 UNCONTROLLED WHEN PRINTED Version 2.3