You are on page 1of 8

Jingyu Du1,2 Peter King1 Andy Gardiner1 Jian-Ping Li2

CEng MIET MIEEE

Electrification and Plant Section Supervisor Senior Electrification and Assistant Professor
Maintenance Engineer [Distribution & Plant] Plant Maintenance Engineer j.p.li@bradford.ac.uk
jingyu.du@networkrail.co.uk peter.king2@networkrail.co.uk andy.gardiner@networkrail.co.uk
Jian-Ping Li (MIEEE) received
Jingyu Du (CEng MIET) works Peter King works as a Supervisor Andy Gardiner is a senior his MSc degree in Mechanical
as an Electrification and Plant for the plant and distribution Electrification and Plant Optimisation from Nanjing
Maintenance Engineer with section on Network Rail’s East Maintenance Engineer University of Science and
Network Rail’s East Coast route. Coast route. Peter started in responsible for the railway high- Technology in 1989, and
Before joining the industry, he the department in 2011 after voltage electrification and low- PhD degree in Mechanical
received his Electrical Engineering completing the company’s voltage fixed plant maintenance Engineering from the University
BEng degree from Hong Kong advanced apprenticeship between King’s Cross and of Manchester in 2004. He is
Polytechnic University in 2015 scheme. Following that Peter Dalton on the East Coast route. currently an Assistant Professor
and a power systems MSc achieved HNC Level 4 in Electrical Andy started his railway career in engineering optimisation with
degree from Imperial College and Electronic Engineering and is as an apprentice with British the Faculty of Engineering and
London in 2016. His focus is on currently looking at furthering his Rail in 1981. Over the past 42 Digital Technologies, University
risk-based decision making for education with Level 5 & Level 6 years, Andy has accumulated a of Bradford. He has published
intelligent asset management Rail & Rail Systems Engineering. substantial amount of experience more than 100 papers in leading
that maximises infrastructure from a variety of technical, journals, such as Evolutionary
reliability via optimal and cost- engineering, training, and project Computation and IEEE
effective combination of asset management roles across Transactions on Reliability. His
renewal and maintenance the country. Andy’s expertise current research interests include
intervention. includes but is not limited to 3rd modelling complex systems,
rail electrification, high-voltage reliability and failure analysis,
switchgear and transformers, the development of modelling
protection testing and other and optimisation system, and
aspects of substation assets the application of optimisation
1
Network Rail East Coast Maintenance - Electrification
management. algorithms.
& Plant, Hitchin, United Kingdom, SG5 1RS
2
University of Bradford Faculty of Engineering &
Informatics, Bradford, United Kingdom, BD7 1DP

RAILWAY ELECTRIC POINTS HEATING:


FROM DESIGN TO MAINTENANCE

A
bstract: Electric points heating Originally, electric points heating was a
has been installed on Britain’s INTRODUCTION heating pad underneath a rail chair. The
railway for decades. It assists electrical power rating of the pad was
Points heating plays a significant role
the normal railway operation in about 100 Watt. Because of the low wattage
in supporting the railway’s normal
adverse weather. The heating and the heat transfer to the rail taking a
operation in adverse weather. The
operates automatically and can lengthy period, pads had to be turned on
heating helps to prevent switch rails
be controlled and monitored remotely, a number of hours in advance to provide
freezing at the point end and snow
which has improved its maintenance. rails with enough heat. A system of cartridge
accumulating between the switch and
This article reviews the current state heaters installed at every sleeper was then
stock rails (Figure 1a and b). In the early
of points heating design, installation, developed. A stainless-steel heater bar was
days, this was achieved by using flame
and maintenance. It proposes inserted into a drilled slot at each chair
guns, locomotive-mounted steam lances,
further improvements of points or clamplock body. However, after a long
and compressed air from a nearby
heating operational performance, by period of time in service, the heater bar
pneumatic point operating installation.
continuously developing a more robust was very hard to remove from its slot due
In the 1960s, gas burning heaters for
and cost-efficient maintenance regime to rust, etc. This brought difficulties when
points were popular in certain areas in
and adopting risk-based maintenance the heater bar needed to be replaced.
the U.K. and the first trial site was at the
and new technologies. Some of the mitigation was applying
north end of York Railway Station. Since
heat-resistant grease and drilling the
Keywords: Railway Points Heating; the 1970s, electricity has been used for
heater bar out of its slot.
Design & Installation; Maintenance & points heating in the U.K. (Dow, 2014)
Performance

22 | THE JOURNAL | January 2024


TECHNICAL ARTICLE

Figure 1: Points heating in snow: (a) heaters on both sides were functioning and (b) heater on one side was not functioning;
points heating thermal images, (c) heaters on both sides were functioning and (d) heater on one side was not functioning

Nowadays, points heating is a mix of electric prevent the track circuit being compromised. may result in a small gap between the rail
strip heaters on rails (Figure 2) and cartridge Alternative to heater strip plug terminations, and the strip. This gap affects the efficiency
heaters for clamplocks. Heat retaining long leaded strips can be directly wired into of the heat transfer from the strip to the
covers can be used on the strips to prevent a trackside transformer, eliminating the need rail. In thermal imaging cameras (Figure 1c
unwanted heat dissipation to the ambient of a 4/8 way connector block on the centre and d), white spots indicated that heat was
air. To provide heat as close as possible of the track and reducing the number of on- not efficiently transferred to the rails and
to the toe end of a switch rail without track connections and the need of on-track accumulated on the strips. Discolouration
interfering with track circuits, electrically- maintenance. on strips may occur at the place of heat
insulated strips are preferably used on accumulation. On points where tubular
switch rails. Where uninsulated strips are To pass around adjustable stretcher bars, stretcher bars are installed, instead of being
used, a gap needs to be maintained between bends have to be formed in the heating bent over the bar, the heater strip can go
the end of the strip and the point toe to strip. Although efforts have been focused on straight through the bar.
fitting a strip tightly to a switch rail, the bend

Figure 2: On-track points heating installation

23 | THE JOURNAL | January 2024


RAILWAY ELECTRIC POINTS HEATING FROM DESIGN TO MAINTENANCE
a precipitation sensor usually on top of the cubicle, up to 12 trackside
DESIGN, OPERATION AND CONTROL transformers, and two rail temperature sensors, (Figure 4). The two
temperature sensors are fitted on the track to provide the controller
The most common rating of strip heaters on Network Rail’s East
with the rail temperature. The ‘hot’ rail sensor is fitted to a heated rail
Coast route is 200 Watt/metre, and for cartridge heaters it is 200 Watt
so as to measure the operation of heating, while the ‘cold’ rail sensor is
per single heater bar. The voltage supplied from a trackside points
fitted slightly away from the heaters to read the unheated ambient rail
heating transformer is 110 V (230/110 V step-down). High-speed rail
temperature. The controller has pre-set thresholds to automatically
has long switches and hence long heating strips. For a 3-6 metres long
turn the heating on and off. The precipitation sensor detects rain or
heating strip, the operating current is in the range of 5.45 A-10.91 A,
snowfall and adjusts the thresholds. This enables a wider window of
theoretically. Clamplocks also need to be heated. A heater cartridge,
the heating in severe weather and reduces the risk of freezing points.
with a 60 ohm heating resistance which is also supplied from the
secondary winding of a trackside points heating transformer, is During the design stage, site visits are carried out to confirm the
inserted inside each of the clamplock bodies. The nominal current topography of the site. This information is then used so the “hot” and
reading should be 1.83 A for each heater cartridge. Figure 3 briefly ‘cold’ temperature sensors and precipitation sensor sited at the most
shows an example of electricity supply from a Distribution Network appropriate location to mitigate any future environmental issues such
Operator (DNO) to a points heating installation. as any sunspots or shadows on the temperature sensors, which could
result in incorrect operation of the heating.
The majority of points heating installations on the East Coast route are
designed and installed with a controller in a trackside control cubicle, Points heating operates
automatically. Two critical
factors affecting points
heating performance are
(1) heat being generated
when needed and (2)
how efficient the heat
is transferred from
the strip to the rail.
Most of points heating
performance issues are
attributed to its operational
condition (e.g. unequal
distribution of sunshine,
large pieces of ice falling
in between switch and
stock rail, clips falling off
due to vibration when
trains pass), design, and
technological limitations.
Effective maintenance is
of great importance for
points heating and the
Figure 3: Schematic diagram of electricity supply from a DNO to a points heating installation; TDBs: Trackside
Disconnection Boxes, PHCC: Points Heating Control Cubicle, EPR: Ethylene Propylene Rubber, railway’s high-performance
PCP: Polychloroprene, XLPE: Cross-linked Polyethylene, SWA: Steel Wire Armour, PVC: Polyvinyl Chloride operation.

Figure 4: (a) Inside of points heating control cubicle and sensors; (b) Trackside view and (c) Inside of 230/110 V transformer; (d) rail-mounted temperature sensor

24 | THE JOURNAL | January 2024


In busy areas like the East Coast route approaching London, line
FAILURES AND MAINTENANCE blockages for staff working on track may only be available at night,
and thus darkness, fatigue, task monotony, and adverse weather
On the East Coast route, the preventive maintenance of points
are to be considered in controlling the quality of the maintenance
heating is schedule-based (Table 1) with the tendency towards
delivery and staff safety.
condition-based.

The C1 Exam is an on-track


check for points heating
mechanical condition and basic MONTH ACTIVITIES
functions. The clips of a heating
strip may be off due to track
vibration etc. and the strip
End of September Pre-season C2 Exam (Remote)
becomes loose (Figure 5a).
The strip may also not cover October C2 Exam (Remote)
sufficiently to the point toe,
(Figure 6).
November C2 Exam (Remote)
It is important to identify
missing clips, and then reattach
the strip tightly to the rail and
December C2 Exam (Remote)
remove extra detached clips
as the small metal piece may January C1 Exam (On-track) or C2 Exam (Remote)
compromise the track circuit
(Figure 5b and 5c). On heavily-
trafficked junctions, for example
February C2 Exam (Remote) or C1 Exam (On-track)
near Peterborough railway
station, incidents like track March C2 Exam (Remote)
circuit occupation by a detached
clip may result in 500-2000
delay minutes.
April – August F/G Exam (On-track)
TABLE 1: Points Heating Maintenance Schedule. C1 Exam is on-track condition check; C2 Exam is remote
condition assessment and test run on the RADAR system; F Exam is annual load current and transformer’s
secondary voltage measurement; G Exam is 2-yearly insulation measurement. If a site is ‘C1’ examined in January,
then its next exam will be a C2 in February. The 5-yearly electrical inspection according to BS7671 is not listed here

b c
Figure 5: (a) No clip was installed at each side of a sleeper; (b) and (c) Detached clips may affect track circuit

25 | THE JOURNAL | January 2024


RAILWAY ELECTRIC POINTS HEATING FROM DESIGN TO MAINTENANCE
Since 2015, points heating installations have been remotely controlled Risk is generally prioritised according to its impact and probability
and monitored on Network Rail’s Realtime Asset Data Analysis for to occur (Khan & Haddara, 2003). According to the “Bathtub Curve”,
Rail (RADAR) system. Figure 7 shows a user control interface. The the probability of an asset failure varies with the asset’s age (Brown,
remote monitoring is set to alarm at different thresholds of electrical 2008). On the railway, the consequence of an asset failure also
current, and these are usually first picked up by the route operating varies with the asset’s location. A ‘one-size-fits-all’ points heating
centre’s engineers who analyse the alarms and decide to mobilise maintenance regime may not be robust or cost-effective for all points
maintenance engineers to site for further investigation. The remote heating installations distributed along the East Coast route.
control and monitoring reduces the need of the regular on-track C1
Exam which used to be monthly during the heating season between Risk-based elements can be added to modernise the existing
October and March. Electrical failures are identified by maintenance points heating maintenance regime. This requires points heating
engineers during the remote C2 Exam analysing the sensors’ maintenance engineers, with the assistance from document
readings. Figure 8 shows graphs depicting (a) normal working and controllers and computer experts, to analyse the historical
(b) a faulty “cold” temperature sensor. These graphs are analysed maintenance records and costs, and together with the maintenance
by maintenance engineers to assess the points heating’s condition engineers’ practical experience, to investigate points heating failure
prior to a site visit. This enables the engineers to prepare spares and modes, causes, rates of occurrence, and effects. After the risk being
equipment for a quick and efficient repair. assessed, with a detailed consideration and predication of cost,
maintenance engineers may redesign certain routine activities to
FUTURE MAINTENANCE DEVELOPMENT make them more bespoke according to the age and location of points
heating equipment or vary their maintenance frequency.
A. Risk-based Maintenance

Figure 6: Insufficient heater cover on left-hand-side stock rail

26 | THE JOURNAL | January 2024


Figure 7: Points heating remote condition monitoring webpage on Network Rail’s RADAR system

Figure 8: Points heating asset trending function showing rail temperature readings in a period of no heating on: (a) normal operation that “hot” and
“cold” temperature sensors had the same readings, (b) faulty “cold” temperature sensor that reported abnormally low rail temperature.

IAB OPPORTUNITY
YOUR LOCAL UNIVERSITY NEEDS YOU!
As part of our engagement with universities, there is opportunity to become a member of their Industrial Advisory Board.
These groups are formed of academics and those working in industry, to work together in ensuring graduates will meet
industry need, to facilitate industrial contributions to students (e.g. guest speakers, site visits), and build engagement
between the university and its local employers. IABs typically meet twice a year.
If this opportunity is of interest, please drop an email with your CV to PROFENG@THEPWI.ORG
27 | THE JOURNAL | January 2024
RAILWAY ELECTRIC POINTS HEATING FROM DESIGN TO MAINTENANCE
Reassessment shall be carried out regularly to check the effectiveness
of the updated maintenance regime. Any updates of regulations ACKNOWLEDGMENT
and standards shall be considered during the reassessment. Risk-
The authors would like to thank James Freemantle, Ashley Randall,
based maintenance is a continuous and dynamic process to achieve
Sean Harris and colleagues from Network Rail’s track, signalling, and
equipment’s maximum safety, environmental and functional
fixed plant engineering and air operations for their input and support.
performance at minimum cost. Reassessment plays an indispensable
role in managing the risk’s development. In the short-term future,
hopefully a combination of schedule-based, condition-based and REFERENCES
risk-based hybrid maintenance regime for points heating will be
Brown, R. E., 2008. 4.2 FAILURE RATES AND BATHTUB CURVES. In:
developed.
Electric Power Distribution Reliability. 2nd ed. s.l.:CRC Press, pp. 165-
B. New Technologies 167.

In recent years, helicopter and train on-board thermal imaging Dow, A., 2014. The Railway: British Track Since 1804. s.l.:Pen & Sword
cameras have been increasingly used to detect failed heating strips. Books Ltd..
Figure 9 shows an image taken from a helicopter. Maintenance
Khan, F. I. & Haddara, M. M., 2003. Risk-based maintenance (RBM):
engineers remotely switch on points heating via the RADAR system
a quantitative approach for maintenance/inspection scheduling and
slightly before the helicopter flies through the area. The heating strips
planning. Journal of Loss Prevention in the Process Industries, 16(6),
raise the rails’ temperature which are shown white in the thermal
pp. 561-573.
image.

Drones may be considered to examine points heating operation


during winter days. The pictures are expected to be closer to track
and reveal more details than pictures from helicopters. Drones are
generally operated on the railway by a minimum of two competent
staff members. Extra care shall be taken for drones to fly safely in
overhead line electrified areas.

The points heating remote monitoring can be further improved by


installing advanced sensors and transducers to detect any mechanical
defects, and to convert the information to electrical signals in the
remote control and monitoring system. Weather forecasting can
also be used in conjunction with the system to achieve improved
efficiency. For example, linking existing lineside weather monitoring
stations and cloud database to the points heating remote system
for forecasting and automatically pre-empting adverse weather
conditions that could result in rail freezing.

CONCLUSION
Electric points heating warms rails and helps to prevent the rails
from freezing in adverse weather. With the successful roll-out
of the remote control and monitoring system and continuous
improvement of its maintenance regime, points heating maintenance
has been greatly improved. In the short-term future, emphasis can
be placed on implementing risk-based maintenance and adopting
new technologies to further improve points heating operational
performance.

Figure 9: Points heating thermal imaging check on helicopter


(courtesy Network Rail Air Operations)

SLIDING FRICTION
BUFFER STOPS
Rawie Friction Buffer Stops provide protection for track ends worldwide.
They can be designed to suit all types of rolling stock, accommodating
varied train weights and speeds.

Manufactured by A.RAWIE GmbH & Co. KG.


Tel: 0049 541 91 2070
bufferstops@rawie.de
www.rawie.de

Supplied in UK & Eire by H.J. Skelton & Co. Ltd.

SKELTON Tel: 0044 1635 866877


sales@hjskelton.com
www.hjskelton.co.uk

28 | THE JOURNAL | January 2024


TECHNICAL ARTICLE www.thepwi.org

AS PUBLISHED IN
THE PWI JOURNAL JANUARY 2024
VOLUME 142 PART 1
If you would like to reproduce this article, please contact: journaleditor@thepwi.org

PLEASE NOTE: Every care is taken in the preparation of this publication, but the PWI cannot
be held responsible for the claims of contributors nor for the accuracy of the contents, or any
consequence thereof.

the PWI the_pwi the PWI

PWInstitution PWInstitution

You might also like