Professional Documents
Culture Documents
1996-Application of Mechanically Stabilized Earth and Segmental Block Walls
1996-Application of Mechanically Stabilized Earth and Segmental Block Walls
ABSTRACT
Thousands of people commute to and from Boston every day, many of them
using the 'T' subway and commuter rail system, owned and operated by the
Massachusetts Bay Transit Authority (MBTA). To provide better service
to a greater number of people, the MBTA decided to re-open two old rail-
way commuter lines, the Plymouth and Middleboro, that have not carried
passengers since the late 1930s (Tensar, 1995). This paper focuses on the
unique manner in which geosynthetic reinforced earth systems were utilized
to eliminate a grade crossing located at the line's intersection with Pearl
Street. This project is unique in that it is the first project to utilize
mechanically stabilized earth ( MSE) slopes and unitized segmental block
walls to support heavy rail traffic (E-80 loading). Copyright © 1996 Else-
vier Science Ltd.
INTRODUCTION
277
278 Mark H. Wayne, Bob Miller
BOSTON
PROJECT SITEI
LINE ] Ht
J PEAR, STREETJ
...."'*"
"""Y'" ..'Y"
Ouln,
Milton \
..........~; \
. ...'" :.
...... "Br Whitma]~ r
! Pembroke ,/
f
yY'""'-.....
,..............
!; " /
Hanson /
ston \ West Ea,t !
Brldgewate?
earth around both the bridge abutments and the area under the rail lines
after crossing the bridge. Beyond the bridge, the tracks split into a 'Y' head-
ing in the directions of Plymouth and Middleboro. In addition to the six
walls specified by Sverdrup for the rail line, an additional three cast-in-place
walls were required to accommodate vehicular traffic on a realigned Pearl
Street.
Under the bid alternate for the contractor, Tensar Earth Technologies,
Inc. designed the retaining wall section of the project, redesigned the
specified precast panel walls and the tieback structure. These were replaced
by three Sierra ~m MSE slopes, one Mesa ;~ unitized segmental retaining
An application of mechanically stabilized earth 279
wall, and three combination slope/wall MSE structures. The three cast-in-
place walls along Pearl Street were also replaced with Mesa walls.
MESA COMB
NOT TO SCALE
4OOmm
I I
I I
I I fCOi4B 275mm
ESA ST~'4DARDU N I T S / I I
WAIL BATTER)
twice the long term design strength of the geogrid. This information is
important when considering the use of segmental block wall systems in the
design of railway transit systems. This is mainly due to the fact that E-80
train loading results in high lateral loads at the top of the wall where
confining pressures are low. Table 1 confirms the fact that the block/
geogrid connector provides adequate connection strength even at low
confining pressures.
DESIGN P R O G R A M S
This project was designed through the use of the Tenswal (Tensar) and
Tenslo (Tensar) computer programs. The Tenswal program uses the tie-
back wedge method of analysis (which is the standard practice in the
United States) to determine the geogrid type, location, and lengths
required to satisfy both internal and external stability. The slope stability
program, Tenslol, uses a modified Bishop method of analysis. The
geometry, soil boundaries and strengths, phreatic surface, seismic coeffi-
cients, geogrid strengths, and geogrid layout are input into the program.
The program then uses a predetermined pattern of failure circle centers
TABLE 1
Mesa/Tensar Structural Geogrid Connection Test Results
5
a
Geogrid Long-term Confining Ultimate F.S. on Connection F.S. on
5
design strength pressure connection ultimate strength at connection n.
kN/m kN/m2 strength connection 19 mm (314 in) strength at f?
6’
(Lbsflttl (psi) kN/m strength displacement 19mm (3/4in) z
(Lbslft) kN/m (lbslft) displacement 2
SURCHARGE LOADING
Several different surcharge loads were used in the design of the walls and
slopes for the Pearl Street project. A 28-7kN/m 2 (600psf) surcharge was
applied to take into account construction loads. A 55.8 k N / m 2 (1165 psf)
railroad train surcharge was determined in accordance with equations
supplied by the MBTA. The equation supplied by the MBTA stated that
the surcharge of an E-80 train is equivalent to approximately 2-9 m (9-5 f)
of soil with a unit weight of 18-9kN/m 3 (120pcf). In addition, a 1.2kN/
m 2 (25 psf) surcharge was included to account for the track. The summa-
tion of these two surcharge loads was used in design. For those track
sections where 1.5m (5 ft) or more of open space existed between the
tracks and edge of a wall or slope, a 12kN/m 2 (250psf) surcharge was
added to account for possible truck traffic. For the temporary wall
system, an additional analysis considered a 12kN/m (250psf) traffic
surcharge, along with 500ram (20in) of ballast at 18.9kN/m 3 (120pcf).
This equated to a dead load surcharge of 21.5kN/m 2 (450psf). Typical
cross-sections for the steep slopes, unitized segmental block retaining wall,
and slope/wall combinations are depicted as Figs 3--5, respectively.
G E O G R I D DESIGN S T R E N G T H S
Since this project involved phased construction, the design analysis inclu-
ded phased, temporary, and permanent walls. Phased and temporary walls
were designed on the basis of a six month service life. Due to the visco-
elastic nature of geosynthetic materials, the tensile strength is dependent
upon the rate of loading of the material. Based on this fact, along with
supporting documentation from external studies, geogrid strengths were
~ - - / OUTIDA~I,ILJI3.'IOILII~IP+I,I~ R I D ~ W I ~ ~" ~'SlL , / • ~ / . / , It
IllllmOIII I ~ IIImt~l"I~lmllml. -,~
~P'~"-
+ " " " sul IUPIIm°tpxs ~ ~ ~ . S
M~2tN O~..lqt A i ~ SILL
L,..,?II~ n E m a ~ m pltDO M l n l $ ~ ~ e~
I
Fig. 3. Typical slope detail.
~ ' " I I I I /
~ " ~ .
~~'M~'~
~,...
-'~
---4.
~' ,,
~
,,
~ ,
.I~
, X
""
t
""
• :
- l
" - - 7 r
., ~
' [
] II .~t. X
I ~-H ~ , I , ~ /
,,\~1 5..'~.~.~1
-'-t'm~' ~ .t
~ w
~N~I~UHDAI~
increased (from their long-term, 100 year design strength) for all short-
term loading conditions.
(l) The Tenswal (Tensar) design program was used to evaluate the
internal stability of the reinforced wall system. A 28.7kN/m 2
(600psf) construction surcharge and a factor of safety for uncer-
tainties of 1-5 or greater was considered in the analysis. For the
temporary wall system, an additional analysis considered a 12 kN/
m 2 (250psf) traffic surcharge and 500mm (20in) of ballast at
18.9kN/m 3 (120pcf). This equated to a dead load surcharge of
21.5 k N / m 2 (450 psf). Since ballast would not be added in the case
of the phased construction wall only a traffic surcharge of 12 kN/
m 2 (250 psf) was considered in this analysis.
(2) The Tenslol (Tensar) design program was used to perform global
stability analysis. Two cases were considered in this analysis.
Global stability analysis took into consideration a 55.8kN/m 2
(l165psf) railroad train surcharge and a 12kN/m 2 (250psf)
surcharge for truck traffic adjacent to the track. In addition, a
28-7 k N / m 2 (600 psf) construction surcharge was considered sepa-
rately. For both cases, a global factor of safety of 1-5 or greater
was used in the analysis.
(3) The Tenslo program was also used to perform seismic stability
analysis on the various cross-sections. Based on a short duration
loading of less than 1 h, the strength of the structural geogrid was
increased. Per MBTA, a peak horizontal acceleration of 0-17 g was
considered along with an acceleration coefficient of 0.10g as per
A A S H T O guidelines (AASHTO, 1991). An overall factor of safety
equal to or greater than 1-13 was used in this analysis.
(4) Railroad train loads were analyzed with the train spreadsheet
calculation. Distances from the appropriate cross-sections devel-
oped by MBTA were used to establish: (a) distance from the wall
face to the first railroad tie; (b) width of the railroad ties; and (c)
distances between the two railroad ties.
CONCLUSIONS
line's intersection with Pearl Street. This project was unique in respect to
the fact that it is the first project to utilize mechanically stabilized earth
(MSE) slopes and unitized segmental block walls to support heavy rail-
road traffic (E-80 loading). This project also demonstrated the unique
manner in which a mechanically stabilized earth slope and unitized
segmental block wall were easily combined into a single MSE structure.
The wall and slope work for the Pearl Street project is expected to be
completed in October of 1995, and the entire project is scheduled for
completion by September 1996. With its completion, the Plymouth and
Middleboro commuter lines will carry passengers once again.
ACKNOWLEDGEMENTS
The authors would like to thank Sean Wokasien, Joe Emberson and Dolly
Cockroft of the TET design group for their assistance with the prepara-
tion of this paper. Special thanks to Francis Clark and Kathy Frederick
for their invaluable article on this topic. The authors would also like to
express their gratitude to the Sverdrup Corporation and the general
contractor, DeMatteo Construction, for considering the use of the Tensar
MSE systems.
REFERENCES
Tensar (1995). GEOTALK, MBTA Brings Old Rails Back "On Line", Issue 5-1,
Fall 1995.
Tensar. TENSWAL: wall stability program, The Tensar Corporation, Atlanta,
Georgia.
Tensar (1994). TENSLOI: slope stability program, The Tensar Corporation,
Atlanta, Georgia.
American Association of State Highway and Transportation Officials (1991).
Standard specifications for highway bridges, 14th Edn with interim specifi-
cations-- bridges. AASHTO, Washington, DC.