WORK DETAIL
NO DESCRIPTION Quantity Starting date Finished date Remark Complete rate
1 TEMPRORARY ACCESS GATE AND ROAD 18/1/2024 24/1/2024
1.1 Entrance Road Gate 1 1 20%
2 TEMPORARY GUARD HOUSE, Gate 1 15/1/2024 22/1/2024
2.1 Foundation + Surface 1 0%
2.2 Installion house + electric 1 0%
3 Temporary Civil Contractor's Store (12mx6m) (Hard surface only) 13/1/2024 15/1/2024
3.1 Foundation 1 100%
3.2 Pourd lean Concrete 1 0%
4 Temporary M&E Contractor's Store (12mx6m) (Hard surface only) 12/1/2024 12/1/2024
4.1 Foundation 1 100%
4.2 Pourd lean Concrete 1 50%
5 Temporary Steel Structure Store (12mx6m) (Hard surface only) 13/1/2024 15/1/2024
5.1 Foundation 1 100%
5.2 Pourd lean Concrete 1 0%
6 Temporary Worker Rest Area (Canteen) (15mx10m) 15/1/2024 19/1/2024
6.1 Installion house + electric 1 50%
7 Temporary Steel Fabrication Yard (15mx10m) (Hard surface only) 13/1/2024 15/1/2024
7.1 Foundation 1 0%
7.2 Pourd lean Concrete 1 0%
8 Material Laying Area (30mx15m) (Hard surface only) 16/1/2024 20/1/2024
8.1 Foundation 1 0%
8.2 Pourd lean Concrete 1 0%
9 Civil Work Fabrication Yard (15mx15m) (Hard surface only) 15/1/2024 17/1/2024
9.1 Foundation 1 0%
9.2 Pourd lean Concrete 1 0%
10 Assembly Area (30mx15m)
10.2 Pourd lean Concrete 1 12/1/2024 12/1/2024 90%
11 Temporary Toilets & Biotank (12mx2m), 2 Females & 2 Males
11.1 Septic tank 2 50%
11.2 Foundation + Surface 2 10%
11.3 Installion house + electric 2 0%
12 Temporary Water Storage Tank, 2 locations
12.1 Water tank 4 0%
12.2 Net cover 1 0%
13 Temporary Drainage
13.1 Installation boundary drainage and connect with MJTD Drainage 1000 0%
14 Washing Bay, 2 locations
14.1 Excavation and building 1 0%
14.2 Installation pump 2 0%
15 Temporary Lighting 12/12024 20/12/2024
15.1 Foundation 33 24%
15.2 Lighting pole installation 33 0%
15.3 Electrict 33 0%
16 Clean Area
16.1 Clean Area 1 0%