K7 CONSTRUCTION OFFICE:
ENGINEER-UDHAYAKUMAR.K SELVI COMPLEX
: 82200-04903, AYYANAR NAGAR
99431-34819 ANDARKOTTARAM POST
Gmail : k7constructionmdu@gmail.com MADURAI-625-020

ESTIMATE FOR PROPOSED CONSTRUCTION OF RESIDENTIAL


BUILDING FOR Mr. at Madurai

WORK DETAILS
GROUND FLOOR

I. Basement:

1. 3’0” X3’0” - 5’0” ePsk; Fop Njhz;b jug;gLk;.


2. 6” PCC 1:4:8 Nghl;Lj;jug;gLk;
3. Mat & Pillar fk;gp fhd;fphPl; Nghl;J jug;gLk; (Mat 10mm, Pillar-
4Nos-12mm, Strippus 8mm)
4. Earth Beam 1’6”X9” fl;b> gyif milj;J fk;gp fl;b fhd;fphPl;
Nghl;Lj; jug;gLk; (12mm X5 Nos)
5. Earth Beam cld; Nrh;j;J 3’0” mb cauk; tiu fl;blk;; jug;gLk;.
cs;Ns Rth; G+rpj; jug;gLk;
6. mjw;F NkNy 9”X6” Belt Nghlg;gLk;
7. midj;Jk; Room-w;Fk; 1 1/2” [y;yp PCC 1:4:8 Nghl;L jug;gLk;.

II. Super Structure

1. Belt -w;F NkNy 7’ mb cauk; tiu fl;blk; fl;bj;jug;gLk;.


2. mjw;F NkNy 9’X6”-w;F Lintel & Concrete Nghl;Lj; jug;gLk;.
3. xt;nthU Room-w;Fk; Loft & Sun Shade Nghlg;gLk;
4. mjw;F Nky; 2’6” mb cauk; tiu fl;blk; fl;bj; jug;gLk;;.
2

5. Ground Floor Roof Height 10’> First & Second Roof Height 10’
6. Roof Slab fk;gp fl;b Nkhy;L milj;J fhd;fphPl; Nghlg;gLk;.
(Including Roof Beam - As per plan)
7. Roof Slab-w;F Nky; ifg;gpb Rth;( and column concrete ) 3 mb
cauk; fl;b jug;gLk;.
(Roof Thickness = 5” - Loft & sun Shade -2” Thick)
8. nkhl;il khbapy; fg;gp mbj;J jsk; /jl;NlhL Nghl;Lj;jug;gLk;.

III. PLASTERING:
1. Rthpy; XL itj;J khh;f; nra;ag;gLk; rPypq; > cs;G+r;R>
ntspg;G+r;R G+rpj; jug;gLk;.
2. Room xd;wpw;F 1 fg;Nghh;L fl;b G+rpj; jug;gLk;
3. Kitchen - Nkil- fhd;fphPl; Nghl;L G+rpj; jug;gLk;.
4. xt;nthU Floor-w;Fk; xU stair case milj;J fhd;fphPl; Nghl;L
gbfl;b G+rpj; jug;gLk;.
5. cs;Rthpy; vyf;l;hpfy; igg; ,uz;bw;F Nky; ,Ue;jhy; mjpy;
tis itj;J G+rpj; jug;gLk;.

CEMENT RATIO:

1. fl;blk; fl;Ljy; - 9” Rth; 1:6


2. 4 1/2” Rth; 1:5
3. G+Rjy; = Ceiling 1:4
ntspg;G+r;R - 1:5
cs;G+r;R - 1:5
4. 1 1/2 “ [y;yp PCC 1:4:8

IV. Extra Work - ,e;j Nul;by; Nruhj Ntiyfs;


1. Sumb, Water Tank, Septic Tank.
2. Compound Wall,tiles work ,electrical and plumbing work ,Painting
3. Entrance Main Grill Gate, Balcony Grill work
4. Building Elevation (Arc, Bargola, Border) Ntiyfs; midj;Jk; jdp Nul;
3

5. Building -w;F ntspNa nra;Ak; Ntiyfs; midj;Jk;jdp Nul;.


6. Site -y; cs;s gioa Rth;fs; my;yJ Fg;igfs; NtW VjhtJ ,Ue;jhy;
mij mfw;WtJ.
7. The curing of the building is incharge of the client.
8. Mazdoor work : Elevation, Decorative works, Skirting touchup work & Clean-
ing work will be Billed Actual labour plus 10% Service charge.
9. Payment to be given by the Client at various stages & Every Week end.

10. If there is any alteration & addition to the existing plan,that will be billed suitably.

11. For any additional works other than specified above rates will be given at the time of
execution
12. Site-y; Ntiy elf;Fk;NghJ VjhtJ khw;wk; ,Ue;jhy; ,e;j Nul;by;
NruhJ. jdp Nul; MFk;. (Fwpg;G Basement cauk;)

Mazdoor Rates :
Mason - Rs. 1200/day
Male Coolie - Rs. 900/day
Female Coolie - Rs. 700/day
13.

Nkw;fz;l Ntiyfs; midj;Jk; ey;y Kiwapy; cz;ikahfTk; cWjpahfTk;


Plan-y; cs;sgbnra;J jug;gLk; ,e;j Agreement Value For 6 Months
4

ESTIMATE : As per plinth area method

TYPE : RCC pillars and RCC Roof

RATE : Arrived as per similar construction and adopting


specification

: Ground floor Rate /Sft = Rs.500/-

:First floor Rate /Sft = Rs.500/-

:Compound wall Rate /Sft = Rs.150/-

:Septic tank brick wall Rate /Lit = Rs.15/-

:Sump RC wall Rate /Lit = Rs.18/-

Signed and delivered for and Signed and delivered for on

On behalf of owner behalf of CONTRACTOR

(ENGINEER)
5

PAYMENT DETAILS

Ground floor

Total Amount Rs. ……………….

SI Stage % Amount Owner Contractor


NO
1 Advance 10%

2 Foundation 10%

3 Base level 15%

4 Lintel level 10%

5 Roof level 25%

7 GF Inner Plastering 10%

8 Outer plastering 15%

10 Finishing work 5%

Signed and delivered for and Signed and delivered for on

On behalf of owner behalf of CONTRACTOR

(ENGINEER)