Answer

Answer:

a)

Based n the given information in the problem, the network drawing covering the processes to
complete the project are given below. The critical path is marked in red color.

Once, ET1 and SP1 (first km.) is completed the sequential process of LP, PT and BF of fist km.
could be completed. The ET and SP for scond and third km. now can be completed simultaneously
and followed by LC, LP, PT and BF sequentially for second and third km. together.

The project minimum completion time = 1+5+2+6+1+2+2+12+2+4 = 37 days

b)

Now, if LP1 is delayed by 1 day, then total duration would alo be extend by 1 day as it is on critical
path.

Even if SP is delayed, it won’t affect proh=ject duration as it is not on critical path.

If LP is delayed by 3 days, then project duration would also increase by 3 days

Aftre above revisions, first part of PT starts after 18days, so if it takes 16 days, then that would not
be any delay for the project.

Therefore the project duration would increase by 6 days, so total 37+4 = 41 days

The revised network drawing is given below: