Professional Documents
Culture Documents
• What is a Standard ?
• It is a model or a general agreement of a
Rule established by authority or
consensus.
• It conforms to widely acceptable
representative features and
characteristics.
Construction Standards
Hence
Use –
Standard Materials
Follow –
Standard Construction Practices
Construction Standards
• Where to Start with Construction ?
• Before Starting 11 KV line Work Finalise
the location of Transformer.
• Location ?
• 1) Nearest to the Load Centre.
• 2) Feasibility of drawl of 11KV line.
• 3) Easy Road access.
• 4) Minimum Public hindrance.
• 5) Safe location.
Construction Standards
• 11 KV Lines :-
• Choice of Route
• 1)Shortest feasible route if possible along
Roads.
• 2)Transportation facility.
• 3)Minimum compensation.
• 4) One side of public path.
• 5) Minimum parallalism with BSNL lines
Construction Standards
• Avoid:-
• 1)Steep Curves.
• 2)Rock Area.
• 3) Steep Hills.
• 4) Thick vegetations.
• 5) School Play Grounds.
• 6) River crossings.
Construction Standards
• Right of Way :
• Approval from concerned authorities for
the drawl of line ,Tree cuttings, Stay
locations etc. so as to avoid further
hindrance to the Work.
• Tree Clearances as per site conditions.
• Preparation of
•
Construction Standards
• Preparation of Route Map.
• Joint Inspection of Route with BSNL
authorities.
• Preparation of Estimates.
• Estimate Reports.
• Sanction from competent authorities.
• Administrative and Technical sanctions.
• Provisional Route approval from BSNL
authorities.
Construction Standards
• Construction of 11 KV lines.
• 1) Erection of Supports.
• 2) Providing Stays.
• 3) Mounting Cross arms, Pins and Pin
Insulators.
• 4) Stinging of Conductors.
• 5) Jointing of conductors.
• 6) Sagging / Tensioning of conductors
• 7) Earthing of Poles.
Construction Standards
• Supports :-
• As per REC standards 7.5 M, 8.0M, 9.0 M
Poles can be used.
• But in K.S.E.B. 9 M PSC Poles and A Type
poles ( 11 M, 12 M) are used.
• Maximum Span Length - 75 M.
• Planting Depth 1.5 M .
• Minimum Factor of Safety is 2.5.
• Working load on the Pole 200Kg at 60 CM
from the Top.
Construction Standards
• Details of PSC Poles
• I. Manufacturing, Testing and handling of
poles:
• As per IS: 1343/80 -- Code of practice for
pre stressed concrete – (concrete mix)
• IS: 1678/60 —specification for PSC
poles
• IS: 2905./66 —Testing of poles
• IS: 7321/74 — Handling of poles
Construction Standards
• Design features of 9 M/ 200 Kg PSC Pole.
• Factor of Safety = 2.5.
• Dia of HTS Wire = 4 mm.
• Ultimate Tensile Strength of Prestressing
Wire. = 17500 Kg /cm 2
• Number of Tensioned Wires = 12.
• Number of UnTensioned Wires = 2
• Weight of Pole = 490 Kg.
• Clear cover to Wires. = 20 mm.
• Steel Quantity / Pole = 11.4 Kg.
8M
Section at Bottom
Categ Working Cross section Number of Depth
ory of load
pole steel wire below
Bottom Top Tensioned Un G.L
4mm dia tensioned
4mm dia
: 420Kg/cm2
Detensioning of wires :After 3 to 4 days
on attaining 210 Kg/cm2
F Type Bracket
11 KV Line
DP-
Construction Standards
• STAYS FOR SUPPORTS
• Unbalanced strain or supports which can
cause tilting, up rooting or breaking of
support
To take care of the above STAYS,
ARE PROVIDED
Construction Standards
• Stays are required
i) Angle locations
• ii) Dead end locations
• iii) Tee-off points
• iv) Steps gradient locations
Construction Standards
Installation of stays include
• i) Excavation of stay pit and fixing stay
rod and stay plate
• ii) Fastening stay wire to the support
• iii) Tightening stay wire and fastening to
the Anchor
Construction Standards
• SINGLE STAY
• DOUBLE STAY
• FLY STAY
• BOW STAY
• STRUT
Construction Standards
• STAY INSULATORS.
• IS : 5300 C - Type for 11 KV.
• Basic Insulation Level : 27 KV (rms)
• Dry one minute power frequently with stand voltage
• Minimum failing Load : 13 KV(rms) Wet
1 2 3 4 5 6 7
20
6/2.11 1/2.11 20.98 24.48 6.33 85 1.403 7.61 70
Squirrel
30
6/2.59 1/2.59 31.61 36.88 7.77 128 0.9352 11.12 100
Weasel
50 Rabbit 6/3.35 1/3.35 52.88 61.7 10.05 214 0.556 18.25 148
60 Mink 6/3.66 1/3.66 63.06 73.57 10.98 255 0.454 22.6 167
80
6/4.09 1/4.09 78.83 91.97 12.27 319 0.3736 26.91 197
Raccoon
Construction Standards
• What is a Standard ?
• It is a model or a general agreement of a
Rule established by authority or
consensus.
• It conforms to widely acceptable
representative features and
characteristics.
Installation of Transformer, Switch gear etc
300
200
12
100
Resistivity
of Soil in
Ohm 0 5 10 15 20 25 30 35 40
Metre.
Moisture in Salt , Percentage
400
350
300
250
200
150
100
50
Resistivity
of soil in
0 2 4 6 8 10 12 14 16
Ohm
Metre. Percentage of Salt in Moisture
Variation of Soil Resistivity with Salt ( NaCl )content
clay Soil having 3 % moisture.
• EARTHING OF DISTRIBUTION
TRANSFORMERS.
• Five earth pipes of 2.5m length each
should be erected into the ground.
• The minimum distance between the earth
pipes should be 5m.
• 8mm G.I wire shall be used for earth
leads.
• Earth No.1 : L.A
• Earth No.2 : Transformer neutral
• Earth No.3 : Transformer neutral
• Transformer body
• Earth No.4 : Transformer Body
• All metal parts of structure
• Earth No. 5 : Metal parts
• : Insulator pins (duplicate
earthing)
• : Stay clamps
• : AB switch body
• : AB handle
• : Supports for insulation etc.
Acceptable Earth Resistance
Limits
POLE
Transformer
Pipe
N
LA
AB Switch
Handle & Position of Transformer
Metal Parts and Earth Pipes.
Coil Earthing
Pipe Earthing
Construction Standards
• Rule 66 Metal sheathed Electric supply
Lines. Precautions against leakage
• Rule 67 connection with Earth.
• Rule 68 General conditions as to
transformation and control of energy –
fencing protection, etc …
• Rule 69 Pole type substation—Hand rail to
be provided; to be earthed.
• PTCC NORMS
• Power cable shall be laid through pipes
at Telephone cable and Road crossings.
• Along roads, concrete/brick covers with
Markings shall be provided.
• Preferably 0.6m but not less than 0.3m
horizontal separation to be maintained
between power cable and telephone
cable.
• For identification of U/G cable, route
markers to be pointed .
• For identification of U/G cable, route
markers to be pointed .
• Minimum depth of cable 0.75m and 1m
at road crossings.
• The angle of crossing shall be 90 degree
but not less than 60 degree.
• The power system shall be equipped
with protective switch gear such that
duration of earth fault current should
not exceed 0.5 Seconds.
– Joint inspection of 11KV route at the time
of preparing estimate.
– Provisional Route Approval to be obtained
from BSNL.
– Detailed Route map of the proposed 11KV
line showing telephone crossings, location
of transformer etc to be prepared and
along with the Performa, to be sent to the
AGM (CP), O/o PGM Telecom, BSNL
Bhavan, Ernakulam, Kochi 682016 with
copy to the Local SDET.
– After verifications, PRA will be given by
the BSNL Authorities.
– An invoice for removal of line, shifting
telephone lines, changing to UG cable etc will be
intimated by the BSNL authorities.
– Assistant Engineer to measure the invoice and is
to be passed by competent authorities from
KSEB and to effect payment by DD to BSNL
authority (to the AGM, with intimation to local
SDET.)
- On receiving, the local BSNL authorities carry
out the proposed shifting work.
• On completion of Line works request for
energisation approval is to be sent to the
AGM along with the remittance details.
• E.A will be issued by the AGM normally
within one month.
• Decision taken at the Central PTCC
meeting held at Darjeeling on 27.2.03
against unilateral charging of power
lines. Penalty for unilateral charges
after 1.4.03.
• 1. 11KV lines : 1 lakh
conductor
• 4. Bearer wire breaking strength : 350 kg
• 5. Porcelain, tension and pin insulators –used
as supporting and stringing the bearer wire.
• 6. The bearer wire shall be sectionalized and
shall not exceed 4 spans. Each section should
be earthed in duplicate at start and points with
No. 8 S,W,G GI wire used Earthing electrodes
of 38 mm diameter.
• 7. 130 mm horizontal clearance from pole
for bearer wire and cable. Cables to be
bound to bearer wire at an interval of
1250mm.
• 8. Operating voltage of booster shall not
exceed 110 v
• GUIDELINES TO BE FOLLOWED FOR
LAYING 11KV /LT U/G CABLES
• KSEB should be the applicant.
• Approval will be given to KSEB only
• Required form (form A&B)
questionnaire, Route Diagram etc should
be attached along with the request.