You are on page 1of 10

An overview of trends in aircraft maintenance program development:

Past, present, and future


A. Ahmadi, P. Söderholm, & U. Kumar
Luleå University of Technology, Luleå, Sweden

ABSTRACT: The purpose of this paper is to describe the trends in aircraft maintenance program develop-
ment during the last 50 years, including the reasons for the aircraft industry to change its view of mainte-
nance. The major milestones and fundamental reasons for such development are also discussed and illustrated
in relation to a flow diagram, which shows the logical and chronological order of the trends. Finally, the pa-
per describes some possibilities and challenges as regards applying Information & Communication Technol-
ogy (ICT) within the emerging approach of e-Maintenance in order to enhance the surveillance of aircraft
maintenance program performance.

1 INTRODUCTION maintenance program’s performance is discussed as


a future development.
Before 1950, technical items were mostly simple,
which made them reliable and easy to maintain. The
maintenance concept were mostly based on the be- 2 EARLY MAINTENANCE STRATEGIES AND
lief that failures were mostly caused by wear and RELATED PROBLEMS
tear and the common maintenance strategy was Cor-
rective Maintenance. By the late 1950s, the second Prior to World War II, maintenance was a skill
generation of maintenance started, with the introduc- learned through experience and rarely based on sci-
tion of more complex items, mostly due to lack of entific theories. The maintenance requirements were
labor and high performance requirements. With in- determined by a few experienced technicians with
creasing complexity and criticality of items, the im- assistance from the Original Equipment Manufac-
portance of a preventive maintenance program for turer (OEM). The items were quite simple, which
failure management increased. However, one of to- made them reliable and easy to maintain. In those
day’s major challenges remains how to determine days, the common maintenance strategy was Correc-
the success of such maintenance programs. tive Maintenance, based on the belief that the fail-
The first part of this paper provides some back- ures were mostly caused by wear and tear. Hence,
ground to the airlines’ problems during the 1960s, the maintenance was applied in order to restore the
with a short discussion on efforts leading to the pub- functional capability of failed items. This was a re-
lication of the first systematic review of aircraft sys- active approach to maintenance since the action was
tems, known as the MSG-1 and the MSG-2 method- done after the failure had occurred. This period of
ologies. Next, the efforts of United Airlines, which maintenance is known as ‘Pre World War II’. (Mou-
led to the Reliability-Centered Maintenance (RCM) bray, 1997)
methodology are described, outlining how the pre- By the late 1950s, or ‘Post World War II’, the sec-
ventive maintenance concept was influenced by sys- ond generation of maintenance started to evolve. In-
tem level thinking. The effect of RCM on the MSG dustry became more competitive and a lack of man-
methodology, which resulted in the publication of power, improved design standards, and new
MSG-3, will also be described. All these develop- performance requirements led to increasingly com-
ments and trends are discussed with the help of a plex and mechanized items. Therefore, the mainte-
flow diagram, which illustrates the developments in nance of items required more downtime and re-
a logical and chronological order. sources. Hence, maintenance costs were high and
Finally, the possibilities and challenges related to availability became another problem. These changes,
e-Maintenance for the surveillance of an aircraft together with penalties associated with loss of pro-
duction, forced industry to consider how to prevent
the item from failing by applying Preventive Main- nance program was applied to all aircraft fleets
tenance instead of relying on Corrective Mainte- regardless of operating profile, weather, opera-
nance. tor, etc. This approach was insufficient, since the
In an effort to reduce the number of failures, in- operating context affects the failure characteris-
dustry concluded that, based on the accepted ‘wear tics and changes the failure rate. Hence, the
and tear’ model of failure, every item had a ‘fixed maintenance task and its interval applicable to
age’ at which either complete overhaul or discard one operating context may not be applicable to
was necessary to ensure safety and operating reli- another.
ability. 4. Maintenance was applied to control the degrada-
Based on these concepts, there was a widespread tion of functional performance and reliability of
belief that all failures could be prevented by age- all items. It was believed that there was always
based overhaul. As a result, Time-Based Mainte- an appropriate maintenance task to retain the in-
nance became the norm for Preventive Maintenance. herent reliability or to restore the functional per-
This kind of approach motivated the indiscriminate formance of the items. However, it is now
use of overhaul or preventive replacement for all known that, due to the nature of some failures, it
items included in a Preventive Maintenance pro- might be impossible to retain or restore the item
gram. (Tsang, 1995) performance to the designated level. Hence,
Consequently, the failure rate increased rapidly some of the maintenance tasks were inappropri-
and maintenance costs grew accordingly. This ate and contributed to anomalous maintenance
prompted the airline industry to look for new pre- effort and downtime without giving any benefits.
ventive maintenance concepts. In addition, the Fed- It should be noted that inherent reliability is a
eral Aviation Administration (FAA) in the US was function of design and cannot be improved with-
concerned that the reliability of some engines had out redesign or modification.
not been improved by changing either the type or the 5. It was incorrectly assumed that all items had
frequency of overhaul. The available data indicated age-related failure characteristics and would
that although the frequency of some failures had benefit from age-based maintenance measures.
been reduced, many more had remained unchanged Therefore, specific actions, mostly overhaul
or actually increased. These findings could not be measures, were planned for every item. How-
explained by using the accepted model of failure. ever, according to the reliability investigations
During this time, a new approach to maintenance conducted by United Airlines, no more than 11%
evolved within the aircraft industry. Based on analy- of the items would benefit from a limited operat-
sis of failure data, it was found that the probability ing age or scheduled overhaul. Thus, for the re-
of failure did not increase with operating age and the maining 89% of the items, these were inappro-
traditional time-based policies were found to be in- priate maintenance measures, which contributed
effective for controlling the failure rate of many to unnecessary maintenance efforts and non-
items. (processonline, 2007) beneficial downtime.
During 1960, FAA was surprised that, 6. Prescribing hard-time actions for non-age-related
notwithstanding many previous efforts, it was not failures had an adverse effect on the availability
possible for airlines to control the failure rate of a and reliability of the items, because it contra-
certain type of engine, by changing the scheduled dicted the actual failure characteristic and degra-
overhaul policy. Moreover, due to congested con- dation processes. Therefore, serviceable items
tinuous maintenance activities, fleet availability were unnecessarily removed from service and
dropped significantly, causing operation and main- sent to shops for overhaul or other maintenance
tenance costs to increase rapidly without equivalent measures. This intrusive maintenance practice
improvements in reliability. The reasons for the had a negative impact on manpower resources,
problems mentioned above can be summarized in spare parts, down time, total costs, and availabil-
the following nine areas: ity performance.
7. Since there is seldom any strong relationship be-
1. Risk analysis was not considered in maintenance tween the items operating time and failure prob-
analysis. The objective of the maintenance ac- ability, many failure modes did not benefit from
tivities was mostly to retain the technical charac- age-based shop visits. These failures were one of
teristics of the items, rather than reduce or miti- the main sources of unscheduled corrective
gate the consequences of item failures. maintenance, sudden aircraft unavailability, and
2. The objectives of preventive maintenance were disturbed operation. Even though many failure
not recognized. Consequently, the applicability modes are not age-related, it is most often possi-
and effectiveness criteria for maintenance tasks ble to identify and recognize the conditions that
were not defined either. indicate an imminent functional failure. Hence, it
3. The operating context was not considered in is possible to apply On-Condition measures, i.e.
maintenance analysis. Therefore, one mainte- scheduled inspections designed to detect a poten-
tial failure condition, in order to initiate preven- “…in the past, a great deal of emphasis has been
tive maintenance actions and thereby avoid the placed on the control of overhaul periods to provide
functional failure or its consequences. (Moubray, a satisfactory level of reliability. After careful study,
1997) the Committee is convinced that: reliability and
8. All the items of systems were considered for overhaul time control are not necessarily directly as-
maintenance regardless of the importance of sociated topics; therefore, these subjects are dealt
their functions for system availability. Hence, with separately.”
limited maintenance budgets were not distrib-
uted in accordance with the importance of the
items function for availability performance of 3 THE FIRST STRUCTURED MAINTENANCE
the system. PROGRAM PROCEDURES: MSG-1 & MSG-2
9. Previous experience in the development of
scheduled maintenance instructions had revealed United Airlines started a research program in 1965,
that a program of effective maintenance meas- to substantiate the outcomes of the FAA task force
ures could be developed through the use of logi- and to provide a generally applicable systematic re-
cal analysis and decision-making processes. view of the aircraft design. Hence, in the absence of
Hence, there was a need for a structured decision operational experience, the best maintenance process
process to assess the maintenance requirements should still be utilized through a structured logical
of the systems, and to develop an applicable and decision tree. In June of 1967, T.D. Matteson and
effective maintenance program. F.S. Nowlan presented a paper on the use of this
methodology at an aircraft design and operations
In order to respond to the above-mentioned chal- meeting of the American Institute of Aeronautics
lenges and to find a proper solution, FAA formed a and Astronautics (AIAA). As a result, rudimentary
task force, including representatives from both FAA decision logic was created and over the next few
and American Airlines. The purpose was to evaluate years, it was developed with the cooperation of air-
the effectiveness of traditional time-based mainte- lines, manufacturers, and FAA. The methodology
nance, investigate the capabilities of scheduled was used to develop the Boeing-747 initial mainte-
maintenance, and find the possible relationship be- nance program document. This document was pub-
tween scheduled maintenance and reliability. These lished on 10 July 1968 by ATA under the title “Boe-
analyses gave rise to the following surprising dis- ing-747 Maintenance Steering Group (MSG)
coveries (Kennedy, 2005; Equipment Links, 2007; Handbook: Maintenance Evaluation and Program
processonline, 2007): Development (MSG-1)” (Nowlan & Heap, 1978).
This was the first attempt at applying reliability-
x Scheduled overhauls had little or no effect on the centered maintenance concepts when developing an
overall reliability of a complex item unless it had aircraft maintenance program.
a dominant failure mode. MSG-1 was a ‘bottom-up’ approach to the Boe-
x There were many items for which there was no ing-747 systems, in which components were the
effective form of scheduled maintenance. highest level to be considered. Hence, MSG-1 fo-
x Many types of failures could not be prevented or cused on a component such as the Fuel Control Unit
effectively reduced by ‘right-age’ overhauls, no (FCU) in a system and analyzed which part of that
matter how intensively they were performed. component might fail. Then, it was determined what
x Cost reductions in maintenance could be kind of maintenance action was required to prevent
achieved with no decrease in reliability. the failure. Through MSG-1, the potential mainte-
x The intrusive nature of the overhauls was itself a nance measures for each maintenance strategy were
major cause of unreliability. selected and evaluated from criteria based on operat-
ing safety or essential hidden function protection.
The outcomes of the efforts mentioned above led The remaining potential maintenance tasks were
to the first formal “FAA - Airlines Reliability Pro- evaluated to determine if they were economically
gram” being issued in November 1961. The program viable.
was developed to improve the control of reliability MSG-1 introduced three broad processes to clas-
through an analysis of the factors that affect reliabil- sify the scheduled maintenance requirements, i.e.
ity and to provide a set of actions to improve low re- Hard Time (HT), On-Condition (OC), and Condition
liability levels when necessary. As the propulsion Monitoring (CM). OC requires an item to be peri-
system had been the area of greatest concern, and odically checked, or tested, against an appropriate
since power plant data was readily available for physical standard to determine whether the item can
study, programs were developed for the propulsion continue in service or not (Nakata, 1984).
system first. The introduction to that program stated The efficacy of the systematic MSG-1 methodol-
that (Nowlan & Heap, 1978): ogy applied to Boeing-747 was considered to justify
a generic solution, which could be applied to other
new aircraft. This resulted in the publication of a ures. This would reduce the downtime and the
second document by ATA in 1970 as MSG-2: “Air- maintenance costs associated with the failure.
line manufacturer maintenance program planning 3. Safety: warning of failure provides time to either
document”. This document was used to develop the shut down an item before the situation becomes
maintenance programs for aircraft such as the L- dangerous, or to move people out of harm’s way.
1011 and DC-10. (Smith & Hinchcliffe, 2004)
The objective of the two MSG methodologies was Today, OC tasks are well known because the in-
to develop scheduled maintenance programs that as- spected items are allowed to be left in service ‘on
sured maximum safety and reliability of the item, at condition’ that they continue to meet specified per-
the lowest possible cost. MSG-1 and MSG-2 both formance standards (Moubray, 1997), until a poten-
followed the same process, but MSG-2 was a ge- tial failure is detected. For example, as many as 400
neric document, and non-aircraft type-related (Now- items that might have required scheduled overhaul
lan & Heap, 1978) . prior to MSG-1/MSG-2/EMSG-2 were reduced to
Subsequently, in 1972, United Airlines used the about 10 afterwards (ATE&M, 2001) .
idea of MSG-2 under the US Department of Defense In 1975, NAVAIR rewrote the MSG-2 proce-
(DOD) contract to develop the P-3A and S-3A main- dures, to apply an ‘analytical maintenance program’
tenance programs, and the F-4J program in 1974. to naval aircraft and engine programs, which re-
(Smith & Hinchcliffe, 2004) sulted in “NAVAIR Systems Command (NAVAIR
An enhanced document was also prepared in 00-25-400)”. This was applied to in-service naval
Europe, called EMSG-2. It was used to develop aircraft and the manual was utilized to revise the
maintenance program requirements for such aircraft preventive maintenance requirements for most of the
as the Airbus A-300 and Concorde. Navy’s in-service aircraft. (MIL-STD-2173)
MSG-2 and EMSG-2 continued to use a ‘bottom- The MSG-2 methodology revolutionized Navy
up’ approach to aircraft systems and were ‘mainte- procedures for developing preventive maintenance
nance process oriented’, whereby the integrity of programs; but there were still aspects to consider for
components in sub-systems was considered before further development of both MSG-2 and NAVAIR
those of the overall system 00-25- 400 documents. For example, they did not
The most important advantage of MSG-1 and cover the procedures for developing inspections in-
MSG-2 was the application of On-Condition (OC) tervals and for refining the initial analysis. (MIL-
maintenance, which made them unique. The intro- STD-2173)
duction of OC began an era of new thinking. It was Moreover, the effectiveness criteria for different
permissable to let an aircraft pass an immediate maintenance strategies and failure consequences
maintenance check with known deterioration, degra- were not considered and there was still a problem of
dation or wear, and postpone the required mainte- balancing the requirements of cost and dependabil-
nance action until the next earliest opportunity, as ity. In addition, there was still pressure to decrease
long as the appropriate physical standard and pre- maintenance costs. In fact, the incentives to reduce
scribed limitations were met. This approach helped the cost were changed from technical and engineer-
the operators to have fleets that were more available ing issues during design to economical issues and
and made planning more flexible. Moreover, since cost-effective maintenance during operation. As a
the cost of correcting potential failures is often far result, the industry was expected to construct a
less than the cost of correcting functional failures, framework that incorporated cost-effective mainte-
OC maintenance reduced the maintenance costs. nance strategies.
Furthermore, OC maintenance strongly reduced the
number of irrelevant scheduled overhauls, which
was the main source of ‘infant mortality’ and unreli- 4 INTRODUCTION OF RELIABILITY-
ability. In addition, by avoiding premature removals CENTERED MAINTENANCE
of items that were still in a satisfactory condition,
required spare part volumes were reduced. The US Department of Defense (DOD) sponsored
Depending on the operating context of the asset, United Airlines to write a comprehensive report, en-
warning of incipient failure enables the users of an titled “Reliability-Centered Maintenance (RCM)”
item to reduce or avoid consequences in a number of (MIL-STD-2173). Stanley Nowlan and Howard
ways (Moubray, 1997): Heap of United Airlines wrote this report in 1978 as
the initial RCM Bible (DOD report AD-A0665791).
1. Down time: corrective action can be planned at a The report gave a detailed rationale and analytical
time that does not disrupt operations. logic, which required a fundamental shift in the cur-
2. Maintenance costs: the user may be able to take rent methodology for maintenance program devel-
actions to eliminate the secondary damage, opment (i.e. MSG-2).
which would be caused by unanticipated fail- RCM is a methodology that supports a well-
structured, logical decision process used to identify
the policies needed to manage failure modes that tional failures, and failure modes of an item. Fur-
could cause the functional failure of any physical thermore, FMEA classifies the severity of each fail-
item in a given operating context. These policies ure effect according to severity classification criteria
will reduce the risk of function loss and are: Preven- established by each program. Hence, the quality of
tive Maintenance, Predictive Maintenance, or Re- the RCM analysis strongly depends on the quality of
design. Hence, RCM can be considered as an overall the FMEA execution.
risk management program, to effectively manage the The RCM logic requires an age exploration pro-
risk of function losses through effective mainte- gram for all maintenance tasks where reliable his-
nance. torical information is not available. It also requires
As one of the major elements in risk management an independent auditing of all performed analyses,
is reliability, the RCM methodology is used to de- see Nowlan & Heap (1978) and Moubray (1997). In
velop and optimize the preventive maintenance and contrast to earlier methodologies supporting mainte-
inspection requirements of an item in its operating nance program development (e.g. MSG-1 and MSG-
context to achieve its inherent reliability, where in- 2), the RCM methodology was based on:
herent reliability can be achieved by using an effec-
tive maintenance program. x System level instead of component level.
Any RCM methodology shall ensure that all the x Top-down instead of bottom-up approach.
following seven questions are answered satisfactory x Function preservation instead of failure preven-
in the order given below (Rausand, 1998): tion.
x Task-oriented instead of maintenance process
1. What are the functions and associated perform- oriented.
ance standards of the item in its present operat- x Consequence-driven, where the consequences of
ing context (function)? failures are far more important than their techni-
2. In what ways does it fail to fulfill its functions cal characteristics.
(functional failures)?
3. What are the causes of each functional failure In an RCM process, the consequences of every
(failure modes)? failure have to be analyzed. It should clearly sepa-
4. What happens when each functional failure oc- rate hidden failures from evident failure modes, and
curs (failure effects)? distinguish events that have safety, environmental,
5. In what way does each failure matter (failure operational and or economic consequences.
consequences)? By using an approach based on system level and
6. What can be done to prevent each failure (pro- function preservation, RCM treats components dif-
active tasks and task intervals)? ferently in terms of relative importance according to
7. What should be done if a suitable preventive task the correlation between the equipment and system
cannot be found (default actions)? function. Huge benefits can be derived by imple-
menting RCM. These achievements include higher
In order to answer the questions above, RCM uses safety and operating performance, better understand-
a structured decision diagram, and encompasses the ing of the failure modes, and reduction of operation
well-known Failure Mode & Effects Analysis and maintenance costs (Tsang, 1995). Figure 1 illus-
(FMEA) methodology to identify functions, func- trates how the maintenance concept has changed in a
First Generation Second Generation Third Generation
Pre World War II Post World War II After Mid 1970s
Failure Consequences

RCM
Approach

Methodology
MSG-3
Methodology
System Safety and Risk Analysis approach

MSG-1& MSG-2
Methodology
Using Condition Based
Maintenance
Failure Mode
Approach

Time Based Maintenance


Technical Characteristic
Approach

Reactive Maintenance

Failure Rectification Failure Prevention Funtion Preservation

Failure management strategy

Figure 1: Changes and milestones in maintenance methodology development with regard to risk and failure management.
logical and chronological order.
Method-
Since Nowlan and Heap’s report, RCM has been Characteristics
ology
widely used by different industries, such as the nu-
clear and power generation industries, offshore oil x Bottom-up approach
and gas industries, and has been refined, developed, x Component level
MSG-1
and customized to their specific requirements. x Maintenance process oriented
x Aircraft type-related (Boeing-747)
(1968)
x Using On-Condition and Condition-
5 PUBLICATION OF MSG-3 Based Maintenance
MSG-2 x Same as MSG-1
A decade after MSG-2 was published and subse- x Generic document, non-aircraft typere-
quent to Nowlan and Heap’s report, US Association (1970) lated
of Air Transport (ATA) formed another task force to
review MSG-2 experience in 1979. In this review, it x Generic document
became obvious that there were some areas for im- x Top-down approach
x System level
provement (Overman et al., 2003; ATA, 2005):
x Maintenance task oriented
MSG-3
x Emphasis on structural inspection pro-
x The rigor of the decision logic. grams
x The clarity of the distinction between economics (1980)
x More rigorous decision logic diagram
and safety. x Distinction between safety and econ-
x The adequacy of treatment of hidden functional omy
failures. x Hidden functional failure treatment

The high fuel price increased the total operating Figure 2: Summary of some of the major conceptual differ-
cost of aircraft, and the pressure to decrease mainte- ences and improvements between MSG-3 and previous ver-
nance costs was still present. In addition, the devel- sions of the methodology.
opment of new-generation aircraft, new regulations
and new damage tolerance rules for structures,
which had a heavy influence on maintenance pro- 6 FURTHER DEVELOPMENTS OF
gram development including the new premises of RELIABILITY-CENTERED MAINTENANCE
Nowlan and Heap’s RCM methodology, provided in
the basis for the development of a new, improved One of the most valuable efforts to develop RCM
“Airline/Manufacturer Maintenance Program Plan- methodologies was performed by the US Depart-
ning Document MSG-3”, published by ATA in ment of Defense (DOD), and was initiated by the
1980. (Transport Canada, 2003; ATA, 2005) AD-A066579 report published in 1978. This report
This methodology was a combined effort by the was based on the principles of MSG-logic and was
manufacturers, regulatory authorities, operators, and the foundation of the most modern RCM method-
ATA. The MSG-3 methodology implicitly incorpo- ologies. Based on that report, DOD issued several
rated the principles of RCM to justify task develop- documents related to RCM analysis; most notably,
ment, but stopped short of fully implementing reli- Military Handbook (MIL-HDBK) 266, “RCM Re-
ability-centered maintenance criteria to audit and quirements for Naval Air-craft, Weapons Systems
substantiate the initial tasks being defined (Transport and Support Equipment” in 1981, which superseded
Canada, 2003). NAVAIR 00-25-400 for all applications of RCM-
Since Nowlan and Heap’s report served as the ba- decision logic. It also applied the principles of RCM
sis for MSG-3, it made major departures from MSG- (as covered by the DOD report and MSG-3) to Na-
2. Hence, MSG-3 involves a top-down, system- val aircraft, weapons systems and support equip-
level, and consequence-driven approach, to classify ment. (Leverette et al., 2005)
failure effects in one of the failure consequences In 1985, as another effort, US Air Force (USAF)
categories, see Figure 2. Since its original publica- issued MIL-STD-1843: ”RCM Requirements for
tion, MSG-3 has been revised five times. Revision 1 Aircraft, Engines and Equipment“. This standard
was issued in 1988 and revision 2 in 1993. MSG3- was similar to MSG-3, which was cancelled without
2001 and MSG-3.2002 were issued in 2001 and replacement in 1995. In 1986, DOD issued MIL-
2002 respectively and the latest revision was made STD-2173, “RCM Requirements for Naval Aircraft,
in 2005. (ATA, 2005) Weapons Systems and Support Equipment” (MIL-
STD-2173; Leverette et al., 2005).
In the early 1990s the DOD decided that new acqui-
sitions should rely, as much as possible, on commer-
cial or performance standards, instead of using Mili-
tary Standards. As a result, a group called
“Reliability, Maintainability and Supportability According to MIL-STD-2173, ‘effectiveness’ is a
(RMS) Partnership”, began coordinating the efforts measure of the result of the task objectives, which is
of various other organizations involved in develop- dependent on the failure consequences. Therefore,
ing related standards. Since no equivalent commer- the effectiveness of applicable tasks in preventing
cial standard existed at that time, the RMS Partner- the failure consequences must be determined.
ship requested the Society of Automotive Engineers Hence, for each failure consequence, it is possible to
(SAE) to lead the development of an RCM standard develop indicators according the effectiveness crite-
(Leverette et al., 2005). ria as follows:
The SAE RCM subcommittee initially consisted
of representatives from the US Navy and some DOD x Safety: the task must reduce the risk of failure to
contractors. As the group was supposed to find out assure safe operation.
more about the lessons learned through commercial x Operation: the task must reduce the risk of fail-
industry efforts, John Moubray and some of his col- ure to an acceptable level from an operational
leagues became involved in late 1997. With new point of view, or remove the operational conse-
participation and a clearer direction, the group was quences.
able to complete the SAE JA1011 standard in 1999. x Economics: the task must be cost-effective.

In order to measure the performance of an aircraft


7 AIRCRAFT MAINTENANCE PROGRAM maintenance program, actual operational and sup-
SURVEILLANCE port data are necessary. This data can be obtained
from sources such as aircraft inspections, pilot re-
The main objective of an aircraft maintenance pro- ports, air safety reports, scheduled maintenance find-
gram is to ensure that the aircraft meets and contin- ings, reliability programs, unscheduled maintenance
ues to meet the designed function to serve depend- actions, deferred maintenance actions, teardown re-
able and airworthy services. Hence, it is important ports, recorded flight data, and so on.
for operators to determine any deviation from this However, gathering data and converting it to in-
objective and to assess the success of the program formation is very time-consuming. In addition, the
after bringing the aircraft into operation. effectiveness of these analyses will decrease with
Today, it is known that an aircraft’s reliability and time. To mange these difficulties, e-Maintenance is
safety will be strongly affected by its operating con- one promising approach.
text, e.g. operator organization, humidity, tempera-
ture, utilization load, and so on. Hence, the original
assumption of effectiveness criteria made during the 8 E-MAINTENANCE AND MAINTENANCE
design of the initial aircraft maintenance program PROGRAM SURVEILLANCE
will probably change and the surveillance of the air-
craft maintenance program will be important. In or- Information resources are critical to maintenance
der to manage this surveillance, the operators nor- and maintenance support, for example to support
mally follow a defined surveillance program, which surveillance of an aircraft maintenance program’s
has been approved by the authorities. performance. Hence, technological opportunities to
In an ideal world, an applicable and effective improve the surveillance, such as innovative design
maintenance program would ensure that there were features in the aircraft or its support system utilizing
no failure events between scheduled aircraft mainte- new technology applications can help to improve the
nance tasks. However, due to differences between maintenance program. The inclusion of developing
design assumptions and actual operational condi- technologies can also avoid early obsolescence and
tions, each maintenance program must be adjusted to extend the useful life of the aircraft at the same time
achieve this ideal situation. (Moubray, 1997) as availability performance and Life Cycle Costs
According to official FAA research “Continuing (LCC) are improved. One example of new technol-
Analysis and Surveillance System (CASS)” , an ef- ogy is Information & Communication Technology
fective continuous airworthiness maintenance pro- (ICT), which to an increasing degree is included in
gram should identify elements that are detrimental to both the aircraft and its support system and that also
the overall effectiveness of the air carrier’s mainte- integrates the two. The application of ICT within
nance program, and correct any deficiencies before maintenance and maintenance support enables the
they become systematic problems. Therefore, the emerging approach of e-Maintenance. (IEC 60300-
operators should develop indicators to determine 3-14; Candell et al., 2007)
possible deviations from defined objectives and to e-Maintenance is the application of ICT for re-
measure the effectiveness of an aircraft maintenance mote maintenance (i.e. maintenance of an item per-
program. These objectives might be based on risks formed without the maintenance personnel having
related to health, business, safety, environment, physical access to the item) and for representing the
property, and on-time services. physical world in an digital model aimed at supply-
ing tailored information such as decision support re- termittent faults and the stresses imposed on an item
garding appropriate maintenance activities for all during operation. Hence, it is possible to obtain an
stakeholders independent of time, geographical loca- enhanced understanding of failures, failure modes,
tion, or organizational affinity. Hence, the e- failure mechanism, and failure effects. However, in
Maintenance approach is not limited to the manage- addition to digitally monitored parameters, relevant
ment of condition monitoring data, explicit tech- operator and maintainer observations, which cannot
nologies, or any specific support service solution. be digitally recorded, such as decisions based upon
(Candell et al., 2007) various circumstances, should also be recorded. All
One important source of information that supports this data can act as input to the surveillance of the
maintenance program surveillance is the mainte- maintenance program’s performance and update the
nance database, which should be structured so that it engineering judgments made during initial aircraft
facilitates the seamless transfer of data to other data- maintenance program development. (Söderholm,
bases (e.g. the maintenance work order system) and 2007)
analysis tools (e.g. RCM software) used by stake- As described above, one important aspect of e-
holders involved in maintenance program develop- Maintenance is the combination of maintenance and
ment. However, it is also important that the mainte- ICT. Hence, it is necessary to have expertise in both
nance database is kept under configuration control to areas in order to achieve a good e-Maintenance solu-
ensure that it reflects the latest design standard of tion that satisfies the requirements for aircraft main-
the aircraft and its indenture levels, to provide an tenance program surveillance. Thereby, maintenance
audit trail and to ensure the integrity and consistent and maintenance support may be seen as the prob-
use of support data. The database should also be lem domain to which selected and adapted ICT is
kept up-to-date to reflect changes in customers’ use used as a solution. (Candell et al., 2007)
and requirements and thereby provide the guidance Some of the obstacles related to e-Maintenance,
necessary for future maintenance program develop- which have to be overcome in order to achieve ef-
ment. In this context, e-Maintenance facilitates the fective and efficient maintenance program surveil-
use of one single maintenance database that is lance, are (Karim & Söderholm, 2007):
shared by all involved stakeholders, which in turn
decreases the risk of redundant, contradictory, and x Heterogeneous organizations: there are different
obsolete data (IEC 60300-3-14; Söderholm, 2007). structures in the organizations involved in pro-
Another important source of information for viding and receiving maintenance and mainte-
maintenance program surveillance is the mainte- nance support.
nance work order system, which is used to initiate, x Heterogeneous ICT-environments: there are dif-
control and document specific maintenance tasks. As ferences in technology in systems that are nor-
stated in the maintenance program, a maintenance mally used for different purposes, but are needed
task is either triggered by a predetermined time to exchange information in order to support
measure (e.g. calendar time, number of flights, or maintenance program surveillance.
flight hours) or the item’s actual condition. The x Information integration strategy: it is necessary
work order is used to identify and plan required re- to have a strategy to integrate a number of dif-
sources and to schedule execution of the work. Fi- ferent types of hardware and software in a seam-
nally, it is used to record results, observations, and less manner. The content type has an impact on
resources actually used, which all provide the basis the overall ICT strategy.
for assessment and improvement of the aircraft x Documentation and archiving strategies: it is es-
maintenance program. An appropriate e- sential to provide and manage documentation of
Maintenance solution should enable easy access to different types. The context requires different
the maintenance work order system and also integra- types of strategies for storage, distribution,
tion with other maintenance systems. (IEC 60300-3- safety, security, accessibility, availability, reli-
14; Candell et al., 2007) ability, archiving, and destruction.
Another important part of an e-Maintenance solu-
tion, which also is valuable for maintenance pro- One example of a civil aircraft with on-board
gram surveillance, is Built-in-Test (BIT) systems in- technologies that support an e-Maintenance solution
cluded in the aircraft. Using BIT systems it is for aircraft maintenance program surveillance is the
possible to analyze the failures at the exact point in Boeing-787, which will be certified during 2008.
time when they occur at a specific indenture level of The aircraft’s on-board technologies will also be in-
the aircraft during operation. Operational data that tegrated with off-board technologies within the sup-
should be monitored and recorded include data on port system. Another similar example is the intelli-
bus inputs, strain gauge and other dynamic data, gent software Airman, which is provided by Airbus.
propulsion parameters, BIT failure data, and envi- This software can connect the different sources of
ronmental data. Continuous monitoring of the air- maintenance information in a seamless manner and
craft’s condition helps to identify the nature of in- also provide tailored information to different stake-
holders. In military aviation, the Joint Strike Fighter Candell, O., Karim, R., & Söderholm, P. 2007. e-
(JSF) program is one example where on-board and Maintenance 24-7: Theoretical framework, re-
off-board technologies are integrated in order to search, and applications. Technical report, Luleå,
achieve an autonomic logistics system. Another Luleå University of Technology.
military example is the Maintenance Work Station Candell, O. & Söderholm, P. 2006. A Customer and
(MWS) efforts connected to the Swedish combat Product Support Perspective of e-Maintenance. In
aircraft JAS 39 Gripen. These aircraft systems are Uday Kumar et al. (ed.), Condition Monitoring
examples where e-Maintenance will be very benefi- and Diagnostic Engineering Management; Proc.
cial to aircraft maintenance program surveillance. Inter. Cong. Luleå, 12-15 June 2006. Luleå:
The reason is that e-Maintenance enables measures Luleå University Press.
supporting surveillance of aircraft maintenance pro- Equipment Links, 2007. What is RCM? Available
gram effectiveness to be more or less automatically online:http://www.equipment-links.com/whati src
collected, analyzed into indicators, and distributed to m .php, Access date: March 2007.
concerned stakeholders independent of the mainte- FAA, 2003. Continuous Analysis and Surveillance
nance echelon. System: Description and Models (DOT/FAA/AR-
03/70). Springfield, Virginia: National Technical
Information Service (NTIS).
9 CONCLUSIONS IEC 60300-3-14: Dependability management. Part
3-14: Application guide. Maintenance and main-
This paper describes the trends in aircraft mainte- tenance support. Geneva: International Electro-
nance program development during the last 50 years, technical Commission (IEC).
including milestones such as different versions of Karim, R. & Söderholm, P. 2007. Application of In-
MSG and RCM. formation and Communication Technologies
Examples of fundamental changes described are: (ICT) for remote support services: Transferring
from failure correction to failure prevention; from experiences from an e-Health solution in Sweden.
time-based to condition-based maintenance, from Submitted for publication.
bottom-up to top-down analysis; from component Kennedy, R. 2006. Examining the Processes of RCM
level to system level analysis; from technical charac- and TPM. Available online: http://www.plant-
teristics to failure consequences; and from item rec- maintenance.com/articles/RCMvTPM.shtml, Ac-
tification to function preservation. cess date: November 2006.
Furthermore, the paper describes some of the rea- Leverette, J.C. & Echeverry A. 2005. RCM in the
sons for these changes, e.g.: item complexity, system Public Domain: An Overview of the US Naval
dependence, competition, and failure consequences, Air Systems Command’s RCM process. Reliabil-
but also increasingly stringent requirements related ity Centered Maintenance Managers’ Forum,
to: dependability, costs, airworthiness, sustainabil- Florida, 9-11 March 2005. MaintenanceConfer-
ity, and safety. ence.com
The paper ends with a description of challenges MIL–STD-2173: Reliability Centered Maintenance.
and possibilities related to e-Maintenance, which is Washington D.C.: Department of Defense.
believed to promote effective and efficient surveil- Moubray, J. 1997. Reliability Centered Mainte-
lance of an aircraft maintenance program in a near nance. Oxford: Butterworth-Heinemann.
future. Nakata, D. 1984. An Introduction to MSG-3. SAE
Aerospace Cong. & Exhi., California, 15-18 Oc-
tober 1984. Society of Automotive Engineers.
10 ACKNOWLEDGEMENTS Nowlan, F.S. & Heap, H.F. 1978. Reliability Cen-
tered Maintenance. Springfield: National Techni-
The authors would like to thank Mr. Dave Nakata cal Information Service (NTIS).
and Mr. Christian Delmas for their useful comments Overman, R. & Collar, R. 2003. The Complimentary
on drafts of this paper: Roles of Reliability Centered Maintenance and
Condition Monitoring; Int. Main. Conf., Florida,
8-9 December 2003.MaintenanceConference.com
11 REFERENCES Process online, 2007. Revolutionizing maintenance
with RCM, Available online:
ATE&M, 2001. MSG-3 maintenance practices. Air- http://www.processonline.com.au/process/feture_
craft Technology: Engineering & Maintenance article /item_052004a.asp, Access date: March
50(-): 1-8. 2007.
ATA, 2005. Operator/Manufacturer Scheduled Rausand, M. 1998. Reliability Centered Mainte-
Maintenance Development: MSG-3. Pennsyl- nance. Reliability Engineering and System Safety
vania: Air Transport Association of America. 60(2): 121-132.
Smith, A.M. & Hinchcliffe, G.R. 2004. Reliability
Centered Maintenance. Oxford: Elsevier.
Söderholm, P. 2007. A system view of the No Fault
Found (NFF) phenomenon. Reliability Engineer-
ing and System Safety 92(1): 1-14.
Transport Canada, 2003. TP 13805E: Civil Aviation
Scheduled Maintenance Instruction Development
Processes Manual. Ottawa, Civil Aviation Com-
munications Centre (AARC).
Tsang, A. 1995. Condition Based Maintenance tools
and decision-making. Journal of Quality in Main-
tenance Engineering 1(3): 3-17.

You might also like