You are on page 1of 47

Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 14 November 2012
Doc. no.: 4530126-R-BJ10-RA53-1000 Rev.: 01
Title: Weekly Progress Report – 05/11/2012 to 11/11/2012 Page: 3 of 13

1 Project Summary
Aker Solution Singapore to disassemble the DDM 650 HY, BJ10 unit, along with the Dolly, and
provide a thorough inspection on the equipment, before establishing a comprehensive
inspection report and quotation for the customer.

2 Incidents and HSE


N/A

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 3


25 Benoi Lane, Singapore 627800 Page 3 of 13
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1000-Weekly Report 10 5 - 11 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 14 November 2012
Doc. no.: 4530126-R-BJ10-RA53-1000 Rev.: 01
Title: Weekly Progress Report – 05/11/2012 to 11/11/2012 Page: 4 of 13

3 Activities performed this week 05/11/2012 to 11/11/2012

3.1 Inspection of 2 x A10V and 2 x A2FLM motors on 07/11/2012

There are a total of 6 motors undergoing repairs with Anda Hydraulics. However, as repairs for
the 2 A10V and 2 A2FLM motors are complete, a pressure test session was conducted on the
premises of Anda Hydraulics’ workshop on the afternoon of 7th November 2012, Wednesday.

The pressure test was witnessed by two Aker Solutions representatives, Overhaul Project
Engineer, Kern Lim, and QAQC, Ramasamy Marimuthu.

During the pressure tests, no abnormalities or leaks were found. The pumps appear to be
working better than expected range.

The 4 motors will be delivered to Aker Solutions workshop next week along with the test
reports.

A detailed test report of the inspection done on the 4 motors is attached at the end of this
document. Please refer to Test Ref no: MA1212449a, MA1212450a, MA1212455a and
MA1212456a.

It is noted that there are remaining 2 A2FLM motors which are not ready for testing yet. The
vendor will update us on the progress of the 2 A2FLM motors as soon as the motors are ready.

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 4


25 Benoi Lane, Singapore 627800 Page 4 of 13
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1000-Weekly Report 10 5 - 11 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 14 November 2012
Doc. no.: 4530126-R-BJ10-RA53-1000 Rev.: 01
Title: Weekly Progress Report – 05/11/2012 to 11/11/2012 Page: 5 of 13

Pressure test of 2 x A10V and 2 x A2FLM motors on 07/11/2012

A10V Pumps A2FLM Motors

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 5


25 Benoi Lane, Singapore 627800 Page 5 of 13
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1000-Weekly Report 10 5 - 11 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 14 November 2012
Doc. no.: 4530126-R-BJ10-RA53-1000 Rev.: 01
Title: Weekly Progress Report – 05/11/2012 to 11/11/2012 Page: 6 of 13

3.2 Assembly Process of DDM and Dolly

3.2.1 DDM

This week, the team commenced reassembling of the DDM from last week.

Firstly, new Bushings for the Swivel Housing were installed. Next, the Main Gear was locked in
position with a reading of 7.5mm. Thirdly, the Bull Gear cover is covered and properly secured
in place.

On top of that, the Accumulator and Gear Lock Assembly were mounted. The Pinion Gear
assembly and the Manifold were installed onto the Main Frame.

Last but not least, the Sub-Assembly was rotated and checked with a hydraulic motor to check
for oil leakages. No leakages were detected visually while the oil level maintained.

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 6


25 Benoi Lane, Singapore 627800 Page 6 of 13
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1000-Weekly Report 10 5 - 11 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 14 November 2012
Doc. no.: 4530126-R-BJ10-RA53-1000 Rev.: 01
Title: Weekly Progress Report – 05/11/2012 to 11/11/2012 Page: 7 of 13

DDM Assembly Activities


New Bushes for Swivel Housing

Main Gear locked in position


Reading – 7.5 mm

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 7


25 Benoi Lane, Singapore 627800 Page 7 of 13
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1000-Weekly Report 10 5 - 11 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 14 November 2012
Doc. no.: 4530126-R-BJ10-RA53-1000 Rev.: 01
Title: Weekly Progress Report – 05/11/2012 to 11/11/2012 Page: 8 of 13

Bull Gear’s Cover is covered and properly


Accumulator & Gear Lock Assembly mounted
secured

Pinion Gear Assembly installed Installing Manifold onto the Main Frame

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 8


25 Benoi Lane, Singapore 627800 Page 8 of 13
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1000-Weekly Report 10 5 - 11 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 14 November 2012
Doc. no.: 4530126-R-BJ10-RA53-1000 Rev.: 01
Title: Weekly Progress Report – 05/11/2012 to 11/11/2012 Page: 9 of 13

Rotating the Sub-Assembly with a hydraulic motor to check for oil leak
Result – oil level maintained and no oil leak detected visually

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 9


25 Benoi Lane, Singapore 627800 Page 9 of 13
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1000-Weekly Report 10 5 - 11 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 14 November 2012
Doc. no.: 4530126-R-BJ10-RA53-1000 Rev.: 01
Title: Weekly Progress Report – 05/11/2012 to 11/11/2012 Page: 10 of 13

3.2.2 Dolly

This week, the team changed the fittings for the Control Valve Cabinet, and installed new
Bushings to the Dolly Frame. And finally, the Control Valve, which was undergoing servicing
with a third party vendor, was delivered back to Aker Solutions workshop upon completion.

For more information regarding the pressure test done for the Proportional Valve, please refer
to test report Q12BL-267 attached at the end of this document.

Dolly Assembly Activities

Change Fittings for Control Valve Cabinet

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 10


25 Benoi Lane, Singapore 627800 Page 10 of 13
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1000-Weekly Report 10 5 - 11 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 14 November 2012
Doc. no.: 4530126-R-BJ10-RA53-1000 Rev.: 01
Title: Weekly Progress Report – 05/11/2012 to 11/11/2012 Page: 11 of 13

New Bushings were installed onto Dolly Frame

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 11


25 Benoi Lane, Singapore 627800 Page 11 of 13
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1000-Weekly Report 10 5 - 11 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 14 November 2012
Doc. no.: 4530126-R-BJ10-RA53-1000 Rev.: 01
Title: Weekly Progress Report – 05/11/2012 to 11/11/2012 Page: 12 of 13

Control Valve back from Third Party Vendor Servicing

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 12


25 Benoi Lane, Singapore 627800 Page 12 of 13
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1000-Weekly Report 10 5 - 11 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 14 November 2012
Doc. no.: 4530126-R-BJ10-RA53-1000 Rev.: 01
Title: Weekly Progress Report – 05/11/2012 to 11/11/2012 Page: 13 of 13

4 Planned activities next week

The DDM and Dolly will resume assembly process. The team aims to complete fully assemble
the DDM and Dolly by the end of November.

5 Area of concern

None

6 Invoice log and forecast

NA

7 VO Register

NA

8 Project Plan

NA

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 13


25 Benoi Lane, Singapore 627800 Page 13 of 13
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1000-Weekly Report 10 5 - 11 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 18 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1100 Rev.: 01
Title: Weekly Progress Report – 10/12/2012 to 16/12/2012 Page: 3 of 6

1 Project Summary
Aker Solution Singapore to disassemble the DDM 650 HY, BJ10 unit, along with the Dolly, and
provide a thorough inspection on the equipment, before establishing a comprehensive
inspection report and quotation for the customer.

2 Incidents and HSE


N/A

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 3


25 Benoi Lane, Singapore 627800 Page 3 of 6
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1100-Weekly Report 11 12 - 18 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 18 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1100 Rev.: 01
Title: Weekly Progress Report – 10/12/2012 to 16/12/2012 Page: 4 of 6

3 Activities performed this week 12/11/2012 to 18/11/2012

3.1 Assembly of Motors

This week, the completed motors were delivered to Aker Solutions workshop. Upon receipt of
the motors, the team proceeded ahead to mount the motors. And while waiting for the spare
parts to arrive at the workshop, the team was asked to wire lock the bolts.

Assembly Activities
Receive Motors in workshop

Mount Motors

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 4


25 Benoi Lane, Singapore 627800 Page 4 of 6
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1100-Weekly Report 11 12 - 18 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 18 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1100 Rev.: 01
Title: Weekly Progress Report – 10/12/2012 to 16/12/2012 Page: 5 of 6

Wire lock the Bolts

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 5


25 Benoi Lane, Singapore 627800 Page 5 of 6
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1100-Weekly Report 11 12 - 18 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 18 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1100 Rev.: 01
Title: Weekly Progress Report – 10/12/2012 to 16/12/2012 Page: 6 of 6

4 Planned activities next week

The DDM and Dolly will resume assembly process. The team aims to complete full assembly of
the DDM and Dolly by the end of November.

5 Area of concern

None

6 Invoice log and forecast

NA

7 VO Register

NA

8 Project Plan

NA

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 6


25 Benoi Lane, Singapore 627800 Page 6 of 6
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1100-Weekly Report 11 12 - 18 November 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 18 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1200 Rev.: 01
Title: Weekly Progress Report – 10/12/2012 to 16/12/2012 Page: 3 of 6

1 Project Summary
Aker Solution Singapore to disassemble the DDM 650 HY, BJ10 unit, along with the Dolly, and
provide a thorough inspection on the equipment, before establishing a comprehensive
inspection report and quotation for the customer.

2 Incidents and HSE


N/A

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 3


25 Benoi Lane, Singapore 627800 Page 3 of 6
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1100-Weekly Report 12 10 - 16 December 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 18 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1200 Rev.: 01
Title: Weekly Progress Report – 10/12/2012 to 16/12/2012 Page: 4 of 6

3 Activities performed this week 10/12/2012 to 16/12/2012

3.1 Continue assembly of DDM

This week, the repairs for the 2 A6VLm motors were complete. Before receiving the items, the
2 motors were sent for a thorough pressure test to check on the mechanisms. As soon as the 2
motors are tested, they were delivered back to the workshop.

Refer to test reports, MA1212451, MA1212452, MA1212644, attached at the back of this
document.

The team then proceeded onto mount the Hydraulic motors and install the Suspension Plate
and Thrust Nut. After which, they moved on to mount and secure the body of the DDM onto the
Skid. Subsequently, the Lubrication pumps were fitted on with new check valves and installed
onto the body of the DDM.

Last but not least, the IBOP is serviced and ready to undergo pressure testing.

Assembly Activities
Install DDM back into Skid Mounted and secured in Skid

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 4


25 Benoi Lane, Singapore 627800 Page 4 of 6
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1100-Weekly Report 12 10 - 16 December 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 18 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1200 Rev.: 01
Title: Weekly Progress Report – 10/12/2012 to 16/12/2012 Page: 5 of 6

Hydraulic motors mounted after bracket is Suspension plate and Thrust Nut installed
repaired

Lubrication Pump with new Check Valve Both Lubrication Pumps are installed

IBOP serviced and ready for pressure test

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 5


25 Benoi Lane, Singapore 627800 Page 5 of 6
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1100-Weekly Report 12 10 - 16 December 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 18 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1200 Rev.: 01
Title: Weekly Progress Report – 10/12/2012 to 16/12/2012 Page: 6 of 6

4 Planned activities next week

The team will first schedule a pressure test for the IBOP with the necessary standards, and
proceed on with the reassembly of other components of the DDM.

5 Area of concern

None

6 Invoice log and forecast

NA

7 VO Register

NA

8 Project Plan

NA

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 6


25 Benoi Lane, Singapore 627800 Page 6 of 6
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1100-Weekly Report 12 10 - 16 December 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 31 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1300 Rev.: 01
Title: Weekly Progress Report – 17/12/2012 to 23/12/2012 Page: 3 of 7

1 Project Summary
Aker Solution Singapore to disassemble the DDM 650 HY, BJ10 unit, along with the Dolly, and
provide a thorough inspection on the equipment, before establishing a comprehensive
inspection report and quotation for the customer.

2 Incidents and HSE


N/A

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 3


25 Benoi Lane, Singapore 627800 Page 3 of 7
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1300-Weekly Report 13 17 - 23 December 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 31 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1300 Rev.: 01
Title: Weekly Progress Report – 17/12/2012 to 23/12/2012 Page: 4 of 7

3 Activities performed this week 17/12/2012 to 23/12/2012

3.1 Continue assembly of DDM

This week, the team focused on fitting the new hoses onto the DDM. The Link Tilt Assembly,
Kelly Valve and Control Panel were all installed on the DDM.

The IBOP underwent a Hydrostatic Pressure Test as recommended by Aker Solutions from a
third party vendor, Pemac, on 22/12/2012 and it was found to be satisfactory. A certificate of
the Hydrostatic test is attached at the end of this document.

Assembly Activities
Link Tilt Assembly installed Link Tilt Assembly with new hoses and fittings

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 4


25 Benoi Lane, Singapore 627800 Page 4 of 7
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1300-Weekly Report 13 17 - 23 December 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 31 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1300 Rev.: 01
Title: Weekly Progress Report – 17/12/2012 to 23/12/2012 Page: 5 of 7

Lubrication pumps with new hoses and check Kelly valve installed after pressure test
valve

New hoses for motor to manifold New hoses fittings painted

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 5


25 Benoi Lane, Singapore 627800 Page 5 of 7
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1300-Weekly Report 13 17 - 23 December 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 31 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1300 Rev.: 01
Title: Weekly Progress Report – 17/12/2012 to 23/12/2012 Page: 6 of 7

New hoses fabricated and installed for all Control Panel re-wired and mounted
motors

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 6


25 Benoi Lane, Singapore 627800 Page 6 of 7
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1300-Weekly Report 13 17 - 23 December 2012.doc
Confidential

Aker Solutions Drilling Technologies Singapore Pte Ltd


Client: Deep Venture Project: DDM & Dolly Overhaul
Equipment: DDM 650 HY Date: 31 December 2012
Doc. no.: 4530126-R-BJ10-RA53-1300 Rev.: 01
Title: Weekly Progress Report – 17/12/2012 to 23/12/2012 Page: 7 of 7

4 Planned activities next week

The team aims to complete assembly of the DDM by the end of December 2012.

5 Area of concern

None

6 Invoice log and forecast

NA

7 VO Register

NA

8 Project Plan

NA

Aker Solutions Drilling Technologies (Singapore) Pte Ltd 7


25 Benoi Lane, Singapore 627800 Page 7 of 7
Tel +65 6262 6633 Fax +65 6303 4444 www.akersolutions.com
Registered No. 1991-01663-Z GST Reg No: MZ-0099647-0 Registered in the republic of Singapore
G:\Overhaul\Deep Venture\2012\ddm dolly 4530126\LA37 DataBook\data books word\15-RA53-1300-Weekly Report 13 17 - 23 December 2012.doc

You might also like