SPECIFICATION
FOR
CALIPER PIGGING
Page 2 of 10
SPECIFICATION NO.: MEC/08PS /05/62/70, Rev-00 Edition : 1
CONTENTS
1.0 INTENT
2.0 OBJECTIVE
Page 3 of 10
SPECIFICATION NO.: MEC/08PS /05/62/70, Rev-00 Edition : 1
AMENDMENT STATUS
Page 4 of 10
SPECIFICATION NO.: MEC/08PS /05/62/70, Rev-00 Edition : 1
1.0 INTENT
2.0 OBJECTIVE
The contractor shall submit the details of each type of pig including foam,
gauge cleaning and caliper for approval of OWNER/ PMC, which he
proposes to use. Pigs shall be launched in the pipeline only after their
design and size has been approved by OWNER/ PMC. Due care shall be
taken not to damage internal coating by the contractor, while proposing
TRANSPORTATION OF OIL THROUGH PIPELINE FROM CHATTOGRAM TO DHAKA
(CDPL), BANGLADESH
Page 5 of 10
SPECIFICATION NO.: MEC/08PS /05/62/70, Rev-00 Edition : 1
The detailed scope of work shall be, but not limited to under
Page 6 of 10
SPECIFICATION NO.: MEC/08PS /05/62/70, Rev-00 Edition : 1
Page 7 of 10
SPECIFICATION NO.: MEC/08PS /05/62/70, Rev-00 Edition : 1
The measurement shall cover the entire 360° of internal pipe wall
circumference using properly oriented and sufficient quantity of sensors.
For internally coated pipelines adequate care shall be taken by using soft
cups so that no damage takes place to the internal coating of pipe. The
tool shall be capable to identify and locate the following features as
minimum.
The caliper pig should have minimum capability to identify and detect the
defects of following threshold.
The movement of any type of pig (Except, foam pig) put into the line
during caliper pigging shall be required to be monitored along the pipeline
length from launcher to receiver trap. The Contractor shall detail out the
complete methodology of pig tracking proposed to be deployed by him
including complete technical details of the equipment and device proposed
to be used for this purpose.
Page 8 of 10
SPECIFICATION NO.: MEC/08PS /05/62/70, Rev-00 Edition : 1
At the discretion of the OWNER/ PMC identify at least two verification dig
sites for each pipeline jointly with PMC and OWNER from the recorded
data and provide OWNER/ PMC with their distance from the nearest
pipeline feature or reference marker to facilitate location of defect in the
field.
Page 9 of 10
SPECIFICATION NO.: MEC/08PS /05/62/70, Rev-00 Edition : 1
If pig do not move from stuck up location, by any measure, then the
pipeline section shall have to be cut for retrieval of Pig. Necessary
erection, fabrication and modification of pipe with new pipe piece after
retrieval of pig shall be done by Contractor. The cost for this works shall
be borne by Contractor on actuals. After fabrication & erection, pigging
contractor shall run Gauge pig to check internal restriction, if any.
Locating the stuck up pig and its retrieval shall be the responsibility of the
CONTRACTOR.
The work report shall be prepared and submitted in hard copy (4 sets)
and Electronics media (2 sets)
Page 10 of 10
SPECIFICATION NO.: MEC/08PS /05/62/70, Rev-00 Edition : 1