Doc Name: Excavation report

NRC 05 Issued Date: 28/12/2023

Rev.: 0
HSES DEPARTMENT DOC NO: TR7

EXCAVATION INSPECTION REPORT

Prepared by: Gohar Ali: HSE Administrator Date Reported: 28/12/2023

Date Conducted: 28/12/2023

MR
Doc Name: Excavation report

NRC 05 Issued Date: 28/12/2023

Rev.: 0
HSES DEPARTMENT DOC NO: TR7

SITE
SI No. LOCATION Discerption PHOTO

Positive observation

1 Phase-3 Excavation protected by hard


barricade & safe access has been
provided

Positive observation

2 Phase-3 Excavation protected by concrete


barrier & safe access has been
provided

Phase-3
Positive observation
3

Phase-3 Positive observation


4

MR
Doc Name: Excavation report

NRC 05 Issued Date: 28/12/2023

Rev.: 0
HSES DEPARTMENT DOC NO: TR7

Phase-3 Positive observation


5

Phase-3 Positive observation


6

Immediate action required on


Phase-3 phase 3 unsafe excavation sandy
7 soil which has been excavated
without provision of required
sloping and benching.

Immediate action required on


phase 3 unsafe excavation sandy
8 Phase-3 soil which has been excavated
without provision of required
sloping and benching

MR
Doc Name: Excavation report

NRC 05 Issued Date: 28/12/2023

Rev.: 0
HSES DEPARTMENT DOC NO: TR7

Immediate action required on


phase 3 unsafe excavation sandy
9 Phase-4 soil which has been excavated
without provision of required
sloping and benching

Phase-4 Immediate action required on


10 phase 4 excavation for providing
proper access

Found unstable Excavation


Phase-4
phase-4 which can cause of
11
Cave-in hazards

12 Phase-5 No proper access & egress

MR
Doc Name: Excavation report

NRC 05 Issued Date: 28/12/2023

Rev.: 0
HSES DEPARTMENT DOC NO: TR7

Found kerb stone material kept


near excavation area at phase-3
Phase-5
13 Immediate action required there
is probability of cave-in and fall
of kerb stone into the excavated
area

No hard barricade ,no proper


14 Phase-5 access and egress

Found GRP pipe kept near


excavation area at phase-3

Immediate action required there


15
Phase-5 is probability of cave-in and fall
of pipe into the excavated area

Missing hard barricade, proper


16
Phase-5 access and egress

MR