GOVERNMENT OF NEPAL

MINISTRY OF PHYSICAL INFRASTRUCTURE AND TRANSPORT

DEPARTMENT OF ROADS

STRATEGIC CONNECTIVITY AND TRADE IMPROVEMENT PROJECT (SRCTIP)

UPGRADING /IMPROVEMENT OF NAUBISE - MALEKHU ROAD


(Km 0+000 to Km 43+542)

TRAFFIC MANAGEMENT PLAN


AT NAUBISE – MALEKHU SECTION OF PRITHVI HIGHWAY
(CONSTRUCTION & OPERATION PHASE)

Submitted by:
SHARMA-LAMA-ZICG JV
Table of Contents
1. Introduction .............................................................................................................................. 1
2. Traffic management options during the construction phase................................................. 1
2.1 Controlled One-Way Traffic Movement ........................................................................ 2
2.1.1 On Straight Road .......................................................................................................... 2
2.1.2 On Curved Road Section ............................................................................................. 2
2.1.3 For Slab Culvert Construction .................................................................................... 3
2.2 Controlled Two-Way Traffic Movement ....................................................................... 4
2.2.1 Two Lane to Four Lane at Market Places .................................................................. 4
2.2.2 For Work Zone Outside Existing Road ...................................................................... 4
2.2.3 For Slab Culvert Extension ......................................................................................... 5
2.2.4 For Construction with Diversion................................................................................. 5
3. Flag-persons’ conduct and their monitoring .......................................................................... 6
4. Speed management during the construction phase................................................................ 6
5. Traffic Management Plan during the operation phase.......................................................... 7
6. Safety, Environment and Maintenance measures.................................................................. 8
7. Other Traffic Management Programs .................................................................................... 8
7.1 Continue road safety awareness campaign with special focus on safe speed and
expand other form of awareness (volunteers, post campaign) ................................................ 8
7.2 Seek traffic police collaboration in curbing over speeding, reckless overtaking and
drunk driving ............................................................................................................................... 8
8. Miscellaneous ............................................................................................................................ 9
9. Traffic Signs.............................................................................................................................. 9
10. Provisions of the Contract Agreement Regarding the WZ safety and Traffic Operation 12
11. Preparation and Implementation of the TMP...................................................................... 12
12. Organizational Structure for Traffic Safety ......................................................................... 13
List of Figure
Figure 1 Traffic Management Plan for controlled one way traffic on straight Road ................... 2
Figure 2 Traffic Management Plan for controlled one way traffic on Curve Road..................... 3
Figure 3 Traffic Management Plan for Slab Culvert Construction -One Way Traffic at a Time..... 3
Figure 4 Traffic Management Plan for Two Lane to Four Lane in Market Area ......................... 4
Figure 5 Traffic Management Plan for controlled two-way traffic for work zone outside
existing zone ..................................................................................................................................... 5
Figure 6 Traffic Management Plan for Slab Culvert extension allowing two-way traffic at a time 5
Strategic Connectivity and Trade Improvement Project (SRCTIP)

1. Introduction
Traffic Management plan details the way activities in the road project will be carried out
such that they minimize inconvenience and help ensure road users and workers remain as safe as
possible. Traffic management along the road works will invariably involve work zone safety
planning with the main aim is to protect both the workers as well as the traffic that ply alongside
these areas.
We can observe reckless driving (over speeding, reckless overtaking, disregard to lane
discipline) along the wider highway without signage, which has contributed to numerous crashes
resulting in death and/or serious injury to the vehicle occupants. Since construction works along
this highway will continue for next three years and over, traffic management is likely to be a major
concern during the construction period, to control safety issues effectively.
The following proceeding is thus a Traffic Management Plan for the project road during the
construction and traffic operation phased.

2. Traffic management options during the construction phase


The following traffic management options that was earlier effective for another similar road
project will continue to take place during the construction phase:
1 Controlled One Way Traffic Movements
2 Controlled Two Way Traffic Movements
As the deadline for the completion of this project road is three years and this road need to
developed to the full road formation, the following construction will take place during the time
outside of the full road closure where controlled one/ two –way traffic movement will be imposed
along the work zones while conducting following different works.
➢ Back-cutting, backfilling for structures, foundations, etc.
➢ Laying the second layer, first layer or wearing course of the pavement;
➢ Concreting works in foundation, RCC drains, RCC Walls
➢ Concreting for culverts extension (sub-structure and super-structure);
➢ Construction of Bridges.
➢ Safety barrier construction.
➢ Laying of pipes for sub-soil drainage, outlets and geo-textile on structures
➢ Construction of kilometre and 5th kilometre stone; laying road marking and installation of
reflective pavement markers (road studs)
➢ Disposal of surplus excavated materials to the spoils

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 1
Strategic Connectivity and Trade Improvement Project (SRCTIP)

2.1 Controlled One-Way Traffic Movement


2.1.1 On Straight Road
The length of work zone varies as per the nature of works and shall be barricaded and
secured from the prevailing traffic by means of traffic cones, barricades, ropes. If the excavation
height is higher than 3 m in work zone, new jersey barriers or similar structure must be used for
barricading. The width of the work zone will depend on the nature of the work involved, the space
required to temporarily store the construction or excavated materials, space required for equipment
involved and the clearance required for the equipment’s operation (e.g., the swing area of the
excavator’s boom).

Figure 1 Traffic Management Plan for controlled one way traffic on straight Road

The traffic cones should gradually taper to the full width of the work area for smooth
transition of the moving vehicle. The taper length shall be between 15 m to 30m. The sign of
“Dangerous Obstruction” and “Keep Left/Right” sign will be placed to identify the hazard and
direct the movement of traffic at both ends as shown in the typical drawing type -1. If any
construction works are to be carried out at night time, the flaggers should use red/ green flashing
hand batons to signal the oncoming traffic.

Fig: Solar LED Traffic Control Baton

2.1.2 On Curved Road Section


For controlled One Way Traffic Movements on a curved section, length of advance warning
zone must be close to 60 m.

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 2
Strategic Connectivity and Trade Improvement Project (SRCTIP)

Rest of the parameters for signs, type and spacing of barricades shall be similar to controlled one
way traffic movement on straight road section as mentioned above and as shown in the typical
drawing type -2.

Figure 2 Traffic Management Plan for controlled one way traffic on Curve Road

2.1.3 For Slab Culvert Construction


For controlled One Way Traffic Movements on section for slab construction, length of
advance warning zone must be close to 60 m to 200 m.
The length of work zone varies as per the nature of works and shall be barricaded and
secured from the prevailing traffic by means of new jersey barrier or similar structures as the
construction site near cross drainage structure is generally higher than 3 m in work zone. Water
filled drum barricade painted with red and yellow shall be placed at start and end of the new jersey
barrier which would act as impact attenuator.
Rest of the parameters for signs, type and spacing of barricades shall be similar to controlled
one way traffic movement on straight road section as mentioned previously and as shown in the
typical drawing type -3.

Figure 3 Traffic Management Plan for Slab Culvert Construction -One Way Traffic at a Time

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 3
Strategic Connectivity and Trade Improvement Project (SRCTIP)

2.2 Controlled Two-Way Traffic Movement

2.2.1 Two Lane to Four Lane at Market Places


For controlled Two Way Traffic Movements at marketplaces, length of advance warning
zone must be from minimum 60 m to maximum 200 m. Starting of advance warning zone is
indicated by sign board of “Road Construction Works Ahead”, which will then be followed by signs
for “Road Work”, “Maximum Speed” and “No Overtaking”.
The length of work zone varies as per the nature of works and shall be barricaded and
secured from the prevailing traffic by means of traffic cones, barricades, ropes. If the excavation
height is higher than 3 m in work zone, new jersey barriers or similar structure must be used for
barricading. The width of the work zone will depend on the nature of the work involved, the space
required to temporarily store the construction or excavated materials, space required for equipment
involved and the clearance required for the equipment’s operation (e.g., the swing area of the
excavator’s boom).

Figure 4 Traffic Management Plan for Two Lane to Four Lane in Market Area

If the existing carriage way, outside the work zone, is not sufficient for allowing two-way
traffic movement, existing shoulder or motorable portion outside the shoulder of marketplace shall
be used. The traffic cones should be used to direct the vehicle for smooth transition of the moving
vehicle from existing carriage way as shown in typical drawing type-5. The taper length shall be
between 15 m to 30m. The sign of “Sharp Change of Direction” and “Keep Left/Right” sign will
be placed to direct the movement of traffic at both ends.

2.2.2 For Work Zone Outside Existing Road


For controlled Two Way Traffic Movements with work zone outside existing road, length
of advance warning zone must be from minimum 60 m to maximum 200 m. Starting of advance
warning zone is indicated by sign board of “Road Construction Works Ahead”, which will then be
followed by signs for “Road Work” and “Maximum Speed”.

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 4
Strategic Connectivity and Trade Improvement Project (SRCTIP)

The traffic movement will not get disturbed as the work zone lies outside the carriageway.
Rest of the parameters for signs, type and spacing of barricades is shown in Typical Drawing type
6.

Figure 5 Traffic Management Plan for controlled two-way traffic for work zone outside existing zone

2.2.3 For Slab Culvert Extension


For controlled Two Way Traffic Movements on section for slab extension, length of advance
warning zone must be close to 60 m to 200 m as shown in typical drawing type 7.

Figure 6 Traffic Management Plan for Slab Culvert extension allowing two-way traffic at a time

The length of work zone varies as per the nature of works and shall be barricaded and
secured from the prevailing traffic by means of new jersey barrier or similar structures as the
construction site near cross drainage structure is generally higher than 3 m in work zone. Water
filled drum barricade painted with red and yellow shall be placed at start and end of the new jersey
barrier which would act as impact attenuator.
Rest of the parameters for signs, type and spacing of barricades shall be like controlled two-
way traffic movement on straight road section as mentioned previously.

2.2.4 For Construction with Diversion


For controlled two-way traffic movements for construction with diversion, length of
advance warning zone must be from minimum 60 m to maximum 200 m. Starting of advance

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 5
Strategic Connectivity and Trade Improvement Project (SRCTIP)

warning zone is indicated by sign board of “Road Construction Works Ahead”, which will then be
followed by signs for “Road Work”, “Maximum Speed”, “No Overtaking”, “Diversion Ahead”,
“Sharp Bend (Temporary Diversion)”.
The length of work zone varies as per the nature of works and shall be delineated and secured
from the prevailing traffic by means of water filled drum barricade painted with reflective red and
yellow, for better night-time guidance.
Rest of the parameters for signs, type and spacing of barricades shall be as shown in typical
drawing type -4.

3. Flag-persons’ conduct and their monitoring


In either one/ two –way traffic movement, the flag-persons must always face the oncoming
traffic and position themselves so that they are visible to ensure maximum advance warning. They
should be alert and maintain direct eye contact with the drivers to whom they must direct, appear
neat and responsible.
Where there are other flag-persons in the vicinity, the leader should maintain continuous
communication with his/ her team at all times. As they are the personnel that the public comes
into contact the most, the flag-persons must be courteous so as to improve they’re as well as the
contractor’s image. The flag-persons should confine to their job (i.e. work zone protection and
traffic control) and should not engage in other activities (e.g. assist the work crews, get involved
in any distraction, etc.).
The Safety Officer should ensure that the flag-persons remain on duty until they are relieved.
He/ She should plan the time to deployment, the numbers to deploy, and the locations of deployment
for the flag persons. The Safety Officer should brief his team about the means of communication to
adopt between multiple flag-persons. This individual should determine whether to deploy traffic
observers (spotters) if necessary to warn workers of errant vehicles, danger from traffic or to assist
construction vehicles in entering, exiting the work zones or making U-turns.

4. Speed management during the construction phase


The entire road formation with back cutting, grade cutting, and structure has to be
constructed first. During the time, speed regulatory information boards with flag mans will be
deputed to regulate the traffic flow and speed will automatically controlled at the time, there after
pavement have to be laid over the road. After completion of the road formation, the road will
good for traffic, there has been significant increase in the vehicular speeds along the project.
Particularly, when the road is open to traffic fully then increase in crashes, some leading to deaths
as well. In addition, there has been more crashes caused by reckless overtaking at high speed. All
these events have led serious safety implications that the project needs to tackle.

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 6
Strategic Connectivity and Trade Improvement Project (SRCTIP)

5. Traffic Management Plan during the operation phase


Once this project road is opened to traffic, there will numerous physical devices as follows
to regulate traffic speeds, dissuade dangerous driving manoeuvres and prompt for lower speed at
vulnerable/ critical areas of the road.
➢ Provision of enhanced signs (retro-reflective) and retro-reflective road marking to increase
delineation;
➢ Delineation of the safety barriers, bridge crossings and improved lateral protection against
run-off the road crashes;
➢ Provision of road pavement markers (studs) strategically placed at narrow bridge crossings,
sharp curves, no overtaking areas and intersections;
➢ Provision of rumble strips sets to calm vehicle speed at Bazar, bridge crossings and sharp
curves, subject to successful result from the pilot test at NM Road Bridge approaches;
➢ Improved speed signs (dual sign provision at strategic location, repeater signs) to
continuously alert drivers about the speed limit applicable at the road segment concerned;
➢ Increased awareness for roadside communities including commercial drivers through the
project initiatives;
➢ Potentially police patrolling to curb and penalise over speeding, reckless overtaking and
drunk driving.
However, despite the interventions above, it will be necessary to introduce additional
measures as follows at the improved Naubise-Malekhu section of Prithvi Highway during
the operation phase.
➢ Enhanced police patrolling to curb over speeding, reckless overtaking, and drunk driving.
➢ More random axle-load checks to curb vehicle overloading of commercial vehicles;
➢ More aggressive publicity against over speeding through the existing and additional
hoarding board with lighting system for greater visibility;
➢ Strict implementation of a time-card system along the highway to discourage over speeding;
➢ Provision of road safety structures such as safety barriers, road marking and signage at the
area still felt deficient.
➢ Regularly maintain all the rumble strips without any delay, if these devices are deemed to
be appropriate for speed management in the Nepalese context.

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 7
Strategic Connectivity and Trade Improvement Project (SRCTIP)

6. Safety, Environment and Maintenance measures

S. N Risk Management Measures


Communication with Public Offices like Ward Office,
1. Lack of Public Information
Local key Stakeholders etc.
As far as easy and safe side for public vehicle. All
2. Route Selection Drivers to be made fully aware on routes including
associated hazards by traffic signs.
3. Driver Competency All the drivers will be oriented time to time.
Frequent monitoring of road condition. Regular &
Periodic improvement of road by repairing potholes,
4. Road Condition
gravelling and removing undulation etc. with proper
guidelines for length workers and backhoe machines.
5. Intersection - Precautions Upgrading of intersection at possible places.
6. Entrance to stock yard & Sufficient directional and warning signage
machinery yard
7. Parking Arrangement of sufficient parking at contractor’s yard.
8. Break down vehicles Arrangement of stand by mechanics or lifting toeing it
and moving to safe location by recovery vehicle.

7. Other Traffic Management Programs


7.1 Continue road safety awareness campaign with special focus on safe speed and
expand other form of awareness (volunteers, post campaign)
Road safety awareness campaign for roadside communities, commercial drivers (bus,
truck, minibus, and microbus) will be a part during execution of works at all time. These
campaigns will be repeated for the above target groups with special focus on safe speed.
Distribution of brochures at the roadside based will also be accelerated immediately.
Feasibility of running different format of the awareness campaign through the deployment
of young student volunteers, traffic volunteers, etc., will also be explored and implemented
accordingly based on the outcome of this assessment.

7.2 Seek traffic police collaboration in curbing over speeding, reckless overtaking and
drunk driving
In order to dissuade motorists to over speed, recklessly overtake or even drive under the
influence of alcohol, traffic police enforcement to curb these dangerous activities is necessary
along the other physical and awareness measures discussed above.
The Traffic Safety Engineer under this project, held discussion with the Dhading Traffic
Police about police enforcement against over speeding, reckless overtaking, drunk driving and

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 8
Strategic Connectivity and Trade Improvement Project (SRCTIP)

enhancing the random vehicle fitness inspections of public vehicles along the project road. While
the above agency is very much willing to cooperate in these areas, they’ve cited lack of equipment
such as required number of radar guns (for speed enforcement), breathalysers (for controlling
drunk driving), lack of axle-load control stations, etc., to take these tasks. The project authorities
along with the CSC will be requested to hold a joint meeting with the Dhading Chief District
Officer and Traffic Police to further discuss this matter and achieve concrete feedback and
cooperation in this aspect.

8. Miscellaneous
I. Traffic management plan will be periodically inspected, monitored and reviewed. If any
change required in TMP it is reported to engineer.
II. Proper coordination with government and nongovernmental stake holders shall be made
with coordination with employer/engineer for better traffic management as per the rules and
regulations of government of Nepal.
III. A Public relation officer will be deputed to deal with any public complaints including traffic
complaints & socials issues.
IV. Periodic maintenance of Vehicles will be done to address noise/exhaust emissions and to
minimize breakdown of vehicles.

9. Traffic Signs
Following sign boards will be used during traffic management to control and regulate the
traffic flow:
SN Symbol and name No's Required Picture sample

1 Construction works ahead Required at every site

Required at the site


A16- No Overtaking (From
2 where overtaking is
right)
forbidden

`
Required at the site
3 A16- No Overtaking (From left) where overtaking is
forbidden

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 9
Strategic Connectivity and Trade Improvement Project (SRCTIP)

SN Symbol and name No's Required Picture sample

Required at bridge or
4 A22- Maximum Speed (20)
diversion

Required at a normal
5 A22- Maximum Speed (30)
construction site

Required at one-way
6 A24- Temporary Stop Sign
only

Required at one-way
7 A25- Temporary Go Sign
only

8 A29- Keep Left Required at every site

9 A29- Keep Right Required at every site

B13- Sharp Change of direction


10 Required at diversion
(Right)

B13- Sharp Change of direction


11 Required at diversion
(Left)

Required at the site


where road is narrow
12 B15- Road Narrows on the right
due to ongoing
construction

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 10
Strategic Connectivity and Trade Improvement Project (SRCTIP)

SN Symbol and name No's Required Picture sample

Required at the site


where road is narrow
13 B15- Road Narrows on the left
due to ongoing
construction

14 B38- Road Works Required at every site

15 B42- Diversion ahead Required at diversion

B43- Dangerous Obstruction Required at bridge or


16
(Left side hazard) slab culvert diversion

B43- Dangerous Obstruction Required at bridge or


17
(Right side hazard) slab culvert diversion

B46- Sharp Bend (temporary


18 Required at diversion
diversion to right)

B46- Sharp Bend (temporary


19 Required at diversion
diversion to left)

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 11
Strategic Connectivity and Trade Improvement Project (SRCTIP)

10. Provisions of the Contract Agreement Regarding the WZ safety and


Traffic Operation
As Kathmandu – Nagdhunga – Naubise is the major highway section which accommodates
all types commercial vehicles and connects the capital city of Nepal, Kathmandu with other parts
of the country, this road cannot be fully closed for traffic for long duration. Hence, their needs be a
traffic management plan in such a way that traffic flow remains open in at least one lane throughout
the Construction Period.

The Contract document Volume II, specific specification is the least requirement for the work
zone safety and traffic operation during the time of the construction at site. The important points
mentioned in the contract document are summarized and listed below:

➢ During the pre-construction phase, Contractor shall prepare traffic management plan which
shall be reviewed by Construction Supervision Consultant, Geo-Environment and Social
Unit of Department of Roads.
➢ Contractor shall provide and maintain traffic safety throughout construction phase in
accordance with “Safety at Road Works” chapter of Traffic Sign Manual of DoR.
➢ Contractor shall always keep one lane open throughout the construction.
➢ Maximum length of one-way working shall be 500 meters, which shall be reduced if
visibility is reduced at bends and traffic delays are excessive. And within any 5 km section
of road length available to the Contractor for major pavement construction, 2 separate
sections of 500m length each shall be provided by minimum of 2 km of unconstructed road
with two-lane serviceable.
➢ Working area shall be isolated from vehicular and pedestrian traffic by providing advance
warning and transition zone. Advance warning zone shall be at least 100 m away. Approach
Transition zone length is 50m.

11. Preparation and Implementation of the TMP


Following are the steps/stages for preparation and implementation of the TMP that would
be followed:

➢ Desk work for the selection and identification of the proper safety Traffic management plan
on the work zone by reviewing the safety literatures and traffic sign manuals shall be done.
➢ Detailed site survey and visual inspection of the working site shall be carried out for the
preparation of the working drawing and the site specific TMP.
➢ Working drawing of construction site with specific TMP would be prepared and submitted
to the engineer along with the RFI before starting the works.

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 12
Strategic Connectivity and Trade Improvement Project (SRCTIP)

➢ In the case of requirement of new type of layout of the TMP (different from the submitted
typical layout), the site specific TMP shall be prepared and submitted with the working
drawing and RFI to the engineer.
➢ Engineer shall verify the site specific TMP along the construction sites and grant Permission
for construction activities.
➢ The work zone safety shall be managed as shown in the site specific TMP by the contractor.
➢ Approved traffic management plan shall be strictly followed throughout the construction
period. Road Safety Officer from Contractor shall be fully responsible for maintenance of
TMP on control zone.
➢ The photographs of the implementation of TMP on each work zone before the
commencement of the work, during the construction and after the completion of the work
will be submit on time periods.

12. Organizational Structure for Traffic Safety

Traffic Management Plan (Construction, Operation Phase) of Naubise-Malekhu Section of Prithvi Highway Page 13
APPENDIX A

TYPICAL DRAWINGS
A22, B38

B15

B43,A29

A24 or A25
A24 or A25
60 to 200m 15 to 30m 15 to 30m

60 to 200m

B43, A29

A22, B38
A29
These safety cones will be placed when the vehicle

B15
coming from right will be stopped using A24 by the signal man

TYPE 1: TRAFFIC MANAGEMENT PLAN FOR CONTROLLED ONE WAY TRAFFIC ON STRAIGHT ROAD

NOTES: Descriptions of the Traffic sign posts used are given below
(Refer Traffic Signs Manual for additional Information)

A22 : MAXIMUM SPEED (2 no.s)


A24: TEMPORARY STOP SIGN (2 no.s)
A25: TEMPORARY GO SIGN (2 no.s)
A29: KEEP LEFT (left if the symbol reversed) (2 no.s)
B15: ROAD NARROWS ON THE RIGHT (left if the symbol reversed) (2 no.s)
B38: ROAD WORKS (2 no.s)
B43: DANGEROUS OBSTRUCTION (verges) (2 no.s)

Legends NOTES:
1. Traffic shall only be allowed one way at the working area.
Water filled drum barricade painted with red and yellow 2. Traffic signs shall be placed at the distance as shown in the typical drawing as above
3. As per the depth of the work zone, the barrier type will be selected. If the depth of the
Safety Cone work zone is less than 3m from the road surface, safety cone and reflector tape
barricade shall be provided, else the New Jersey barrier shall be provided
Caution tape barricade 4. Spacing of safety cone shall be 1.5m C/C in the transition area and 9m C/C in straight
New jersey barrier portion.
5. Flag men shall be present at site throughout the working duration.the
6. Flag men shall be provided at both ends of diversion start and on every curves.

1
B43,A29

A24 or A25
60 to 200m
15 to 30m
B1
5

A2
2,
B3
8

A2

A22, B38
A29
4o

B15
These safety cones will be placed when the vehicle

B10
rA coming from right will be stopped using A24 by the signal man
25
100 to 200m

TYPE 2: TRAFFIC MANAGEMENT PLAN FOR CONTROLLED ONE WAY TRAFFIC ON


CURVED ROAD
0m
to 20
10 0

NOTES: Descriptions of the Traffic sign posts used are given below
(Refer Traffic Signs Manual for additional Information)

B10
A22: MAXIMUM SPEED (2 no.s)
A24: TEMPORARY STOP SIGN (2 no.s)
A25: TEMPORARY GO SIGN (2 no.s)
A29: KEEP LEFT OR RIGHT (2 no.s)
B10: SHARP BEND TO THE RIGTH (left if the symbol reversed) (2 no.s)
B15: ROAD NARROWS ON THE RIGHT (left if the symbol reversed) (2 no.s)
B38: ROAD WORKS (2 no.s)
B43: DANGEROUS OBSTRUCTION (verges) (2 no.s)

Legends NOTES:
1. Traffic shall only be allowed one way at the working area.
Water filled drum barricade painted with red and yellow 2. Traffic signs shall be placed at the distance as shown in the typical drawing as above
3. As per the depth of the work zone, the barrier type will be selected. If the depth of the
Safety Cone work zone is less than 3m from the road surface, safety cone and reflector tape
barricade shall be provided, else the New Jersey barrier shall be provided
Caution tape barricade 4. Spacing of safety cone shall be 1.5m C/C in the transition area and 9m C/C in straight
New jersey barrier portion.
5. Flag men shall be present at site throughout the working duration.the
6. Flag men shall be provided at both ends of diversion start and on every curves.

2
Length of working area may
vary as per site condition

B43, A29
A24 or A25
A22, B38

A24 or A25
B15

B43,A29
60 to 200m 15 to 30m 15 to 30m

Existing Slab Culvert


60 to 200m

B43,A29

A22, B38
A29

B15
These safety cones will be placed when the vehicle

B43, A29
coming from right will be stopped using A24 by the signal man

TYPE 3: TRAFFIC MANAGEMENT PLAN FOR SLAB CULVERT CONSTRUCTION - ONE WAY
TRAFFIC AT A TIME
NOTES: Descriptions of the Traffic sign posts used are given below
(Refer Traffic Signs Manual for additional Information)

A22: MAXIMUM SPEED (2 no.s)


A24: TEMPORARY STOP SIGN (2 no.s)
A25: TEMPORARY GO SIGN (2 no.s)
A29: KEEP LEFT OR RIGHT (5 no.s)
B15: ROAD NARROWS ON RIGHT (2no.s)
B38: ROAD WORKS (2 no.s)
B43: DANGEROUS OBSTRUCTION (verges) (4 no.s)

Legends NOTES:
1. Traffic shall only be allowed one way at the working area.
Water filled drum barricade painted with red and yellow 2. Traffic signs shall be placed at the distance as shown in the typical drawing as above
3. As per the depth of the work zone, the barrier type will be selected. If the depth of the
Safety Cone work zone is less than 3m from the road surface, safety cone and reflector tape
barricade shall be provided, else the New Jersey barrier shall be provided
Caution tape barricade
4. Spacing of safety cone shall be 1.5m C/C in the transition area and 9m C/C in straight
New jersey barrier portion.
5. Flag men shall be present at site throughout the working duration.the
6. Flag men shall be provided at both ends of diversion start and on every curves.

3
Water filled barricade painted
with red and yellow

B13
B46

B13
15 to 30m 15 to 30m

B42
A22, B38

A16
Temporary Diversion Road

A29
(Width of the diversion may vary as per site condition)

60 to 200m

B13

B13

A22, B38
A16
Water filled barricade painted

A29

B13
with red and yellow

B42
60 to 200m

TYPE 4: TRAFFIC MANAGEMENT PLAN FOR NEW SLAB CULVERT CONSTRUCTION WITH
DIVERSION NOTES: Descriptions of the Traffic sign posts used are given below
(Refer Traffic Signs Manual for additional Information)

A16: NO OVERTAKING (2 no.s)


A22: MAXIMUM SPEED (2 no.s)
A24: TEMPORARY STOP SIGN (2 no.s)
A25: TEMPORARY GO SIGN (2 no.s)
A29: KEEP LEFT OR RIGHT (2 no.s)
B13: SHARP CHANGE OF DIRECTION (4 no.s)
B38: ROAD WORKS (2 no.s)
B42: TEMPORARY DIVERSION AHEAD (2 no.s)
B46: SHARP BEND (temporary diversion) (2 no.s)

NOTES:
1. Traffic shall only be allowed two (or one way as per site condition) at the working area.
Legends 2. Traffic signs shall be placed at the distance as shown in the typical drawing as above
3. As per the depth of the work zone, the barrier type will be selected. If the depth of the
Water filled drum barricade painted with red and yellow work zone is less than 3m from the road surface, safety cone and reflector tape
barricade shall be provided, else the New Jersey barrier shall be provided
Safety Cone 4. Spacing of safety cone shall be 1.5m C/C in the transition area and 9m C/C in straight
portion.
Caution tape barricade 5. Flag men shall be present at site throughout the working duration.the
New jersey barrier 6. Flag men shall be provided at both ends of diversion start and on every curves.

4
A29
B15
A29
A22, B38

Water filled drum as Impact Attenuator


A16

B15
painted with red and yellow

60 to 200m

60 to 200m 15 to 30m 15 to 30m

A22, B38
A16
Water filled drum as Impact Attenuator
painted with red and yellow

B15
A29
Existing Road edge

A29
B15

TYPE 5: TRAFFIC MANAGEMENT PLAN FOR TWO LANE TO FOUR LANE IN MARKET AREA

NOTES: Descriptions of the Traffic sign posts used are given below
(Refer Traffic Signs Manual for additional Information)

A16: NO OVERTAKING (2 no.s)


A22: MAXIMUM SPEED (2 no.s)
A24: TEMPORARY STOP SIGN (2 no.s)
A25: TEMPORARY GO SIGN (2 no.s)
A29: KEEP LEFT OR RIGHT (4 no.s)
B38: ROAD WORKS (2 no.s)

Legends NOTES:
1. Traffic shall only be allowed two way at the working area.
Water filled drum barricade painted with red and yellow 2. Traffic signs shall be placed at the distance as shown in the typical drawing as above
3. As per the depth of the work zone, the barrier type will be selected. If the depth of the
Safety Cone work zone is less than 3m from the road surface, safety cone and reflector tape
Caution tape barricade barricade shall be provided, else the New Jersey barrier shall be provided
4. Spacing of safety cone shall be 1.5m C/C in the transition area and 9m C/C in straight
New jersey barrier portion.
5. Flag men shall be present at site throughout the working duration.the
6. Flag men shall be provided at both ends of diversion start and on every curves.
Water filled drum barricade painted with red and yellow

5
A22, B38

A29
Work Zone outside existing road
60 to 200m 15 to 30m 15 to 30m 60 to 200m

A22, B38
TYPE 6: TRAFFIC MANAGEMENT PLAN FOR CONTROLLED TWO WAY TRAFFIC FOR WORK ZONE
OUTSIDE EXISTING ROAD

NOTES: Descriptions of the Traffic sign posts used are given below
(Refer Traffic Signs Manual for additional Information)

A22 : MAXIMUM SPEED (2 no.s)


A29: KEEP LEFT (left if the symbol reversed) (1 no.s)
B38: ROAD WORKS (2 no.s)

Legends NOTES:
1. Traffic shall only be allowed two way at the working area.
Water filled drum barricade painted with red and yellow 2. Traffic signs shall be placed at the distance as shown in the typical drawing as above
3. As per the depth of the work zone, the barrier type will be selected. If the depth of the
Safety Cone work zone is less than 3m from the road surface, safety cone and reflector tape
barricade shall be provided, else the New Jersey barrier shall be provided
Caution tape barricade 4. Spacing of safety cone shall be 1.5m C/C in the transition area and 9m C/C in straight
New jersey barrier portion.
5. Flag men shall be present at site throughout the working duration.the
6. Flag men shall be provided at both ends of diversion start and on every curves.

6
Extension Slab

Length of working area may


vary as per site condition

B43,A29
A22, B38

B15

60 to 200m 15 to 30m 15 to 30m

60 to 200m

A22, B38
B15
B43, A29
Existing Slab Culvert

TYPE 7: TRAFFIC MANAGEMENT PLAN FOR SLAB CULVERT EXTENSION ALLOWING TWO
WAY TRAFFIC AT A TIME
NOTES: Descriptions of the Traffic sign posts used are given below
(Refer Traffic Signs Manual for additional Information)
A22: MAXIMUM SPEED (2 no.s)
A29: KEEP LEFT OR RIGHT (3 no.s)
B15: ROAD NARROWS ON THE RIGHT (left if the symbol reversed) (2 no.s)
B38: ROAD WORKS (2 no.s)
B43: DANGEROUS OBSTRUCTION (verges) (2 no.s)
NOTES:
Legends 1. Traffic shall only be allowed two way (or one way as per site condition) at the working
area.
Water filled drum barricade painted with red and yellow 2. Traffic signs shall be placed at the distance as shown in the typical drawing as above
3. As per the depth of the work zone, the barrier type will be selected. If the depth of the
Safety Cone
work zone is less than 3m from the road surface, safety cone and reflector tape
Caution tape barricade barricade shall be provided, else the New Jersey barrier shall be provided
4. Spacing of safety cone shall be 1.5m C/C in the transition area and 9m C/C in straight
New jersey barrier portion.
5. Flag men shall be present at site throughout the working duration.the
6. Flag men shall be provided at both ends of diversion start and on every curves.

7