Professional Documents
Culture Documents
Boiler Manual Thermax 150 TPH IRCFBC
Boiler Manual Thermax 150 TPH IRCFBC
5 HOT STARTUP............................................................................................................... 64
SECTION B PAGE I
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
8 WINDBOX CO VENTING................................................................................................ 69
SECTION B PAGE II
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION OVERVIEW
This section describes in brief about IR-CFBC operation philosophy, Boiler start-up, Shutdown,
Emergency procedures & Safety aspects of the boiler.
Note
• Procedures explained in this section apply for start up of a boiler already commissioned.
Commissioning a new boiler calls for several additional requirements, which are not
explained here.
• It is assumed that the boiler operating team is fully familiar with the design and construction
features described in section A.
• It is assumed that operators are trained in operation of similar IRCFBC boilers and have
been licensed to operate boilers by the concerned authorities.
• Owner is encouraged to evolve standard operating procedures (SOP) based on the
framework and recommendations that are explained in the subsections below. The SOPs
have to be well understood by the utility managers and operators for safe and reliable
operation.
OPERATOR’S RESPONSIBILITY
Boiler operator is responsible not only for the smooth operation of the boiler and its related
equipments, but also for the safety of all the personnel involved. Operator must be aware of any
operating conditions affecting the boiler or related equipments and should be able to recognize
hazardous conditions and to act properly to avoid injury/ damages.
Even though the operating procedures are normally given for each piece of equipment, but
complete knowledge of all components, their design, purpose, limitations and relationship with
other components is must for the operators.
SECTION B PAGE 1
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Fig. 1A shows illustration of furnace with an air supply plenum at the bottom an air distributor
that promotes even air flow through the bed and a chamber filled with Bed Material or other
granular material.
If a small quantity of air flows through the air distributor into the Bed Material, it will pass
through the voids of an immobile mass of Bed Material. For low velocities, the air does not exert
much force on thebe Material particles and they remain in place. This condition is called a fixed
bed and is shown in Fig. 1B.
By increasing the air flow rate/velocity, the air exerts greater forces on the bed material and
reduces the contact forces between the bed material particles caused by gravity. By increasing
the airflow further, the drag forces on the particles will eventually counterbalance the
gravitational forces, and the bed material particles become suspended in the upward stream.
SECTION B PAGE 2
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Point where the bed starts to behave as a fluid is called as minimum fluidization condition.
Increase in bed height is insignificant when compared with the non-fluidized case (fig 1B).
As the airflow increases further, the bed becomes less uniform, bubbles of air start to form,
and the bed becomes violent. This is called a bubbling fluidized bed (BFB), shown in Fig. 1C. At
this stage the volume occupied by the air/solids mixture increases substantially.
By increasing the airflow further, the bubbles become larger and begin to coalesce; forming
large voids in the bed. This condition is called a turbulent Fluidized bed Fig. 1D
As the velocity of air is further increased (around 6 m/s), a condition is reached wherein the
whole of bed material is in circulation from furnace to a collection chamber (U beam hopper)
and back to furnace resulting in a uniform temperature profile throughout the furnace. Because
the whole bed is in continuous circulation internally, this boiler is called Internal
Recirculation Circulating Fluidized Bed Combustion (IR-CFBC) boiler as described in Fig
In circulating beds, more particles are blown from the bed than bubbling bed. The particles are
then collected back by a particle separator and recycled to the furnace. Residence time of the
particle is determined by the collection efficiency of the particle separator and the solids
circulation rate. As the result of the recirculation process, the effective particle residence time
greatly exceeds the gas residence time.
SECTION B PAGE 3
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
1 BOILER START UP
This chapter describes the boiler start up and load operation
During cold start up of the boiler, equipment should be sequentially started, as per
the requirements; the start up sequence may be as follows
• I.D. Fan
• P.A. Fan
• S.A. Fan
• Feed Water Pump (as per requirement)
• Start up burners
• Fuel handling system
• Fly ash handling system
• ESP
• LP & HP dosing system
• Bed material feeding system
• Bed ash drain system
1.1 START-UP OF A COLD BOILER
Boiler start-up can be termed as cold start-up when there is no pressure or when pressure is
less than 2 Kg/cm2 (g) in the steam drum.
In a cold start up, possibilities of some inspection or maintenance works having been done is
presumed. A walk down check is required and the boiler and its auxiliaries are to be prepared
meticulously for a start up from the control room. Before a walk down check ensure that all
work permits have been returned, safety tags are removed and permission from maintenance
department is available for boiler.
Sequence to be followed to bring the boiler into service during cold start up is as below.
SECTION B PAGE 4
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 5
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
ECONOMISER
• Verify the internal is clean and all the manholes are closed with proper sealing.
• Ensure drain and vents are kept in position as described below.
Description Tag No. Status
Top header vent ECO-1001/1002 Open
Drain valve of top header ECO-1005/1006 Closed
Drain valve of bottom header ECO-1003/1004 Closed
STEAM DRUM
Ensure that valves are kept in position as described below
Description Tag No. Status
Drum vent valve SD-1039/1040 Open
CBD line isolation valve ( near drum) CBD-1001 Open
Motorised CBD valve EM-1007 Close
CBD isolation valve CBD-1003 Close
CBD line sampling isolation valve SAM-1003 / 1004 Close
HP dosing line isolation valves HP-1025 Open
IBD line isolation valve ( near drum) IBD-1001 Open
Motorised IBD valve EM-1006 Close
IBD isolation valve IBD-1003 Close
All drains and vents of standpipes provided for level -
Close
transmitters, indicator & gauges
All root valves for instruments - Open
SECTION B PAGE 6
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SUPERHEATER SECTION
SECTION B PAGE 7
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 8
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Attemperator –I
Attemperator-1 control valve ( TCV) TCV-1010A Close
Temperature Control Valve (TCV) upstream motorised
EM-1013 Open
isolation valve
TCV downstream isolation valve DSH-1009 Open
Attempertion-1 control station drain valves DSH-1007/1008 Close
TCV bypass valve EM-1010B Close
Isolation valve at upstream of bypass valve DSH-1010 Open
Isolation valve at downstream of bypass valve DSH-1012 Open
Attemperator-II
Attemperator-II control valve ( TCV) TCV-1011A Close
Temperature Control Valve (TCV) upstream motorised
EM-1014 Open
isolation valve
TCV downstream isolation valve DSH-1019 Open
Attemperation-II control station drain valves DSH-1007/1008 Open
TCV bypass valve EM-1011B Close
Isolation valve at upstream of bypass valve DSH-1020 Close
Isolation valve at downstream of bypass valve DSH-1022 Open
All root valves for instruments - Open
SECTION B PAGE 9
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
START UP BURNER
• Verify that the igniters and burner fuel line flexible hoses are connected to the respective
nozzles properly.
• Verify power cables are connected to the igniters.
• Verify that the flame scanners are installed properly, cooling air hoses are connected and
valves are open.
• Verify that the air dampers at individual burners are at pre-set start-up position and air
supply to actuator is available.
• Verify physically in PLC/DCS that the fuel shutoff valves are fully closed.
• Spark gap is set at 2-3 mm. Gap between the burner tip to the swirler must be maintained as
per the drawing.
• Check the operation of gun forward and retract movement.
• Gun nozzles are clean without any blockages.
SECTION B PAGE 10
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
NOTE:
a. Manual operated fuel isolating valves are to be verified for shut. These valves have to be
opened just before firing.
b. All root valves for instruments should be open.
SECTION B PAGE 11
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 12
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Bed material rotary feeder outlet slide gate valve SG-1012/1013 Open
SECTION B PAGE 13
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 14
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 15
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
• Switch ON the ash handling system below the hopper prior to solid fuel firing.
• Ensure all access doors are closed with proper sealing rope to avoid air infiltration.
• Access door mechanical key close interlock is activated.
Note: Refer ESP supplier’s manual for safe operation detail.
GENERAL CHECKLIST
• Ensure that the battery limit valves are open and the inputs are available
• Ensure availability of instrument air and service air at rated pressure.
• Ensure all the measuring and monitoring instruments are installed at position.
• Ensure that all the measuring and monitoring instruments root valves are open.
• Availability of sufficient quantity of feed water as per recommended quality
• Power up the feeders at MCC.
• Availability of LDO up to terminal point isolation valve.
• Ensure cooling water supply to the various equipments.
• Fuel bunker is filled up with specified fuel.
• Bed material and limestone bunker is filled with specified quality of material
• Availability of initial filling and makeup bed material.
• Availability of chemical for feed and boiler water treatment.
• Availability of lubricants for normal operation.
• Ash handling system is ready for normal operation.
It is recommended to use specified quality of feed water through the filling line for initial water
filling of the boiler.
Before filling water into boiler ensure following drain & vent position as described below.
SECTION B PAGE 16
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
PROCEDURE
• Ensure feed water for boiler fill up is available at boiler filling line.
• Open the filling line isolation valve (FD-1015) and fill up the boiler.
• Water will start flowing from all bottom headers and starts rising in boiler & economiser.
• Close economiser top header vent valve as soon as free flow of water start coming out and
air is expelled completely.
• Keep vigilance and allow water to fill in steam drum up to 30% drum level (NWL = 25 mm
above drum center line).
• Close filling line isolation valves (FD-1015) and all the downcomer drain valves
(FD-1001 to FD-1008) and economiser bottom header drain valves (ECO-1003/1004).
SECTION B PAGE 17
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Caution:
While filling the water care should be taken to maintain the metal temperature
above 21°C to avoid brittle fracture, hence the water temperature must be
maintained to meet this requirement.
SECTION B PAGE 18
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
• Verify furnace DPT purging shut off valve (UV-1041) open automatically through logic.
• PA air flow to wind box to be adjusted by wind box damper (FCV-1026A/B) as per
process requirement.
SECTION B PAGE 19
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Pre-Requisites
• Ensure that the bed is empty without any bed material.
• Verify the bubble cap for any physical damages or any blockages and replace the damaged
bubble cap if any and clear the blockage by pinning.
• Verify the floor panel seal welding for any cracks /damage and rectify the defect if any.
• Ensure that the manhole doors / inspection doors are properly secured and tightened on the
air / gas ducting.
Procedure
• Start ID & PA fans as per the fan startup procedures.
• Maintain furnace draft of – 5 mmH2O by modulating ID fan I/L damper or ID fan speed
through VFD.
• Note down the windbox pressure and bubble cap cold dP corresponding to 45%,60 %
,75% and 100 % MCR PA Fan air flow.
SECTION B PAGE 20
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Note: Bed material size and chemical property must be maintained strictly as per the
specification for smooth start up and efficient operation. (Refer section A)
Procedure:
• Ensure specified bed material is filled in bed material bunker.
• Start the ID fan as per fan start-up procedure (refer section 1.1.4)
• Adjust the furnace pressure to –2 to – 4mmH2O.
• Start PA fan as per fan start-up procedure (refer section 1.1.4)
• Maintain the PA air flow to windbox (35.5 TPH) sufficient enough to fluidize by adjusting PA
fan speed through VFD and spread bed material uniformly in the entire combustor.
• Open DCF outlet KGV (UV-1031/1032/1033). DCF may be operated if required.
• Ensure the isolation gate above (SG-1010/1011) and below (SG-1012/1013) the rotary feeder
are open.
• Switch ON the rotary feeders at bed material bunker outlet and operate at minimum speed
and start filling the bed material to the furnace.
• Bed material filling should be done in batches; it should not be in one stretch as it may cause
accumulation of material at the drop point and restrict the fluidisation of bed material and
spreading.
• Bed material shall be filled up-to 600 mm heights above the bubble cap, which is to be verified
physically.
• Prior to confirm the bed height, it is recommended to fluidize the bed thoroughly to spread the
material uniformly. Adjust the PA air flow suitably to ensure uniform distribution of the bed
materials evenly across the combustor.
• Record the minimum fluidization windbox pressure, lower dP and PA air flow as these are the
guiding parameter during cold startups.
WARNING
If the bubble caps are not cleaned properly, fluidization may affect and back shifting of bed
material into windbox and erosion of bubble cap at the vicinity of choked bubble caps.
SECTION B PAGE 21
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 22
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
FURNACE PURGING
• Whenever the Pre interlocks are satisfied, the system is “Ready for purging” and is
indicated by the glow of lamp “Purge ready to start”.
• For purging, maintain PA air flow as per the minimum fluidisation (established during bed
material filling) or > 45% of the max PA air flow (>45.6 TPH) whichever is higher and SA
air flow > 30% of the max SA air flow (>33.6 TPH) by adjusting the fan speed /damper
opening.
• Initiate the purge start from DCS. At this stage “Purge in progress” indication will appear.
After the pre set time i.e. 5 mins, purge complete indication will appear.
• After completion of purging windbox air sleeve damper moves to start up position.
• Normalize the PA & SA air flow for burner start up.
MFT Reset:
On completion of purging all conditions for MFT (refer vol. 3 BMS logic) need to be satisfied for
MFT Relay to be reset.
OIL FIRING
With MFT Reset, permissive shall be available for start the oil burner.
• Open main fuel shut off valve (UV-1070) and set the oil flow control valve (FCV-1078) to the
start up position (to be determined during commissioning/burner trials).
• Whenever Main fuel control valve /shut off valve opens, short recirculation valve (if
provided) closes & oil circulation starts through long recirculation line.
• “Burner ready to start” indication will appear. Initiate burner start command to the
selected burner.
• Whenever the burner start command is initiated the following actions takes place.
Oil gun of the respective burner goes to insert position (Firing Position).
Burner Atomising Air valve (UV-1072A) for that burner opens.
Igniter of the respective burner goes to the insert position.
With igniter insert position proved, igniter is energised for spark generation.
Igniter will be in energized condition for 15 sec.
Selected burner shut off valve will open & Oil re-circulation valve will be closed. (Once
first burner is established, the re-circulation valve will continue to remain close)
• Main flame will be established & “Burner-on” indication will be generated.
• Stabilise the burner operation & adjust the oil firing rate as per requirement.
• Number of burners operation can be decided as per requirement.
SECTION B PAGE 23
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
CAUTION:
If the burner fails to light up, find out the cause of failure. Do not attempt repeatedly
to light up the burner unless the fault is established. Repeated failures in lighting of
the burner may cause accumulation of un-burnt fuel and make a threat of explosion.
BOILER PRESSURING
• Increase the burner oil pressure by increasing oil flow after burner light up, according to the
pressurizing curve.
• Maintain the furnace pressure around -3 to –5 mmH2O and normal water level in drum.
• Whenever the steam drum pressure reaches about 2kg/cm2, close the steam drum vent
valve (SD-1039/1040).
• Whenever the pressure reaches to 3kg/cm2 close the superheater header drain valves (DR-
1009/EM-1040/Dr-1011/EM-1041/DM-1013/EM-1042) & wing wall drain valves
(DR-1005/EM-1045/DR-1007/EM-1046).
• Intermittently fluidize the bed at regular intervals, so as to avoid over heating of bed
material.
• Along with the boiler pressurization raise the bed temperature gradually.
CAUTION:
• Firing rate to be adjusted in such a way to maintain the flue gas temperature
at “U” beam inlet at 450ºC till 20% of MCR.
• Monitor and maintain the steam drum metal differential temperature
at 25°C by modulating the firing rate.
SECTION B PAGE 24
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 25
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
• Raise the drum pressure upto rated pressure in accordance with the enclosed boiler cold start
up pressure raising curve.
• Adjust the fuel feed rate, primary and secondary air flow according to the fuel firing rate to
maintain the boiler outlet pressure and bed temperature.
• For lignite firing follow the above procedure.
SECTION B PAGE 26
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
CAUTION:
• Once the coal/lignite/petcoke firing is initiated there will be a sharp rise in the bed
temperature, should be controlled by reducing the over bed burner oil flow and increasing the
primary air flow suitably.
• Monitor the O2 level leaving the economiser carefully during coal/lignite/petcoke firing, it
should not be allowed to drop below 6%. If the O2 level falls below 6%, do not continue to
increase the main fuel feeding rate. Instead, increase the primary air to the bed slightly.
Furnace draft controls should have been tuned to maintain furnace draft to set point, and it is
recommended that the draft controls to be in auto mode, if the draft controls not be in auto,
adjust the ID fan dampers/speed to maintain furnace draft set point. Once the forced draft air
supply has been increased and furnace draft adjusted, main fuel feed rate can be increased
and continue with the monitoring of the O2 level. Adjust the OFA flow and ID fan speed to
maintain the acceptable O2 level in the flue gas.
• Maintain normal water level in the drum.
• Boiler pressure to be raised in accordance with boiler cold start up curve.
• Start-up vent valve (EM-1018) should be in full open condition during pressure rising and till
the steady flow of steam from the boiler.
• Immediately after stabilising the coal/lignite/petcoke firing, operate all the bed drain valves
intermittently to avoid choking of bed drain pipes due to gas condensation and clinker
formation at bed drain mouth.
• Firing rate to be adjusted in such a way to maintain the flue gas temperature at “U” beam
inlet at 480ºC till 20% of MCR steam flow is established.
• Monitor and maintain the steam drum metal differential temperature at 25°C by modulating
the firing rate.
SECTION B PAGE 27
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 28
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
2 LOAD OPERATION
Mode of Operation:
During low load operation i.e. < 60% MCR, the boiler operation may be semi CFBC mode.
Along with the increase in load i.e.> 60% MCR, the combustion mode shifts to CFBC mode.
Once the boiler load reaches above 60% MCR, switchover the following controlls in
automatic control mode
• PA & SA APH outlet pressure
• PA flow to windbox
• OFA flow to furnace
Once all above loops are stabilized take coal flow in auto mode.
CAUTION:
While loading the boiler following conditions are to be ensured to achieve the desired output;
Input:
• Ensure the fuel being fired is as per the design specification i.e. coal size distribution,
proximate & ultimate analysis.
• Adequate quantity of specified bed material /inert should be available, sieve size
distribution and bulk density must be as per design specification.
• Adequate quantity of specified feed water & fuel should be available.
SECTION B PAGE 29
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Fuel
Quality of fuel is to be maintained to ensure availability and efficiency of the boiler.
Hence, it is essential to maintain the fuel as per the design limits. Following needs to
be monitored during operation.
♦ Fuel sieve analysis
♦ Fuel moisture
♦ Presence of shale and stones
♦ Heat value
♦ Ash content in fuel
Bed material
For CFBC boiler operation bed material plays an important role as it is responsible for
maintaining the furnace shaft dP and temperatures as per steam flow demand.
Following to be monitored & maintained during operation:
♦ Sieve size distribution
♦ Chemical properties
♦ Bulk density
♦ Fusion temperature
♦ Iron content
Steady state operation and control philosophy
The intend of this write-up is to guide /enable the boiler operator to apply the control
principles described herein to specific cases characterized by peculiar fuel and sorbent
properties, equipment and measurement/control systems configurations. The steady state
operation control philosophy described herein is to limited specific areas.
SECTION B PAGE 30
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
The controlled variable is the bed (primary zone/lower furnace) temperature. Bed temperature
is controlled primarily by manipulating the furnace operating parameter viz. shaft differential
pressure/upper dP (DPT-1049 A/B) primary air ratio (PAR - fraction of the primary air in the
total combustion air) and excess air.
Bed temperature and primary air flow changes with the boiler load, hence the temperature
control method varies depending on load as mentioned below;
a) The shaft differential pressure and primary air ratio are the main parameters controlling
the lower furnace temperature in this load range.
b) An increase in the shaft dP/upper dP will increase the heat transfer thereby reducing
furnace temperature. However low shaft dP/upper dP will decrease the heat transfer
thereby increase in furnace temperatures.
The required shaft dP/upper dP is adjusted if the lower furnace temperature deviates
from its target value. Shaft dP/ upper dP is increased when the lower furnace
temperature is above its target value and decreased in the opposite case.
Shaft dP/upper dP cannot be increased when middle dP/ Furnace primary zone dP (DPT-
1048A/B) or windbox pressure (PT-1026) are at or above their maximum limits.
Shaft dP/upper dP is increased by increasing multiclone dust collector (MDC) ash recycle
RAV (M-1049A/1049B) speed provided at each MDC ash hopper discharge.
The MDC recycle increases the solid inventory to the furnace thereby retaining more
circulating material in the CFB system. It also reduces the overflow of solids from the
MDC hoppers.
When burning fuels with low solids input (e.g. low-ash coal) or incase of abnormally low
MDC efficiency (worn out collection elements), Shaft dP/upper dP control via MDC
recycle control might not be possible, during such situations make-up bed material to be
feed to maintain the required Shaft dP/ upper dP (see make-up material control below).
In case of Shaft dP/ upper dP decrease the opposite actions are taken.
SECTION B PAGE 31
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
c) If the primary zone temperature cannot be controlled by the MDC recycle rate within the
limits of the shaft dP /upper dP, or when MDC recycle and/or make-up rate is limited,
use one or a combination of the following means to bring the primary zone temperature
to the desired range:
Increasing primary air ratio results in MDC recycle and shaft dP/upper dP increase
which enhances the heat transfer in the furnace shaft and reduces the primary zone
temperature. The reverse is also true.
The range of primary air ratio and the rate of change of primary air ratio are limited
by middle dP/ Furnace primary zone dP (DPT-1048A/B), primary air ratio cannot be
increased when middle dP/ Furnace primary zone dP is at its minimum limit, and
cannot be decreased when middle dP/ Furnace primary zone dP is at its maximum
limit.
The effect of PRIMARY AIR RATIO on the primary zone temperature may be
enhanced or mitigated by its influence on the fuel burnout distribution. For some
fuels a PRIMARY AIR RATIO increase tends to increase the primary zone
temperature due to the increase of fuel burnout in the lower furnace prevailing over
the diluting effect of greater primary air flow. For other fuels the opposite is true.
Other areas affected by changing PRIMARY AIR RATIO include NO, and CO
emissions, carbon utilization and CO burnout in the U-beams. The result of a
PRIMARY AIR RATIO change is fuel specific and needs to be determined
during the boiler tuning. Changes of PRIMARY AIR RATIO should be done
slowly and within a limited range.
SECTION B PAGE 32
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
100
Total PA fan air
80 flow
60
Total SA fan air
flow
40
20
0
0 10 20 30 40 50 60 70 80 90 100
Steam Flow (%)
140
120
20
0
0 10 20 30 40 50 60 70 80 90 100
Steam Flow (%)
Total PA fan air flow
SECTION B PAGE 33
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
140
120
100
80
0
0 10 20 30 40 50 60 70 80 90 100
Steam Flow (%)
Note: This is an indicative curve may change during operation based on fuel being fire and
operating condition.
Changing the fuel feed rate is an emergency short term means to prevent
temperature excursions in the primary zone and will cause a subsequent load
change.
The effect of fuel feed rate change on the lower furnace temperature also depends
on the type of fuel. When low-reactivity fuels are burned (like anthracite or Petcoke)
and the carbon content in the primary zone is high, the response of the temperature
to the fuel feed rate is slow. In this case changing of the fuel feed rate is not
effective for a short term temperature control. Higher reactivity solid fuels, such as
coals and lignite, which have more volatile content that burns quickly, will result
greater short term fuel feed rate change effect on the lower furnace temperature.
Changing of the bed particle size is a long term means used to change both the
furnace temperature and pressure differential.
The effects of the particle size distribution of circulating solids are explained as
below.
SECTION B PAGE 34
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
In addition to the quantity of solids in the furnace, the size of the particles also has a
significant impact on furnace heat transfer. In general, the finer the particles, the
higher the heat transfer rate. Typically, the mean size of the particles in the lower
furnace is from 250 to 350 microns and the mean size in the upper furnace is from
100 to 200 microns.
For the furnace of a CFB boiler to operate properly, the quantity of particles as well
as the size of the particles in the furnace must match the design values. If the
quantity of solids in the furnace is less than the design value, or if the size of the
particles is too coarse, the furnace operating temperature will exceed the design
value, and it will be necessary to limit boiler load to maintain the furnace
temperatures to within their design values.
The quantity of particles or solids in the furnace is measured by the gas side
pressure drop of the middle dP/ Furnace primary zone dP and shaft dP/ Upper dP. It
is also necessary to achieve the proper split between the lower bed pressure drop
and the shaft pressure drop.
A higher content of smaller particles in circulating solids results in the higher furnace
heat transfer and lower furnace temperature.
Bed particle size distribution change may be effected by modifying the sieve size for
fuel feed, sorbent (limestone), fresh inert bed material (crushed refractory) and
recycle bed ash feed to the boiler. Bed particle size distribution can also be changed
by rate of MDC ash recycle and bed drain.
SECTION B PAGE 35
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
The control strategy is similar to that for 70-100% MCR load range with addition of excess
air (EA) as a means of the lower furnace temperature control.
With load decrease, the influence of the shaft dP/ Upper dP (and its controlling variables)
reduces, due to overall reduction of solids circulation rate. Excess air and primary air ratio
are increased as load is reduced below 70% MCR to control the lower furnace temperature
through the effect of dilution and to maintain furnace solids circulation and heat transfer to
furnace surface at lower loads. MDC recycle plays a lesser role at lower loads as a
controlling variable.
Shaft dP/ Upper dP, excess air (EA) and primary air ratio targets for the boiler load range
are established during process tuning taking into consideration of lower furnace
temperature, solids inventory control, superheater temperature control requirements and
emission limits. These parameter may be adjusted automatically or maintain by the operator
within the established limits.
Considerations for using the fuel feed rate and bed particle size for lower furnace
temperature control are similar to those described above for the 70 to 100 % load
operation.
The following describes the role of the major controlling variables during partial load
operation:
If the minimum MDC Recycle rate limit is reached, other controls i.e. primary air ratio,
excess air should takeover. Below 50% load MDC Recycle feed rate is limited hence lower
furnace temperature is controlled by primary air ratio and excess air.
SECTION B PAGE 36
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
air ratio for the primary zone temperature control are limited due to effects of primary air
ratio on carbon utilization, NOx, and CO emissions, and solids inventory in the primary zone.
The allowable span of the primary air ratio adjustment for the temperature control within
the boiler load range is determined during boiler commissioning tuning.
Note:
• During part load operations combustion control may have to be operated in manual
mode
• At any given time the primary air should not be reduced below purge air requirement.
Bubble cap dP should be always above 260 mmH2O
• O2% in flue gas must be maintained as recommended.
• Total air (PA + SA) flow should not be reduced below the minimum air flow at any point
of time after coal firing.
• In case of sudden bed temperature rise, reduce the coal feed rate to control the bed
temperature till the temperature become normal. The coal flow will be reduced
automatically through the drive logic if the controls are in automatic mode. Rate of fuel
flow change may be decided at site as per the operating conditions.
• While firing multiple fuels if the fuel configuration change happens there will be bed
temperature fluctuation hence the fuel configuration must be in a control manner to
avoid such situations.
SECTION B PAGE 37
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
12.00 O2 Level
10.00
8.00
6.00
4.00
2.00
0.00
0 10 15 20 30 40 50 60 70 80 90 100
Steam Flow in %
12.00 O2 Level
10.00
8.00
6.00
4.00
2.00
0.00
0 10 15 20 30 40 50 60 70 80 90 100
Steam Flow in %
SECTION B PAGE 38
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
12.00 O2 Level
10.00
8.00
6.00
4.00
2.00
0.00
0 10 15 20 30 40 50 60 70 80 90 100
Steam Flow in %
Note: This is an indicative curve may change during operation based on fuel being fire and
operating condition
a) Total solids inventory built-up in the furnace is depend on the following factors:
SECTION B PAGE 39
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Solids feed size distribution and attrition / decrepitating properties which determine the
size distribution of particles over their time of residence in the CFB process.
Coarse and fine circulating particles form most of the circulating inventory. Coarse
circulating particles (>300 microns) are collected completely by U-beams, and leave the
system with the bed drain only. Fine circulating particles (<300 microns) passing through
U-beams are completely collected by the MDC and leave the system with the bed drain
and MDC ash hopper purge.
Fine particles that are essentially not collected by U-beams are collected by the MDC and
are not retained in the dense bed. Fine particles 70 - 100 microns (normally) & 100-150
microns (occasionally) leave the system through the MDC ash hopper purge and exit with
the gases leaving the MDC.
c) During steady state conditions the amount and size distribution of solids fed and then
transformed in the CFB process are balanced with solids losses.
The following governs distribution of solids flows within the system and solid losses:
The solids flow at U-beam inlet is maintained for the furnace temperature control.
The inventory of coarse particles in the primary zone is controlled by the bed drain rate.
When no bed drain recovery/recycle is provided, useful solids particles are drained
through the bed drain together with coarse particles. A certain minimum bed drain rate is
needed for most fuels to insure purging of the oversized bed material that includes shales
and stones to maintain the bed bulk density 1000 - 1100 Kg/m3 and lower furnace dP/
middle dP/ Furnace primary zone dP.
SECTION B PAGE 40
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Flow and size distribution of solids passing the U-beams depend on the solids flow at the
U-beam inlet and the U-beam efficiency. This solids stream consists of fine particles and
fine circulating particles not collected by the U-beams.
Fine circulating particles and some of the fines are collected by MDC. When the solids
inventory in MDC hoppers increases to the high level, the excess quantity including both
the fine circulating and fine particles, is lost through the MDC ash hopper drain. The fine
circulating particles that are recycled back to the furnace leave the system through the
bed drain.
If the inventory/solids generation in the boiler is lower than required and to make up the
losses while burning fuels with low solids (e.g. low-ash and low-sulfur coal), addition of a
make-up material (limestone, crushed refractory) may be required to maintain the solids
inventory for CFB unit operation. To reduce the amount of the fresh makeup material, bed
ash & fly ash recycle system may be used depends upon the quality of ash material. With
bed ash and fly ash recycle arrangement, no useful solids will be lost from the system
except the ash that is leaving MDC to ESP.
SECTION B PAGE 41
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 42
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
interrelated with the inventory in MDC hoppers. For example, when MDC recycle is
increased to increase Shaft dP/Upper dP, according to the lower furnace temperature
control, the solids are transferred from MDC hoppers to the furnace. When MDC recycle
is reduced to decrease Shaft dP/Upper dP, the inventory is not recycle to the furnace
then it will be collected in the MDC hopper whenever the hopper level is above its high
limit will be purge out through the overflow.
When primary air ratio and/or excess air is increased, it results in transfer of some
solids inventory from the primary zone to upper zone. Subsequently, the solids flow at
the U-beam inlet increases thus increase the furnace heat transfer and reduce the
furnace temperature to some extent.
Also middle dP/ Furnace primary zone dP shall not be above 800 mmH2O at full load.
The middle dP/ Furnace primary zone target dP and maximum dP values are
established as functions of boiler load and normally increase with the load reduction as
well as consideration of reduction/ optimization of the primary air fan power
consumption established during boiler tuning.
SECTION B PAGE 43
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
900
Bubble Cap dP (mmwc); Furnace Primary Zone dP
800
(mmwc);Upper Furnace/Shaft dP (mmwc)
Furnace Primary
700
Zone dP
600
500
400
Bubble Cap dP
300
0
10 20 30 40 50 60 70 80 90 100
Load (%)
Note: This is an indicative curve may change during operation based on fuel being fire and
operating condition
SECTION B PAGE 44
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Manual Mode: In manual mode of operation, each valve of the ash cooler has to be
operated individually using their respective Open Push button in a sequence. All ash
cooler valves (except Bed drain valve) remain open for a preset time and closes
automatically after the timer is elapsed. The protection interlocks are in line during
manual mode of operation.
Semi Automatic Mode: In Semi Automatic Mode, each valve of the ash cooler operates
in automatic predetermined sequence. However the start of the sequence shall be
triggered individually using their respective cooler sequence command from DCS.
Automatic Mode: In Automatic Mode, each valve of the ash cooler operates in
automatic predetermined sequence. However the start of the sequence shall be
triggered through preset middle dp/Furnace primary zone dP.
SECTION B PAGE 45
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Controlled feeding of inventory from MDC to furnace as per the bed temperature and
Shaft dP/Upper dP.
Prior to initiate the MDC recycle system lineup the dampers & valve as described in walk-
down checks section 1.1.2.
OPERATIONAL SEQUENCE
• PA hot air inlet damper UV-1060 will open in auto when SA fan starts.
• Maintain PA air pressure at airslider, 200-250mmWC more than wind box pressure
• Open the MDC RAV inlet KGV (UV-1061A/1062A).
• Start corresponding MDC RAV.
• Ash will start sliding into the furnace via airslide. Monitor airslide skin
temperature.
• Run MDC RAV as per boiler load requirement.
• Monitor and maintain the bed temperature and main steam pressure as per load
condition.
MDC recycle is controlled by changing the speed of RAV installed at the MDC hoppers
discharge. A target MDC recycle value, preset as a function of boiler load, is adjusted
by demand to provide a set point for the recycle RAV control.
i) MDC recycle shall not exceed its maximum limit, except for a limited time (not longer
than a predetermined period) if needed for the control purposes. The value of the
maximum limit is determined based on process performance requirements (heat
transfer, combustion efficiency and sorbent utilization) and an acceptable erosion rate
of convection heating surfaces which depends on the solids loading in flue gases. After
a predetermined time limit is reached, MDC recycle shall be ramped down to its
maximum limit, and other means of the bed temperature control shall be employed.
ii) MDC recycle shall not be below its minimum limit, which is a preset empirical
function of boiler load. The minimum limit is established based on combustion/sorbent
utilization considerations. This limit is applied only when MDC hopper level is at or
above its high limit i.e. MDC solids are being purged.
iii) MDC recycle cannot be increased when middle dP/ Furnace primary zone dP or Total
dP are at their respective maximum level and it cannot be decreased when middle dP/
Furnace primary zone dP is at or below its minimum limit.
iv) MDC recycle is reduced when MDC hopper level is at or below its low limit. In this
case MDC recycle is actually controlled by the requirements of the MDC hopper level
control.
SECTION B PAGE 46
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
v) MDC recycle shall be stopped if MDC hopper level reaches its “Low-Low" value. In
such a case the operator would be required to reduce boiler load or feed bed inventory
from the make-up bunker and take measures to correct this abnormal condition.
Caution:
Do not allow wet / moist ash to enter airslide.
In case of tube failure, isolate the MDC outlet RAV immediately and drain
the ash through the bypass arrangement.
If Low-Low level occurs, the corresponding MDC RAV will trip and the addition of make-
up material is needed to maintain the furnace inventory at the target level. The
addition of make-up material should bring Shaft dP/Upper shaft dP to the required level
with MDC hopper level not exceeding its high limit, i.e. no solids are purged from MDC
hopper. In this case MDC hopper level is maintain between its high and low limits by
balancing the make-up material flow rate (feed from inert bed silo and/or adjustment
to limestone feed rate) and bed drain flow, while maintaining the desirable Shaft
dP/Upper shaft dP value. In certain cases the transition to the make-up feed mode can
be avoided by changing limestone size distribution/properties or coal size distribution
(mainly, for high-ash coals). In this case, the input of circulating particles shall be
increased, and inputs of coarse and fine particles shall be reduced.
The inert bed silo should be maintained in as full status as possible by storing recycle
from bed drain material (classified and/or sieved). If solids input to the silo with all
recycled streams is less than the make-up requirement the silo is to be filled with solids
from some external source, e.g. with purchased bed material with the proper physical
and chemical properties, to provide continued supply of material needed for adequate
furnace inventory control.
SECTION B PAGE 47
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
While limestone feed rate affects overall solids inventory, and thus can be used as a
means for solids inventory control, such a use is generally discouraged. This is due to
typically higher cost and lesser effect on the solids inventory than that of properly sized
spent bed material or sand. Another potentially detrimental impact of overfeeding
limestone on boiler performance is its catalyzing effect on oxidizing nitrogen
compounds released with fuel volatiles to NOx.
Bed material size and distribution of particles of different sizes in a CFB system depend
on:
1) Fuel, limestone and make up Bed material size distribution and attrition
characteristics.
For low ash coal and Petcoke, the fuel size distribution may not have a strong
effect on the size of circulating bed material. Fuel sizing may affect the content
of oversized particles (shale’s & stones) in the dense bed.
For high ash coal, the coal ash makes up a considerable part of the circulating
inventory as well as non-entrainable particles. In this case, coal sizing may
strongly influence the bed particle size distribution.
Limestone size distribution has a major effect on the inventory size for low ash
coals and Petcoke.
Inert make-up material sizing has a major effect when the make-up is needed
for the inventory control.
SECTION B PAGE 48
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 49
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 50
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
• Fill the deaerator slowly through the makeup water inlet connection by opening the
deaerator level control valve. Watch the water level in the level gauges and ensure that
the gauges are indicating the correct water level. Cross check with the level indication
available at control room through the level transmitter. Stop the water supply to the
deaerator when normal water level has reached.
• Charge the steam up to the pressure control valve to warm up the line and keep the
steam readily available for charging into deaerator. Once, water level has attained NWL,
slowly admit the steam into deaerator through the pegging steam line. Whenever the
water temperature reaches 60 to 70 0C, deaerator is ready for charging the steam
through main supply line.
• Maintain the level before admitting the steam through the main supply line. Level may
be maintained well above the very low level and below the center line of the tank. Due
to direct scrubbing of steam with warm or cold water there may be little hammering or
vibration in the storage tank. By keeping the low water level, quantity of water in the
storage tank will be less and less steam will be required initially to heat it. Thus vibration
or hammering can be reduced while pressurizing the deaerator. Keeping low water level
will have to be done manually watching the level in the direct level gauge and by
maintaining the water intake manually, as the level transmitter will be out of its range.
• Charge steam gradually by opening the pressure control valve, water will be heated up
and steam will start coming out of the vent. Whenever the steam vapour start flows
increase the steam flow (slowly) and maintain the pressure as per the desired value.
• Along with steam, increase water flow simultaneously but gradually. Objective is to
maintain Normal Water Level and to increase deaerator pressure up to the required
SECTION B PAGE 51
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Prior to passing the process samples through the sample coolers ensure specified quality
of cooling water at rated pressure is circulated through the sample coolers.
Before start of the boiler, ensure the dosing systems valves are lined up as per “System
Line up procedure”. Also ensure that pump suction filters are clean.
Prepare recommended concentration solution of Trisodium Phosphate (5%) in HP. &
Hydrazine solution in LP Dosing tank.
Start the dosing pumps and adjust the dosing rate based on water analysis report, aim is
to maintain recommended water chemistry in feed & boiler water. Operate tank stirrer
periodically.
Refer supplier instruction manuals for safe operation and maintenance of
dosing system.
Caution: Whenever dosing is to be stopped, flush the dosing piping upto steam
drum and deaerator by pumping fresh water for cleaning the pump internals
and piping.
SECTION B PAGE 52
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 53
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Bed Ash cooler sequence will be initiated in auto mode based on the middle shaft dP set
point. Number of cooler in operation shall be selected by the operator. Cooler can be
selected for manual operation as per the operator convenience.
Prior to initiate the bed ash cooler sequence lineup the dampers & valves as described in
walk-down checks section 1.1.2.
Note:
For detail Bed Ash Cooler logic and write-up, refer Volume-3
MANUAL OPERATION
While initiating the cooler Manual operation following sequence is to be followed:
• Open Cooling Air Valve (UV-1051/1054/1057) to BAC (Secondary air from SA fan). This
valve will close after cooling cycle time of 25 minutes. (Will be set during
commissioning).
• To open cooling valve, following interlocks shall be satisfied.
a. Close PB for cooling valve is not actuated
b. Manual mode is selected.
• When Cooling Air Valve ‘Open Feedback’ is available, open bed ash drain valve
(LCV-1050/1053/1056). To open bed ash drain valve, following interlocks shall be
satisfied.
a. Cooling air valve is open.
b. Furnace drain valve close P.B. (HSC-1051) is not operated.
c. Manual mode is selected (HAS-1051).
d. Ash cooler bed level not high.
e. Emergency Stop not operated
• Regulating Furnace drain valve (LCV-1050/1053/1056) shall be opened in three steps,
First 15 sec at 100% opening then next 15 sec at 30% opening and further 15 seconds
at 100% opening. (will be set during commissioning).
• Bed drain valve will close after a specified third pulse timer (15 sec, will be set during
commissioning).
• Since the cooling air valve is in open condition, bed ash inside cooler will be cooled.
• Whenever the ash temperature is dropped safe enough for disposal (<160 °C), ash
cooler drain line KGV (UV-1052/1055/1058) should be opened to dump the ash to the
SECTION B PAGE 54
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
handling system. This valve close after a specified time interval (2mins). To open cooler
drain valve, following interlocks shall be satisfied.
a. Manual mode is selected
b. Furnace drain is closed and cooling air valve open
c. Ash cooler temperature is less than 160°C.
d. Ash cooler drain valve close P.B. not operated.
e. Ash cooler bed level not low
f. Emergency stop not operated.
• Once the bed draining from the cooler is completed the cooling air valve will close.
NOTE:
1. Ensure the ash handling system is lined up and in healthy operating conditions.
AUTO OPERATION
Bed drain and bed ash cooling sequence will initiate automatically to maintain the following
conditions:
• Middle dP/ Furnace primary zone dP set point (760 mmH2O - Set during commissioning
trials)
NOTE:
1. Operator to select the coolers to be operated in auto mode as per process
requirement.
2. Ensure the ash handling system is lined up and in healthy operating conditions.
SECTION B PAGE 55
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
• Bed drain valve will close after a specified third pulse timer (15 sec, will be set during
commissioning).
• Cooling air to ash cooler damper remains open till the ash temperature drops to desired
limit.
• Whenever the ash temperature drops to safe disposal limit (<160 Deg°C), ash cooler
KGV (UV-1052/1055/1058) opens automatically to dump the ash to the handling system.
This valve closes after a specified time interval 2 mins. (Will be set during
commissioning).
• Once the bed ash draining from the cooler is completed the cooling air valve
(UV-1051/1054/1057) will close.
• The entire bed ash cooling system will be operated from the DCS in sequence on
selection of BAC and auto-start command.
SEMI-AUTO SEQUENCE
In semi auto mode operator to initiate bed drain and cooling sequence start command
instead of auto-start command through logic and the sequence will be completed through
auto logic.
CAUTION
• Do not open Access doors on the bed drain system unless it is isolated and
depressurized
• Ensure the evacuation of ash from the Ash cooler outlet duct swirler and APH ash
hopper regularly, failing may cause mal operation/ non operation of ash cooler.
Above system will be operated only when imported coal is fired. However the system has the
flexibility to capture bed ash while firing Lignite, which can be stored and utilized as and when
required.
The operation of the system is quite simple. In level probe mode, level sensing probe provided
in the product buffer / reject buffer hopper above transfer vessel shall sense the presence of
material in the hopper and initiate the conveying cycles. Dome valve shall open and allow the
material to gravitate into the transfer vessel for a preset time & then close automatically. On
closure of dome valve, its seal get inflated and signals the conveying air injection into the
transfer vessel. The vessel gets pressurized and material resistance help pressure build up and
SECTION B PAGE 56
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
conveys the material through steel piping to the destination silo. When conveying is completed,
the pressure drops down and is sensed by the control system, the air supply to the system is
stopped and the cycle is completed. The transfer vessel is ready for the next cycle.
The total system is made automatic by use of level probe in destination silo to control the
transfer of material. Complete system is flexible enough and programmable and automatically
operated through a PLC based central control panel.
OPERATION
During imported coal firing diverter valves will be operated to pass the ash in to the Feed Bin.
Same shall be operated by level switch contact through PLC. At any time flow from only 2
conveying lines will be diverted to the intermediate silo.
Ash flow to the intermediate silo will continue till the intermediate silo level reaches high. When
intermediate silo level reaches high, ash entering to the intermediate silo has to be stopped and
will be taken in to the bed ash silo.
Start permissive will be provided to RAV & vibrating screen, based on the intermediate silo level
and fresh bed material make-up silo level healthy. Standby system can be started by operator in
case of problem in the working system. Thus 500 micron size bed ash is collected in the Product
buffer hopper.
Pneumatic conveying of the ash from buffer hopper will be controlled based on the level high
signal from the buffer hopper & will continues till the fresh bed material make-up silo level
reaches high. Fresh bed material make-up silo high level trip is provided to trip the rotary
feeder below the intermediate silo, vibrating screen & ash conveying vessel.
Pneumatic conveying of the ash from Reject Hopper will be controlled based on the level high
signal from the Reject Hopper & will continue till the bed ash silo level reaches high.
SECTION B PAGE 57
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
4 CONTROLS
Boiler is provided with various controls to ensure safe, efficient and reliable operation of the
plant. This section provides brief description of various control loops, for detail refer vol-3
section under control schematic narrative.
Following are the major control loops employed in the boiler plant operation;
• FURNACE PRESSURE
• DRUM LEVEL
• S.H. STEAM TEMPERATURE
• AUTO COMBUSTION
• EXCESS AIR CONTROL
• BED LEVEL CONTROL
• BED TEMPERATURE CONTROL
• U-BEAM TEMPERATURE CONTROL
• PRIMARY AIRFLOW CONTROL
• OFA FLOW CONTROL
Caution: Though the controls monitor the operation in auto mode, control room
operator must be alert and vouch for any upset and disturbances in the process to
save the boiler from tripping and damage.
SECTION B PAGE 58
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 59
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 60
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
4 EMISSION CONTROL
To control emissions from boilers and combustion processes to the desired limits, boiler
operation needs to be optimized. Emission gases includes sulfur dioxide (S02), nitrogen oxides
(NOx), carbon monoxide (CO), hydrocarbons and particulate matter.
Once formed, solid CaO reacts with gaseous SO2 and oxygen to form CaSO4 according to
the following exothermic reaction:
SO2 (g) + 1/2 02 (g) + CaO (s) - > CaSO4 (s) + 1696Kcal/kg (of S)
The resulting calcium sulfate is a chemically stable solid at CFBC operating temperatures and
is removed from the system for disposal. Sulfur dioxide reductions of 90% are typically
achieved in a CFBC boiler with calcium to sulfur (Ca/S) molar ratios of 2 to 2.5, depending on
the sulfur content of the fuel and the reactivity of the limestone.
In general the lower the sulfur concentration in the fuel, the greater the calcium to sulfur
molar ratio must be for a given SO2 removal efficiency. For removal requirements greater
than 90%, the amount of limestone needed must be increased, and for removal efficiencies
less than 90 percent less limestone is required.
The quantity of limestone fed to the boiler depends upon the physical properties & reactivity
of limestone, sulphur content in fuel and boiler operating parameters corresponding to SO2
concentration in the flue gas leaving the stack.
SECTION B PAGE 61
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
The nitrogen oxides that are present in flue gas come from two sources: the oxidation of
nitrogen compounds in the fuel and the reaction between the nitrogen and oxygen in the
combustion air. It is common to refer to the nitrogen oxides in the flue gas as NOx, where
the subscript “x” implies the presence of several different nitrogen/oxygen compounds. The
NOx formed by oxidizing fuel nitrogen compounds is referred to as fuel NOx and the NOx
formed from the nitrogen and oxygen in the combustion air is called thermal NOx, because
it is a product of a high temperature process (above 1482 °C).
The relatively low combustion temperature helps reduce NOx formation. As a result of the low
temperatures at which a fluidized bed operates, thermal NOx makes a minor contribution to
overall emissions. CFBC boilers are also designed to suppress the amount of fuel NOx
formed. This is accomplished by optimizing amount of combustion air through the windbox
(furnace bubble caps) and adding the remainder of the combustion air to the furnace above
the dense bed by way of the over fire air ports (secondary air). As a result of this staged air
admission process, some of the fuel nitrogen compounds released in the lower zones of the
furnace decompose into molecular nitrogen rather than forming fuel NOx. This air admission
process is referred to as staged combustion.
The degree of air staging is a function of the fuel, and the ratio of primary air to secondary
air. It is established when the boiler is designed to provide for both good combustion
efficiency and low NOx formation. In practice, the primary to secondary air ratio may be
adjusted, to a limited degree, to arrive at the best combination of fuel burnout and NOx
emissions.
SECTION B PAGE 62
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Coarse Fly ash is collected from the hopper below MDC and recycled back to furnace. Fine
fly ash in the flue gas after air heater is removed in the ESP to control the particulate
emission from the boiler.
SECTION B PAGE 63
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
5 HOT STARTUP
Average Bed Temperature ≥ 600°C (Imported coal / Lignite)
After boiler tripping, if average bed temperature is ≥ 600DegC, boiler can be restarted directly
with solid fuel feeding.
Note:
1. Windbox needs to be purged with steam as per the Windbox steam purging procedure”.
However air purging is not required if average bed temperature is ≥ 600DegC.
Below mentioned sequence to be followed to bring back the boiler into service during hot
startup.
• After completion of windbox steam purging, normalize the dampers in air and gas circuit.
• Normalize the drum level.
• Drain the bed through the bypass gate and observe for any large amount of unburnt/fresh
coal, if so continue the drain until clear bed material flows from the drain. If no unburnt coal
is observed in the drain, close the drain.
• Bring back all the fan and fuel feeder drives to the minimum speed/flow setting.
• Start the ID Fan, PA fan and SA fan as per fan start-up sequence described in boiler cold
start up procedure.
• Start PA fan and keep the PA air flow to windbox damper in close position.
• After PA fan, start the SA fan and normalise the DCF Seal air pressure (>425mmH2O).
• Open the PA air flow damper to windbox, adjust the PA flow to windbox 45 % of MCR
quickly and start the coal feeding.
• In case, bed temperature drops below 600°C, oil burner support can be taken to increase
the bed temperature before starting the coal firing.
• Open the start-up vent valve (EM-1018)
• Start the fuel feeders.
• Observe the rise in bed temperature.
• Stabilize the coal firing & normalize the boiler operation.
• Adjust the fuel and airflow to maintain the flue gas temperature at “U” beam inlet at 480ºC
till 20% of MCR steam flow is established through the superheater coils.
• Raise the boiler pressure to the rated pressure as per ‘Hot pressurization curve’.
Whenever the boiler rated pressure is attained, connect the boiler to CSDH.
SECTION B PAGE 64
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
140.0
350
325 120.0
300
275
100.0
250
Sat Temp. (Deg C)
Pressure kg/cm2(g)
225
80.0
200
175
150 60.0
125
100 40.0
75
50 20.0
25
0 0.0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70
Time in min
Saturated Steam Temperature Drum Pressure
SECTION B PAGE 65
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
6 WARM START UP
Average Bed Temperature ≤ 600°C
OR
Average Bed Temperature ≥ 200°C
After boiler tripping, if average bed temperature is <600°C and ≥200°C, boiler cannot be
started directly with solid fuel feeding.
Note: Windbox needs to be purged with steam as per the Windbox steam purging procedure”.
Apart from steam purging, Furnace purging also need to be carried out as per “Furnace Purging
Procedure” (Refer section 1.1.6)
Following sequence may be followed to bring back the boiler into service.
• After completion of wind box steam purging, normalize the dampers in air and gas circuit.
• Start the ID fan, PA fan and SA fan as per fan start-up sequence described in boiler cold
start up procedure.
• Prior to start the burner; confirm the bed height to be 600 mm. If it is more, drain the bed
material and maintain bed height of 600 mm above the bubble cap.
• Carry out furnace air purge as per furnace purging procedure. Normalize the dampers in air
and gas circuit.
• Normalize the drum level.
• Open the startup vent valve (EM-1018)
• Start the over bed burner as per burner start up procedure.
• Adjust the oil flow and airflow to raise the bed temperature.
• Once the required bed temperature is attained, initiate the solid fuel firing as per the
procedure (refer section 1.1.8).
• Raise the boiler pressure as per warm start up curve.
• Whenever the boiler rated pressure is attained, connect the boiler to CSDH
SECTION B PAGE 66
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 67
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Post boiler trip i.e. blackout condition or PA fan trip condition, windbox need to be purged by
steam injection to remove the combustibles gas trapped inside the windbox if the average bed
temperature is higher than 200°C.
Operation sequence
• The windbox damper (FCV-1026A/B) force closes automatically through control logic
during MFT condition.
• The steam purge valves (UV-1015/1016) opens. (Automatically through control logic
after 5 minutes of black out condition OR PA trip condition).
• Observe the windbox pressure and should be < 1100-1200mmH2O.
• The steam purging is carried out for 5 min.
• After 5 min the steam purge valves (UV-1015/1016) closes (automatically through
control logic).
• In case of over pressurisation of windbox >2000mmH2O, the steam purge valves
(UV-1015/1016) will close automatically through windbox pressure controller.
• The sequence will repeat every 10 minutes until bed temperature is less than 200°C or
main steam pressure is less than 3 kg/cm2 OR the unit is started.
• Windbox dampers (FCV- FCV-1026A/B A/B) are released for normal operations on PA
fan run feedback.
SECTION B PAGE 68
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
8 WINDBOX CO VENTING
To evacuate CO gases accumulated if any; inside the windbox during boiler tripping & blackout
windbox steam purging venting system is provided. To ensure complete evacuation of CO gases
from the windbox, system is also provided with a gas venting system through flue path to
chimney.
In case of boiler blackout or tripping of the PA fan, windbox venting will be initiated
automatically through logic by opening dampers (UV-1027) at windbox vent duct to APH
hopper. This damper position will prevail until restart of the PA fan.
After PA fan run feedback is available, damper (UV- 1027) at windbox vent duct to APH hopper
will close automatically through control logic after 7 mins of PA fan run feedback.
NOTE:
Ensure the evacuation of ash from APH ash hopper regularly; failing may lead to
stopping the evacuation of gases from the windbox.
SECTION B PAGE 69
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
During black plant condition/boiler tripping, establish steam flow through the steam cooled
section to protect steam cooled section from overheating.
For wing wall protection emergency vent valve UV-1017 is provided which will open
automatically through logic during boiler tripping if the Furnace Exit Gas Temperature (FEGT) at
“U” beam inlet is above 480°C. Bleed steam flow will be stopped once the FEGT / U beam
temperature drops to 480°C.
A) Auto Mode
B) Manual Mode
A) Auto Mode:
In case of boiler tripping if the Furnace Exit Gas Temp at “U” beam inlet is above 480 °C. and
tripping of the PA fan, the wing wall protection valve / Emergency vent valve (UV-1017) opens
automatically & remains open until the restart of PA fan OR Furnace Exit Gas Temp (Average U
beam) reduces below 480 °C
The valve will open to ensure 5 % MCR steam flow through wing wall and superheater coils.
B) Manual Mode:
In manual mode, wing wall protection valve/ emergency vent valve (UV-1017) can be force
open by the operator satisfying the operating conditions. As a precaution an alarm is provided
when valve is operated manually.
Note: Advice to keep the controls in automatic mode to avoid manual error.
The following interlocks are monitored continuously throughout the operation of the unit:
SECTION B PAGE 70
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 71
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
1) Very low bed inventory / Bed level 1) Maintain the bed level / inventory
(middle dP) (middle dP) as per the steam flow.
2) Very High bed inventory / Bed level 2) Maintain the bed level / inventory
(middle dP) (middle dP) as per the steam flow.
3) Inadequate fly ash recycling 3) Verify the MDC ash hopper level,
operation of RAV, condition of airslide
porous sheet, air pressure at airslide.
4) Use of non specified fuel 4) Use only the design fuel
5) Fuel rich bed 5) Adjust the air to fuel ratio as per the
load
Unable to 6) Higher oil firing rate. 6) Modulate oil flow rate
control bed
temperatures 7) Inadequate combustion airflow 7) Adjust the air flow through windbox
through windbox. suitably
8) Measurement error 8) Verify the condition of thermocouple
and cross check the readings at field.
9) Quality of bed material 9) Maintain silica & alumina content in
make-up bed material.
10) Improper bed material size 10) Use only the recommended size bed
distribution material
11) Collection of Shale & stones in bed 11) Restrict the shale and stones feeding
to boiler along with fuel. Increase bed
ash draining frequency and maintain
fuel sieve size suitably.
SECTION B PAGE 72
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
1) Very low bed inventory / Bed 1) Maintain the bed level / inventory
level (middle dP) (middle dP) as per the steam flow.
2) Inadequate fuel supply 2) Maintain the fuel feeder speed as per
the operating load
3) Low feed water temperature 3) Maintain the feed water temperature
as specified
4) Use of non specified fuel 4) Use only the design fuel
Unable to load
5) Fuel chocking in the feeding 5) Inspect the feed system for chock and
the boiler
system clear as required
6) Non availability of fly ash recycle 6) Ensure that ash recycling system is
system available for operation
7) Inadequate combustion air 7) Verify the bubble caps chocking, air
supply to furnace. leakage from air path, verify damper
positions, & verify & maintain the air
flow according to steam load.
1) High furnace dP 1) Maintain the bed level / inventory as
per the steam flow.
2) Air flow more than required 2) Adjust the air flow as per the
operating load
3) High bed ash Bulk density 3) Drain the coarse ash settled at
Windbox bottom furnace periodically and
pressure high maintains the bulk density below
1200 kg/m3.
4) Bubble cap chocking 4) Verify the dp across the bubble cap
and inspect & clean the bubble caps
5) Measurement error 5) Verify the transmitter calibration for
correct reading
SECTION B PAGE 73
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 74
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
2) Chocking of airslide porous sheet 2) Verify and clear the airslide porous
sheet.
3) Damaged porous sheet 3) Verify and replace the damaged
porous sheet
SECTION B PAGE 75
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 76
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 77
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 78
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 79
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
• Verify that furnace refractory is intact without any damages during boiler outage.
• Inspect the bed bubble caps for any damages & replace as required during boiler outage.
• During outages preserve the boiler & auxiliaries as per preservation procedure.
• Inspect the floor panel for any leakages & rectify if required during boiler outage.
DONT’S
• Don’t bypass any instruments and safety interlocks.
• Don’t throttle the feed water pump balancing leak off valve while the pump is in operation.
• Don’t operate the furnace header drain valves while the boiler is in operation.
• Don’t open the furnace manhole during boiler operation.
• Economiser ash hopper need not to drain during normal operation.
• Don’t leave the boiler control room / Panel unattended.
• Don’t allow unauthorized persons to operate the boiler and associated equipments.
• Avoid continuous operation of boiler at low loads (low backend temperature) to protect
downstream equipments from dew point corrosion.
• Don’t operate the boiler below the recommended steam outlet pressure.
• Don’t load the boiler beyond rated capacity.
• Don’t operate boiler on very low & very high steam drum level.
• Don’t use non specified fuels.
• Avoid frequent starts & stops of the boiler.
• Don’t restart boiler after tripping until the cause is identified and rectified.
• Don’t carry out any maintenance without proper work permits and safety compliance.
SECTION B PAGE 80
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 81
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
14 BOILER SHUTDOWN
Boiler shut down can be of two types:
• Planned / Normal shut down, where the operator gets advance notice and adequate time
to shut down the boiler in an orderly manner.
• Boiler Trip on interlock protection (MFT Condition) or emergency shutdown by the
Operator.
14.1 NORMAL SHUTDOWN PROCEDURE
• Reduce load at the rate established by the turbine, until the turbine is at its minimum load
point.
• During the period of load reduction, operator should maintain continuous steam flow
through the superheater.
• Steam flow is decreased by reducing fuel feed rate and combustion air flow (primary and
secondary) either manual or automatic operation. While pressure reduction, flue flow to be
reduced first followed with corresponding air flow however the air flow should not be
reduced below the purge air or minimum fluidisation air flow whichever is higher to prevent
solids shifting back.
• Trip the turbine and bring the boiler down by shutting off the following feed systems:
Stop the limestone/ make up bed material rotary feeder & MDC ash recycle rotary
feeder along with load reduction.
Stop the fuel feeders.
If the unit is to be shutdown for maintenance, the coal bunker isolation gate valves
(H-1001/1002/1003) should be closed prior to shutting down the fuel feeders, the
fuel feeders should continue to run for at least 5 minutes after isolating the bunker
to empty the DCF and fuel feeding chute.
• The operator should adjust the start-up vent (EM-1018) so as to provide at least 20%
steam flow to protect the superheater from overheating until the flue gas temperature
entering the U-beams is below 480°C.
• Switch off the ESP whenever the backend temperature drops below 140°C but never OFF
the rapping system of ESP instantly.
• De-energize the overbed burners if in service.
• Stop HP / LP dosing.
• Close the CBD valve (EM-1007).
• Close the sample lines.
• Maintain normal water level.
• Verify the IBD valve (EM-1006) is closed.
SECTION B PAGE 82
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
NOTE: If the unit is shut down for a short period of time AND NO PERSONNEL WILL BE
ADMITTED TO THE BOILER, store the solids inventory in the MDC ash hopper & leaving enough
bed material in the furnace to provide at least 600mm bed height.
• Whenever the gas temperature entering U-beams has cooled below 480°C, steam flow is no
longer needed to cool the superheater. Now close the start up vent valve (EM-1018).
Increase the air flow to 100% MCR through the primary and secondary air ports to cool the
bed ash temperature to 200°C.
• Stop the fans and allow boiler to cool naturally. SHUT DOWN THE SA FAN BEFORE
SHUTTING DOWN THE PA FAN, TO PREVENT FLOW OF HOT AND COMBUSTIBLE GASES
INTO THE WINDBOX. Shut down the ID fan and keep the fan damper open position.
• Whenever the steam drum pressure drops to 2-kg/cm2 (g), open the steam drum vent
(LHS (SD-1039/1040) and the start-up vent (EM-1018).
• Pressure reduction should not be faster than the boiler depressurization curve (attached
below)
CAUTION
IF PERSONNEL NEED TO ENTER THE UNIT, ALL SOLIDS MUST BE REMOVED COMPLETELY
FROM THE BOILER INCLUDING THE FURNACE, U-BEAM ZONE, SUPERHEATER PASS FLOOR,
MDC HOPPERS, ESP AND WINDBOX. THE BOILER TEMPERATURE MUST BE AMBIENT, AND THE
FOLLOWING EQUIPMENT/SYSTEMS BE LOCKED OUT BEFORE PERSONNEL ARE ALLOWED TO
ENTER FOR MAINTENANCE OR INSPECTION: FEED WATER SYSTEM, ID, PA & SA FANS,
BURNERS & IGNITERS, SOLID FUEL FEEDERS, LIMESTONE FEED SYSTEM, MAKEUP BED
MATERIAL SILO.
SECTION B PAGE 83
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
100.0
70.0
fanning slowly with 300
Stay on this side of curve
60.0
Open Superheater drains to equalize
temp of the drum shell (3 rounds)
50.0
Shut off air heaters Open Drum Vent at
40.0
2 Kg/cm2 (g)
30.0 Close pressure
Superheater Maintain
20.0 drains high water
10.0 level until
zero press.
0.0
0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850
Time in minutes
SECTION B PAGE 84
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
• Boiler trip during load operation, especially due to loss of feed water supply to the
boiler; immediate response should be to restore feed water supply through emergency
boiler feed water pump. The goal is to maintain safe water level; if not in the normal
operation range, at least up to the minimum visibility of drum direct level gauge glass.
The target is to restore a water feed to the drum within 5 to 7 minutes of the trip.
• Generally, loss of feedwater supply to the drum will result in low water which trip the
fuel will feed system. Should the loss of the entire main BFP system occur, it is
recommended if possible to trip the fuel feed system (main and auxiliary fuel) before
low water trip occurs. This may help to conserve drum water inventory as preparations
are made to restore water flow to drum.
• Establish steam flow through the superheaters through start up vent (EM-1018) and
emergency vent valve (UV-1017) immediately after tripping to protect steam cooled
section from overheating. Though there is loss of water due to venting through startup
SECTION B PAGE 85
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
vent valve/emergency vent valve; controlled venting of small amount of steam may
reduce pressure rise and prevent lifting of safety valves to the large extent.
NOTE: BLEED STEAM FLOW WILL BE STOPPED ONCE THE FEGT / U BEAM
TEMPERATURE DROPS TO 500°C.
• Ensure ID fan dampers (HCV-1037A/1037B) are open to facilitate evacuation of gases
from the furnace.
• Windbox steam purging and venting should be online during blackout.
SECTION B PAGE 86
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
SECTION B PAGE 87
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
The operator must be aware of any operating conditions affecting the boiler or related
equipment, should able to recognize hazardous conditions and act properly to avoid injury and
damage. Even though operating procedures are given for each system, it is expected that the
operating personnel should acquire complete knowledge of all components - their design,
purpose, limitations and relationships with other components / systems.
• The reducing atmosphere in the lower furnace due to the staged combustion results in the
presence of relatively high concentrations of carbon monoxide, hydrogen and other toxic
and combustible gases. Operating personnel should be aware of the potential safety hazard
of gases leaking from the pressurized lower furnace. The operator/owner is responsible for
the installation of gas monitors and development and implementation of safety procedures
to alert the operating personnel about the leakage of harmful gas & hot bed material from
the lower furnace and attachments such as the fuel feed system and MDC fly ash recycle
connections.
• Operating the boiler with low feed water temperature along with high excess air will
result in exceeding metal temperature. During such conditions load must be bring down
immediately, if this temperature cannot be brought under control by other means.
• In case of tube leakage, which can be identified by hearing the noise from the boiler
surroundings and cross checked by difference in steam and water flow, gas and steam
temperature, the boiler should be shut-down at the earliest depends upon the nature of
failure for inspection & repair work. Otherwise large number of tubes may fail due to
steam impingement & erosion.
• Entry of wet steam into superheater will results in thermal shock. Austenitic steel is
worst affected due to stress corrosion in this case. Hence temperature after the
de- superheater should be maintained well above the saturation point.
• Always use deaerated, de-mineralised water for boiler feeding with the recommended
feed water quality.
• Feed water temperature must also be maintained as per design by heating the water in
deaerator. Low feed water temperature during low load operation will result in external
corrosion of economiser.
• Steaming in economiser is harmful to economiser unless otherwise it is designed as
steaming type and hence steaming should be prevented by passing water through
economiser continuously when there is fire in boiler.
• Carryover of salts in steam occurs either due to mechanical or vapour carry over from
steam drum. Efficient drum internals can only reduce mechanical carry over. Silica is
SECTION B PAGE 88
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
always carried over in vaporous form. Continuous monitoring of sodium and silica in
steam is desirable.
• Before operating a boiler, ensure complete knowledge of water chemistry.
• Whenever boiler is started after a shutdown of more than 3 days, check all safety
interlock before boiler start up for proper functioning.
• Superheater drain valve (DR-1011/EM-1041, DR-1013/EM-1042) should be operated as
per recommendations.
• The steam drum should normally be filled up to 30% drum level (NWL = 25 mm above
drum centre line).
• Firing should be limited depends upon the steam flow & furnace exit gas temperature
for protection of superheater during start-ups.
• Once the boiler is boxed up after shutdown, the water level in the steam drum must be
raised to the very top of the drum. Filling the drum like this will prevent excessive
temperature differentials along the drum wall during natural cooling.
• While raising pressure on boilers, a technique of continuous firing should be developed if
possible, since intermittent firing may result in re condensation in the tube loops.
• Where spray type attemperator is fitted, it is very important that control of steam or
superheater tube metal temperature is not attempted by the use of the spray during
pressure raising. This can lead to the entry of spray water into the secondary
superheater tube loops. Temperature must be controlled by modulating the rate of firing
and steam venting.
• Operate the boiler with recommended dP i.e. bubble cap dP, lower furnace and upper
furnace dP this is to prevent back shifting of bed material into windbox blocking fly ash
recirculation from airslide and damages to the airslide components.
• Establish steam flow through the superheaters through startup vent (XV-1018) and
emergency vent valve (UV-1017) immediately after tripping to protect steam cooled
section from overheating.
• Ensure the availability of fuel / make up bed material in the bunkers.
• Never allow gas to accumulate anywhere, other than in a tank or lines which form a part
of a fuel supply system.
• Purge the furnace completely before introducing any light or spark.
• Light up the burner with help of igniter & not from any other source.
• Ensure operation staff alerts to all abnormal conditions.
SECTION B PAGE 89
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
Personnel protection is an important part of proper operation. Listed below are some of the
items foreseen as potential safety hazards:
• Do not attempt to open the furnace doors or observation ports during boiler operation
without observing the proper safety procedure. The furnace is under pressure, and
improper handling of doors or openings will lead to severe injury and may result in
death. High concentrations of harmful gases such as carbon monoxide, carbon dioxide,
hydrogen sulfides, sulfur dioxide and nitrogen oxides are the major known components.
The hot gases and hot solids will escape from the furnace doors, ports and other
openings if the instructions given in the safe handling of doors are not followed. The
observation port located on the large access door in the lower furnace must not be
opened during operation of the boiler. Access doors must never be opened when the
boiler is in operation.
• Always use a full face mask with tinted glass to protect the eyes and face from hot
gases, harmful light rays, and ash particles when viewing furnace conditions.
• Do not stand directly in front of the open ports or doors especially when they are being
opened. The solids in the furnace, windbox (if any), dust collector hopper, air heater
hopper and the final particle separation unit (ESP) hopper remain hot for extended
periods of time. When opening doors, even when the unit is shutdown, care must be
taken to avoid injury from the avalanche effect of the solids accumulated behind the
doors.
• Furnace pulsations caused by firing conditions or upset conditions such as tube failure
can blow hot furnace solids and gases out of open doors, even on the negative pressure
point near the U-beams. Use aspirating air before opening the inspection doors and
ports to prevent the escape of hot furnace gases and hot solids to protect against
furnace pulsation. Ensure that the aspirating air lines are not blocked or the aspirating
air supply is not fail/interrupted.
• Since observation ports are connected with aspirating air it will be quite noisy, hence ear
protection should be worn whenever these doors are opened.
• Wear protective gloves when working around boiler doors and openings.
• Do not use open-ended pipes for rodding observation doors or ports. Hot gases and
solids can be flow out through the open-ended pipe directly onto its handler. The pipe
can also become excessively hot. Use solid rods made of non-combustible material and
wear protective gear (gloves, safety glasses, and gas mask).
SECTION B PAGE 90
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
• Never enter vessels, especially boiler drums, until all the steam and water valves,
including the drain and blowdown valves, have been closed, locked and tagged. It is
possible for steam and hot water to back up through the drains and blowdown piping
especially when some of boiler drains are connected together. When vent valves are
connected to a nitrogen system, these valves should also be closed, locked and tagged.
• Do not enter a confined space until it has been cooled below 48°C and properly
ventilated. Completely drain and clean all the solids from the bed, U-beam zone, super
heater enclosure, dust collector hoppers, economiser and the air preheater ash hoppers.
• Use low voltage extension cords and light bulbs with properly connected grounds. Bulbs
on extension cords and flashlights should be explosion proof.
• Never open or enter the rotating equipment until it has come to a complete stop and its
circuit breaker is locked open. Some types of rotating equipment can be set into motion
with very little force. This type should be locked with a brake or locking device to
prevent rotation.
• Be prepared for falling ash when entering the boiler furnace by wearing a facial mask,
helmet and covered tight goggles to protect the eyes.
• Never step into fly ash or drained bed material. It can be cold on the surface but remain
hot smoldering underneath for longer period of time.
• Verify and ensure the drive mechanism of dampers, gates, and doors are secured/locked
before passing through them.
• Watch for hot water in drum and headers while opening the manhole and hand hole
covers.
• Never use toxic fluids, such as cleaning solvents, in confined spaces without adequate
ventilation. Follow Occupassional Safety & Health Administration (OSHA) -recommended
procedures for handling such material in confined spaces.
• Never direct an air or water stream into an accumulation of fly ash in a confined area. If
the fly ash is smoldering, the disturbance by air / water jet could result in an explosion.
WARNING
THE U-BEAMS, U-BEAM BOTTOM AND SIDE BAFFLES AND ATTACHMENTS ARE MADE OF
AUSTENITIC STAINLESS STEEL. EXPOSURE OF AUSTENITIC STAINLESS STEEL TO OPERATING
TEMPERATURES EXPERIENCED IN THIS AREA HAS BEEN FOUND TO SIGNIFICANTLY REDUCE
THE AMBIENT OR ROOM TEMPERATURE IMPACT STRENGTH OF THE MATERIAL. DUE TO THE
REDUCED AMBIENT OR ROOM TEMPERATURE IMPACT STRENGTH, FRACTURE FAILURE OF
THE STAINLESS STEEL MAY OCCUR UPON APPLICATION OF SUDDEN IMPACT LOADS WHEN
THE BOILER IS NOT IN OPERATION. THEREFORE, SHARP BLOWS OR IMPACTS TO THE U-
BEAMS, BOTTOM AND SIDE BAFFLES AND ATTACHMENTS MUST BE AVOIDED WHEN DOING
SECTION B PAGE 91
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
CLEANING, MAINTENANCE OR REPAIR WORK ON, OR IN THE VICINITY OF, THE BEAMS.
PROCEDURES MUST BE DEVELOPED BY THE OPERATOR FOR PREVENTING ANY IMPACTS TO
THE U-BEAMS, BOTTOM AND SIDE BAFFLES AND ATTACHMENTS SUCH AS HAMMER BLOWS
OR BLOWS FROM IMPACT HAMMERS OR CHISELS. WHEN MAKING REPAIRS TO, OR
OTHERWISE MODIFYING THE U-BEAMS, BOTTOM AND SIDE BAFFLES AND ATTACHMENTS,
REPAIR AND INSPECTION PROCEDURES MUST BE USED WHICH ELIMINATE ANY CRACK TYPE
STRESS RISERS OR CONCENTRATORS SUCH AS PLATE CRACKING, LACK OF WELD FUSION OR
OTHER WELD DEFECTS.
BED MATERIAL USED IN THE OPERATION OF THIS EQUIPMENT MAY CONTAIN FREE
CRYSTALLINE SILICA. REPEATED INHALATION OF RESPIRABLE FREE CRYSTALLINE SILICA
DUST MAY CAUSE LUNG INJURY. RESPIRATORS SHOULD BE WORN WHEN WORKING IN
CONFINED AREAS WHERE ADEQUATE VENTILATION IS NOT APPARENT OR AVAILABLE AND
WHERE BED MATERIAL PARTICLES ARE PRESENT IN THE ATMOSPHERE IN AMOUNTS IN
EXCESS OF ALLOWABLE LEVELS ESTABLISHED BY THE OCCUPATIONAL SAFETY AND HEALTH
ADMINISTRATION (OSHA). THESE CONDITIONS MAY EXIST IN AREAS SUCH AS TANKS,
HOPPERS AND BOILERS. APPROPRIATE VENTILATION SHOULD BE PROVIDED AND
PROTECTIVE EQUIPMENT SHOULD BE WORN IN COMPLIANCE WITH STANDARDS
ESTABLISHED BY OSHA. PROCEDURES SHALL BE DEVELOPED BY THE OPERATOR FOR
MEASURING ATMOSPHERIC LEVELS OF BED MATERIAL/SILICA AND FOR RESPIRATOR USE.
POSSIBLE EMERGENCY AND ROUTINE USES OF RESPIRATORS SHOULD BE ANTICIPATED AND
PLANNED FOR. WARNING: LIMESTONE USED IN THE OPERATION OF THIS EQUIPMENT IS
CONVERTED TO LIME DURING THE CALCINING PROCESS WHICH OCCURS IN THE FURNACE.
CALCIUM OXIDE (LIME) IS A STRONG ALKALINE DEHYDRATING MATERIAL WHICH UPON
CONTACT WITH SKIN AND EYES WILL CAUSE IRRITATION OR PERMANENT DAMAGE TO THE
EYES.
INHALATION OF LIME DUST MAY CAUSE COUGHING, SNEEZING AND INFLAMMATION OF THE
RESPIRATORY SYSTEM. RESPIRATORS AND TIGHT PROTECTIVE EYE GOGGLES SHOULD BE
WORN WHEN WORKING IN CONFINED AREAS WHERE ADEQUATE VENTILATION IS NOT
APPARENT OR AVAILABLE AND WHERE LIME PARTICLES ARE PRESENT IN THE ATMOSPHERE
IN AMOUNTS IN EXCESS OF ALLOWABLE LEVELS ESTABLISHED BY THE OCCUPATIONAL
SAFETY AND HEALTH ADMINISTRATION (OSHA). THESE CONDITIONS MAY EXIST IN AREAS
SUCH AS TANKS, HOPPERS AND BOILERS. APPROPRIATE VENTILATION SHOULD BE
PROVIDED AND PROTECTIVE EQUIPMENT SHOULD BE WORN IN COMPLIANCE WITH
STANDARDS ESTABLISHED BY OSHA. PROCEDURES SHALL BE DEVELOPED BY THE OPERATOR
FOR MEASURING ATMOSPHERIC LEVELS OF LIME AND FOR RESPIRATOR USE. POSSIBLE
EMERGENCY AND ROUTINE USES OF RESPIRATORS SHOULD BE ANTICIPATED AND PLANNED
FOR.
SECTION B PAGE 92
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
• Sampling should not be done in such a way that there is an open path from the drain
line or the furnace to the atmosphere. The material surges and pressure pulses can
cause material to splash out of drain ports or spurt out of the opening and miss the
collecting vessel/container. The samples should be obtained from the cooled ash
downstream of the metering/isolating valves.
• Never attempt to rod out a plugged bed drain with the unit in service or with any bed
material in the furnace. When it starts to flow it will spew out and will not stop until the
furnace is empty. Pocking of bed drains should be done from the top (bed side). Clear
the area underneath of all personnel.
• Probes connected to bed ash drain system should be tightly fitted and secured in the
respective ports to minimize the blowout of material from the furnace.
• Do not leave any rod or probe in the furnace for long. It will heat up quickly making it
difficult to handle and hazardous when removed.
• Never look directly into the port or stand directly in front of the open port. If there is a
pressure fluctuation in the furnace, hot bed material can suddenly and unexpectedly
spurt out.
• The access door/inspection port cover will probably be hot. Protective gloves and
glasses should be worn at all times.
• Secure and lock the manhole and observation port cap any time the port is not in use,
even for short periods of time.
• Never use anything that may burn or melt, such as plastic or rubber, to temporarily
block the port. It will contact the hot gas and the result will be fire with noxious or toxic
fumes.
• Always wear insulated gloves and covered tight protective safety glasses when using
these ports. It is also advised to wear long sleeve shirts.
• Properly dispose of all combustible material from the port area. If any hot material blows
out from the boiler it presents a potential fire hazard.
SECTION B PAGE 93
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
• Turn on the aspirating air. Be SURE aspirating air is “ON” before you open the port
door. If the aspirating air is not “ON”, a stream of hot furnace gas and bed material will
blow out of the boiler.
• Open the port cap slowly.
• If the port is blocked by ash or bed material, rod it out with a long (greater than 6') solid
steel rod. DO NOT USE PIPES.
CAUTION
THE ASPIRATING AIR WILL BE BLOWING MATERIAL OUT AND WHEN THE PLUG IS CLEARED
THE ASPIRATING AIR CAN BLOW A FEW PARTICLES OF BED MATERIAL OUT IN YOUR
DIRECTION. DO NOT TURN OFF THE ASPIRATING AIR UNDER ANY CIRCUMSTANCES. THE
OPERATOR SHOULD ENSURE THE ASPIRATING AIR SOURCE IS RELIABLE AND NOT SUBJECT
TO BEING INADVERTENTLY TURNED OFF AT A REMOTE POINT.
• When inserting a probe in the port, stand as far back as you can. The aspirating air
WILL be blowing a few particles of hot bed material out of the port. Also, if a pressure
pulse occurs in the furnace, some bed material can blowout.
• When extracting the probe, again stand well back. The probe, even if water-cooled, will
be HOT. Any un-cooled portions of the probe such as a tip or filter will be at furnace
temperature.
• After using a port, close the door first, and then turn off the aspirating air. NEVER,
under any circumstances, leave a port door open and unattended, even for short
periods. A pressure pulse in the furnace can cause bed material to blow out
unexpectedly. The aspirating air can be left on to keep the port clear if it will be used
again in a few minutes. Do not leave the aspirating air on permanently.
SECTION B PAGE 94
THERMAX LIMITED PROJECT: RSPL LIMITED.
BOILER AND HEATER GROUP JAMNAGAR, GUJARAT
PUNE, INDIA PROJECT NO.: PC 0531/32/33
• Operation of the ports immediately after shutting down the boiler must be treated the
same as if the boiler were still operating. Any residual material inside the U-beam zone
such as that collected on the convection pass floor, U-beam segments and attachments,
etc. will remain aerated and hot for a considerable period of time after the boiler is shut
down. Sufficient waiting time must be allotted for the material to de-aerate and cool
down. A minimum of 48 hours should be allowed between shutting down the boiler and
opening a port if aspirating air for the port is not operable.
• The ports in the U-beam zone should be opened only when needed. Do not leave open
ports unattended.
• Penetrations in the U-beam zone such as pressure taps should NEVER be opened when
the boiler is in service.
Repair or changing of thermo wells during boiler operation is absolutely prohibited, particularly
in the positive pressure zone of the boiler. Changing thermocouples embedded within thermo
wells during boiler operation is not a recommended procedure. However, if the need arises,
when for example only one thermocouple is in operation in a particular zone, then the following
procedure must be followed.
When replacing thermocouples (TC) located in the furnace, always recall that the furnace is
pressurized and that the thermo well may be an open path to the pressurized furnace. Slowly
and carefully disconnect the thermocouple from the well. If you encounter resistance in
removing the thermocouple, or solids start to flow out of the well, it is an indication that the
thermo well has eroded and is packed with ash and bed material. Abort the attempt to replace
the thermocouple and refasten it until the boiler is off line and cooled. If no resistance is
encountered, then carefully remove the faulty thermocouple and replace it. Always wear
protective glasses and eye protection and always stand to one side when working on the TC.
NEVER look into a TC well opening. It is advised that if a TC is removed from the well, the
opening should be plugged with a steel plug or cap. Never use plastic or rubber. These can melt
or burn resulting in fire with noxious or toxic fumes.
PROPER HANDLING OF ACCESS DOOR
Never open an access door while the unit is operating.
Any access door can have large amount of material built up behind it even after the bed has
been drained. This material will fall out when the door is opened. Bed material can stay hot for
many days even after boiler shutdown.
Open the door slowly and always stand to the side of the opening.
SECTION B PAGE 95