Professional Documents
Culture Documents
For
KHARTOUM NORTH POWER STATION-
PHASE III (2×100MW) PROJECT
Section 13
Volume 01
Version G
1
Table of Contents
1 DESULFURIZING SYSTEM ................................................................................................. 5
2
4 L IM ESTONE SLURRY CHEMICAL DOSING SYSTEM ................................................ 46
3
10.1 MAIN TASKS FOR OPERATION ADJUSTMENT................................................................. 82
10.2 OPERATION ADJUSTMENT OF DESULFURIZATION SYSTEM ............................................. 82
10.3 INSPECTION DURING THE OPERATION OF DESULFURIZATION DEVICE ............................. 84
13.1 SULPHUR CONTENT IN FUEL OIL EXCEEDING THE STANDARD ..................................... 109
13.2 INSUFFICIENT OXIDIZING AIR ..................................................................................... 109
13.3 ‘VIRUS’ OF ABSORBER ............................................................................................... 110
13.4 TREATMENT OF ABSORPTION TOWER ‘VIRUS’ .............................................................. 110
13.5 EXCESSIVE FLY ASH .................................................................................................. 110
13.6 PROBLEMS CAUSED BY EXCESSIVE CL- ..................................................................... 111
13.7 PROBLEMS OF LIMESTONE QUALITY ........................................................................... 111
13.8 HIGH WATER PERCENTAGE OF GYPSUM ...................................................................... 111
13.9 PROBLEMS OF MECHANICAL SEAL ............................................................................. 112
13.10 PROBLEMS OF WATER BALANCE ................................................................................ 112
13.11 PROBLEMS OF OXIDIZATION AIR FAN .......................................................................... 112
13.12 PROBLEMS OF FLUSHING EFFECT OF DEMISTER ......................................................... 113
13.13 ABSORBER INLET FLUE GAS FLUSHING AND EMERGENCY ATTEMPERATOR .................. 113
13.14 RECYCLE PUMP OF ABSORBER .................................................................................. 113
13.15 VACUUM DEHYDRATION SYSTEM ................................................................................ 113
13.16 BYPASS FLUE GAS DAMPER ...................................................................................... 114
13.17 PROBLEM OF ABSORBER LIQUID LEVEL ..................................................................... 114
4
1 Desulfurizing system
It is kind of alkaline ore added to the FGD system. Reacts with acidic
sulfur dioxide (SO2) of the flue gas becoming neutralized; the source of
calcium ion (Ca2+).
1.1.3 pH
It is also called inert matter, refers to the scrubber solid matter that
does not dissolve in the strong acid. The acid insoluble matter is the
measure of fly ash and other inert maters in the scrubber solid matter.
1.1.6 Ion
Ions with different charges often react with each other to generate
deposition or ion pair.
1.1.7 Deposition
1.1.8 Dissolution
The tendency that the solid in the solution dissolves and generates
ions.
The tendency that the ions in the solution constrain dissolution of solid.
5
Analyze the solid SO42- and SO32-.
The filtrate returns to FGD system after the solid in the slurry is
condensed and removed.
The SO2 in the flue gas is absorbed into the circulating slurry in the
absorber.
The air blown in the absorber oxides the absorbed SO2 into sulfate
(SO42-).
The SO42- in the solution reacts with the calcium ion to generate
gypsum.
Separate the deposited gypsum from the slurry and the water is
removed. This is the solid by-product of the process. The filtrate returns
to the FGD system.
6
1.3 Basic chemical theory
− 1 =
2) Oxidation: HSO3 + O2 → H + + SO4 (3)
2
=
4) Deposit Ca + + + S O4 + 2 H 2O → CaSO4 *2 H 2O (5)
CaSO3.1/2H2O+SO2+1/2H2O ◊ Ca(HSO3)2
From this, we can see when the pH value is lower, it is easy to dissolve
the limestone; while the pH value is high it is easy to absorb SO2. Thus
dissolving much limestone is helpful to increase the pH value to absorb
SO2.
Function:
7
1.4.2 Flue gas system
8
Supply oxygen necessary for oxidizing the absorbed SO2 to sulfate;
Function: separate and remove the slurry solution drops in flue gas.
Direction
Design
Blade shape
Air flow
Air flow
Horizontal air flow ME Vertical air flow ME
9
2 Waste Water Treatment System
2.1 Introduction
2) pH value: 5.5-6.0;
2) When the PH value of water outlet box is higher than 9, start the
HCl chemical-dosing pump; when lower than 8, stop HCl dosing
pump.
10
is lower than 1.1m, low-level alarm occurs; when lower than 0.8,
start the alarm and turn off the agitator and water outfall pump of
water outfall box L0HTZ30BB001.
2.4 Operation and Stop of Sludge Recycling System and Water Pump
Switch Sequence
11
L0HTZ22AP001 stops due to check or accident, sludge recycling
pump L0HTZ22AP001 or L0HTZ21AP001 starts running.
12
7) When waste water inlet flowmeter L0HTS50CF101 has no flow
signal, stop the limestone slurry chemical dosing pump to the
neutralization box, and start the stop program of limestone slurry
chemical dosing pump.
13
2) When the liquid level meter reaches 1.4m, start drainage pump
L0HTZ71AP001 or L0HTZ72AP001.
4) When the liquid level meter is lower than 0.8m, low-liquid alarm
occurs.
5) When the liquid level meter is lower than 0.6m, stop blowdown
pump L0HTZ71AP001 or L0HTZ72AP001, and stop agitator
L0HTZ70AM001.
14
3 Control Logic and Introduction of Desulfurizing
System
3.1 Flue and Booster Fan System
Steps:
Steps:
15
(L0HTF11AP001/ L0HTF12AP001/ L0HTF13AP001/
L0HTF14AP001)(Isolate FGD of two units)
C. The inlet baffle is not open when the booster fan operates
for 60 seconds (L0HTA01AA002/L0HTA02AA002) (Isolate
the FGD of the corresponding unit)
2) Isolation steps
16
D. Close down the FGD outlet baffle
(L0HTA01AA003/L0HTA02AA003);
Startup conditions:
Any of the baffle valves is closed (any bypass baffle valve, FGD flue
gas outlet valve closed, FGD flue gas inlet valve closed).
1) Startup conditions:
C. Interlock;
2) Sequence startup
A. Permit:
B. Steps
3) Sequence stop:
Steps:
17
A. Stop the lower pressure baffle sealing air electric heater
(L0HTW31AC001);
Start-up conditions:
1) Start-up conditions:
C. Interlock
2) Consequence startup
A. Permit conditions:
B. Steps
3) Sequence Stop
Steps
(L0HTW33AN001/L0HTW34AN001)
B Shut down two high pressure baffle sealing air fans by half
an hour delay (L0HTW33AN001/L0HTW34AN001)
18
3.3 FGD Inlet Flue Gas Baffle (L0HTA01AA002/L0HTA02AA002)
1) Shutdown permit:
2) Override start:
19
3.6 Booster Fan System
1) Startup permit:
2) Stop permit
20
L0HTC20CT307—08;
h) Stall alarm signals and the inlet guide blade position >42%
(L0HTC10CP001/L0HTC20CP001, delay 120 seconds);
Interlock startup: The interlock system is put into operation and the
lubricant oil volume is low. Will the interlock starts the standby pump?
Interlock startup: The interlock system is put into operation and the
hydraulic oil pressure is low. Interlock starts the standby pump.
Interlock startup: The interlock system is put into operation and the air
intake case sealing pressure is lower. Interlock start the standby pump.
2) Sequence startup
21
G. Start the booster fan
H. Open the fan inlet baffle (adjustable) after the booster fan
starts 10 seconds
3) Sequence Stop
Stop the diffuser sealing air fan and the air intake case sealing air
fan when the booster fan stops operation for 2 hours?
4) Outlet and inlet baffles interlock: BUF trips, the outlet and inlet
baffles is closed interlock.
1) Sequence startup
A. Permit conditions:
B. Steps:
2) Sequence stop
Steps:
22
A. Close the gate valve of the selected limestone belt weighing
machine (L0HTK23AF001/ L0HTK23AF002);
3) Interlock stop
z Startup conditions
z Startup conditions
23
No trip condition exists.
z Interlock stop
b) Trip
c) Materials unsupplied
(L0HTK21AF001XB33/L0HTK22AF001XB33)
e) Non-alignment
(L0HTK21AF001XB23/L0HTK22AF001XB23)
3.9.1 Mill
24
L0HTK31CT309/L0HTK32CT309);
2) Trip conditions:
25
3.9.3 Mill bearing lubricant tank heater
Interlock
A. Select 1# cooler (or 2# cooler) as the main cooler and the other
cooler as standby.
B. When the oil inlet temperature is higher than 45℃, start the main
cooler;
C. When the temperature at the oil outlet is lower than 35℃, stop
the main cooler;
26
3.10.1 Slurry recycling pump
A. Start permit:
B. Trip:
b) Outlet valve not opened after slurry recycle pump runs for
30S.
27
Open permit:Corresponding slurry recycle pump stopped.
3.10.6 Valve for controlling the flow from mill cyclone A/B to limestone slurry
tank (L0HTK41AF001/L0HTK42AF001)
3.10.9 General makeup water valve for process water to grinding system
(L0HTQ31AA515)
No interlock.
A. Conditions:
B. Steps:
28
A. Stop the slurry recycle pump for the mill.
1) Start permit
2) Trip
C. Agitator stopped.
No interlock.
29
Start permit:Corresponding limestone slurry pump stopped.
Permit conditions:
30
3.12 Oxidation fan system
2) Trip
3) Interlock start
In case of tripping of the running fan, the spare fan will start.
No interlock.
31
3.13.1 Demister flushing subgroup start procedures
2) Interlock stop:
All inlet unprocessed flue gas baffles are closed and all outlet flue
gas baffles closed.
3) Start procedures:
32
demister (open for 60S)
AA. Close back flushing electric valve three for the 2nd -step
level demister
33
2) Close absorption tower’s inlet flushing valve A, lasting 100s;
No interlocks.
Interlock: when the recycle tank’s level is high, open; while low , close.
No interlock.
No interlock.
1) Start permit
34
E. Inlet valve of the recycle pump is open.
(L0HTF11AA001/L0HTF12AA001/L0HTF13AA001/L0HTF
14AA001)
2) Trip
C. Stator temp. of the motor of the recycle pump Two items for
any phase are high;
Open permit: the corresponding recycle pump stopped and inlet valve
is closed.
1) Start permit:
35
2) Procedures:
1) Start permit:
FGD inlet and outlet flue baffles are closed and boosting fan
stops.
2) Procedures:
1) Start permit:
36
F. Another pump started or the outlet of another pump is
closed;
2) Tripping
2) Procedures:
37
G. Open outlet valve of slurry discharge valve, with a delay of
10s.
Procedures
38
Start permit: PH meter’s inlet electric valve is closed.
1) Start permit
A. No tripping conditions.
39
E. No alarm from vacuum belt conveyor’s left belt
misalignment limit switch.
(L0HTM21CG002/L0HTM22CG002)
2) Tripping
1) Start permit:
40
(L0HTQ61AA202/L0HTQ61AA203)
2) Tripping:
3) Open the seal water valve for the vacuum pump and the belt
conveyer with a delay of 60s.
5) Open the inlet general pipe’s electric valve from gypsum slurry to
the cyclone station (L0HTL10AA002)
41
1) Start permit
42
3.20.2 Waste water tank agitator
3.22.1 Process water pump (one for use and another for standby)
(L0HTQ21AP001/ L0HTQ22AP001)
43
z Protection trip:Water level of process tank <800mm
Blowing system: it includes main air pipe, blowing pipe, impulse valve
Ash discharging part of air inflow is divided into two types: one is
standard ash hopper (type A), the other one is openness flange type
(type B)
Dusty air enters in the filter bag chamber through openness flange; the
big particle dust will drop into the ash hopper; fine dust will be absorbed
to outer wall by different effects, then it is filtered to clean air through
filter bag then it enters in air inflow chamber, after which it is exhausted
by fan through exhaust hole of air purifying chamber. The dust
absorbed on the filtered bag is increasing all the time so that the
resistance of bag will increase continuously; therefore the bags need
cleaning periodically in order to keep the resistance less than 1200Pa
and the bag type dust collector could continue work. During the dust
cleaning, the program controller will start the impulse valve regularly so
that the compressed air (0.5-0.7Mpa) from air chamber will enter in the
filter bag through holes of blowing pipe. The filter bag will expand
instantly and the dust will be shaken down by the back action of air flow.
Therefore, the dust is cleaned.
44
meanwhile the high pressure air will pass several groups of filter bag
chambers and treat dusty air. Therefore, during the dust treatment, the
pressure loss of dust treating air and the volume of treated dusty air
hardly change, which are the advantages of impulse bag type dust
collector.
Check access hole and whether the flange contact is sealed or not
before the unit begins to work so as to avoid leakage and reduce the
dust removing effect.
The unit voltage is 415V; it can be used when the outside wire of unit is
connected with power source. Pay attention to the rotary direction (if it
is reverse, change the connection of power source) during the
beginning running.
The cover of electric control box can not be opened without permission
during its working; if it is necessary to adjust the dust cleaning time or
repair the circuit, the unit should be shut down and the power source
should be cut off and then perform the work.
Adjust the timing cleaning time in accordance with the dust character
and dusty concentration.
Dust hood is a key part which can ensure the unit remains in optimum
state; proper dust hood should be made during the usage in
accordance with the appearance dimensions of processing part and
dust nature.
3.23.4 Maintainance
45
4 Limestone Slurry Chemical Dosing System
When the liquid level meter J0HTS50CL002 is lower than 0.5m, output
alarm signal and start stop program of limestone slurry chemical dosing
pump.
46
4.5 Stop and Switch Programs of Limestone Slurry Circulating Pump
Starting the stop program of limestone slurry circulating pump goes like
this: open its flushing water valve J0HTQ70 AA207, close its main inlet
valve J0HTS50 AA201, delay for three minutes, close limestone slurry
circulating pump A:J0HTS51AP001 or B:J0HTS52AP001, and then
close flushing water valve J0HTQ70 AA207.
47
5 Inspection and Preparation of FGD Devices
3) The flues and pipes are in good condition with thermal protection
in place. The equipment and structures are free of painting
peeling off. The newly-replaced pipes should meet the relevant
requirements on the color of painting. The flow signs should be
marked correct.
48
4) The internal space of the flue gas duct, basin, tank, chamber and
absorber should be cleaned and free of residue. The man holes
and inspection holes should be closed tightly after inspection.
5) The DCS and power supplies for each system and instrument
have been put into usage. The parameters of all configurations
are correct. The measurement display and adjustment action are
normal. The industrial TV is in good condition.
8) The local control panel and all installed equipment can work
normal, and the indicators are tested meeting the requirements.
9) The anchor bolts for the machines and electric equipment are
completely reliable. The coupler shield is completely good. The
connectors and fasteners are properly installed.
10) The manual valve, electric valve, and control valve switches can
work freely with correct indication; the LCD display is consistent
with the local indication.
11) The electric system instrument and meters are completely good.
The switchboard cabinet has sufficient illumination. The terminal
block and plug don’t have abnormal loose or heating
phenomenon.
12) The switches, contactors and fuses are completely good. The
fuse specification accords with the designed parameters. The
electric heater and the motor heater are connected correctly and
in good condition.
1) Inspect the booster fan inlet baffle, outlet baffle, FGD inlet baffle,
FGD outlet baffle and bypass baffle of the FGD device to confirm
they are installed properly. The bypass baffle should be open.
The processed flue gas baffle and the unprocessed flue gas
baffle should be closed tightly. The differential pressure between
seal air pressure and the baffle value are normal.
49
2) The baffle electric executors are in good condition. The crank
arm is connected firmly. The baffles should run freely without jam.
The baffle switch position is correctly indicated and consistent
with the LCD display as well as be in remote control position.
4) The inlet and outlet pipes of the sealing air fan should be installed
firmly. The seal air inlet manual baffle should be closed and the
heater should be in good condition and shut down.
5) The baffles seal devices are in good condition and the seal pipe
should be clear.
2) The rubber lining of the cases, tanks, basins and the absorber
should be complete without aging and corrosion; the rubber lining
is firmly glued to the absorber wall without any bubble.
50
6) The demister flushing nozzle should be installed firmly and
completely; the spout direction should be correct without jam.
7) The baffles in the limestone slurry tank and the gypsum slurry
tank should be installed firmly without abrasion and corrosion.
1) General provisions
A. The oil levels of the decelerator and the bearing oil chamber
should be within the normal scope. The oil lens should be
clear; the oil should be in high quality, with clear oil level
indicators of high, low and normal. The bearing is lubed
well. The bearing lubed by lube oil should be sufficient with
grease.
G. The oil cooler cooling water can run clearly and the
connection is firmly; the valve and pipe are free of leakage.
51
I. The emergency pushbuttons and shield should be in good
condition.
2) Inspection of agitator
3) Inspection of pump
F. The pump and motor base should be fixed firmly with the
anchor bolt.
52
water level of water tank is normal.
2) Inspect and confirm that the vibration feeder and the metal
separator can work normally.
3) Confirm the power switches of control room and the local cabinet
are closed.
6) Inspect whether the wet ball mill and the slurry recycling pump
can work properly.
2) Inspect whether the system slurry transport pipe is clear and the
valve switch position is correct.
3) Confirm that at least one processing water pump has been put
into operation and its pressure and flow are within the normal
scope.
53
3) Inspect the booster fan bearing and the hardened grease must
be replaced.
5) All the pipes, flanges and bolts should be tight and in good
condition.
6) Turn the booster fan rotor manually by 4-5 rounds and the rotor
must be easily turned.
7) Inspect the inlet guide vane adjuster. Turn the guide vane
executor manually. Test the guide vane adjuster several times
respectively at 25%, 50%, 75% and full open position. Check the
calibration board to see whether the remote and local openings
match each other when the guide vane at the full open or close
position.
11) The bearing and the oil pipe are filled with grease.
13) The instruments of the flue gas monitor system are connected
properly and the standby ones are in good position.
14) The flue gas continuous emission monitor system (CEMS) should
work properly without humidity alarming. Collate the flue gas
CEMS with the chimney CEMS and confirm the display of tested
elements is correct.
2) Inspect the absorber, water tanks and the basin to confirm their
internal spaces are clean and have no foreign articles; the
anti-corrosion layer is in good condition; the man hole is closed
down and in good condition.
3) The pipe flushing valves and discharge valve are closed without
54
leakage.
8) The local control cabinets can work properly and the indicator
lights are tested qualified.
10) The indications of On and Off of switches are clear and correct;
the switches are confirmed qualified by the switching-on and
switching-off tests.
1) The oxidation fan proper and the motor appearance are complete
and the air pipe silencer and filter are clean without sundries.
4) The lubricant oil level is within the normal scope and there is no
oil leakage or dripping.
5) Turn the fan power switches to the test position and switch on the
55
power; when the power switch is confirmed working properly,
switch on and switch off remotely once. Locally check whether
the switches act properly.
B. The belt and filter cloth roller should run freely without jam
and hindering.
C. The main wheel and tail wheel of the belt are installed
properly. There should be no foreign articles existing
between the belt and the wheel. The belt and filter cloth
should be in good condition without nick or reeling off.
56
F. The flushing water pipe of filter cloth and the sealing water
pipe of vacuum box should be clear without jam.
H. The vacuum pump, the filter liquid pump and filter cloth
flushing pump should be installed properly and the pipeline
is clear.
1) Inspect and confirm the tanks are clean without sundries and the
lining is completely good;
3) Inspect the emergency slurry tank pump, the process water pump,
57
demister flushing water pump and other draining sump pumps
are in good condition and reliable.
4) Check and confirm that the process water tank has sufficient
qualified industrial water and the liquid meter works properly.
58
6 Protective Tests for Desulfurization System
The FGD protection order will start automatically because of any of the
following condition:
7) The flue gas bypass baffles alarming for high differential pressure
or low differential pressure;
10) The unit FGD inlet flue gas temperature>180℃(two out of three)
1) Switch off the power supply to the rotary machine and switch on
the test power supply;
59
3) Switch on the interlock and linkage switches of booster fan, slurry
recycle pump and oxidation fan. Switch on the switches of the
rotary machines and shut down the equipment with the
emergency buttons one by one. The reaction of machines should
be normal.
2) Test the valve motor insulation before the electric valve test. If it
meets the requirement, supply power to it. Check if the electric
valve control device can work properly.
3) Fully open and close the tested electric valve which should react
flexibly without jam.
60
6.5 Booster Fan Inlet Baffle Test
1) Under normal conditions, open the outlet baffle and close the
inlet baffle in order to prevent the damage or too high current
from damaging motor when the booster fan starts with load. If the
booster fan starts normally, open the inlet baffle within 60
seconds. If the inlet baffle is not open or the signal fails when the
inlet baffle is fully open within 60 seconds after the booster fan
started, the booster fan will stop running for protection. Therefore,
it is necessary to do switch test on inlet baffle before starting the
booster fan, to ensure that switches work properly.
4) Report to the shift foreman when the booster fan inlet baffle test
is completed.
61
submitted to the shift head in the process.
1) Confirm the repair work has been completed and the safety
protection measures have been recovered; the work permit has
been ended;
2) The sundries have been removed from the site; the passage is
clear with sufficient illumination; the handrail and staircase are
complete and firm; the ducts are clear and the covers are
complete;
3) Each equipment oil level is within normal scope, with good quality;
the oil meter and oil level glass are clear;
5) The flue and pipes are equipped with good insulation and the
signs are clear and complete;
10) The pipes and valves in the FGD system are connected
completely and properly, with good condition;
11) The process water and industrial water systems have supplied
water to the FGD device.
62
7 Startup of FGD Equipment
3) The local control cabinet and the installed equipment can work
properly and the indicator light passes the test;
5) The manual valve and electric valve can run freely and the
electric valve indication accords with the DCS display;
The cold start refers to the first start of FGD system or restarting it after
repair. Before the cold start, the mechanical equipment of FGD system
is in outage. All the tanks, basins, silos and sumps are in condition of
no liquid (no water or slurry).
63
7.3.2 Short-term start
The short-term start refers to the restarting of the FGD system when it
stops operation because of failure for more than 24 hours and less than
72 hours. Before the short-term start, the agitator of the liquid container
is working continuously and the other mechanical equipment stops
running. When start the system, some systems should be recovered.
z Put one filter into operation; close the front and rear stop
valves of another filter for standby;
64
level of process water tank normal.
The absorber slurry basin is the main site for absorption reaction and
oxidation reaction; the absorber slurry basin should be ready for startup.
65
The slurry injection can be divided into the first-startup injection and
injection after repair.
z When the liquid level of absorber reaches 8.2m, close the electric
valve of demister flushing water to stop water injection.
2) Start the liquid transport from the emergency slurry tank to the
absorber, and start the emergency slurry pump;
3) Supply liquid to the absorber from the emergency slurry tank with
the emergency slurry pump through the slurry pipeline; when the
liquid level of the absorber reaches 8.0m, stop injection;
Inject liquid to the limestone slurry tank with the process water.
2) Open the manual valve in front of the water inlet electric valve of
limestone slurry tank;
4) When the water level of limestone slurry tank reaches 1/2 level,
close the electric water makeup valve from process water to
limestone slurry tank;
66
5) After water injection is completed, only the liquid level
measurement system is put into operation; the system is at cold
standby.
2) When its liquid level reaches 2/3, close the water inlet electric
valve;
3) Put the liquid level control system into operation; the filter cloth
flushing water is at cold standby status.
The baffle sealing air fan should be put into use when any of baffle
valves is closed.
2) Start FGD baffle sealing air fan, and turn on electric heating
system of sealing air.
4) Put the online monitoring system of inlet and outlet flue gas of
67
FGD.
Start the equipment of FDG system when the following are satisfied:
boiler runs normally; the flue gas concentration is below 2% displayed
by the outlet flue gas turbidity meter; inlet flue gas temperature of FGD
is between 100℃ and 170℃; the operation conditions for FGD device
are satisfied.
2) Confirm that the absorber liquid level is higher than the “low liquid
level”.
Do not start FGD system until flue gas conditions are satisfied.
68
3) Start the booster fan system including the lubricant system of
booster fan motor and sealed air system. Manually turn on the
booster fan under the control of inlet guide vanes which are at
minimum opening position.
6) When the opening range of booster fan guide vane reaches 30%,
shut off the FGD bypass baffle valve with the command of shift
leader. Ensure the inlet flue gas pressure of FGD is around
designed value, and control guide vane opening range until FGD
bypass baffle closed.
7) For the first start, manually adjust the booster fan guide vane,
and perform programme control after getting the performance of
controlling the guide vane.
69
SO2 removal rate is determined by the adding amount of fresh
limestone slurry poured into the absorber. The fresh limestone slurry
amount is determined by predicted SO2 removal rate, boiler load, and
the pH value of slurry inside absorber.
After the start conditions for vacuum belt drier are met, start it.
9) Put the gypsum plate thickness into automatic control after 10min
delay (forming a loop with the transducer).
After the gypsum slurry concentration is met for the vacuum belt drier
start, switch on the electric valve in front of gypsum cyclone, which will
be then under operation.
70
7.7.10 Start of the overfall box system of gypsum cyclone
Put the liquid control system of gypsum cyclone overfall box, and set
the agitator to be automatic. Then, the liquid level will be automatically
controlled for operation.
5) When at least two absorber recycling pumps are running, the flue
gas is introduced to the system. The absorber recycling pumps
should be started in turn in order to avoid that the equipment of
electric system is damaged due to the high start current of motor.
71
equipment and system must be restarted as follows in order to suspend
the solid inside the tank and make the slurry flow inside the pipes.
1) Set all liquid sump pumps to be manual, and confirm that all
agitators are under operation when there’s liquid in the sumps;
72
8 Maintenance After FGD System Start
73
system can still operate for six hours. In this case, the PH value
of absorber slurry should be reduced to 5.0 and the content of
CaSO3·1/2H2O inside the absorber should be examined once an
hour. Providing there’s no oxidization air in the oxidized air nozzle
for a long time, the pipes must be cleaned.
9) Monitor the demister flushing water flow, and deal with it if it has
large changes.
10) If the pressure difference between the front and the back of
demister reaches a high value of alarm, and it’s ineffective after
flushing, the operator should stop the absorber and check it.
12) The on-duty operator should be familiar with the normal readings
of the monitoring instrument, analyze the cause in case of
deviations, and take steps to minimize potential problems.
13) Frequently monitor the liquid level of boxes, tanks and sumps.
Ensure that the equipment that can come into operation
automatically works normal. Standby equipment must be in good
condition.
14) Frequently monitor the pressure and flow of process water, and
make sure the pressure of compressed air is normal.
17) For the device to transport the slurry, analyzes and judges
whether there is sediment or dirt in the pipes according to the
device’s flow and pressure. If there is, take measures to deal with
it immediately.
18) When the open range of limestone slurry adjusting valve remains
74
the same for two hours, open it to the full range and clean it
periodically in order to prevent valve sticking.
A. Limestone: CaCO3
75
Particle
Item CaCO3 MgCO3
grade
CaSO3·1/2H2O。
(CaSO3) % 0.15~0.18 0.20~0.21
76
9 Shutdown of FGD Equipment
2) When the bypass baffle opens to over 30% range, the open
range of booster fan moving vane should be adjusted and
controlled until booster fan out of operation.
3) Close the FGD outlet flue gas baffle valve after the oxidation fans
turned off.
2) Switch off main pipe of demister water supply, and turn off electric
valve;
77
3) The demister can be turned to manual status through DCS to
stop flushing.
When FGD set stops, turn off the limestone slurry pump, and execute
drainage and flushing.
4) The liquid level controls the stop of filtrate pump and agitator.
Open the drainage box of filtrate water tank, and drain the liquid
to the drainage sump in the gypsum dehydration area.
5) Turn off the waste water flow valve, and stop the waste water
disposal system. Waste water system will execute discharge and
other tasks under check and repair demand.
Flush the gypsum transmission pipes and drain the water inside the
pipes.
2) Clear the pipe connecting the absorber and the emergency slurry
box.
78
4) Start gypsum discharge pump as maintenance status, and
discharge absorber slurry to the emergency slurry box.
When both of two FGD systems stop, do not stop the process water
system until all flushing work in the system are completed.
1) Turn off mechanical sealing air water and cooling water of all
slurry pumps.
Cut off the power supply of shutdown system, keep power supply for
liquid level monitoring devices, agitators and baffle sealing air fan of
boxes, tanks and sumps with liquid level remained, as well as the
agitator of the emergency slurry box. Periodically check the operating
equipment.
79
5) Absorber and FGD stop.
7) Turn off electric inlet valve of the gypsum cyclone station when
absorber slurry concentration is lower than 1125 kg/m3 and the
absorber liquid level is lower than. 7.0m
3) Don’t drain boxes, tanks or sumps. Liquid level will control the
start and stop of devices automatically.
80
1) Flush the shutdown equipment in time.
3) Flushing time for pumps, pipes and other objects must be enough
(judge the flushing status according to personal experience). Pay
much attention to flushing the slurry transport pipes in order to
prevent residual slurry from depositing or drying as well as
blocking pipes.
81
10 FGD Device Operation Adjustment
82
10.2.2 Adjustment of concentration of slurry liquid in the absorber
83
personnel to assay the limestone material and slurry qualities. If
the particle size of limestone slurry is too big, the fineness should
be adjusted to a proper range. Material purchase department
should ensure the material quality be in proper range if there is
excessive impurity in the limestone materials.
If the limestone slurry quality does not and can still not meet the
requirement after adjustment during operation, it is required to inform
the lab to analyze the limestone quality.
84
be complete.
11) The inlet and outlet of motor’s cooling air should be clear. The
inlet temperature should be less than 45℃, and the air
temperature difference between inlet and outlet should not be
higher than 30℃, and the shell temperature should not exceed
70℃.
12) The motor’s cable head, wiring and earthing wire are proper and
tightly connected. The temperature measuring devices for
bearing and motors are normal and correctly work. Normally, do
not start the motor continuously for two times under hot status (it
is called hot start when the motor’s coil temperature is above
50℃.)
13) Check the equipment’s cooling water pipes and cooling air duct
which should be clear. The cooling water quantity should be
proper.
85
14) During the running, the belts of belt driving equipment do not
slide, not run out of alignment and has no damage. The belt
wheel should be aligned.
15) All belt conveyers must not run out of rating range. Restart with
lower load in case of first start failed. No continuous start is
allowed in case of a second failure. It can only be started after
discharging all loads on the belt. Meanwhile, report to the shift
leader and office.
16) All drive mechanism should be complete and flexible. The pin
connects firmly.
17) Electric executors for air valves and baffles should be complete,
connected firmly and positioned at automatic control.
18) The tanks and vessels are in good shape, with levels normal.
19) The agitators run well. The vibration and temperatures are in the
range.
1) Confirm the sealing system has been shut down, and the spare
system is under good condition.
86
2) The booster fan’s shell vibration value does not exceed 62um,
and the measured value of vibration monitoring complies with the
actual vibration value.
4) The bearing lubricant and grease are within the grease filling
cycle, and no oil leakage occurs to the pipes.
6) The cooling air fan for the booster fan properly runs and the
interlock is put into operation.
7) High and low pressure sealing air fans are in good condition as
standby.
10) All manholes in the flue system are tightly closed. No flue, water
and steam leakages occur.
11) The flue dampers are opened and closed properly, with correct
signal indication.
10.3.4 Absorber
1) No slurry and flue leakage occur to the absorber proper, and its
liquid level, slurry concentration and PH value should be in the
regulated range.
87
points exist at the joints between the flue pipes and absorber.
8) The I & C instrument are in good shape, the wiring is stable and
the measured value is correct.
1) The pump’s gland seal is tight without any leakage of slurry and
water.
3) If the inlet pressure of pump is too high, the water levels of tanks,
vessels and ponds should be timely adjusted to avoid
overloading of pumps. If low, the spare pump should be started.
Manually carry out backwash to the inlet of failed pump, and do
maintenance when necessary.
88
1) Check if the slurry distribution pipe spreads the slurry evenly
without any deflexion, the thickness of the gypsum cake is evenly
suitable, the water content of discharged material is normal
without blockage.
6) The cooling water flow for the water-ring type vacuum pump is
normal, about 6~8m3/h.
7) Check if the pipeline for the process water to filter cloth flushing
water tank is clear or not.
89
the lubrication should be good.
2) The vibration of pumps and motors does not exceed the regular
value.
3) The bearing temperature does not exceed 70℃, and the motor
not exceed 65℃.
4) Regularly check the oil quality and oil level, and replace or fill
lubricating oil.
8) The water pump’s oil tank level and oil quality should be checked
each shift to confirm oil level and lubrication situation normal.
10) The pressure drop should not be large when increasing water
pump’s flow to avoid overloading of the motors.
90
11 Procedures for Accident Treatment and
2) When the persons who are not on duty arrive in the malfunction
site, they are not permitted to perform any operation or treatment
without permission from the shift operator or shift foreman. If the
situation in fact poses threat to safety of persons or equipment,
they could immediately report to the shift operator or shift
foreman.
91
the accident and the shift-in persons could assist to deal with it
under permission. Then the shift turnover work should be carried
out after the accident treatment finished.
8) After the accident is solved, the shift operator should record the
detailed information about the occurrence and treatment of
accident. The contents include: operating status before the
accident, description of accident site, protection action, and
trouble shooting time, sequence of accident treatment, and the
final results, and the damage to equipment if there are some.
8) The inlet pressure of air fan is higher than 800Pa or lower than
-800Pa.
92
closed manually on the site;
1) Phenomenon
2) Causes
3) Treatment
z Confirming the power supply for USP board and that for DC
system is normal. The switches of operating and
emergency power are in power-off position, and switches of
all loads should be off;
93
demister in manual way if necessary;
1) Phenomenon
2) Causes
3) Treatment
z If the 415V power sources are all cut off and the power can
not be resumed within eight hours, please use emergency
equipment to discharge the slurry retained in all pumps and
pipelines. Flush them immediately;
94
are caused by electric protection action.
1) Phenomena
2) Causes
3) Treatment
95
z If the trip of booster fan is caused by the malfunctions of fan
equipment, report the situation to shift leader in time and
contact maintenance personnel for further treatment
immediately. Restart of booster fan is strictly forbidden
before the malfunction is solved.
1) Phenomenon
2) Causes
3) Treatment
z Find out the causes of slurry circulating pump trip and then
96
deal with the problem in line with relevant regulations;
1) Phenomena
2) Treatments
1) Causes
97
z pH value too low (<5.0);
2) Treatment
z Calibrate pH meter;
1) Causes
2) Treatment
Inspect and determine the scaling area on site, and change the
procedures to increase the flushing time of scaling area.
1) Causes
98
z Scaling of gypsum cyclone;
2) Treatment
z Report to the shift leader, and adjust the inlet flue gas flow;
2) Cause analysis
3) Treatment
1) Common malfunctions
99
z Rapid change occurs to the measurement value of pH
meter
2) Treatment
Phenomenon: the running sealing fan trips and the standby one can
not start automatically, and LCD sends out alarm signal.
100
gas. Therefore open the inlet emergency water spraying valve of
absorber and the flushing valve of one-layer demister for cooling.
1) Phenomena:
2) Causes
z The liquid level of process water tank too low, and the pump
trips;
3) Treatment
101
Malfunction
Possible causes Treatment measures
phenomena
Blockage of pipeline
Decrease in Clean the pipeline
flow of slurry Blockage of nozzle
Clean the nozzle
circulating Relevant valves not
pump of switched properly Check and calibrate the status of
absorber valve position
Decrease of pump rating
Maintain the pump
102
Malfunction
Possible causes Treatment measures
phenomena
103
and fan blade).
104
12 Operation of Auxiliary FGD Equipment
6) If the electric motor has been shut down for more than seven
days or locates in relatively humid place, the external inspection
should be done to confirm it is in good condition before startup.
The trial running could be carried out after the insulation is tested
acceptable;
105
8) Persons on duty should stay beside the 6.6KV auxiliary
equipment for monitoring when it is started; when abnormal
situation happens, report to the shift foreman or press the
emergency button to shut down the equipment immediately;
11) After the trial running of auxiliary equipment, the results should
be recorded on record notebook.
106
12.2 Operation and Maintenance of Auxiliary Equipment
2) Electric motor and its mechanical parts should not have strong
vibration, and meet following standards.
750 and
Rated Revolution (r/min) 1000 1500 3000
below
9) There should no water, flue gas and oil leakage in equipment and
system;
107
12.3 Shutdown of Auxiliary Equipment
7) There are fires or floods that pose serious threat to the safety of
equipment;
108
13 Common Problems During the Operation and
System
2) High SO32- content will result in slurry with virus, because the
SO32- covering limestone can prohibit the chemical reaction of
limestone, thus, desulphurization efficiency can not be achieved.
109
13.3 ‘Virus’ of Absorber
2) Excessive dust in flue gas, or too much oil sludge in fuel oil,
aluminum fluoride formed by aluminum and fluorine elements in
fly ash can coat the surfaces of limestone and sulphite
crystalline,which prohibits the chemical reaction, so do the oil
flue, carbon, asphalt, polycyclic aromatic, etc.
110
13.6 Problems Caused by Excessive Cl-
111
13.9 Problems of Mechanical Seal
2) The principle of water balance control is: control the water flow in
all water inlet points in accordance with the data on material
balance sheet provided and designed by Bo Qi Company, and
the slurry flow direction based on material flow process. Don’t
add process water usage point randomly. Do not take the
temporarily-used public water as long-term used water.
During the oxidization air operation, there should be sufficient water for
wetting the air to avoid scaling on pipes.
The flow and current of oxidization air fan should be monitored in its
operation to identify whether the system is normal or not. The inlet filter
should be maintained frequently and cleaned up periodically.
112
13.12 Problems of Flushing Effect of Demister
3) Different flushing water flow is for different load, the parameter for
judging whether flushing water flow is appropriate or not is that
whether the differential pressure of demister is maintained within
the normal range or not.
113
2) The gypsum on filter cloth must be removed prior to operation;
otherwise, long-term staying of gypsum can cause the
deformation of components such as carrier roller, etc.
1) The bypass flue gas damper closed for a long time should be
started up periodically in case that rejection to act causing
accident by accumulated dust cause blockage.
3) For such FGD system without GGH, under the condition that this
baffle is open for a long term, high temperature flue gas should
be prevented from going to FGD outlet gas duct which causes
corrosion-proof layer ineffective.
For such FGD system without GGH, if the liquid level of absorber
exceeds the cofferdam of inlet gas duct, a great amount of slurry may
go into booster fan, probably causing blades damaged. Therefore, the
liquid level must be controlled severely to prevent the false one. The
means to prevent false liquid level is that flush the pressure sampling
orifice of pressure transmitter periodically (once half a month or a
month). The gypsum accumulation can cause false level. Because this
level is related to many protections, these protections should be
shielded or make the DCS level signal normal before flushing.
114