You are on page 1of 37

7

COFFERD AMS
Creupe A. Ferzen EowtN Peul SwerEK, JR.
Consulting Geotechnical Engineer Consultant
Cincinnati. Ohio Lake Bluf, Illinois

STEEL SHEETPILE CELLULAR COFFERDAMS


EpwrN Pnul Swerer, Jn.

lntroduction dam for construction of this project was out of the ques-
tion. The base width would have had to be 230 ft (70 me-
The one-to-one ratio of height to width of cellular coffer- ters), as compared with the 62-ft (18.9-meter) width of the
dams makes their use effective in the construction of dams cells.
and other projects on rivers. Freestanding cellular coffer- Where a river arrn must be located adjacent to a fast-
dams, without stabilizing inside berms, have been built to flowing diversion channel, a cellular cofferdam or portion
a height of 115 ft (35 meters). Figure 7-l shows the cof- thereof is also used. Figure 7-5 shows the cofferdam layout
ferdam for the Markland Powerhouse. This layout was ac- for the Rock Island Second Powerhouse on the Columbia
complished with a double row of 62-ft (18.9-meter)-di- River. The river arm of this cofferdam paralleled the high-
ameter cells upstream. Sheetpiles I 15 ft (35 meters) long velocity river flow upstream and downstream of the dam
were used for the outside sheets of the cells on the water spillway.
side. These sheetpiles reached rock and provided an effec- Upstream, in the deep still waters of the power pool. a
tive water cutoff. 75-ft (22.9-meter)-high earth embankment was constructed
Most of the navigation dam projects on the Ohio River of local sand and gravel terrace materials. An impervious
system have been constructed within cellular cofferdams, seal of sand and silt mixture was tipped over the upstream
one of which is shown in Figs. 7-2.7-3, and 7-4, the Pike face of this embankment. At the river end of the embank-
Island Locks and Dam. The Ohio River in this stretch is ment, the cofferdam terminated in five sheetpile cells 65.8
narrow. Existing navigation had to be maintained, and nor- ft (20 meters) in diameter. These cells were adjacent to the
mal high water had to be accommodated without intem.rpt- spillway gates. High water flows of 400,000 cfs (l1,300
ing construction. To meet these conditions, the work had m3/sec; had to be bypassed through the dam spillway.r
to be staged in sequence across the river. First, the locks The line of cells in the downstream river arm of the cof-
were built in a cofferdam on the left bank. Sheetpile cells ferdam also bordered the high-velocity spillway discharge.
located close to the lock wall provided the necessary clear- Again, cells were required instead of an embankment-type
ance for river barge traffic and for passage of floods. The cofferdam, in this case because of the limited horizontal
height of the cofferdam was set for a two-year-frequency clearances between the tailrace excavation insidc ofthe cof-
return flood. This required a cofferdam height of 63 ft (19.2 ferdam and the adjaccnt river channel spillway discharge.
meters). Fish migration upstream also figured in the choice and lo-
After completion of the locks, the dam was built in three cation of these cells.
cofferdams, staged in sequence as shown in Figs. 7-3 and Were this project locatecl on a virgin river rather than the
74. Figure 7-2 shows the transition from the first-stage well-regulated Columbia River. the upstrearn ernbankment
lock cofferdam to the second-stage, fint dam cofferdam. would have been vulnerable to ovenopping. In such a case.
A 63-ft (19.2-meter)-high alternate embankment coffer- the upstream cells could have been extended to the right
219
220 ADVANCED DAM ENGINEERING FOR D€SIGN, CONSTBUCTION, AND REHAEILITATION

Figure 7- I . The I l5-ft-high Markland Powerhouse Cofferdam.

bank and capped with an impervious pavement of concrete unit oI length for cofferdams of equal height. The length
8 in. (20 cm) thick. Such protection will accommodare an of the cellular cofferdam perimeter is also si_enificantly
overtopping rvithout structural damage to the cofferdam. shorter than that of an embankment cofferdam. This is ap-
The economic comparison between a cellular sheetpile parent in Fig. 7-3, Stage IV of the Pike Island Locks and
and an embankment cofferdam is complex. For the cellular Dam project cofferdams. The desi-en height of cellular cof-
sheetpile type the quantity of fill is less than one-half per ferdams can be lower because they are easily protected from

Figure 7-2. Cofl'crdarn for Pike Island Locks and Darr.


COFFERDAMS 221

infiltration rates are reduced, as are pumping costs. River


closures can be more rcadily made with proper arrange-
ment of cells, and tie-ins with existing structures are more
easily made. Costs of cofferdam removal are also reduced,
by the handling and disposal of less matcrial.
On the other hand, the free{raining select sand and
gravel cell fill required for cellular cofferdams sometimes
is not locally available. The transport of long sheetpiles
into foreign areas without good roads or rail or water trans-
port can also rule out the use of cellular cofferdams.
)
\ The techniques of installing cellular cofferdams are
I sometimes intimidating. This is especially so in dealing
oHro Rtv€R with fast currents and deep water. Major river projects in
developing countries appear to shun the use of cellular cof-
STAGE I ferdams, but the extensive use of these structures in the
LOCKS COFFERDAT.,I United States and Europe attests to their favorable econ-
omies.
Production rates for constructing large cells, such as for
the cofferdam for the Lock and Dam 26 Replacement on
the Mississippi River, are on the order of four cells a
month, with a peak of six. These figures are based on
working around the clock, with floating cranes, and with
experienced crews.
The best work is done with the use of floating cranes.
The work can be spread out over many cells, with conti-
Figure 7-3. Cofferdam stages for the construction of Pike Island Locks
and Dam.
nuity of working crews. If a cofferdam is built with cranes
located on top of the cells, the pace of the work is appre-
ciably slowed; also the work of the pile crews and the fill-
overtopping floods. Riprap stone protection for high-veloc- ing of the cells are not continuous.
ity flows and scour is practically eliminated with the cel-
lular type. Multiple use of the sheetpiles (up to three uses) History and Development
reduces material cost. Recent development of high-strength
sheetpile interlocks has extended the design height of cel- The first cofferdanr of full circular cells was designed by
lular cofferdams. Where foundation conditions are favor- Gen. Harley B. Ferguson and C. S. Boardman and was
able and sheetpiles can reach rock or impervious strata, completed in l91l for the raising of the battleship Maine,

Figure 74. Third-stage cofferdam for Pike Island Locks and Dlm.
222 ADVANCED DAM ENGINEERING FOR OESIGN, CONSTRUCTION, AND REHABITITATION

Figure 7-5. Cofferdam layout for the Second Powerhouse at Rock Island Dam on the Columbia River.

sunk in Havana Harbor. The cofferdam was not an entire 28,000 lb/in. (500 metric tons/merer) in rhe lasr l5 years,
success, as the cells were filled with mud. They partially the development of higher-head cofferdams is advancing.
failed in shear.
The first cellular cofferdam built on the Ohio River in
Height of Cofferdams
1924 was designed by J. S. Miller of the Dravo Corpora-
tion for the construction of Dam 22 bear traps. The cells Freestanding cofferdams consisting of a single row of cir-
were partial rectangles with inside circular arcs, and they cular cells now can be designed for a height of 95 ft (29
provided for a 30-ft (9.1-meter) dewatering head. In 1928 meters). Special layouts with cloverleaf cells or double
the first full-circle cellular cofferdam was constructed on rows of circular cells can be used for even hi_eher heads
the Ohio River by the same company, at Dashields Dam (Fig. 7-6). The term freestanding denotes the absence of
below Pittsburgh. It consisted of 40-ft (12.2-meter)-diam- an inside berm.
eter cells for a 40-ft (12.2-meter) head. The connecting For a cofferdam founded on rock and with an inside
arcs between cells were made with T-piles. The sheetpiles berm, it is possible to desi_en for heads in the range of 120
were Carnegie M-107 section. After this project the con- ft (36.6 meters). The fullness of the inside berm should be
nections between cells were made with 3O-degree Y-piles, contained within the envelope of a line drawn from the wet-
which provided a l0-ft gap berween cells. With this fea- side top of the cell. on a two-horizontal-to-one-vertical
ture, an arm of cells built across a flowing river can easily slope, to the top of the rock on the dry. unwatered side.
be closed. The use of 3O-de_eree Y-piles also improves the This design was used for Racine Locks, as shown in Fig.
structural geometry of the connection. It is the recom- 7-7. This berm was adequate for stability.
mended Y-pile connection in use today. Limitations to increasing the height of cells concern in-
The Tennessee Valley Authority designed and built its terlock strengths, connection piles, cell fill drainage. the
first cellular cofferdam for the Pickwick Dam project in splicing and handling of long sheetpiles. high foundation
1935.2It was 55 ft (16.8 meters) high. By l94l TVA was pressures, and required driving penetration.
building the 98-ft (29.9-mcter)-high Kentucky Dam coffer- With flat rollcd sheetpile sections oi 28.000 lb/in. (500
dam. This cofferdam consisted of 58.89-f,t (17.9-rneter)- metric tons/metcr) interlock strength, cells of 95- to 100-
diarneter cells backed by a 60-ft (18.3-metcr)-high inside ft (29- to 30.5 meter) diameter are fcasiblc, using a facror
bemr. The ntaximum allowable shcetpile interlock value of safety of two for the intcrlock strengrh: ancl 3O-degrce
lorthc M-l0l sheetpiling used in this coff'erdam was 12,000 Y connection piles are available for such eonfigurations.
lb (214 metric tons/mcrer). This value provided a fac-
/in. Sheetpiles 80 to 90 fr (24.4 to 27 .4 metcrs) long are rou-
tor of safety of 1.5. tinely handlecl with slight but inconsequential bending
With the introduction of high-strength interlocks of damage. Sheetpiles I 15 ft (35 nrerers) long have been
COFFEROAMS 223

CONCRETE

SAG FILL

SECTION A -A

38.28'
l_.--------..-l
POWER
HOUSE
,ro.rY -[zez.-,.
lr)
t:
EXC. I N
(,
339
rA
a/
6/
120" Y 7

PLAN

Figure 7-6. Markland Powerhouse I l5-ft-deep cofferdam ofdouble cells. Figure 7-7. The 76-ft-high cofferdam for Racine Locks.

picked up with multiple part slings or tilting beams. With diameter were combined to provide for a 140-ft (42-7 me'
such a device, up to six to eight piles are laid horizontally ter) head. The sheetpiles of the outer row had two-piece
in a beam cradle, which is then pivoted to a nearly upright spliced sheetpiles. The sheetpiles of the inner row were 70
position for hoisting the sheetpiles to set around the tem- ft (21.4 nreters) long.
plate. The process is reversed in pulling and laying down Penetration of sheetpiles into the overburden should be
the piles. Although it has not been done, it is to be expected limited to a maximum of about 30 ft (9.1 meters) for cel-
that sheets longer than I 15 ft (35 meters) can be handled lular cofferdams, but even this is extreme. Difficulties in-
in such fashion, up to the 130-ft (39.6-meter) range. crease rapidly when driving exceeds this amount (Fig.
The manufacturer's length limit on rolling sheetpiles ap- 7-8). Site excavation can effectively reduce the depth of
pears to be 105 ft (32 meters) to I l5 ft (35 meters). Longer penetration.
sheets can be either spliced or set in two pieces. If the nor- Penetration, of course, is a factor that must be consid-
mal elevation of the river permits, the bottom piece is set ered in contemplating cofferdam height. At Tarbela Third
and driven to grade. The top pieces are then set with 5-ft Powerhouse cofferdam, the penetration of the sheetpiles
(1.5-meter) stagger splices' Such splices need not be rein- was extremely compromised by the cobbly nature of the
forced with plates; bead welds are sumcient. Sheetpiles river bed. Driving was limited to a depth of about 5 ft ( I .5
spliced with reinforcing plates can be driven and pulled. meters). Figure 7-9 shows how relatively shallorv cells 50
Cloverleaf cells are a device used to translate the radius ft (15.2 meters) deep were combined with an extensive in-
of curvature of the cell arc from 50% to 33% of the cell side berm and a cement-bentonite panel cutoff wall to de'
width. The interlock stress is directly proportional to the water an excavation 90 ft (27 .4 meters) deep. Again a cof-
radius of curvature; so for any particular interlock stress ferdam o[ cells was required to rnaintain the width of the
the cell width, and corresponding height, can bc increased adjacent tailrace channel and to accommodate the deep
50Vo by using the cloverleaf configuration. scour wall and powerhouse excavation.
Cloverleaf cells are difficult to build. Instead' two rows
of cells, such as the layout used at Marklancl Darrt Pow- Hydrology
erhouse (Fig. 7-6) can be combined to accommodate ex-
tremely high-head cofferdams. At Cannelton Dam cofler- For projects on developed rivers, such as the U.S. inland
dam on the Ohio River, an outer row of 60.48-ft (18.4- river system, a retum floocl of two to ten yean typically is
meter)-diameter cells and an inner row o[ cells of the same chosen. One coft'erdam in a very restricted location, sur-
224 ADVANCEO DAM ENGINEERING FOR DESIGN. CONSTRUCTION, AND REHABILITATION

Figure 7-8. Sheetpile splits and cell distortion with 50 ft of driving

rounded by the steel mills of Pittsburgh, was overtopped elevation. based on retum flood frequencies of 50 years or
and flooded l9 times during the two years of construction. more. For cells, only the economics of flooding and cleanup
Cellular cofferdams can be overtopped without damage. of the cofferdam are involved.
All that is required is a plain concrete cell cap of about g Ifthe cells ofa cofferdam are not capped. then controlled
in. (20 cm) thickness. Cracks that develop between the cap flooding is required before the overtopping of any porrion.
and the perimeter sheetpiles are filled with tar to provide Generally. preflooding is planned to at least a three-quarter
the impervious lid. Another prerequisite is the use of weep depth inside the cofferdam. The time frame is important.
holes for cell draina_ee. If the overtopping depth of water A decision to flood is usually delayed until the lasr mo-
is considerable. say for an upstream arrn, it might have to ment, and is made only after all equipment and movable
be figured in the overturning moment and sliding force. materials have been safely removed from the cofferdam.
Stone riprap provided at the inside base of the cells will The flooding time is dependent upon rhe rate of rise in ihe
protect soft rock from the overtoppin_e waters. river, the volume inside the cofferdam. and the capacity of
If floodwaters were to overtop a major embankment cof- the floodin_e device. A weir-type floodin_e sill can be pro-
ferdam, especially an upstream arm. the ensuing washout vided in a connectin_q arc between cells on the downstream
and sudden release of impounded waters could be a disaster arm of the cofferdam. This location is usually free of float-
and a dan,ger to life and property downstream. Such an em- ing debris. Except on a flashy river, 12 hours is a reason-
bankment is generally carried above any possible floodin_e able fi,eure for flooding time.
The need to preflood a cofferdam before the overtopping
of any of the outside sheetpiles is apparent from a look at
BENToHITE - CEM€Nt the design assumptions. The line of saturation inside the
PANEL CU'TOTF WAIL
CELLULAR cell on the dry side is generally assumed to be at one-third
of the cell height. This results in a certain interlock design
Powt RHous€
TAlLRACE value. Were the ccll to fill with watcr to the top of the
insidc sheetpiles, the combined full hydraulic and fill pres-
sure would morc than doublc the strcss in thc interlocks.
This would probably ruprurc the ccll.

Geology
^4's'
'<(t<'
^\' The inrportant faetors are depth to beclrock or irnpewious
Figure 7-9. Coflbrdam for Tarbela Third Powcrhouse. stratunl. and the overburden profile. The presence ancl size
COFFERDAMS 225

of cobbles and boulders in the soil matrix. and other ob- tant in setting the horizontal penetration of the sheetpile
structions to driving, are to be investigated. Silt and clay cutoff wall. Short flow lines can cause blow-ins.
layers must be identified. An adequate program of borings' The containment and the good dninage of cell fill prob-
with casing drive blows, blow counts on sample spoon, and ably eliminate concem over soil liquefaction in seismic
permeability tests are required. areas. There is no known failure of eithcr cofferdam cells
The steel sheetpile membrane of the cell must be driven or retaining wall or dock cells from earthquakes. Some
to the required founding depth wholly intact, without in- compaction of the sand and gravel cell fill can be achieved
terlock splits. Obstructions to driving' such as cobbles and by dropping it from a clamshell. The impact involves no
boulders larger than l2 in. (30 cm), often can be eliminated danger of splitting a cell. Compaction is also improved by
by site excavation, especially when identilied in soil layers inundating the cell during clamshcll filting. Placing a tem-
of moderate depth. Even for driving through medium sands' porary surcharge of heaped fill adds to compaction.
it is generally more economical to extend site excavation
to a considerable depth to decrease penetration and driving Types of Cells
shifts. In the Ohio River it was common practice to site-
excavate to within 5 ft (1.5 meters) to l0 ft (3 meters) of The literature on cellular cofferdarns adequately describes
rock to eliminate 20 ft (6 meters) of driving. With de- the circular. diaphragm. and cloverleaf cell layouts.
creased driving penetration, the quality of workmanship Where it can be used, the diaphragm cell with straight
greatly improves. crosswalls and 120-degree Y-piles has several advantages.
If weak soils are present in the overburden, they must be First, it generally uses less tonna-se o[ sheetpiles than the
replaced. This can be accomplished before the cell is set other types. by about l0%.3 Second, it is easier to con-
and driven, again by site excavation; or the objectionable struct. Each succeeding template placement is supported
material can be excavated from the cell after it is driven' by the previously driven diaphragm wall. Location prob-
Pumping a head of water inside the cell is a trick some- lems and placement of Y-piles are simplified. Third, the
times used to permit the excavation and replacement of ob- I20-degree Y-piles are more statically determinate and
jectionable materials. This often can be accomplished provide for an easier connection in setting and driving.
without the need for internal bracing. The diaphragm cell must be step-filled over a series of
The presence of highly pervious strata under the wet- cells with the fill initially placed straddling the crosswalls.
side sheetpiles compromises the drainage of the cell fill and This is done by clamshell bucket; hydraulic filling is not
the general stability of the cofferdam. The line of defense possible. (For an illustration of this, see page 410 in ref-
against infiltration is always at the outside sheetpiles' Either erence 4.) Obviously the diaphragm cell does not permit
the outer sheetpiles must be carried a considerable distance construction with a crane working on top of the cells: the
into such soil, again by the help of site excavation, or ad- cells nrust be constructed with cranes on barges. This cell
ditional cutoffs such as by grouting or a slurry trench must is particularly suited to use for long river arms parallel to
be used. the stream flow.
Where the cofferdam base rests on rock, the borings In crossing a river, and where there is appreciable cur-
should be carried a reasonable distance below the top of rent, circular cells must be used. This approach permits the
the rock to check for weak clay seams' cavities, or porosity completion and filling of each cell as the construction pro-
that would add to excessive infiltration. An open stratum gresses. The circular cell configuration also permits con-
below the top of the rock can produce uplift under the cell' structing the cofferdam with a crane on top of the cell,
In such a case, vertical relief holes are drilled down into which is an advantage where floating equipment cannot be
the rock just inside the toe of the cells. One spectacular used.
sliding failure of cells in the 66-ft (20.1-meter)-high cof- Circular cells can be used with T-pile or Y-pile connec-
ferdam for Uniontown Dam occurred along a clay seam 16 tions, but 30-degree Y-pile connecting arcs are recom-
ft (4.9 meters) below the top of the rock. The rock inside mended over T-piles. (See reference 5, pages 416' 417,
the cofferdam was bisected by faults, which weakened it' and 420-423 for a complete discussion of the merits of the
(See further reference to this in the section on "Failures," 3O-degree Y-pile connection.) Thc Y-pile connection is su-
below.) perior to the T-pile in atlowing for a better flow of hoop
The top of the rock profile is also important where abrupt stress and for its better constructibility. Also it is cheaper
slopes are to be encountered. This is espccially so when than the T-pile. When 30-degree Y connection piles are
there is no overburden over the rock. In sonlc cases' tremie used, the connecting arc shoulcl have at least an I l-ft (3.4-
concrete platforms have been uscd uncler certain cells to meter) raclius.
bridge deep chasms in the rock. Moderute river closures of up to 2 ft of clifferential head
Where cellular cofferdams are joined to existing river- can be made by constructing full circular eells across a
banks, the permeability of the terrace materials is impor- river. About l0 ft (3 meters) of space is leti between the
226 ADVANCED DAM ENGINEERING FOR OESIGN, CONSTRUCTION, AND REHABILITATION

cells. The individual cells can be built without difficulty in of the cell diameter. Ten 60-ft ( 18.3 meter)-diameter cells
currents of up to 4 ft/sec. placed in a line have the same perimeter as twenty 30-ft
After the line of cells has been placed and filled across (9.1-mete r)-diameter cells. For low-head cofferdam cells.
the river. the connecting arcs arc progressively placed and shallow arch web sheetpiles of 3000 lb/in. (53.6 mctric
filled. For thc last several arcs a bulkhead can be dropped tons/meter) interlock strength offer tonnage savings.
on the upstream side to cut off the current. This permits In the layout of cells, whether T-pile or y-pile connec-
placing and driving of the downstream connecting arc. tions are used, it is necessary to pay attention to the con-
After its completion, the upstream arc can be placed and necting arc radius. Too large a radius will put too much
the bulkhead removed. Other more complex schemes can pull on a T-pile connection. In fact. a T-pile connecrion
be used in cell arrangements to make river closures against radius equal to the cell radius will always cause distonion
higher heads, up to 20 ft (6 meters). to the main cell, with a tendency to shape the main cell
The U.S. Army Corps of Engineers has prohibited the into a square. The radius of 30-degree Y-pile connecting
use of welded connection piles, whether T-piles or Y-piles. arcs is generally about one-fifth to one-sixth of the main
Several disastrous failures of cofferdams have resulted from cell diameter, whereas a T-pile connection radius is about
welding failures of connection piles.3'6 On the other hand" one-third to one-fourth of the diameter.
properly welded connection piles have better stress flow In the layout of connection piles around the cell perim-
from hoop tension than riveted or bolted piles. eter. it is ahvays desirable to have an odd number of piles
The chemistry and rolling of the sheetpiles are factors in spaced between the four connectors. In this way all of the
producing good weldable metal. Sheetpile st6el has low connection piles are alike, and no mistakes are made in the
cold-weather impact resistance. Laminations rolled in the field. This arran_gement calls for the number of sheetpiles
pile webs from uncropped ingots contribute to the failure in the main cell always to be divisible by four.
of welds joined to the sheetpile web (Fig. 7-10). Connec- Since equipment generally uses the top of the cells for a
tion piles made with bolts add strength through a lamina- roadway, it is important to check the clearance between y-
tion, but welded piles are generally cheaper than bolted or T-piles for road width, leaving a generous safety lane
piles. Although the statistical record of failures favors for pedestrian tramc.
bolted piles, European practice universally accepts the use
of welded connection piles.
Cofferdam Layout
In the selection of cell type and size, it is advisable to
work with one size to reduce template cost. In a line of The construction plant arrangement and the location of ac-
cells, the tonnage factor of sheetpile used is independent cess roads into and around the cofferdam must be planned
in the cofferdam sizing and layout. Additional ctearances
for pump sumps and drainage ditches inside the toe of
berms and cells also must be provided. Flooding gates must
be safely located. Safe excavation slopes in earth and rock
must be planned so that cells are not undermined.
In some situations, cranes located on top of the cells are
of great advantage in reaching the work. With such ..close-
in" positioning, and by using floating concrete mixing
plants, concrete can be placed directly from mixer to forms
without transport (Fig. 7a).
The staging of the work for river diversion has already
been mentioned. River closure is always a problem. but
cells can be arranged to facilitate such closure. At Union-
town Dam Cofferdam, Stage II, the upstream connecting
arcs between cells were made into small 24-ft (7.3-meter)-
diameter full cells. These picket cells were placed first dur-
ing moderately low river llows. When the time came to
close off thc river. a pair of W36 bcanr wales was droppcd
across the upstrcam side of a pair of picket cells. Z-piles
could then bc driven across the gap supported by the tu,o
W36 walcs, thus cuuing off the l2 ft/scc (3.7 meters/sec)
curent. This arrangement, then, provided quiet water to
sct the cell template and sheetpiles (Fig. 7-l l).
Figure 7-10. Laminations in a '*elded Y-pile failure. More and more cofferdams are incorporating wide inside
COFFERDAMS 227

For cells founded on rock, the cell weight is determined


by assuming the bottom 40% of the cell fill buoyant' the
top 60% dry. This follows observation of normal cell
drainage with free{raining sand and gravel fill. Next. the
average width of the cofferdam is usually on the order of
0.90 of the cell diameter. This is with 30-degree Y-pile
connecting arcs carried tangent to a line drawn tangent to
the full cell. This figure can be increased somewhat by in-

36f ,Y creasing the width across the connecting arcs to more than
the cell diameter, a layout exercise.
The moment arm a for resisting moment determination,
FLOW O€tAtL weight X a, is something more than one-half the average
Z -piLg width. This is so because the inside sheetpiles are driven
to refusal, and there is transfer through friction between
the sheetpiles and fill. A usable figure for this is one-half
Ro(t< A -A of the average of the cell diameter and the avel?ge width,
or about 47% of the cell diameter. A "factor of overtum-
Figure 7-11. River closure with picket cells at Uniontown Dam'
ing," which is resisting moment divided by the horizontal
load overturning moment, of not less than 3.6 is the value
berms. This design often is dictated by the sliding potential recommended. This will give a cell diameter very close to
of weak rock strata under the cell foundation. While berms the cell height, and it places the base resultant well within
often are required for this and other reasons, they add the middle third of the cell avera-qe width- The 3.6 value
greatly to the coffendam area, perimeter, and cost. Their has been found to give stability against horizontal displace-
need always should be questioned because high-strength ment of the top of the cell-shear failure.
sheetpiles are available for designing without berms. In designing for cells not on a rock base, it is first as-
sumed that the inner, dry-side' sheetpiles are driven to a
reasonable refusal. A point of overturning at some eleva-
Design
tion below the top of the overburden and above the sheet-
With all the theorizing that has been done in the last 50 pile tip is selected. This elevation is probably the resultant
years concerning cellular sheetpile structures, design is still of all horizontal resisting forces at the base of the cell. Ap-
empirical, with a good flavoring of experience and judg- proximately 0.67 of the penetration depth is another esti-
ment. Space does not permit a full commentary on the nu- mate for this elevation. This point is then used in the over-
merous conflicting ideas that have been developed, but ref- turning stability determination. Penetration for reasonable
erences 7 and 8 provide a good summary. The Terzaghi refusal is probably never more than 20 ft (6 meters) in sand
papeP on vertical midplane shear evaluation has been chal- and gravel. A penetration oftwo-thirds ofI/, suggested by
lenged.ro The gravity block overtuming exercise, often Terzaghi, is not required or realistic.
criticized, is still used. The Cummings shear With such an overturning calculation as that above, in-
determinationrl is extensively used, but again it is based ternal shear determinations are academic. So is the calcu-
on empirical observations and small-model testing. The in- lation for sheetpile friction against cell fill at the wet-side
teraction of the steel shell membrane and the earth fill, base ofthe cell, the so-called sheetpile pull-up failure. Such
amazingly efficient and practical, has yet to be accurately a failure has not been observed in the field: it has been
modeled and probed. found only in small models where gross horizontal deflec-
It is of first importance that cell fill always be free-drain- tions of the top of the cell have been produced. These are
ing granular material with few fines, free of silt and clay' on the order of 10 to l5%, whereas field deflections are
This just about automatically takes care of the shear and seldom over 1.5%. Deflections of cells are often moni-
sliding problems, provided proper width is established to tored. Survey punch marks on the top of the Y-piles are
meet the stability test. And for this the block overturning just as good as more expensive slope indicators.
stability determination is useful. Terzaghi sidestepped this The preference for cells using 30-degree Y-pile connec-
point in his analysis, observing only that double-walled tors has already been mentioned. Even 40-degree to 50-
sheetpile structures of width equal to 85% of the height degree Y-pile connections are preferred to T-piles. For
have stood the test of time. The following observations are bolted and riveted connections of the 3Gdegree Y-pile' a
offered for use in making such an overturning determina- balanced design is desired. After many pul[ tests it has been
tion. They have been a base for "designing" successful determined that the web stress based on thc net area, the
structures for the past 50 Years.3 interlock stress, and the single shear bolt stress should all
22A ADVANCED DAM ENGINEERING FOR DESIGN. CONSTRUCTION, ANO
REHABILITATION

MANUFAqTURCR S'IOLERANCES tolcrances (Fig. 7-l3). or ro make such on-sitc inspcction


aftcr dclivery and bclonc usc. Opcn slots and narrow thurnbs
arc mcasurcs of wcakncss. The amount ol grip. which is
-l thumb rvidth minus slor width, is lound to bc dirccrly re-
latcd to intcrlclck stren-{th.
', ).- sreet cr-are
Hydraulic filling ol cclls can add considcrably and un-
I
necessarily to thc dcsign pressurcs uscd in dctermining in_
terlock strcss. This is espccially so whcrc there is o t igt
flood freeboard of cell height abovc nonnal water levels.
Hydraulic filling can add .10 to 60% ro rhe inrcrlock srrcss
INTERLOCK GAUGE
during filling. strcss rhar othcrwisc is limitcd by the final
Figure 7-13. Gage tbr checking shcerpile inrerlock tolcmnccs. dewatercd conditions. It can cause- lailures in tabricatccl
piles due to oversrress. A comprornisc is to fill hyckauli_
cally to 8 ti (2.4 nrerers) above the nonnal rvarcr level and
be sized fora factorof safety of 2. This increases the rvork- then top out with clamshcll filling.
ing values in single bolt shear by some ZO% over handbook Il an inside berm is pan of the dcsi_gn. consideration oI
values. It permits a more reasonable spacing of bolts. Fur_ berm draina-ee is important. Berms of fine sand can su_9ar
ther reduction in the web stress in the main sheet down rvhen saturated by rvater flow,ing throu*gh the cells.
,eenerally
is provided by increasing rhe *eb thickness to 0.5 in. for either from outside splits and windows or from orher
this pile. sources of infiltration. Stone French gravity drains between
Hand in hand with design goes confidence in the mate_ the cells and berm can prevent this. These drains are day_
rials used. There have been documented instances w,here lighted ro the inrerior of the cofferdam.
new sheetpiles delivered to the job were found si_enificantly Past practice in designing the Ohio River coft'erdams has
deficient in interlock strength-even rvhen backed by cer_ set the elevation of cell saturation at one-third of the height
tified representative mill pull tests. Trvo sample pull tests of the cell on the dry side. By the use of weep holes, and
are no proof for an entire rolling. Tests made subsequent rvith attention to their maintenance. such cell drainage eas_
to delivery have shown deficiencies of 20 to 25% below ily can be achieved (Fig. 7-13). The maximum bulge in the
guaranteed minimum interlock values. cell is generally figured at one-quarter the cell height above
The only way to be assured of interlock quality is to the rock or ground line. Althou,eh this value is used alntost
insist on mill inspection by
-eaging the thumb and finger universally, most field measurements with plurnb lines in_

Figure 7-13. Weep hole drainaee w.irh low phreatic line


COFFERDAMS 229

dicate a bulge much higher. Many sheetpile splits are dis- immediately above the cell basc. the same value is found
covered when the cofferdam is first pumped down and ex- ifgood clean sand and gravel are used. Tan d of28" cquals
cavated. The lack of distress shows that maximum intcrlock 0.53. A factor of safety of 1.25 is adequate .
stresses occur well above the bottom of excavation. How- Where cells are to be founded on bare rock. and often
ever, the H f 4 point is a reasonable estimate of the eleva- this also involves flast-flowin-9 water, a startcr fill is re-
tien of maximum interlock stress. quired to stick the sheetpiles. This can be 6 ft (1.8 meters)
The determination of maximum soil pressure at this F1/4 to 8 ft (2.4 meters) of 3-in. (8-cm) to 6-in. (1S-cm)-size
point has been the subject of much conjecture and field rock. Such open rock fill at the base of the sheetpiles would
testing. Some authorities propose a K. of 0'5. This would result in gross infiltration: so this rock fill must be grouted
appear to be much too high. For the "dry" fill in the top at the bottom of the wet-side sheetpiles. Four-inch ( l0-cm)-
portion of the cell, and where free-draining sand or sand diameter grout pipes welded to the sheetpiles at about 'l-ti
and gravel fill has been used, an equivalent liquid pressure (1.2-meter) centers can help in accomplishing the grouting
of 35 lb/fC seems to be adequate and has stood the test of and seal. When this does not u'ork. a continuous tremie
time. This suggests an active state of stress with Ko : concrete curb can be placed at the top of the rock along the
0.30+. base of the sheetpiles on the water side. Windorvs formed
In applying the final equation in the determination of in- at the bottom of sheetpiles on sloping rock, and left un-
terlock stress, a factor of some percentage is added for the grouted or unprotected, can cause loss of sand fill. In fact.
component force joining the connecting arc to the main cell one cell was completely lost over a weekend through such
at the Y- or T-pile.3''2 This varies from' a value of zero a window. The window was located adjacent to a l5-ft/sec
increase to that figured according to the secant of the angle (4.6-meter/sec) diversion flow,.and the cell fill rvas fine
between the cell centerline and the line joining the center sand.
of the cell and the Y-pile. A lO% increase is considered Where cells are founded on a deep sand and gravel stra-
more than ample. The resultant interlock stress is generally tum. the cell-soil stability analysis is -eenerally satisfied.
limited to one-half of the published ultimate interlock This is especially so if excavation slopes inside the coffer-
strength, or slightly more. dam do not penetrate below a tlvo-horizontal-to-one-veni-
A surcharge from a crane working on top of the cell does cal slope line drarvn from the top of the cell. wet side,
not add to the interlock stress. The interlocks in the top l0 down to the bottom of the excavation or top of the rock- If
to 15 ft of the cell are understressed. At greater depth. there are weak soils under the cells, or deep adjacent ex-
where maximum stress occurs, the horizontal pressure from cavations, whether in rock or soil, the cell and its foun-
crane loads is minor. dation should be investigated for critical slip circle failure.
It is prudent to downgrade second-hand pile interlock Poor workmanship can ruin a good design. We tend to
strength by 25% unless a rigorous program of gaging and look at our designs only on paper. A connecting arc u'ith
pull tests is undertaken. Second-hand piling generally tests 30-degree Y- or T-pile connection on paper looks good and
out well. The slot openings at the ends of the piles espe- figures easily to accommodate the hoop forces. Often. a
cially should be checked. walk around the top of the cofferdam reveals astonishing
Cell fill should be fast-draining, clean sand and gravel departures from the theoretical. In our example. a 90de-
fill containing not more than 15% passing the 100 mesh. gree T-pile may have to accommodate. through distortion
It should be well graded. Gravity drainage with adequate and misplacement of the cells, a I l0-degree attitude '*'ith
weep holes burned in the sheetpiles should be sufficient. If a sharp swing in the adjacent sheets. We need to ask what
more fines must be tolerated, then artificial drainage de- stress anomalies are introduced. Familiarity with actual
vices may be required, such as gravel lenses, vertical filter field construction practices can temper and sharpen design
wicks, and/or deep pumping wells inside the cell. considerations.
Compaction of cell fill is desirable. When filling is done
by clamshell, dropping the fill from some reasonable height Dewatering
will achieve some additional compaction and cause no harm
to the sheetpiles. A moderate amount of water pumped into There arc two major considerations in the dewatering of a
a cell during filling, say 8 ft (2.4 meters) of head, will aid cellular shcetpile coffcrdam. First. a proper defense is nec-
in compaction. A heaped surcharge on top will also help. essary against intlltration of water from outsidc the coffer-
Cell-fillsettlementof about lVosf thedepthof fill istobe clam. Hcre we are dealing with watcr either corning through
expected. the shectpile ntcmbrane-splits, windows, or holes-or
Where foundation rock is competcnt and contains no passing underncath it. Second, water thilt has penetrated
shallow weak seams, design tbr sliding is perfunctory. this outcr defcnse must be controlled. Water that inundates
Sheetpile contact at rock, on smooth concrete, or in soil the cell must be speedily drained, ancl water that passes
exceeds a friction value of 0.50. In the cell-fill material through or under the inner row of sheetpiles must be ade-
230 ADVANCED DAM ENGINEERING FOR DESIGN, CONSTRUCTION, AND REHABILITATION

quately intercepted to prevent movement of soil pafticles. at the top of the sheetpiles, it may be desirable to drape a
Such inflows, if large and uncontrolled, can cause quick- PVC sheet inside the cell on the outside sheetpiles, l0 fr
ness, blow-ins, loss of berm, loss of passive restraint at the to 15 ft down from the top, before the cell fill is topped
inside bottom of the cell, and possible eventual collapse. out.
Reference l3 provides a thorough treatment of the theory With major high head cofferdams it is prudent to have a
of flow nets in the analysis of flows under a coffendam on diver inspection after final driving and before filling of the
a sand foundation. Depending on the permeability of the cell, to check for split sheets and windows.
foundation soils, and whether or not an inside berm is used, Where cells are built in the dry on a blasted rock bottom,
toe filters, french drains, well points, or deep wells may be the blast hole depressions in the rock surface have gener-
required at the inside toe to maintain stability. ally been neatly filled and leveled by a dozer. These shoutd
If the river current is not too great, dumping a sandy silt be cleaned out with a high pressure water jet before the
or clay blanket on the river bottom on the outside may be sheets are seated. In such a case it may be desirable to build
beneficial. For higher currents a PVC membrane ballasted a concrete seal ring on top of the rock to seat and seal the
on the river bed may achieve the same results. Deep grout bottom of the sheetpiles.
curtains, which are an extension of the outside sheetpiles, With regard to floodwaters rising to the top of the sheet-
can be used to depress and lengthen flow lines. A benton- piles, never try to extend protection above the tops ofsheets
ite-cement panel slurry cutoff wall was used through and by adding a low earth dike on the top of the cell fill. This
under the cell sheetpiles to reach an impervious stratum has been attempted, and it has been found that the water
(see Fig. 7-9). The flow net analysis will indicate the prac- retained by such a dike spills over the tops of the outside
tical depth needed for cutoff. sheetpiles, and will completely inundate the cell. It adds
For cells on a rock foundation, several points must be greatly to the hoop tension, and would probably result in
emphasized. Sheetpiles are usually driven in pairs. In seat- rupture of the cell.
ing the sheetpiles on or into the rock, it is desirable to make Reasonable design practice establishes a line of satura-
one last driving pass on every individual pile to avoid win- tion at one-third the height of the cell on the dry side. With
dows at the bottom. Sheetpiles damaged at the top through clean sand and gravel fill this can be controlled in the field
drivin_e are often trimmed by burning off the damaged sec- with an adequate number of weep holes burned in the
tion. Thus, the individual lengths of a pair may not be sheetpiles. Gravity drainage through these holes will gen-
equal. Paint marks on each pile near the top, placed a fixed erally lower water levels inside the cell to within 5 to l0 ft
distance from the bottom of the sheet, will readily indicate (1.5 to 3 meters) of the rock (Fig. 7-13).
a high sheet. Weep holes should be spaced about 8 ft (2.4 meters)
In the process ofsetting and driving the sheetpiles, holes apart veftically, at about 5-ft (1.S-meter) centers around
are burned in the sheets to attach guy lines with rope block- the inside perimeter of the cofferdam. For coarse sand and
and-falls to hold the sheetpiles in alignment. These should gravel fill, the weep holes can be 1.5 in. (4 cm) in diam-
be carefully covered with a welded patch before disap- eter. With finer sand fill the diamerer should be limited to
pearing underwater. There should be no holes left in the 0.75 in. (2 cm). The elevation of the first top row of holes
outside sheetpiles. should be about 5 ft (1.5 meters) below the water level at
The mismatch of the square bottoms of sheetpiles on a the start of pumping. If a cell fails to drain properly, ad-
sloping hard rock bottom requires a positive seal. This can ditional weep holes should be provided. Ifthey cannor con-
be a grouted gravel choke, sand cement bags, or a pourcd trol the problem, then a deep well pump in the cell may be
underwater tremie concrete curb on the outside, water side required. The elevation of cell drainage is readily apparent
of the piles. from weep hole drainage and wet interlocks.
In assessing actual leakage through the sheetpile inter- The rate of pump down of the cofferdam is generally not
locks, several phenomena require attention. In the region over 5 ft (1.5 meters) per day. This is ro provide an op-
of the high interlock stress, the leakage should be of minor portunity for the celt fill to establish proper drainage. The
consequence; normal river silt will plug these openings. same is true of any high excavated earth slopcs inside the
However, in the upper part of the sheetpiles, the stress is cofferdam. If drainage in any cetl is held up, rhen the
low, and the interlocks are relaxed and open. Infrequent pumping should be stopped until more weep holes are
high water does not carry much silt into these upper inter- burned, and the cell drains.
locks; so a high river will produce a marked increase of In the initial pump down, it is important to poke man-
flow into the cell fill. This is especially noticed with the ually into the weep holes with a rod to dislodge gravel
first flood. It is important at this time to watch the satura- blockage and to develop a coarse filter in back of the hole.
tion buildup in the cells and to take necessary action. At This is also an important exercise during subsequent major
extreme high water, 24-hour vigilance is necessary. Where river rises.
a cofferdam is built in a stable resen'o;r with water always It is desirable to have a row of weep holes at least l0 ft
COFFEROAMS 231

(3.5 meters) below the top of an inside berm. This is in the ber, and sticking a bent sheetpile into the river bcd in the
region where the berm passive pressure is still at a low proper circular pattern is extrcmely ditficult. To overcome
value. These holes can be burned in the sheetpiles before this problem, a stiffening beam, of WlO x 30 lb size, is
the sheets are set and driven. attached to every lOth or l5th pile. By fint positioning
Pumping rates can vary widely. A rate of 10,000 gpm these stiffened master pile sheetpiles around the template
(630 liters/sec) is a maximum figure for a cofferdam the at their exact location, a true cylinder can be closely ap-
size of the Markland Powerhouse cofferdam. The pumping proximated. These first master piles are tacked down into
of the Rock Island Second Powerhouse cofferdam was ini- the river bed, and then the balance of the sheetpiles are set
tially over 40,000 gpm (2520 liters/sec), finally reduced symmetrically around the template between the master
to 7000 gpm (zt4l liters/sec). At Lock and Dam 26 Re- piles. (For a good description of this process, see reflerence
placement, a24-acre cofferdam on a sand bottom, pumping 4, pages 395-396.)
peaked at 90,000 gpm (5680 liten/sec) and stabilized at Time is a factor in fighting deep water and high river
about 60,000 gpm (3780 liters/sec). During initial pump- currents. The work of setting the sheets around the tem-
down, when a large volume of water must be evacuated in plate and securing a reasonable penetration should be
a short time, and before soil voids and interlocks are plated scheduled around the clock, seven days a week. lf water
with fines, the pumping rate is at least 1.5 times the fol- velocities exceed 3 to 4 ft/sec ( I to 1.2 meters/sec), and
lowing maintenance pumPing rate. if the water is deep, some form of current deflector will be
needed. Actually, building of the vulnerable part of the cof-
ferdam, such as the upstream arm, should be scheduled
Construction
during the dry, low-flow season. An ingenious deflector
Mistakes made during the construction of cellular coffer- was successfully used in currents of 15 ft/sec (4.6 me-
dams are legend. Whether throu-sh ignorance, inexperi- ters/sec) in building the upstream arm of the cofferdam
ence, or impatience with detail, they are repeated over and for the Long Sault Dam on the St. Lawrence River (Fig.
over again. 7-14). It was portable and was jumped ahead with each cell
The most common involve the initial setting of the sheet- completion, with little time involved.
piles aroirnd the template, before driving is started. Where Once the sheetpiles are set around the template, the next
the sheetpiles enter the river bottom, it is essential to crucial operation is the driving. Here again mistakes are
achieve as near a true circle as is possible. With increased easily made. A variety of driving conditions must be met,
penetration, this is even more important. Of course, if there from loose sands to very compact dense sands, from clean
is distortion of the bottom of the cell with only 5 ft (1.5 homogeneous soils to strata containing isolated boulders or
meters) total driving, little can go wrong. With all sheets nested cobbles, tree trunks, or scattered rip.ap.
interlocked their entire length, even with the distortions the
cell is still structurally sound. However, if the pattern where
the sheetpiles enter the river bottom is not a circle, then
the sheets are also out of plumb. If portions of the cell are
in the form of a truncated cone, then progressive driving
and further penetration will continue to exaggerate the dis-
tortion until a rip or a split occurs.
Related to this geometry problem are three other factors:
the depth of water, sheetpile length, and water current.
Water depths of 30 ft (9.1 meters) and current velocities
below 3 ft/sec ( I meter/sec) cause little or no problem.
This is so with sheetpiles up to 80 ft (24.3 meters) long
and with a two-tier template. With greater water depth and
higher curents it is desirable, first, to add to the template
depth: three rings to the template, with the bottom ring
within 15 to 20 ft (4.6 to 6 meters) of the river bottom,
will improve the control of the sheet setting.
When sheetpiles are greater than 80 to 90 ft (24.3 to 27 .4
meters) in length, the sweep or bend introduced in the pile
during pickup causes problems; and these problems are
magnified as water depth and currents increase' The setting
process is started with key sheetpiles placed in proper lo- Figurc 7-14. Ponabte current deflector used on Long Sault Dam coffer-
cations around the template. A single sheetpile is very lim- dam constnrction.
232 ADVANCED DAM ENGINEERING FOR DESIGN, CONSTRUCTION, AND REHABILITATION

A single sheetpile or pair of sheetpiles by itself has a A328 steel has a low Charpy impacr value. Ir is suscep-
weak axis with a low section modulus. It is easily de- tible to notch failure at low temperaturcs. In burning off
flected, especially when driven deeper than the adjacent sheetpiles, or burning holes in them, a clear straight or cir-
sheetpiles. With the universal use of vibratory pile ham- cular cut should be made. Sheetpiles have been known ro
mers, considerable penetration is easily achieved, particu- rip apart, starting at a notch accidentally burned in a cutoff.
larly in the upper loose soils. Without patience and disci- Most of these accidents have happened at temperatures be-
pline the penetration around a cell can become erratic. low 20'F (-6'C).
One of the important criteria for good driving control is In making splices of sheetpiles with plates, a level work
paced progress in penetrating the river bottom. First, and bed should be provided, and the ends to be matched should
before any driving commences, all of the sheetpiles should be of the same widths. Failures have occurred from mis-
be completely set around the template. Once production matched sheetpiles. Also, if the sheets have been mishan-
driving begins, penetration for the first round should be dled or pulled from a cofferdam such that they have a per-
limited to an S-ft (2.4-meter) lead. Following this, the lead manent sweep, they should not be used for splicing.
should be reduced to 5 ft (1.5 meters). For driving in dense Splicing stock cut from such sheetpiles will form a kinked
sands, the lead should be reduced further, to 2 ft (0.60 splice that makes for setting difficulties.
meter). A sweep in a pulled pile does not preclude its reuse. If
When a large boulder or some other obstruction is met it can be set in a cell, then the driven structure is structur-
that stops the sheet, driving on the adjacent sheets should ally sound. Kinks in a sheetpile make it unusable.
be stopped. The obstruction should be removed or de-
flected by excavation, jetting, or some other means such as
Failures
use of a chopping beam (reference 4, pp. 396-397). Even
in loose soils, use of excessive lead with a vibratory ham- There have been sliding failures of cellular cofferdams, but
mer can easily result in splits. Piles carried down evenly not at the interface between the sheetpiles and rock. Sev-
and together will remain interlocked. eral have occurred in shale rock formations within the top
There are many good vibratory hammers. The high en- 15 ft of the rock. The one at Uniontown Dam was caused
ergy is such that interlocks can be melted if the hammer by a thin horizontal layer of coal and fire clay approxi-
sits on an immobile pile. When penetration can no longer mately 15 ft below the rock surface. Water in this seam not
be advanced with a vibratory hammer, an impact hammer only lubricated the clay, but added uplift pressure. A con-
must be used. A double-acting hammer of 8750 ft-lb (1209 tributin-e factor was a further weakening of the rock strata
kg force-m) energy is a good size for sheetpiles of ]-in. by intersecting faults. A large slab ofrock rotated 70 ft into
(9.5-mm) web. Impact hammers with energies up to 13,100 the cofferdam with four undamaged cells riding on top of
ft-lb (l8ll kg force-m) can be used on 0.5-in. (12.7-mm) it.la
sheetpile webs. Impact hammers with energies above The sliding failure at Cannelton Damr5 was caused by
15,000 ft-lb (2073 kg force-m) will cause excessive dam- the breakup of the top layers of shale rock due to excava-
age to the sheetpiles. A measure of refusal is ten tion of the dam piers adjacent to the cells. A large clover-
blows/in. on driving two sheetpiles with an impact ham- leaf cell split, at Lower Monumental Dam on the Snake
merwith 8750 ft-lb (1,209 kg force-m) of energy. River, was attributed to plywood protection sheets under
If split interlocks are encountered in the pump down and the sheetpiles. These were placed on the stilling basin floor.
excavation of the cofferdam, then pumping operations Sheetpiles have a good bite even on smooth concrete, as
should be suspended while straps are welded across the split has been demonstrated where high cells have been placed
(Fig. 7-8). For welding on sheetpiles, a low-hydrogen on concrEte lock sills. Wood protection is unnecessary and
welding rod should be used, with attention given to pre- undesirable.
heat. The phenomenon of repair of splits is worth analyz- Many cells have ripped apart, and for a multitude of rca-
ing. The first observation is that split interlocks do not rend sons. Overstress due to conrplete flooding of the cell by
to unzip. They are produced in the driving operation and overtopping flood waters was a cause of a breached up-
hardly ever are caused by excessive hoop tension. The split stream arm at Lower Monumental Dam. Bad nretallurgy in
never shows cell membrane distortion that would suggest thumbs and fingers, laminations in sheetpiles, poor welds
distress from high hoop tension. The adjacent sheetpiles in fabricated T-piles, and mismatched splices have all taken
bridge this discontinuity of hoop tension, through anchor- their toll. Deficiencies in the net web area along a line of
age of the lower driven ends in the soil below and the com- bolts in fabricated sheetpiles have caused fractures and cell
plete interlock of the upper portion of the ring of the cell emptying. (There is a good accounring of such failures in
above. This behavior says something about assumed large references 6 and 16-18.)
hoop tensions and the distribution vertically along the Cells do not fail by overtuming. Excessive horizontal
sheetpile interlock, and is also a reflection on the magni- movement at the top has been observed; it does not cause
tude of the K, factor of horizontal soil pressure. failure, but can render a structure inoperable. This is a shear
COFFERDAMS 233

failure, the cause of which is inadequate cell width or im- a mass of several thousand tons have struck cofferdams.
proper cell fill. The sand drains installed in the cells of leaving a dent several feet deep without rupture of the cell.
Shipways l0 and I I at Newport Newsr3 were a remedy for Cellular cofferdams, while temporary, are often major
weak cell fill. Observations indicate that a 60-ft-high cell dams themselves. The trend to higher cofferdams will con-
could move 3 or4 ft at the top without rupture. tinue. These temporary structures rcquire the same nurture
Sheetpiles can absorb heavy impacts. Barge tows having and care as that given to perrnanent dams.

EARTH AND ROCKFILL COFFERDAMS


Cleuor A. Fe'rze,n

lntroduction may suggest changes that will make the scheme more prac-
tical. If the contractor proposes
a different scheme for con-
Earth and rockfill cofferdams are the most iommonly used struction of the cofferdams, the designer and resident en-
structures for diversion and for protection of the work area gineer have a well thought-out plan with which to compare
during construction of the main dam. The diversion coffer- the contractor's proposal.
dam is normally a temporary structure that diverts the The importance of development of a detailed diversion
stream while the main cofferdam is being constructed. On scheme and cofferdam construction schedule cannot be
most projects, the main upstream cofferdam involves a sub- overemphasized. An entire construction season may be lost
stantial amount of materials, and it is incorporated into the through unforeseen difficulties if a well thought-out plan is
upstream section of the embankment. Hence, its design is not prepared and specified, and the contractor is permitted
an integral part of the embankment design, but special fea- to proceed without one. The owner inevitably pays in many
tures such as an impervious slope blanket may be required ways when a construction season is lost.
to the height of the cofferdam. Sheetpile walls or cells may
be used in combination with earth and rockfill cofferdams
as tie-ins to structures or as filling and overflow structures. Diversion Cofferdams
All surface drainage should be diverted beyond the limits
of the upstream and downstream cofferdams, as the dis- The layout of the diversion cofferdam must be based on the
charge from side draws or from the adjacent mountainsides site topography and on the location of the outlet works.
during major storms can damage upstream blankets and fill When the outlet works are designed, consideration must be
the embankments area with water. The surface drainage given to the ultimate need for a tie-in to the diversion struc-
diversion features should be designed to handle a major ture. The diversion cofferdam is considered to be a high-
storm and be adequately protected against the high-velocity risk, temporary structure, and the designer must determine
flows generated from the adjacent mountainsides. what frequency of overtopping and what consequences
Cofferdams are constructed under time constraints re- thereof are acceptable for the planned life of the structure.
lated to the weather and to the quantity of streamflow. The amount of water stored behind the upstream diversion
Hence, it is imperative that the cofferdam materials be se- cofferdam normally would be relatively small, so that there
lected so that they can be placed on a regular schedule re- would be little damage to the downstream public from a
gardless of the weather conditions at the site. Access to the failure; however, a failure could cause a substantial delay
materials must be ensured, and in some cases the materials and increased costs in constructing the main cofferdam. Al-
should be stockpiled nearby to ensure orderly delivery to though the divenion cofferdam is a temporary structure.
the cofferdams. The designer should preconstruct the cof- the design must take into account all the factors related to
ferdams on paper based on a thorough knowledge of the the safety and stability of a permanent structure, including
site conditions, and should develop a time and materials seepage through the dam, underseepage. slope stability,
chart for each step of the construction work. The designer slope protection, and so on. In some cases, a smaller pre-
should develop specific requirements to ensure that the cof- diversion cofferdam must be constructed so that cutoff or
ferdam will be constructed in accordance with the devel- other foundation treatment measures may be accomplished
oped plan. During development of the plans and specifi- for the diversion cofferdam.
cations, the resident engineer should review the diversion The height and the related frequency of overtopping must
scheme and the cofferdam plans, as the resident engineer be based on judgmental factors related to the risks involved
234 ADVANCED DAM ENGINEERING FOR DESIGN, CONSTRUCTION, AND REHABILITATION

during the time span requircd to raise the main cofferdam Main Cofferdams
to tlrc same elevation as the diversion cofferdam. Diversion
cofferdams normally are constructed for a high frequency The main cofferdam usually is a large structure containing
of overtopping, but some diversion structures have been a considerable quantity of material. For instance, the main
constructed for a relatively low frequency of overtopping. cofferdam at Areia Dam2o had a height of approximately
The crest elevation of the diversion cofferdam at R. D. Bai- 306 ft (93.3 meters). For this reason, the main cofferdam
ley Damre was established at the 5-year flood level for June is usually included in the upstream section of the embank-
to December floods but less than the l-year flood level on ment as stage I embankment construction; and its design
an annual basis. For Areia Dam,20 a lO-year return period must include adequate pmvisions to ensure that it will be
risk was taken for the initial closure cofferdam. stable and have adequate watertightness for the storage and
Most diversion cofferdams, or at least that portion of the drawdown conditions to which it will be subjected. [n many
cofferdam that actually diverts the stream, must be con- cases, this will require foundation and abutment treatment,
structed very rapidly under a favorable 5-day weather fore- cutoff walls through pervious foundation materials, grout-
cast. Hence, the closure section must be constructed of ing, and other provisions associated with the main dam
weatherproof materials that often must be placed under construction. These same requirements apply to cofferdams
water. Dumped rock with sufficient fines to form an im- located outside the embankment limits. At Patoka Dam2l'22
pervious barrier would be an ideal material. Sand and gravel the main upstream and downstream cofferdams were lo-
with an upstream impervious blanket may also be used. cated outside the embankment limits, as the overbunden
Materials for the closure section must be readil! available. under the entire embankment area had to be excavated to
To effect a quick closure, it is often expedient to stockpile the top of the rock-a maximum depth of 70 ft (21.3 me-
all of the needed materials on the streambank. The time ters). In this case, the eductor dewatering system for the
limits for completion of the closure section of the coffer- upstream and downstream excavation slopes served as
dam should be based on reasonable production require- seepage-control measure for the cofferdams. When water
ments for a 24-hour workday. was impounded against the cofferdams, it was extremely
Most diversion cofferdams are constructed without pro- important that the eductor system be kept in operation; oth-
tection for overtopping. However, in many situations erwise, the excavation slopes and cofferdams would have
overtopping protection is considered necessary. The diver- collapsed; and for this reason, an emergency backup power
sion cofferdam for R. D. Bailey Damle was a semiperma- system was required for the pumps serving the eductor sys-
nent structure approximately 60 ft (18.3 meters) in height. tems. The cofferdams and the excavation during the flood
It was needed to protect the area at the toe of the main of January 1976 are shown in Fig. 7-16.
cofferdam for an extended time during the installation of a The main cofferdam for any major dam has the capacity
concrete cutoff wall into the rock foundation along the up- to store an appreciable quantity of water that, if suddenly
stream toe of the main dam. The diversion cofferdam con- released, could cause catastrophic damage to the down-
sisted of seven, rock-filled, interconnected, 65-ft (19.8- stream public and to the work site. To reduce the chances
meter)-diameter, steel sheetpile cells that were supported of failure, many designers now are providing higher cof-
on the downstream side by a protected rock fill. The mod- ferdams, and devising methods for constructing them to
ified design for the diversion cofferdam overflow section, full height in short periods of time. The cofferdam with the
based on hydraulic analyses, is shown in Fig. 7-15. After least known chance of overtopping is the main cofferdam
modification of the downstream prctection, the cofferdam at Areia Dam,2o which was designed to prevent overtop
withstood several overtoppings without substantial dam- ping by a 500-year return flood.
age. For small- and medium-size dams, the diversion capac-
ity is usually based on the capacity of the permanent low-
level outlet works. For large dams, a special diversion tun-
FL(T
nel may be constructed with a much higher flow capacity
than would be required for permanent low-level dis-
cr0
charges. After the size of the divenion conduit or tunnel
III. SLIISHED 6TOIIIEl) RIPRAP has been established, a graph can be developed showing
the pool elevation versus exceedance frequency per l0O
years, as shown in Fig. 7-17 for East Fork Dam.23 On the
graph, data from historical floods are plotted, which are
DRAIXA6E LAYER
'I.I[. usually grouped into floods within the normal construction
Figure 7-15. R. D. Baitey Dam. Cuyandot River, West Virginia. diver- season and floods for the remainder of the year (all-season
sion cofferdam, dctails of downstrcam protcction. storms). The exceedance frequencies are based on the con-
COFFERDAMS 235

Figure 7-t6. Patoka Dam. Patoka River. Indiana. lv{ain upstreanr and doqnstrcam cofferdanrs during fiood ofJanuary 1976. Photo counesy ofU.S
Arm_v Engineer District. Louisville.

duit and gates being fully open, and log booms and trash 4. In wide valleys construct the cofferdam to full height
racks must be installed prior to diversion to prevent the except lor a closure section at one abutment. and re-
outlet uorks from bein_s plu_e_eed by trees and other debris. quire the closure section to be constructed at a min-
The gates must be tested to ensure that they are fully op- imum daily placement rate.
erable. and emer_gency power must be available for oper- 5. In narrow valleys use staged construction. as shorvn
ation of the gates unless they are left fully open at all times. in Fig. 7-18, to maximize the protection level wirhin
From the -sraph. the cofferdam elevation is selected that the least amount of time.
will give the de_sree of risk desired. However, it must be
considered that storms can occur at any time that will cause The cofferdam for East Fork Damrs was considered to
the historical floods to be exceeded. At East Fork Dam. be a well-planned structure. but the problems encountered
the elevation selected for the main cofferdam was 737 ft during construction illustrate the difficulties rhat ma]- be
(221 .6 meters). From Fig. 7-17 the exceedance frequency expected on any project. A temporary diversion cofferdanl
per 100 years at this elevation is 1.5: that is. the cofferdam to EI.635 lt (193.5 meters) rvas provided ro prorecr rhe
has been designed to protect against a 67-year flood, or a workin_e area lor the main cofferdam. The latter had to be
flood that is expected to occur once in 67 years. The plot constructed in three successive stages, utilizing randonl
tbr the construction season in Fig. 7-17 rvas used to estab- rock (interbedded shale and Iimestone) in stages I and II at
lish intermediate elevations f,or the cofferdam to achieve a minimum placement rare of 10.000 yOr lZOlS.O mr) per
the minimum risk lor overtopping during its construction. day on a 7-day-week schedule. Stage I \.{'as to be con-
Methods to assure that a cofferdam will be constructed structed to El. 689 fr (2 l0 meters) during the period o[ Ivlay
on schedule and constructed to tull hcight with a minirnum 15. 1974 to July l. 1971: this provided protection in cxcess
exposure to overtopping include the lollowing: of the flood of rccord lor the construction season, as shorvn
in Fig. 7-17. Stagc il was requircd to bc complctcd to El.
l. Whcnever possiblc, select materials that can bc l16 ft (218.2 mctcrs) by August 15. 1974. and stage III
placed and compactcd undcr advcrse wcathcr condi- was rcquired to be completcd to El. 131 tt (221.6 meters)
tions, and specify minimum daily placenrcnt ratcs. by Octobcr I. 197.1. Ranclom earth u,as originatly specified
2. Minimizc the use ol u'cathcr-scnsitive materials. Ior stagc III to utilize thc glacial till overlying the bedrock
3. Provide material sources that arc readily availablc in thc spillwuy excavation. but during construction random
undcr all weather conditions, or providc tbr stockpil- rock was utilized above El. 615 ft (205.7 meters) to ex-
ing. peditc constnrction.
236 ADVANCED DAM ENGINEERING FOR OESIGN. CONSTRUCTION. AND REHABILITATION

737 .5

t)
=
laJ
LrJ
u-
-
-

trJ 680
LrJ
)o
o
o-
670

CI
^t
cl
s-l -l^l =l '."l -l
dl =l*l
EXCEEDAHCE FREOUE}ICY PER 1OO YEARS
Figure 7-17. East Fork Dam. Little Miami River, Ohio. Frequency of storage utilization for l4-ft oblong conduit with gates fully open.

During construction of East Fork Dam, an environmen- placing the materialar a rate of 20,000 yd3 (15,291 m3; per
tal suit resulted in a work stoppage on the main dam from day. The material was placed in 8-in. (20.3-cm) lifts, and
July 25, 1973 until May 2l , 1974. The preparatory work each lift was compacted at natural moisture content with
in the valley bottom including construction of the upstream four passes of a Hyster Model C455A self-propelled tamp-
diversion cofferdam and the downstream cofferdam re- ing roller, followed by two passes of a towed Bros Model
quired considerable time. The actual stream diversion was 450 50-ton (a5,359-kg) rubber-tired roller. Because of
not made until August 12, 1974. The stage I cofferdam area heavy rains that fell on August 29 and 30, 1974, the cof-
was stripped to bedrock, approximately minimum El. 615 ferdam was overtopped on Augusr 30, 1974. The overtop-
ft (187.4 m), and fill placement was srarted on August 17, ping eroded a 150-ft (45.7-meter)-wide gap through the
1974. By August 29, 1974, stage I cofferdam had been stage I cofferdam. Approximately 50,000 yd3 (38,167 m3)
constructed to El. 648 ft (197.5 m) with rhe conrracror of disturbed material was excavated from the cofferdarn
COFFEROAMS 237

u tttttaM OOWN'ITT M

tr. tra

Ir. It. ,2 !
'1,

T'I.OTAINAGT IIANXTI

tor ot tocx
ttrrt lo uNw:atxltto
rocx

Figurc 7-18. East Fork Dam, section through three-stage main upstreanr collcrdarn.

area and hauled to a waste area. By September 8, 1974, REFERENCES


the cofferdam had been reconstructed to El. 6-18 it (197.5
meters). The stage I cofferdam rvas completed to El. 689 l. Stone & Wcbster Engincering Corporation. "The Rock Island Proj-
ect." American Pou'er Conierence, Chicago. Apr. 1981.
ti (2 l0 meters) on September2O. 1974, stage II was com- l. TVA. "Stecl Sheet Piling Ccllular Coff.'rdams on Rock," Technical
pleted to El. 716 fr (218.2 meters) on October 22, 1974, lllonograph No.75. Vol. l. l9-57: reprinted 1966.
and stage III was completed to El. 737 ft (22-1.6 meters) 3. Srvatek, Edwin Paul. Jr.. "Cellular Col{c'rdanr Design and Prac-
on November 26, 1974. Even rvith the delays caused by tice," Jrrrrrnal of the lydtcntovs and Harbors Divi.siorr. rlSCt. Vol.
the storm and washout. stage I cofferdam was completed 93. No. WW3. Proc. Papcr 5398. pp. 109-131. Aug. 1967.
4. Patteson. J. H.. "lnstallation Techniques for Cellular Stnrcturcs."
in fewer days than originally specified, as were stages II
ASCE Confcrence on Design and Installation of Pile Foundations
and III also. The rapid construction of alI three stages can and Cellular Structures. Lehigh Universit;-. Apr. 1970.
be attributed to the skill of the contractor, in addition to 5. Srvatek, Edwin Paul. Jr.. Summary of Day Remarks. "Cellular
the ready accessibility of an all-weather material. The com- Structure Design and lnstallation." Lehigh UniversitJ' Conference on
pacted random rock had a low permeability, so that an up- Design and Installation of Pile Foundations and Cellular S(ructures.
pp. .ll3-423. Apr. 1970: Library of Congress Catalogue Card Num-
stream impervious blanket was not needed. The highest
ber 77-1.11705.
pool against the cofferdam during construction of the re-
6. Crayman. Roben F.. "Cellular Structure Failures." Lehigh Llniver-
mainder of the embankment was El. 696.5 ft (2 12.3 me- sity Conference on Design and Installation of Pile Foundations and
ters), on February 25, 1975. Cellular Structures, pp. -183-385. Apr. 1970.
As no one can predict when a probable maximum storm 7. Lacroix, Yves et al.. "Design. Construction. and Performance of
will occur, neither the cofferdam nor the embankment can Cellular Cofferdams." ASCE Specialty Conttrence. Ithaca Section.
Comell University. "Lateral Stresses in the Ground and Design of
be considered to be safe against overtopping until the em-
Eanh-Retaining Structures." pp. 271-328. 1970.
bankment is completed to full height. and the spillway is 8. Lehigh University Conterence on Design and Installation of Pile
fully operational. One solution to this potential problem is Foundations and Cellular Structures. pp. -'ll9-.138. Apr. 1970: Li-
to arrnor the crest and downstream slope to prevent erosion brary of Congress Catalogue Card No. 77-l'11705.
durin-e overtopping. An example of how a hard rockfill dam 9. Tezaghi. Karl. "Stability and Stillness of Cellular Cofferdams."
was successfully protected from overtopping is described Transactiorts,..ISCE. Vol. I 10, pp. t08-l-l I l-1, l9-15.
10. Esrig. N{. I.. "The Stability of Cellular Cofferdams against Venical
by Leps.la Armoring of a soft rockfill cofferdam or an
Shear," l.!CE. JSlvlFD. Vol. 96. No. Sitl6. Proc. Paper 765{. pp.
earthen cofferdam to withstand an overtopping is more dif- 1853-1862. Nov. 1970.
ficult. A properly anchored 80-mil PVC membrane placed l[. Cumnrings, E. M.. "CellularCollerdamsand Docks." Proc., ASCE,
in a notch could possibly pass a limited flow over an em- Vol. 83, No. WW3. Sept. 1957 (also lrar.roctions. ..lSCE. Vol. tl5.
bankment. Attempts to armor one earthen embankment with 1960).
rock-filled gabions indicate that this method of armoring is [2. Rossow, Mark P.. "Shcetpile Interlock Tension in Cellular Coffer-

slow, expensive, and possibly not successful. Whenever


danrs," Jorrnral d Gcotcclurical Engintering. Vol. It0. No. 10.
ASCE. Paper No. 19210. Oct., 198.1.
possible, the cofferdam area should be backflooded prior t3. Whitc. Lazarus. and Prcntis, Ednrund Astlcy, Colfenlazrs, ?nd cd.,
to overtopping. to help reduce crosion of thc toc ol thc Colunrbia Univcrsity Prcss, Nc*' York. I950.
cofferdam and to rcduce the possibility ola brcach. Hence, l{. Fishcr, Paul R.. ct al.. "Fountlation Construction Pnrblcnrs at Corps
consideration should be given in the dcsign to methods of of E,nginccr Projccts." ,ISCE Pro<'culilgs for "Fountlutions For
preflooding that could raise the water in the protccted arca Darns." rn Enginccring Foundation Conference, Pacific Crovc, Ci\.
pp. 133-l.ll, Mar. 197,1.
to the elevation oI the downstream coffcrdam.
[5. Fetzcr, Claudc A., "Prurgrcssivc Failure in Shale (Cannclton Dant
Further guidance in the design and construction of cot'- Stagc I Coftcrd:rnt Failure)." Ohio River Vallcy Soils Scnrinar Vl,
f'erdams for large dams is prcsented in a notable work by Seminar Pr<tceulitrgs. Ft. Mitchcll, KY, Oct. 17, 1975.
Wilson and Marsal.25 16. Carle, Rtlbcn J., "Discussion of 'Ccllular Collerr.lant Design and
238 ADVANCED DAM ENGINEERING FOR OESIGN, CONSTRUCTION. AND REHABILITATION

Practice' by E. P. Swrtek." ASCE, JW'WHD, Vol. 93, No. WW2. sion on Qucstion No. 48. l3th Congrcss on Largc Dams (ICOLD).
Proc. Paper 592a, p. 267, May t968. New Delhi, India. 1979.
17. Grayman. Roben F., "Discussion of 'Ccllular Coffendam Design and
22. Feuer, Claude A., "Patoka Dcm Tesrcd," USCOLD Neu.slettcr,
Practice' by E. P. Swatck." ASCE, JWWHD. Vol. 93, No. WW2.
Nov. 1979. pp.6-9.
Proc. Paper 5924, p. 269. May t968.
[8. Depanment of the Army. Corps of Engineers. Officc of The Chief 23. Fetzer. Claude A., "Use of Compacted Shale as Dam Embank-
of Engineers. "An Analysis of Cellular Sheetpile Cofferdam Fail- ments," Proceedings, Seventh Ohio Valley Soils Scminar. Lcxing-
ures," Apr, 1974. ton. KY, Oct. 1976.
19. Fetzer. Claude A., "R. D. Bailey Dam. Performance during April 24. Leps, Thomas M.. "Flow Through Rockfill." Embanlonent-Dam
1977 Flood," Proceedings, U.S. Army Corps of Engineers Geo- Engineering, Casagrande Volume. John Wiley and Sons, New York.
technical Conference, New Orleans, LA, Nov. 1977. t9't3.
20. Cooke. J. Barry, "Progress in Rockfill Dams," Journa! of the Geo- 25. Wilson. S. D., and Manal, R. J.. "Current Trends in Design and
technical Engineering Dit'ision,,{SCE, Vol. I10, No. 10, proc. pa- Construction of Embankment Dams," ASCE, prepared for ICOLD
per 19206, pp. 1383-14l{, Oct. 1984. Committee on International Relations, C. S. Ospina. Chairman. and
21. Feuer, Claude A., "Patoka Dam-Foundation Treatment," Discus- ASCE Geotechnical Division, W. F. Swiger, Chaimran. 1979.
8
EARTHOUAKE RESPONS E ANALYSIS OF
EMBANKMENT DAMS
I. M. Ionrss Jnugs Mlcsael DuxcnNl
Managing Principal Professor of Civil Engineering
Wood*'a rd - C l1'd e Consu It ants Virginia Pol;'technic Institute and State Universitt'
Oakland. California Blacksburg, Virginia

lNTRODUCTION of shaking. If these soils are unlikely to be vulnerable


(either because of the nature of the soil as described above,
Observations of the behavior of earth dams in past earth- or because the anticipated level of shaking is too small),
quakes have highlighted the value of seismic stability eval- then the pseudostatic method of analy'sis should provide a
uations in assessing the overall performance of an eafth reasonably adequate desi-en procedure. For soils that are
dam in a seismic area. The near failure of the Lower San likely to be vulnerable to major strength loss or to the de-
Fernando Dam in the February 9, 197 I San Fernando velopment of high excess pore water pressure. the dynamic
earthquake increased the importance of such evaluations method of analysis offers a more realistic approach. It
among design engineers. should be noted that the dynamic method can be used for
The general practice for evaluating the seismic stability all soil types.
of all earth dams had been the use of pseudostatic analysis The dynamic method of analysis is described in this
procedures,a'*5 but experience gained from evaluating the chapter. and an example is provided of its use in evaluating
performance of the Lower San Fernando Dam and other the behavior of an existing hydraulic fill dam during a ma-
dams built of cohesionless soils indicated that there are se- jor earthquake.
rious limitations to the pseudostatic method of analysis.
Dynamic analyses, which provide better indications of the OUTLINE OF DYNAMIC METHOD OF ANALYSIS
behavior of such dams under earthquake loading condi-
tions, have been developed and refined over the past 20 The use of a dynamic method of analysis was first sug-
years. Nevertheless, pseudostatic analysis procedures con- gested more than 20 years ago.s With the advent of finite-
tinue to offer a simple and reasonable means tbr evaluating element procedures, improventent in characterization of
the potential behavior of embankments built of clay soils, static and dynamic material properties, and advances in
or those constructed of very dense cohesionless soils with cyclic testing, the dynamic method of analysis has been
little likelihood of major decreases in undrained shear continuously improved and refined.{6 The first detailed ap-
strength due to anticipated levels of shaking. The pseudo- plication of the full procedure involved the evaluation of
static method of analysis, coupled with an evaluation of the failure of the Sheflicld Dam in the 1925 Santa Barbara
possible permanent deformations, can provide an adcquate earthquake made by Sccd, Lec. and Idriss.6 Thus, the pro'
evaluation procedure, depending on the charactcr o[ thc cedure olten has becn rcfcrrcd to as thc Sced-Lee-Idriss
slope-forming materials. More details regarding thc mcthod analysis proccdurc. It should be notcd that nlany othcr gco-
of analyzing embankment deformations and additional re- technical engineers havc contributed to the refincnrents and
cent refinements can be f,ound in the refercnces.'-* enhancenrcnts incorporatcd in the procedurc, espccially
The decision about whether or not to use the pseudo- over the past [5 years.
static nlethod for any given dam is dependent on whether Once an analysis cross section (or sections, as appropri-
the embankment or the foundation soils are likely to be ate) has been selected, the following stcps are undertaken
vulnerable to major strength loss due to the postulated level in the dynamic method oi analysis:
239
24O ADVANCED DAM ENGINEERING FOR DESIGN. CONSTRUCTION. AND REHABILITATION

l. Calculation of the initial static stresses existing in the STATIC ANALYSIS PROCEDURES
embankment and its foundation before the earth-
quake. Typically, plane strain conditions are used in The procedures used for complete analysis of thc strcsses
this step. and movements in earth dams under static conditions.
2. Selection of a time history of base excitation to which which were developed by Clough and Wooclward,t Kul-
the dam and its foundation might be subjected. Ap- hawy et al.,e and Duncan et al.,lo'llare performed in a
propriate inputs from geologists and seismologists are number of steps, or increments. Using incremental analysis
needed to complete this step adequately. procedures provides a convenient means of representing
3. Assessment of the dynamic properties of the soils changes in geometry during construction of the embank-
comprising the dam and its foundation, such as shear ment, changes in loading during filling of the reservoir,
modulus, damping characteristics, bulk modulus, or and nonlinear stress-strain behavior of the cmbankment
Poisson's ratio, that influence response to earthquake materials. As noted later in this section, however, simpli-
excitation. Because the material characteristics are fications are used in specific applications.
nonlinear, it is also necessary to determine how the Incremental analyses follow the stages of construction
properties vary with strain. and loading as they occur in the embankment, step by step.
4. Calculation of the response, using an appropriate dy- At each stage of the analysis the stress-strain properties of
namic finite-element analysis procedure, of the em- the embankment materials are adjusted in accordance with
bankment-foundation system to the selected base ex- the calculated values of the stresses in the elements, to
citation, including determination of thb stresses model their nonlinear stress-strain behavior. Applied in the
induced in the embankment and its foundation. Plane most straightforward way, an analysis to determine pre-
strain conditions are also used in this step. eafthquake stresses in an embankment involves:
5. Conducting cyclic tests on representative samples of
the dam and its foundation, to measure the combined l. A number of steps (usually eight or more) to simulate
effects of the initial static stresses and the superim- construction of the embankment.
posed dynamic stresses in order to evaluate the gen- 2. A number of steps (usually fouror more) to simulate
eration of pore water pressures and the development filling of the reservoir and development of steady
of strains in these soils. A sufficient number of these seepage conditions within the embankment and its
tests should be performed to permit similar evalua- foundation.
tions to be made, by interpolation, for all elements
comprising the embankment-foundation system. Al- Such an analysis is followed faithfully through the stages
tematively, for the foundation layers and for existing of construction and loading that actually occur in the em-
embankments, the cyclic strength characteristics may bankment. Sequential simulation of the events involved in
be estimated, based on standard penetration (SPT) construction and loading of the embankment affords a log-
blow count and existing correlations of SPT blow ical analysis scheme. Provided the stress-strain propenies
count and cyclic strength. These blow counts are also of the embankment and the foundation used in the analysis
helpful in estimating the residual strength in these are appropriate, incremental analyses should result in
soils.T stresses and deformations that reasonably approximate the
6. Evaluation of the factor of safety against failure, actual conditions in the field.
either during or following the earthquake, based on . In the case of analyses to establish pre-earthquake
pore pressures generated by the earthquake, the soil stresses in an embankment dam, the calculated deforma-
deformation characteristics, and the strength charac- tions are not of interest. As a result, the analysis procedure
teristics. can be simplified. The stresses in the embankment are de-
termined almost entirely by (l) the requirements of equi-
In addition to the above steps for a dynamic analysis, the librium, (2) the final geometry, and (3) the loads due to
following advice, offered by Seed,a is quite appropriate: seepage that act on the embankment. The sequence ofsteps
"Be sure to incorporate the requisite amount of judgement involved in construction of the embankment and develop-
in each of the steps . . as well as in the final assessment ment of seepage through it have little or no effect on rhe
of probable performance, being guided by a thorough long-term static stresses in the embankment. Therefore. it
knowledge of typical soil characteristics, the essential de- is not necessary to follow precisely the various steps in the
tails of finite element analysis procedures, and a detailed history of the construction and loading of the embankment.
knowledge of the past performance of embankments in provided that the final condition inclucles the appropriate
other earthquakes. " geometry and loads due to seepagc.
The above steps are discussed in more detail below. An For this reason, pre-earthquake stress analyses are usu-
example is presented later to illustrate their application to ally performed as follows:
an existing earthfill dam in northern California. l. Construction of the embankment is simulated using
EARTHOUAKE RESPONSE ANALYSIS OF EMBANKMENT OAMS 241

buoyant soil weights for materials below the phreatic sur- in which Ao,. Ao.,, and Ar,_, are the increments of stress
face in the embankment and foundation, and total soil during a step of the analysis; and Ae,, Ae-r, and A7., are
weights for materials above the phreatic surface. Using the corresponding increments oF strain. E, is the tangent
buoyant weights for submerged materials accounts for the value of Young's modulus, and r,, is the tangent value of
buoyancy effects of seepage in the embankment. Eight or Poisson's ratio.
more steps, each corresponding to addition of a layer of Duncan and Changl2 showed that E, can be related to the
elements to the fill, are used for this part of the analysis. stresses in the soil by means of a number of stress-strain
2. The remainingeffects of seepage in the embankment parameters whose values can be determined from the re-
and foundation are included by applying seepage forces to sults of triaxial tests on the soil. The relationship between
nodal points in the region beneath the phreatic surface. E, and the stresses is expressed as:
These forces are calculated for each element, using the
expression: Rr(l - d)(o, - or)lr *, /o,\"
sin
E' : [, _
L 2ccosd*2o3sin{ l^P"V,)
S:it*A (8-r)
(8-3)
in which S is the seepage force per foot of length of dam
(two-dimensional analysis), i is the hydraulic gradient. 7,., in which o1 and 03 are the principal stresses, and p, is at-
is the unit weight of water, and ,4 is the area of an element. mospheric pressure. (Other pardmeters are defined below.)
These forces act in the direction of the hydraulic gradient, As shown in Fig. 8-1, the stress-strain characteristics of
and are distributed equally among each of the nodes at- almost all soils exhibit two characteristics that make it very
tached to the element. The seepage forces are calculated difficult to represent their stress-strain behavior by a single
only for the final pre-earthquake seepage condition. The modulus value. First, the stress-strain behavior of soils is
loads are usually divided into five to ten equal increments, nonlinear. As the deviator stress increases, the axial strain
and applied in as many analysis steps, to reduce the chances increases in a nonlinear fashion, and when the deviator
of local overstress due to too-rapid application of large stress becomes equal to the strength of the soil, the strains
forces. increase without limit. Second, both the stiffness and the
stren-qth of the soil depend on the value of the confining

Material Properties for Static Analyses


lA'* -*-T {
ro
Both the "construction" and the "seepage" phases of the
analysis are performed using drained stress-strain and
strength properties of the embankment materials, consis-
tent with the notion of using a long-term steady seepage
I
E
o
o
I
8
o-i--f
,f'
xerc^"
b
condition as the pre-earthquake stress condition.
The most widely used method of modeling soil stress- 6
I

6
rl
strain and strength behavior in these analyses is the hyper-
bolic stress-strain relationship developed by Duncan and
Changr2 and modified by Duncan et al.l0
In each increment of the analysis the stress-strain be-
o
o
c
o
q,

:
o
I

4
{,4{
rt 5
havior of the soil is treated as being linear, and the rela- ,
tionship between stress and strain is assumed to be gov- o -l;Peok,volue
emed by the generalized Hooke's law of elastic
o
a
H
,F
deformations, which can be expressed as follows for con- v
ditions of plane strain: o
o 4 t2 r5 20
Axiol Slroin-€-o/o .lol
aor E. 812 r6 20 3l
- ;e osP 3l
;;:, (r + v,)(t -2v,) .g
o o
rul

- v,) Y' 0 lIr,.1 o


cl
,-ol|
vt (t - r,) o lJ ae,i .9
o
EI
ol

[., 00 +)lo,.,j E
3
6
EI
ol
(-)+

(8-2) Figure 8-1. Drained triaxial tcsts on loose silic:t srnd.


242 ADVANCED DAM ENGINEERING FOR DESIGN, CONSTRUCT]ON. AND REHAEILITATION

pressure. As the confining pressure increases, both the the reduction in friction angle for a tenfold incrcase in
stiffness and the strength increase. confining pressurc, as described below.
The volume change characteristics of soils exhibit sim- o The parameter R. relates the actual strcngth of the soil
ilar behavior. Volumetric strains increase nonlinearly as the to the asymptotic value of deviator stress, and, to-
axial strain increases, and the magnitude of the volumetric gether with the initial tangent modulus value, governs
strain depends on the magnitude of the confining pressure, the shape of the stress-strain curve. The value of RTis
as shown in Fig. 8-1. the ratio of the actual strength to rhe asymproric de-
The hyperbolic stress-strain relationships were devel- viator stress value.
oped to make it possible to represent these types of behav- o The bulk modulus number K6 and the bulk modulus
ior in finite-element analyses of stresses and movements in exponent m, which relate the bulk modulus of the soil
earth masses and in soil-structure interaction problems. The to the confining pressure. The larger the value of K6,
hyperbolic relationships use eight parameters to character- the larger the value of the bulk modulus at a confining
ize the stress-strain behavior of soils: pressure of one atmosphere. The larger the value of
rn, the more rapidly the bulk modulus increases with
o The modulus number K and the modulus exponent rt, increasing confi ning pressure.
which relate the initial slope of the stress-strain curve
(the initial tangent modulus) to the confining pressure. Additional details concerning these parameters and the hy-
The higher the value of K, the larger the initial tangent perbolic stress-strain relationships are given in Duncan et
modulus of the soil at a confining pressure equal to al.
lo
one atmosphere; and the larger the value of n, the more Typical values of the hyperbolic parameters for various
rapidly the modulus increases with increasing confin- typesof compacted soils are shown in Table 8-1. These
ing pressure. parameter values were determined from analysis of several
o The strength parameten c, @0, and Ad, which govern hundred triaxial tests on more than 50 different soils com-
the way the strength of the soil varies with confining pacted to various densities and water contents. The strength
pressure. For cohesive soils, the pactmeters c and @ and stiffness of each of the soils shown in Table 8-l in-
are used to relate the strength ofthe soil to the confin- crease with increasing degree of compaction. The quantity
ing pressure by means of the conventional Mohr-Cou- RC in Table 8-l is relative compacrion, or dry density ex-
lomb strength relationship. For cohesionless soils, @o pressed as a percentage of the maximum dry density as
and A@ are used. The parameter @o is the value of @ determined by the Standard AASHTO compaction test.
at a confining pressure of one atmosphere, and A{ is The parameters @o and Ad listed in Table 8-l are used

Table 8-'1. Soil properties.


Relative RC
Unified density Stand. 'r^ do Adc
classification D. Proctor lbld des deg lb/ft2 K Rl Kh
GW, GP lOOTo t05% 105-150 42 9 06m 0.40 0.7 t75 0.2
sw, sP 75% 100% 100-145 39 7 0 450 0.40 0.7 125 0.2
50% 95Vo 95- l.l0 36 5 0 300 0.40 0.7 75 0.2
25% 90% 90-135 33 1 0 200 0.40 0.7 50 0.2
t0o% I l0-135 368 0 600 0.25 o.7 450 0.0
95% I05-130 346 0 450 0.25 0.7 350 0.0
90% 100-t25 324 0 300 0.25 0.7 250 0.0
85% 95- 120 302 0 150 0.25 0.7 t50 0.0
l0OVo ll5-135 33 0 500 400 0.60 0,7 200 0.5
9s% I l0- 130 33 0 400 200 0.60 0,1 100 0.5
90% 105- I 25 33 0 300 150 0.60 0.7 15 0.5
85% 100- r 20 33 0 200 100 0.60 0.7 50 0.5
CL tN% I l5-135 30 0 400 150 0.45 0.7 t40 0.2
95% I l0-r30 30 0 300 120 0.45 0.7 il0 0.2
9OVo t05- r 35 30 0 200 90 0.45 o.7 80 0.2
85% 100- I 20 30 0 100 60 0.45 0.7 50 0.2
Relativc density: ASTM D 0253-d
=rcductioniodperlO-foldincrcaseinol:c=cohesionintercept;K=mqtulusnumberl'n=moduluserponinr:f,)=6o;iur"orio:trr=bulkmodulusnunrU.r,.=tJit
modulus exponcnt.
EARTHOUAKE RESPONSE ANALYSIS OF EMBANKMENT DAMS 243

to repnesent the effect ofconfining pressure on the angle of viously. Values of ,(6 and m can be determined from the
internal friction of cohesionless materials. Mainly because results of conventional drained triaxial tests with volume
of particle crushing, values of { for sands, gravels, and change measurements.
rockfill materials decrease as confining pressure increases. The values of the hyperbolic parameters listed in Table
This behavior can be represented effectively using the fol- 8-l can be used to estimate Parameter values for analysis
lowing equation: of pre-earthquake stress conditions in embankment dams.
If goodnuality drained triaxial tests on the embankment
soils are available, it is preferable that they be used to de-
: - ad r"c,, (84)
0 do
e) termine the parameter values for analysis, instead of using
the values in Table 8-1. The calculated stresses are deter-
mined largely by equilibrium considerations, however' and
in which d is the angle of internal friction at confining pres-
so are not highly sensitive to the values of the stress-strain
sur€ 03 : I atmosPhere, A@ : decrease in @ for a tenfold
paErmeters.
increase in confining pressure, and po is atmospheric pres-
sure.
Effects of Stress-Strain Parameters on Values of
To determine whether the soil is being loaded or un-
Catculated Stresses. Two components of the pre-
loaded, each step is analyzed twice. If the changes in stress
earthquake stresses are of principal interest in earthquake
calculated the first time a step is analyzed indicate that an
analyses of embankmentsl the vertical effective stress (o-')
element is being unloaded or reloaded, thq element is as-
and the shear stress on horizontal planes (z,r).
signed a value of unloading-reloading modulus (8.),
Calculated values of oy vary somewhat with the relative
rather than 8,, and this value is used the second time the
stiffness between adjacent zones in embankments. For ex-
step is analyzed. The relationship between E, and the
ample, if the core of a dam is much more compressible than
stresses in the element can be expressed as follows:
the adjacent shell, the values of o, near the base of the core
witl be smaller than the values of o., at the same level within
Eu,: Ku,r"C:)" (8_s) the shell, as a result of the tendency for the stiffer material
to carry more load. The effect is not highly sensitive to the
value of relative stiffness, however, and acceptable accu-
in which K,, is the unloading-reloading modulus number, racy can usually be achieved using estimated values of the
and the other terms are as previously defined. Values of stress-strain parameters.
K,,can be determined using data obtained during unload- Calculated values of zo. in embankments vary with the
ing in conventional triaxial tests. Values of K,, vary from values of Poisson's ratio, or bulk modulus, used in the
1.5 times K for stiff soils to 3.0 times K for soft soils. analysis. All other things being equal, the higher the values
As originally developed,l2 a constant value of Poisson's of K6 and m, the larger the calculated values of r.*. This
ratio was used for the soil. Subsequent research and ex- occurs because the tendency for lateral spreading in an em-
perience with practical applications have shown that closer bankment increases as the values of Poisson's ratio and
simulation of the soil stress-strain behavior can be achieved bulk modulus increase. As the tendency for lateral spread-
if the value of Poisson's ratio is varied during the analysis. ing increases, the shear stresses on horizontal planes also
Duncan et al.ro developed a procedure for evaluating Pois- increase.
son's ratio using the bulk modulus of the soil. The rela-
tionship between the tangent value of Poisson's ratio and
bulk modulus is expressed as follows: EARTHOUAKE GROUND MOTIONS
A dynamic analysis requires the use of an acceleration time
IE,
,,=;_# (8-6) history, to be applied at the base of the embankment-foun-
dation system. Available empirical and analytical proce-
dures offer the means to estimate the main characteristics
in which B is the bulk modulus, and the other terms are as (e.g., pcak acceleration, velocity, frequency content, du-
defined previously. The value of B can be related to the ration, etc.) as needed to select an appropriate time history,
stresses as follows: or, in some cases, a number of time histories. Typically'
such a time history is applicablc in thc free'field, either at
B= Kur.C:) (8-7) the ground surface prior to construction of the dam or on a
hypotheticat outcrop of the material underlying the em-
bankment-foundation system, which is typically a rock or
in which K6 is the bulk modulus number, m is the bulk rocklike formation. For this purpose, a rocklike formation
modulus exponent, and the other terms are as defined pre- is typically defined as a formation having a shear wave ve-
244 ADVANCEO DAM ENGINEERING FOR OESIGN. CONSTRUCTTON, ANO REHABILITATION

tn
c
.o
o
L
c,
(l,
o
(,

, t8 ?t ?4 ?7 30 33 36 39 4? 45 48 5t 54 57 60
Time - seconds
Figure 8-2. Time history ofapplied base rock accelerarions.

locity in excess of 2500 fps (762 meters/sec). In the larter DYNAMIC SOIL PROPERTTES
case, the ground-surface or the outcrop motion can be read-
ily converted to an interface motion for input into the re- Properties of soils under dynamic loading conditions are
sponse analysis.13 An example of a time history represent- nonlinear and hysteretic. The quasi-nonlinear (also called
ing an interface or an applied base rock acceleration is equivalent linear) representation23 of this nonlinear behav-
shown in Fig. 8-2. ior has been most widely used for embankment and foun-
Chapter 5 in this book offers some guidance regarding dation soils. In this representation, the shear modulus and
this aspect of the problem. In addition, available empirical damping ratio of the soil are expressed as a function of
procedures for estimating the needed ground motion pa- strain. Curves such as those shown in Fig. 8-3 for the vari-
rameters in the free-field are included, for example, in pub- ations of G/G^u* as a function of strain appear to be ap-
lications by Bolt,r{ Idriss,15.16 Dobry et al.,t7 sadigh et plicable to most soils. The value of G_o" is usually ob-
al.,rE Seed and ldriss,re Hermann and Nuttli,2o Clmp- tained from cyclic tests at very low strain levels or from
bell,2l and Joyner and Fumal.:2 in-situ shear wave measurements. For most soils, this max-

x lc
lo
c lo
o IL
l8
@)
lr
oilo
olItr
!l
2llx
o Ronge of volues for dolo
ol
-l
3l ,
6

EI :
EI Eo o.
ol
E
=l
-t o
ol
ol o
!l (n
E
arrl

o
to-4 O-3 to-a
Sheor Stroin, I -p€rcenl
Figure 8-3. Variations of shear modulus with strain. From Seed and ltlriss.2l
EARTHOUAKE RESPONSE ANALYSIS OF EMEANKMENT DAMS 245

imum modulus, in psf, can be approximately expressed by of a compliant base. The user is encouraged to use a ver-
an equation of the following form: sion that allows for a compliant base.

G.u* : l000li2*.(o.)^ (8-8) CYCLIC STRENGTH CHARACTERISTICS

Cyclic strength characteristics are generally determined by


in which /cr** is a coefficient that varies from about 40 to an appropriate laboratory testing program on either recon-
80 for clean sands and from about 70 to 150 for gravelly stituted samples or high-quality undisturbed samplcs, as
soils, o. is the mean effective pressure in psf and n = I /2 appropriate. Testing procedures as well as test interpreta-
for clean sands and gravelly soils. The mean effective pres- tion are discussed in many publications (e.g., Lee and
sure is obtained from the static analyses summarized in an Seed,ro'll Lee et aI.,32 Finn et al.,ll and the document on
earlier section of this chapter. "Liquefaction of Soils during Earthquakes."aT
More information regarding the basis for equation (8-8) Soil samples in the laboratory, which are consolidated
and values of&2-". for various cohesionless soils are avail- under initial stress conditions similar to those of an element
able in the references.2a-26 of soil in the field, are subjected to cyclic stress loading
Figure 8-4 shows average values of damping for sands, conditions to estimate the potential for pore-pressure
clays, and gravelly soils. The references cited above also buildup and development of strain (or deformation), to
include fu rther information regarding dampin g. evaluate the cyclic resistance of the soil.
Curves such as those shown in Figs. 8-3 and 8-4 are used These strength characteristics may also be estimated
in total stress analysis, and the nonlinear stress-strain be- using correlations with standard penetration test (SPT) re-
havior of the soil is accounted for by iteratively adjusting sults, such as those shown in Fig. 8-5.
the modulus and damping values until a reasonable con- Typically, cyclic strength is expressed in terms of the
sistency is obtained between the selected parameters and cyclic shear stress (or cyclic shear stress ratio, i.e., cyclic
the computed strain levels throughout the embankment- shear stress divided by the precyclic effective normal stress
foundation system. on the plane of failure) required to cause a given level of
In recent years, effective stress analyses and nonlinear strain, or excess pore-water pressure, in a specified number
analyses have been proposed. Space limitations preclude of loading cycles. Examples of the results of a series of
discussing these procedures in this chapter; an excellent laboratory cyclic tests are shown in Fig. 8-6. Note that the
summary of the procedures was included in the document results are for samples isotropically (K. : l) as well as
on "Liquefaction of Soils during Earthquakes," issued by anisotropically (K. ) l) consolidated prior to the appli-
the National Research Council in 1985.47 cation of the cyclic load. The results shown in Fig. 8-6 are
for 30 cycles and 5% strain. The parameter cr shown is the
RESPONSE ANALYSIS ratio of the shear stress prior to the application of the cyclic
load, on the plane of failure during cyclic loading, divided
The response of the embankment-foundation system to the by the initial effective normal stress on the same plane.
applied base rock motion is most conveniently obtained by This ratio was also discussed earlier in this chapter in the
using a dynamic finite-element procedure. Computer pro- section pertaining to static stresses.
grams QUAD 4?7 and FLUSH28 have been used for this A criterion of 5% axial strain, for example, has fre-
purpose. Both programs utilize the equivalent linear pro- quently been used for evaluations of dams subjected to
cedure outlined above. earthquakes (e.g., Seed et al.2e). This criterion was estab-
The response of the embankment-foundation system is lished on the basis of correlations between the results of
calculated in the time domain in QUAD4. Thus, the ma- seismic stability evaluations by the procedure described
terial properties can be adjusted over specified intervals of herein and the performance of earth dams that were sub-
the duration of shaking, as appropriate. This allows for jected to significant earthquake loading. Case histories of
evaluating the influence of progressive failure on the be- earth dams subjected to earthquake loadings show that if
havior of the dam (e.g., the Lower San Fernando Dam, as the strain at any location within the dam and its foundation
discussed in Seed et a[.2e;. is smaller than 5 %, the earthquake had no significant effect
The response ofthe system is calculated in the frequency on the stability of the dam. It should not, however, be con-
domain in the program FLUSH. Accordingly, it is not pos- cluded that the stability or intcgrity of the dam is neces-
sible to conduct progressive failure analyses using this pro- sarily impaired if the strain exceeds 5Vo at some lscations
gram. within the dam or its foundation, The effect of strains ex-
In their original formulation, both QUAD4 and FLUSH ceeding 5% depends on the zone of the dam-foundation
use a finite-element mesh supported on a rigid base. Recent system where they occur, and on the relative extent and
modifications of each program now can incorporate the use location within a specific zone, as described in greater de-
245 ADVANCEO DAM ENG]NEEBING FOR DESIGN. CONSTRUCTTON, AND REHABILTTATION

I o'.1 lo o o
I E-t
tn

'i\i
C
q

c
I
6
'6
v,
I
i
o
3
qr

F.
3g =6 ggE
--!
U I
a
(a

.42 :=
-6 --e
t.:r E
c

{isiilEi{i >q 'b.. t_


lr

i3!!rli3!E t(o D<s o\ .'g :?


Oo o,|oa(o+) oo* ot. I' +ri
rr'l
69
v, '6=
Er- o\.
lua!rad-rollou 6urOuoO
}C E3P
GoO
roc \o' ry lno
{
>
o
,A-
,:-:J v\
- o. ,ar*
tt 9 OE
,o 6 €€
cc
|ui
Yo,
!uro
--tr!
d\ rl
U' ;.
uz
o
o
c
t.
.
tl o t :i
oJCl
9
..\ i -tb
L'!
(,, ;
t.? Y Et,'
a
a\ '.Un
o
o .E
o
B
3 bdl
EE )

a f{o 18.{* ?
E :9s
o li
\ t:

Ir
i,Xi {
TO
t
t
I
!r
o,
I

t-
N (, ilL
o- u

E 3;, it
roF
loto
9g
:c.
I
I

e
(
iil! I
3t
v)
% - ollou 6u1dwo6 ;ue ;oatnb3

E riE-;E 'Bs 6

I -J

;ci;r:ii €
o
{
ii!i;sii
(aooa()D
J,
o
tt
? 9:
uoe

lualrad . OrIOU 0u'6uOO


EARTHOUAKE RESPONSE ANALYSIS OF EMBANKMENT DAMS 247

0.5
tail by Seed et al.lr in thcir evaluation of the Lower San
Fernando Dam as it was affcctcd by thc l97l San Femando
earthquake.

0.q
STABILITY EVALUATION
D Thc seismic stability of the earth dam is evaluated by com-
o paring the calculated equivalent uniform cyclic shear
0'3 stresses induced by the earthquake wirh the cyclic shear
d
F strength characteristics, to determine the potential strains
s in the embankment and foundation. These potential strains
represent the strains that would develop in that part of the
r
d
F embankment or foundation if it were not constrained by
q 0.2
a deformations in the surrounding soil. These strains may.
a
then, be considered as strain potential caused by the eanh-
=
a quake, and can be used to assess the deformation potential
of the embankment and foundation soils. This procedure
CURVES APPLICABLE FOR
may be used to delineate zones of strain potential in the
CONDITIoNS I,/HERE or(
V
embankment-foundation system for aid in the assessment
TOH PER SQ FT of seismic stability.
Generation and dissipation of excess pore-water
pressuresa'3s'36 within the embankment-foundation system
0 r0 20 30 q0 during and following shaking (i.e., post-earthquake) also
l{0DlFlE0 PEHETMTI0N RESISTAHCE, N, blows/ft are used in the stability evaluation,a'37 including the effecrs
of pore-pressure redistribution.
Figure 8-5. Variations of cyclic stress ratio with modified penetration
The post-earthquake stability of the dam may also be
resistance for various magnitude earthquakes. From Seed and ldriss.re
evaluated by using standard slope-stability procedures and
the residual strength of those parts of the dam-foundation
system where high strains or high excess pore-water pres-
sures are induced by the earthquake ground motions.
Ranges of residual strength for cohesionless soils were re-
cently proposed by Seed:7 these ranges may be used as a
t guide for the purpose ofevaluating the post-earthquake sta-
3 bility of the dam.
o;
!r The stability of the dam may also be determined by using
.!a
the undrained steady-state strength of the soils. Evaluation
g.; of the undrained steady-state strength is summarized, for
3B example, by Castro3s and Poulos et al.3e
:.s
A.so
o-
6* EXAMPLE

o As part of a reevaluation program for its existing dams. the


East Bay Municipal Utility District (EBMUD) had several
Ellectivc Normol Slrr33 - lt, of its danrs in northern California evaluared using the dy-
Ft6: namic method of analysis summarized in the preceding
l. o lr.!!.t r. t6. t.tlo o( t[. laltl.t .t.il. ti... pages of this chapter. One of thcse dams was thc Uppcr
ttr..r (. (i. lnlll.l .l(..ilv. @rgl .(...r 6 th.
pt.n. ol ,.llur.,
San Leandro Dam,tn'or the gcncral location of which is
2. Cr<ltG tk.t .lr.t. tn.lvd.t @lt ti. r!9.tt.ts..d
cr.ll< r.r.r. .6P....r' shown in Fig. 8-7.
,. ft. a.t. lo? c. o (1. ' 1.0) l.(oiFr.!.. The dam was initiated in 1924. and the latest modifica-
.ot..c!lon t.ct6? o( 0.61 .rPlt.a to tk r"ui"
.h... rrr.r....
tion, lcading to the cross section shown in Fig. 8-8, was
Figure 8-6. Deformation characteristics of embankment soil under cyclic completed in 1970. The dam was zoned as shown in Fig.
loading conditions. 8-8 and, except tbr thc downstream buttress, was con-
248 ADVANCED DAM EilGINEERING FOR DESIGN, CONSTRUCTION, AND REHABILTTATION

meters) long. At the maximum section, the height of the


dam is about 190 ft (58 meters) and the width of rhe cresr
is about 75 ft (23 meters).
The section shown in Fig. 8-8 was analyzed using the
static and dynamic analysis procedures outlined earlier in
this chapter. Figure 8-9 shows the finire-element mesh used
in the static and dynamic analyses. The time history shown
in Fig. 8-2 was used as input base rock motion to the dam-
foundation system. This motion was selected to represent
an earthquake with a magnitude of about 8.3 originating
some 23 miles (37 km) from the dam site on the San An-
dreas fault.
The soil parameters for the nonlinear static analysis are
summarized in Table 8-2. Calculated values of static o-,,
r..,, and cu along three selected planes in the embankment
are shown in Fig. 8-10.
The soil parameters used in the dynamic analysis are
listed in Table 8-3.
The selection of these material properties was based on
shear wave measurements made in the upstream and down-
stream parts of the embankment. For the core and pans of
the foundation alluvium, data for similar soils were used.
The modulus reduction curve presented in Fig. 8-3 and the
damping curves for sands and for clays shown in Fig. 84
were used in this analysis to obtain strain-compatible shear
moduli and damping values in the embankment-foundation
Figure 8-7. Location of Upper San lrandro Dam.
system.
The results of the response analysis of this dam-foun-
structed almost entirely as a hydraulic fill with a clay "pud- dation system are presented in Figs. 8-ll through 8-14.
dle" core. At the time of its evaluation in 1972, the res- The time histories of applied base rock and computed crest
ervoir formed by the dam provided about 41,000 acre-feet accelerations are shown in Fig. 8-ll. Shear stresses in-
(50.6 million m31 of storage at elevarion 460 ft. The crest duced by the earthquake ground motions were also ob-
ofthe dam is at elevation 476 ft and is about 600 ft (183 tained for each element shown in Fig. 8-9; typical com-

500
t,
a,
450
I 400
C
.9
o 350
a,
lrl 300
250 200 o 200
Dislonce lrom Cenlerline - {eet
DOWNSTREAM SHELL CORE
Consists of a mixture of siley gravel, Consists mostly of silty cLay and some
clayey gravel, silty sand and clayey clayey sand and gravel layers.
sand.
UPSTREAM SHELL
ALLUVIUM Consists of a mixture of silLy and
Consists mostly of sandy clay, silty clayey gravels and silty and clayey
and clayey sand and gravel. sand, with some clay seams of
considerable lat,eral extent.
Figure 8-8. Typical cross section thmugh Upper San Leandm Dam.
EARTHOUAKE RESPONSE ANALYSIS OF EMsANKMENT OAMS 249

o
!
c
o
o
lr,

6@ 400 200 0 2@ 400 600


Oi:loacc lrom Ccnlerlhc - fcel
Figure 8-9. Finite-elemenr represenration of embankment dam-foundation system.

Table 8-2. Soil parameters used in nonlinear static analysis.


Values Used in Analysis

Soil parameter Symbol Shell Material Clay core Buttrcss fiil Foundation alluvium
.Y
12l. 130.
Unit weight
(pcf) 54' l2l r
63' 6g'
c
Cohesion
(ts0 0.2 0. l5 0.2 0.2
Friction angle dr* 36" 36" 36"
Modulus number K 200 100 200 200
Modulus exponent n 0.7 0.85 0.? 0.7
Failure ratio Rl 0.7 0.6 0.7 0.7
Bulk modulus Kb 500 500 500 5m
parameters m 0 0 0 0
.Total unit weight.
'Buoyant unit weight.
srFriction angles are efective stts values.

puted time histories of shear stresses induced by the soils in 30 cycles, zy. As can be noted, the values of r,
earthquake ground motions in three elements are shown in exceed the values of zy throughout most of the embank-
Fig. 8-12. The time history of shear stress was converted ment. In other words, the cyclic strength in the shell ma-
to an equivalent number of uniform shear stress cycles using terial along this plane is not sufficient to prevent the de-
a weighting procedure fof stress cycles with different am- velopment of the selected strain potential of 57o. The ratio
plitudes (e.g., l,ee and Chan;a2 Seed et a1.43;. The results r1f tuis also shown in Fig. 8-14. This ratio may be consid-
of this conversion, showing the equivalent uniform cyclic ered to represent a local factor of safety. For values of this
stresses developed along three horizontal planes within the ratio less than unity, deformations exceeding 5 % strain can
embankment, are shown in Fig. 8-13. Note that the time be expected to develop during the earthquake under con-
histories of shear stress were converted to 30 equivalent sideration.
uniform cycles. (Also note, however, that because of the The values ofthis local factor ofsafety are considerably
consistency of the weighting procedure, any other number lower than unity along most of the plane within the up
of cycles could have been selected, resulting in different stream and downstream parts of the embankment below the
amplitudes of equivalent uniform stress corresponding to phrcatic surfiace. It should be noted that the cyclic strcngth
different numbers of cycles. In all cases, the amplitude of data are presented only for the parts of the dam below the
the uniform stress and the number of cycles associated with phreatic surface. The cyclic strengths of partially saturated
this amplitude provide the same final conclusion because or essentially dry soils in the downstream part of the em-
they are based on the same relationship bctween deforma- bankment would be considerably higher, and the ratio of
tion rcsistance and number of stress cycles.) q/ ra within this part would be targer than unity. It is also
Figure 8-14 illustrates the evaluation ol strain porential interesting to notc that within the clay core the induced
within the embankment. The upper part of this 6gure shows stresses arc considentbly lower than those required to cause
a comparison of the values of equivalent uniform shear 57o strain of representative test specimens.
stress induced in 30 cycles, 27, during the earthquake and With the aid of data such as those shown in Fig. 8-14,
the stress required to cause 57o strain in the embankment the stability of the embankment and underlying foundation
25O ADVANCED DAM ENGINEER]NG FOR OESIGN, CONSTRUCTION, AND REHABILITATION

el
olO
-an
Eh -Almg
9,;
Z6
Plone ol EL 324
(!,
(ur u
.26
Ou
oo
90)
ur d6

,;t
U'
o,
eU,
0r)0
I
oF
c,
-c
(n
o.4

--b o.3
alOl
l. o.?
EL EL 370 1_- --4rrro
lt
o \,r
o.t

200 o
X- z'-
200 400 600
500 Distonce From Cenlerline - Feet
o, 450
Lo
I 400
c
.o L_-:. ? -.+.+.i.-. eL-e.--
o 350
o 300
tr
250 200 0 200
Dislonce From Centerline - Feet
Figure 8-10. Computed static shear srresses in Upper San l,eandro Dam.

layer can be assessed for the earthquake under considera- bility and integrity of this dam were likely to be seriously
tion. In the example presented in this chapter, the induced impaired during the postulated earthquake. The owner of
stresses far exceed the cyclic strengths of the soils within the dam immediately lowered the reservoir level and pro-
the embankment below the phreatic surface and in the ceeded with the design and then construction of a new dam
foundation layer. Therefore, it was concluded that the sta- downstream from the existing dam. The new dam was
completed in 1977.
Had the results indicated that the local factor of safety
was higher than unity in a significant portion of the em-
Table 8-3. Soil parameters used in dynamic bankment and foundation layer, it would have been appro-
analysis. priate to conclude from the analysis that the integrity and
Total unit Poisson's stability of the dam would not be seriously impaired during
Material weight, pcf ratio Modulus pararnetcr the postutated earthquake. In many cases, certain parts of
Shell 125 0.30 t;,,*. = 130 the dam may show local factors of safety somewhat lower
Core 125 0.40 G,,. = 3450 ksf than unity, while in the majority of the embankment this
Buttress fill 125 0.40 6',, = 4600 ksf factor of safety would be greater than unity. For these
Foundation 130 0.30 /l:,,.. = 120
cases, further detailed work, taking into account the distri-
alluvium
bution of strain potentials, would be required.
EARTHOUAKE RESPONSE ANALYSIS OF EMBANKMENT DAMS 251

o.6
Cornputcd Cterl Acttlcrottst:
o.
C'
I o.2
.E
o o
g
o
(, -o.2
(,
-o.4

-o.
3? 40
f rme -seconds

o.
Apglied 8o:c Rocl Acccletotion!
O.4
CI
I
G
o.?
.9
o o
g
au
(, -o.2
(J

-O.4

-o.6
o 816243?404856
Time -secdndr
Figure 8- I I . Time histories of applied base rock and computed crest accelerations.

CONCLUDING REMARKS 7. Overtopping of dam due to seiches in reservoir.


8. Overtopping of dam due to slides or rockfalls into
Some two decades ago, Sherardaa listed the following as reservoir.
possible ways in which an earthquake may cause failure of 9. Failure of spillway or outlet works.
an earth dam:
Considering these possible ways in which an earthquake
may cause failure of an earth dam. Seed,a in his Rankine
l. Disruption of dam by major fault movement in foun-
lecture, offered the following as possible defensive meas-
dation.
ures:
2. Loss of freeboard due to differential tectonic ground
movements.
3. Slope failures induced by ground motions. l. Allow ample freeboard to allow for settlcment.
4. Loss of freeboard due to slope failures or soil com- slumping, or fault movements.
paction. 2. Use wide transition zones of material not vulnerable
5. Sliding of dam on weak foundation materials. to cracking.
6. Piping failure through cracks induced by ground mo- 3. Use chimney drains near the central portion of the
tions. enrbankment.
252 ADVANCED DAM ENGINEERTNG FOR DESIGN. CONSTRUCTION, AND REHAEILITATION

SOOr

64501
0l
io-[
CI
.9 1

E :ooJ-
st
L,'mFI

,50L o 1@ 200 300 qoo soo soo


Clislonce lrom Ccnlerlinc - ,cet

6
4 Sheor Strers ot Pornt A

2 il
o l,lllllhlt[,t, l\t.1, r,1' ,,,. . .,.
-2
h^,1,4fi,{ ,tt Trwrr,ryr1,IrsT-r
'filil,l
-4

6
Shcor Stress ol Poinl I
4
i
t 2
,aI
o
UI

o
O
I
UI

Shcor Slress d Point C

8t62432404856€/
Timc - ceconds

Figure 8-12. Typical computed time histories of shear stresscs.

4. Provide ample drainage zones to allow for possible 9. Locate the core to minimize the degree of saruration
flow of water through cracks. of materials.
5. Use wide core zones of plastic materials not vulner- 10. Stabilize slopes around the rcservoir rim to prevent
able to cracking. slides into the reservoir.
6. Use a well-graded filter zone upstream of the core ll. Provide special details if there is danger of fault
to serve as a crack-stopper. movement in the foundation.
7. Provide crest details that will prevent erosion in the
event of overtopping. The analytical procedures (including appropriate use of
8. Flare the embankment core at abutment contacts. the pseudostatic method of analysis when applicable) out-
F
6o
fL,
ig
it
E5
to
N.C}r3 PI.A}TE AT E1.324

--o
E>
s 81.370
B(,
=o
Co
3.
5: tooo "l
.- gt . 410

9e
.2o
2-r
lrJ o
o
2ooo2@
0ittonca |rom Crnl!rlina - trrt
5OOr

aoL45ol-
IcLooo[-
€ rsol-'
3l3OOf
r.r
250L 400 200
Dislonca l?om Cant!rlina - lc3l
Figurc 8-13. Typical variation of equivalent uniform shear stresses in embankment.

PTANE AT EL.37O

a
o
I
a
a 2000
gl
o SIRESS REQUIRED 10 CAI.'SE
3o 5t STRAIN IN.3O CYCI,,ES
att t@o

o
2.O
-t t.
r9
t.
.E
rt o.5
o
Di3lonca lrom Crnhrlina - t..l
!OOr
a .3of-
a
a 400f-
C
o
o
""F
a
lr, .-F
25& 2o0 400
Dirtoacr lrom Cratrrlinc - l.at
Figure 8-14. Analysis of strain potential along a typical horizontal plane.

253
254 ADVANCED DAM ENGINEERING FOR DESIGN, CONSTRUCTION, ANO REHAEILTTATION

lined in rhis chapter rogerher with the above considerations Foundation Engincering. San Francisco, CA. Vol. l. pp. 255-320.
provide a guide to assessing the probable performance of Aug. 1985.
17. Dobry, R.. ldriss, I. M.. and Ng. E.. '.Duration Characterisrics of
earth dams under eanhquake loading conditions.
Horizontal Comgrnents of Strong-Motion Eanhquake Rcconls...
Bulletin of the Seismologica! Socierv of America, Vol. 68, No. 5.
REFERENCES Oct. 1978.
18. Sadigh. K.. Power, M. S., and Youngs. R. R.,..pcak Horizontal
l. Newmark. N. M., "Effects ofEanhquakes on Dams and Embank- and Venical Accelentions, Velocities. and Displaccmcnts on Deep
ments," Giotechaique. Vol.5, No. 2, June 1965. Soil Sites During Moderrrely Strong Eanhquakes." proceedings,
2. Goodman. R. E.. and Seed. H. 8., "Eanhquake-lnduced Displace- Second International Earthquake Nticrozonation Conference, Vol. II.
ments in Sand Embankments," Journal ol the Soil Mechanics antl pp. 801-81 I, 1978.
Foundarion Engineering Division.,{SCtr, Vol. 92, No. SM2. pp. 19. Seed. H. 8.. and ldriss, I. M., "Cround Motions and Soil Lique-
125-t46. t966. faction During Earthquakes," lvlonograph Serics No.5. Earthquake
3. Ir{akdisi. F., and Seed, H. B., "simplified Procedure for Estimating Engineering Research Insritute, Berkeley, CA. Dec. 19E2.
Dam and Embankment Eanhquake-lnduced Deformations," Journal 20. Hermann. R.. and Nuttli. O.. "scaling and Attenuation Relarion for
of the Geotechincol Engineering Division,.4Str. Vot. 104, No. GT7, Strong Gmund Motion in Eastern North America." Eighth World
pp.8.19-867. 1978. Conference on Eanhquakes Engineering, No. II. p. 305. 1984.
4. Seed. H. B.. "Considerations in the Earthquake-Resistant Design of 21. Campbell. K. W.. "strong Motion Attenuation Relations: A Ten-
Earth and Rockfill Dams," Ctotechnique, Vol. 29, No. 3, Sept. Year Perspective." Eanhquake Spectra, Vol. l. pp. ?59-80.1, lgg5.
1979. 22. Joyner, W. B., and Fumal, T. E., "Predicted Mapping of Earth-
5. H. B.. "A Method for Eanhquake-Resistant Design of Earth
Seed. quake Cround Motion," in Ziony. J. I. (ed.), ..Evaluating Earrh-
Dams." Journal of the Soil Llechanics and Foundation Dit'ision. quake Hazards in the Los Angeles Region-An Eanh Science per-
XSCE, Vol. 92, No. SMl. Proc. Paper4616. pp. l3-4t. Jan. 1966. spective," U.S. Geological Survey Professional Paper 1360, pp. 203-
6. Seed. H. B.. Lee, K. L., and ldriss, I. M., "Analysis of Sheffield 220.1985.
Dam Failure." Journal of the Soi! Mechanics and Foundation Di- 23. Seed, H. B., and ldriss, l. M.. "Rock Motion Accelerograms for
vision,ASCE, Vol.95. No. 51116. Proc. paper6909, pp. 1453-1490, High Magnitude Earthquakes." Eanhquake Engineering Research
Nov. 1969. Center, Repon No. EERC 69-7. Univenity of Califomia, Berkeley,
7. Seed, H. B.. "Design Problems in Soil Liquefaction," Journal of Apr. 1969.
the Geotechnical Engineering Division, ASCE, Vol. t t3, No. 8, pp. 24. Seed. H. B., and ldriss. I. M.. "Soil Moduli and Damping Factors
827-845, Aug. 1987. for Dynamic Response Analyses," Eanhquake Engineering Re-
8. Clough. R. W., and Woodwand. R. J.. "Analysis of Embankment search Center, Repon No. EERC 70-10, University of Califomia,
Stresses and Deformations," Journal of the Soit Mechanics and Berkeley. 1970.
Foundations Didsion.,{SCE, Yol. 93, No. SM4, pp. 529-549. July 25. Hardin, B. O., and Dmevich. V. P., "Shear Modulus and Damping
1967. in Soils: Design Equations and Curves," Jountal of the Soi! Me-
9. Kulhawy. F. H., Duncan, J. !vt., and Seed, H. 8.. ..Finite Element chanics ond Foundation Diyisiorr. zl.lCE. Vol. 98, No. SM7, proc.
Analyses of Stresses and Movements in Embankments During Con- Paper 90O6, pp. 667-692. July 1972.
struction," Ceotechnical Engineering Repo( No. TE 69Ol to U.S. 26. Seed.H. B., Wong. R. T.. Idriss, I. M., and Tokimatsu. K., ..Mod-
Army Engineers Waterways Experiment Station. University of Cal- uli and Damping Factors for Dynamic Analyses of Cohesionless
ifomia, Berkeley. Nov. 1969. Soils." Earthquake Engineering Research Center. Report No. UCB/
10. Duncan. J. ivl.. Byme. P., Wong. K. S., and Mabry, p.,..Strength, EERC-8.l/14, University of California, Berkeley. Sept. l9B.t.
Stress-Strain and Bulk Modulus Parameters for Finite Element Anal- 27. Idriss, l. M., Lysmer, J., Hwang. R., and Seed. H. B.. ..eUAD4,
ysis of Stresses and Movements in Soil Masses." Geotechnical En- A Computer Program for Evaluating the Seismic Response of Soils
gineering Report No. UCB/GT/80-01, University of Califomia, Structures by Variable Damping Finite Elements," Earthquake En-
Berkeley. Aug. 1980,77 pp. gineering Research Center, Report No. EERC 73-16. University of
ll. Duncan. J. M.. Seed. R.8.. Wong. K. S.. and Ozawa, y.. California. Berkeley. June 1973.
"FEADAlt8.l: A Computer Program for Finite Element Analyses 28. Lysmer. J., Udaka, T., Tsai. C.-F.. and Seed. H. 8.. ..FLUSH-A
of Dams," Georechical Engineering Report, Depanmenr of Civil Computer Program for Approximate 3-D Analysis of Soil-Structure
Engineering. Viqginia Polytechnic Institute and State University. Feb. Internction Problems." Report No. EERC 75-30, University of Cal-
1985.79 pp. ifornia, Berkeley. Nov. 1975.
12. Duncan. J. M.. and Chang, C.-Y., ..Nonlinear Analysis of Stress 29. Seed, H. B., Lee, K. L., ldriss, I. M.. and Makdisi. F. I.. ..Analysis
and Strain in Soils," Journal ofthe Soil Mechanics antl Foundation of the Slides in the San Femando Dams During the Eanhquake of
Division.,{5C8. Vol. 96. No. SM5, proc. paper 7513. pp. 1629- February 9. 1971," Report No. EERC 73-2, Earthquake Engineer-
1653. Sepr. 1970. ing Research Cenrer. University of Califomia, Berkeley. 1973.
13. Schnabcl. P. 8.. Lysmer. J.. and Seed, H. B., ..SHAKE-A Com- 30. Lee. K. L., and Seed. H. 8.. "Cyclic Srress Conditioos Causing
puter Program for Eanhquake Response Analysis of Horizontally Liquefaction of Sand," Jounrul of the Soit lvlechanics and Founcla-
Layered Sites." Repon No. EERC ?2-12, Earrhquake Engineering tion Division,.4SCE. Vol. 93. No. SMl. proc. paper 505E. pp. 47-
Research Cenrer, Univenity of Califomia, Berkeley. CA, Dcc. 1972. 70. Jan. 1967.
14. Bolt. B. A.. "Durarion of Srrong Crsund Motion," proeeedings, 31. Lee, K. L.. and Sced. H. 8.. "Dynanric Strengrh of Anisorropically
5th World Conference on Eanhquake Engineering. Rsme. 1973. Consolidated Sand." Jolrnal of the Soil Mechanies aru! Fountlution
15. Idriss. l. M.. "Characteristics of Earthquake Ground Morions..' Dit'ision,,4SCE, Vol. 93, No. SMS, Proc. paper545l. pp. 169-190,
Proceedings, ASCE Specialty Confercnce on Eanhquake Enginecr- Scpr.1967.
ing and Soil Dynamics, Pasadena, CA. Vol. IIt, pp. l15l-t265. 32. Lce, K. L.. Seed. H. 8.. tdriss, l. M.. and Mrkdisi, R. I., ..prop-
I 978. crties of Soil in the San Fcrnando Hydraulie Fill Dams," Journal of
16. Idriss, t. M., "Evaluaring Seismic Risk in Engineering pncricc." the Geotechnicul Engineering Dit,ision, ztSCt. Vot.. l0l. No. GT8,
Proceedings, XI Intemational Conference on Soil Mechanics and Proc. Paper I 1527. pp. 801-811. Aug. 1975.
EARTHOUAKE RESPONSE ANALYSIS OF EMBANKMENT DAMS 255

33. Finn. W. D. L., Lee. K. W.. Maanman. C. H. and Lo, R.. "Cyclic uation Procedurc." Jouraol of thc Gcotcchnical Engineering Divi'
Porc Pressurcs under AnisotroPic Conditions," Proceedings, ASCE sion. ASCE. Vol. I t I, No. 6. Junc 1985.
Ccotechnical Engineering Division Specialty Confercnce on Earrh- 40. Woodwanl-Lundgrcn & Associatcs. "Evaluation of thc Scismic Sta-
quake Engineering and Soil Dynamics, Pasadena. CA. June l9-21' biliry of the Upper San Leandm Dam, Alamcda County. Calitbr-
1978. nia." Repon prcparcd for Eal Bay Municipal Utility District. 1972.
34. Seed, H.8.,Idriss. [. M., Lee, K. L., and Makdisi, F.. "Dynamic 41. Gordon, B. 8., Dayton. D. J.. and Sadigh. K.. "Scismic Stabitity
Analysisof the Slide in the Lower San Femando Dam during the of Upper San Leandro Dam." Joumal of the Geotechnical Engi'
Eanhquake of February 9. 1971," Joumal of Geotechnical Engi'
neering Ditision. ASCE, Vol. 100. No. GT5, Proc. Papcr 10553.
neering Division, ASCE, Vol. l0l, No. GT9, Proc. Paper I l5'll' pp. 523-5.15. MaY 197;t.
pp. 889-911, Sept. 1975. 42. Lee. K. L.. and Chan. K., "Numbcr of Equivalent Significant C)'clcs
in Strong Motion Eanhquakes," Proceedings. International Confer-
35. Booker, J. R., Rahman, M. S., and Seed, H. B.' "GADFLEA: A
ence on Microzonation. Seattle. WA. Vol. ll. pp. 6O9-627. Oct.
Computer Program for the Analysis of Pore Pressure Generation and
1972.
Dissipation During Cyctic or Earthquake Loading." Repon No'
43. Seed. H. B.. Duncan, J. M.. and ldriss. I. M.. "Criteria and lv{eth-
EERC 76-24, Eanhquake Engineering Research Center. University
ods for Static and Dynamic Analysis of Earth Dams." in Naylor. D.
of Califomia. Berkeley, Oct. 1976.
J., Sragg, K., and Zienkiewicz. O.C.' eds., Criteria arul Assunrp'
36. Sadigh, K., Idriss, I. M., and Youngs, R. R., "Drainage Effects on tionsfor Numerica! Anall'sis of Dams, Swansea: University College,
Seismic Stability of Rockfill Dams," Proceedings, ASCE Geotech- 1975, pp.56r-588.
nical Engineering Division Specialty Conference on Earthquake En- 44. Sherard, J. L.. "Eanhquake Considerations in Eanh Dam Design."
gineering and Soit Dynamics, Pasadena, CA, pp. 802-818' June l9- Journal of the Soil Mechanics and l:oundations Divrsion' rlSCE. Vol.
21, 1978. 93, No. SM.t. pp. 377-.101. July 1967.
37. Idriss. I. M., Cluff, L. S., Tocher, D., Makdisi,.F., and Knuefper, 45. Tezaghi, K., Mechanisms of ktn<lslides, The Geological Survey of
P. L.. "Geologic, Seismologic and Geotechnical Considerations Re- America. Engineering Geology (Berkey) Volume' 1950.
lated to Performance of Dams during Earthquakes," Proceedings, 46. Seed, H. 8., "Eanhquake-Resistant Design of Eanh Dams"' Pro-
l3th International Congress on Large Dams, New Delhi' India, Nov. ceedings, International Conference on Recent Advances in Geo-
1979. technical Eanhquake Engineering and Soil Dynamics. University of
38. Castm, G., "Liquefaction and Cyclic Mobility of Saturated Sands"' tvlissouri-Rolla. Vol. 3, pp. ll57-l 175, 1981.
Journat of the Geotechnical Engineering Division, ASCE. Vol. l0l ' 47. Committee on Eanhquake Engineering. Iiquefacrion ofSoils during
No. GT6. pp.55l-569, 1975. Eanhquakes, National Research Council. Repon No. CETS-EE-O01.
39. Poulos. S. J., Castro, G., and France, J. W., "Liquefaction Eval- National Academy Press, 1985.

You might also like