MONITORING MOS (MATERIAL ON SITE) - DETAIL

BAHAN/PERALATAN MASUK LOKASI


TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
1 MINGGU 17-Apr-22 KT 8150 1 4,00 m3
2 MINGGU 17-Apr-22 KU 8860 2 4,00 m3
3 MINGGU 17-Apr-22 KT 8549 3 4,00 m3
4 MINGGU 17-Apr-22 KT 8161 4 4,00 m3
5 MINGGU 17-Apr-22 KT 8024 5 4,00 m3
6 MINGGU 17-Apr-22 KU 8166 6 4,00 m3
7 MINGGU 17-Apr-22 KT 8265 7 4,00 m3
8 MINGGU 17-Apr-22 KT 9305 8 4,00 m3
9 MINGGU 17-Apr-22 KT 8720 9 4,00 m3
10 MINGGU 17-Apr-22 KU 8314 10 4,00 m3
11 MINGGU 17-Apr-22 KU 8547 11 4,00 m3
12 MINGGU 17-Apr-22 KU 8145 12 4,00 m3
13 MINGGU 17-Apr-22 KT 8279 13 4,00 m3
14 MINGGU 17-Apr-22 KU 8509 14 4,00 m3
15 MINGGU 17-Apr-22 KT 8829 15 4,00 m3
16 MINGGU 17-Apr-22 KU 8074 16 4,00 m3
17 MINGGU 17-Apr-22 KU 8375 17 4,00 m3
18 MINGGU 17-Apr-22 KU 9674 18 4,00 m3
19 MINGGU 17-Apr-22 KU 8351 19 4,00 m3
20 MINGGU 17-Apr-22 KT 8150 20 4,00 m3
21 MINGGU 17-Apr-22 KU 8860 21 4,00 m3
22 MINGGU 17-Apr-22 KT 8549 22 4,00 m3
23 MINGGU 17-Apr-22 KU 8161 23 4,00 m3
24 MINGGU 17-Apr-22 KU 8166 24 4,00 m3
25 MINGGU 17-Apr-22 KT 8024 25 4,00 m3
26 MINGGU 17-Apr-22 KU 8958 26 4,00 m3
27 MINGGU 17-Apr-22 KU 8265 27 4,00 m3
28 MINGGU 17-Apr-22 KU 9305 28 4,00 m3
29 MINGGU 17-Apr-22 KT 8720 29 4,00 m3
30 MINGGU 17-Apr-22 KU 8314 30 4,00 m3
31 MINGGU 17-Apr-22 KU 8547 31 4,00 m3
32 MINGGU 17-Apr-22 KT 8145 32 4,00 m3
33 MINGGU 17-Apr-22 KT 82791 33 4,00 m3
34 MINGGU 17-Apr-22 KU 8509 34 4,00 m3
35 MINGGU 17-Apr-22 KU 8829 35 4,00 m3
36 MINGGU 17-Apr-22 KU 8074 36 4,00 m3
37 MINGGU 17-Apr-22 KU 8375 37 4,00 m3
38 MINGGU 17-Apr-22 KU 8351 38 4,00 m3
39 MINGGU 17-Apr-22 KU 9674 39 4,00 m3
40 MINGGU 17-Apr-22 KT 8150 40 4,00 m3
41 MINGGU 17-Apr-22 KU 8860 41 4,00 m3
42 MINGGU 17-Apr-22 KT 8549 42 4,00 m3
43 MINGGU 17-Apr-22 KU 8854 43 4,00 m3
44 MINGGU 17-Apr-22 KU 8161 44 4,00 m3
45 MINGGU 17-Apr-22 KU 8166 45 4,00 m3
46 MINGGU 17-Apr-22 KT 8024 46 4,00 m3
47 MINGGU 17-Apr-22 KU 8958 47 4,00 m3
48 MINGGU 17-Apr-22 KU 8265 48 4,00 m3
49 MINGGU 17-Apr-22 KU 9305 49 4,00 m3
50 MINGGU 17-Apr-22 KT 8720 50 4,00 m3
51 MINGGU 17-Apr-22 KU 8314 51 4,00 m3
52 MINGGU 17-Apr-22 KT 8145 52 4,00 m3
53 MINGGU 17-Apr-22 KT 8279 53 4,00 m3
54 MINGGU 17-Apr-22 KU 8509 54 4,00 m3
55 MINGGU 17-Apr-22 KU 8829 55 4,00 m3
56 MINGGU 17-Apr-22 KU 8547 56 4,00 m3
57 MINGGU 17-Apr-22 KU 8074 57 4,00 m3
58 MINGGU 17-Apr-22 KU 8375 58 4,00 m3
59 MINGGU 17-Apr-22 KU 8351 59 4,00 m3
60 MINGGU 17-Apr-22 KU 9674 60 4,00 m3
61 MINGGU 17-Apr-22 KU 8088 61 4,00 m3

Page 1 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
62 MINGGU 17-Apr-22 KT 8150 62 4,00 m3
63 MINGGU 17-Apr-22 KU 8860 63 4,00 m3
64 MINGGU 17-Apr-22 KT 8549 64 4,00 m3
65 MINGGU 17-Apr-22 KU 8854 65 4,00 m3
66 MINGGU 17-Apr-22 KU 8161 66 4,00 m3
67 MINGGU 17-Apr-22 KU 8166 67 4,00 m3
68 MINGGU 17-Apr-22 KT 8024 68 4,00 m3
69 MINGGU 17-Apr-22 KU 8958 69 4,00 m3
70 MINGGU 17-Apr-22 KU 8265 70 4,00 m3
71 MINGGU 17-Apr-22 KU 9305 71 4,00 m3
72 MINGGU 17-Apr-22 KT 8279 72 4,00 m3
73 MINGGU 17-Apr-22 KU 8375 73 4,00 m3
74 MINGGU 17-Apr-22 KU 8074 74 4,00 m3
75 MINGGU 17-Apr-22 KU 8829 75 4,00 m3
76 MINGGU 17-Apr-22 KU 8351 76 4,00 m3
77 MINGGU 17-Apr-22 KT 8721 77 4,00 m3
78 MINGGU 17-Apr-22 KT 8150 78 4,00 m3
79 MINGGU 17-Apr-22 KU 8314 79 4,00 m3
80 MINGGU 17-Apr-22 KU 9674 80 4,00 m3
81 MINGGU 17-Apr-22 KT 8781 81 4,00 m3
82 MINGGU 17-Apr-22 KU 8860 82 4,00 m3
83 MINGGU 17-Apr-22 KU 8438 83 4,00 m3
84 MINGGU 17-Apr-22 KU 8547 84 4,00 m3
85 MINGGU 17-Apr-22 KT 8145 85 4,00 m3
86 MINGGU 17-Apr-22 KT 8549 86 4,00 m3
87 MINGGU 17-Apr-22 KU 8854 87 4,00 m3
88 MINGGU 17-Apr-22 KU 8161 88 4,00 m3
89 MINGGU 17-Apr-22 KU 8166 89 4,00 m3
90 MINGGU 17-Apr-22 KT 8024 90 4,00 m3
91 MINGGU 17-Apr-22 KU 8958 91 4,00 m3
92 MINGGU 17-Apr-22 KU 8265 92 4,00 m3
93 MINGGU 17-Apr-22 KU 9305 93 4,00 m3
94 MINGGU 17-Apr-22 KT 8720 94 4,00 m3
95 MINGGU 17-Apr-22 KU 8314 95 4,00 m3
96 MINGGU 17-Apr-22 KU 8547 96 4,00 m3
97 MINGGU 17-Apr-22 KT 8145 97 4,00 m3
98 MINGGU 17-Apr-22 KU 8509 98 4,00 m3
99 MINGGU 17-Apr-22 KT 8279 99 4,00 m3
100 MINGGU 17-Apr-22 KU 8829 100 4,00 m3
101 MINGGU 17-Apr-22 KU 8074 101 4,00 m3
102 MINGGU 17-Apr-22 KU 8375 102 4,00 m3
103 MINGGU 17-Apr-22 KU 8351 103 4,00 m3
104 MINGGU 17-Apr-22 KU 9674 104 4,00 m3
105 MINGGU 17-Apr-22 KT 8150 105 4,00 m3
106 MINGGU 17-Apr-22 KU 8860 106 4,00 m3
107 MINGGU 17-Apr-22 KU 8438 107 4,00 m3
108 MINGGU 17-Apr-22 KT 8781 108 4,00 m3
109 MINGGU 17-Apr-22 KU 8161 109 4,00 m3
110 MINGGU 17-Apr-22 KU 8265 110 4,00 m3
111 MINGGU 17-Apr-22 KT 8720 111 4,00 m3
112 MINGGU 17-Apr-22 KU 9674 112 4,00 m3
113 SENIN 18-Apr-22 KT 8145 113 4,00 m3
114 SENIN 18-Apr-22 KU 8547 114 4,00 m3
115 SENIN 18-Apr-22 KT 8279 115 4,00 m3
116 SENIN 18-Apr-22 KU 8829 116 4,00 m3
117 SENIN 18-Apr-22 KU 8074 117 4,00 m3
118 SENIN 18-Apr-22 KU 8375 118 4,00 m3
119 SENIN 18-Apr-22 KU 8351 119 4,00 m3
120 SENIN 18-Apr-22 KU 9674 120 4,00 m3
121 SENIN 18-Apr-22 KT8150 121 4,00 m3
122 SENIN 18-Apr-22 KT 8549 122 4,00 m3
123 SENIN 18-Apr-22 KU 8161 123 4,00 m3
124 SENIN 18-Apr-22 KU 8166 124 4,00 m3
125 SENIN 18-Apr-22 KT 8024 125 4,00 m3

Page 2 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
126 SENIN 18-Apr-22 KU 8265 126 4,00 m3
127 SENIN 18-Apr-22 KU 9305 127 4,00 m3
128 SENIN 18-Apr-22 KT 8721 128 4,00 m3
129 SENIN 18-Apr-22 KU 8854 129 4,00 m3
130 SENIN 18-Apr-22 KU 9674 130 4,00 m3
131 m3
132 m3
133 SABTU 23-Apr-22 KU 9305 133 4,00 m3
134 SABTU 23-Apr-22 KU 8509 134 4,00 m3
135 SABTU 23-Apr-22 KU 8074 135 4,00 m3
136 SABTU 23-Apr-22 KT 8549 136 4,00 m3
137 SABTU 23-Apr-22 KU 8375 137 4,00 m3
138 SABTU 23-Apr-22 KU 8699 138 4,00 m3
139 SABTU 23-Apr-22 KU 8161 139 4,00 m3
140 SABTU 23-Apr-22 KU 8265 140 4,00 m3
141 SABTU 23-Apr-22 KT 8549 141 4,00 m3
142 SABTU 23-Apr-22 KU 8860 142 4,00 m3
143 SABTU 23-Apr-22 KT 8720 143 4,00 m3
144 SABTU 23-Apr-22 KU 9305 144 4,00 m3
145 SABTU 23-Apr-22 KU 8547 145 4,00 m3
146 SABTU 23-Apr-22 KU 8829 146 4,00 m3
147 SABTU 23-Apr-22 KU 8166 147 4,00 m3
148 SABTU 23-Apr-22 KT 8279 148 4,00 m3
149 SABTU 23-Apr-22 KT 8024 149 4,00 m3
150 SABTU 23-Apr-22 KU 8351 150 4,00 m3
151 SABTU 23-Apr-22 KU 8074 151 4,00 m3
152 SABTU 23-Apr-22 KU 9438 152 4,00 m3
153 SABTU 23-Apr-22 KU 8375 153 4,00 m3
154 SABTU 23-Apr-22 KU 8699 154 4,00 m3
155 SABTU 23-Apr-22 KU 8161 155 4,00 m3
156 SABTU 23-Apr-22 KU 8265 156 4,00 m3
157 SABTU 23-Apr-22 KT 8549 157 4,00 m3
158 SABTU 23-Apr-22 KU 8860 158 4,00 m3
159 SABTU 23-Apr-22 KU 8854 159 4,00 m3
160 SABTU 23-Apr-22 KU 9305 160 4,00 m3
161 SABTU 23-Apr-22 KU 8829 161 4,00 m3
162 SABTU 23-Apr-22 KU 8166 162 4,00 m3
163 SABTU 23-Apr-22 KT 8279 163 4,00 m3
164 SABTU 23-Apr-22 KT 8024 164 4,00 m3
165 SABTU 23-Apr-22 KU 8351 165 4,00 m3
166 SABTU 23-Apr-22 KU 8074 166 4,00 m3
167 SABTU 23-Apr-22 KU 8438 167 4,00 m3
168 SABTU 23-Apr-22 KU 8375 168 4,00 m3
169 SABTU 23-Apr-22 KU 9674 169 4,00 m3
170 SABTU 23-Apr-22 KU 8699 170 4,00 m3
171 SABTU 23-Apr-22 KU 8509 171 4,00 m3
172 SABTU 23-Apr-22 KU 8161 172 4,00 m3
173 SABTU 23-Apr-22 KU 8265 173 4,00 m3
174 SABTU 23-Apr-22 KU 8860 174 4,00 m3
175 SABTU 23-Apr-22 KU 8547 175 4,00 m3
176 SABTU 23-Apr-22 KU 8829 176 4,00 m3
177 SABTU 23-Apr-22 KU 8166 177 4,00 m3
178 SABTU 23-Apr-22 KT 8024 178 4,00 m3
179 SABTU 23-Apr-22 KU 8438 179 4,00 m3
180 SABTU 23-Apr-22 KT 8720 180 4,00 m3
181 SABTU 23-Apr-22 KU 8375 181 4,00 m3
182 SABTU 23-Apr-22 KU 9764 182 4,00 m3
183 SABTU 23-Apr-22 KU 8699 183 4,00 m3
184 SABTU 23-Apr-22 KU 8509 184 4,00 m3
185 SABTU 23-Apr-22 KU 8161 185 4,00 m3
186 SABTU 23-Apr-22 KU 8265 186 4,00 m3
187 SABTU 23-Apr-22 KU 8860 187 4,00 m3
188 SABTU 23-Apr-22 KU 8547 188 4,00 m3
189 SABTU 23-Apr-22 KU 8829 189 4,00 m3

Page 3 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
190 SABTU 23-Apr-22 KU 8166 190 4,00 m3
191 SABTU 23-Apr-22 KT 8024 191 4,00 m3
192 SABTU 23-Apr-22 KU 8438 192 4,00 m3
193 SABTU 23-Apr-22 KU 8161 193 4,00 m3
194 SABTU 23-Apr-22 KT 8720 194 4,00 m3
195 SABTU 23-Apr-22 KU 9674 195 4,00 m3
196 SABTU 23-Apr-22 KU 8699 196 4,00 m3
197 SABTU 23-Apr-22 KU 8509 197 4,00 m3
198 SABTU 23-Apr-22 KU 8265 198 4,00 m3
199 SABTU 23-Apr-22 KU 8860 199 4,00 m3
200 SABTU 23-Apr-22 KU 8829 200 4,00 m3
201 SABTU 23-Apr-22 KU 8438 201 4,00 m3
202 SABTU 23-Apr-22 KT 8024 202 4,00 m3
203 SABTU 23-Apr-22 KU 8509 203 4,00 m3
204 SABTU 23-Apr-22 KU 8161 204 4,00 m3
205 SABTU 23-Apr-22 KU 8166 205 4,00 m3
206 SABTU 23-Apr-22 KT 8720 206 4,00 m3
207 SABTU 23-Apr-22 KU 8265 207 4,00 m3
208 SABTU 23-Apr-22 KU 8699 208 4,00 m3
209 SABTU 23-Apr-22 KU 9674 209 4,00 m3
210 SABTU 23-Apr-22 KU 8074 210 4,00 m3
211 SABTU 23-Apr-22 KU 8375 211 4,00 m3
212 SABTU 23-Apr-22 KU 8829 212 4,00 m3
213 SABTU 23-Apr-22 KT 8549 213 4,00 m3
214 SABTU 23-Apr-22 KU 8438 214 4,00 m3
215 SABTU 23-Apr-22 KT 8279 215 4,00 m3
216 SABTU 23-Apr-22 KT 8024 216 4,00 m3
217 SABTU 23-Apr-22 KU 8161 217 4,00 m3
218 SABTU 23-Apr-22 KU 8166 218 4,00 m3
219 SABTU 23-Apr-22 KT 8720 219 4,00 m3
220 SABTU 23-Apr-22 KU 8265 220 4,00 m3
221 SABTU 23-Apr-22 KU 8699 221 4,00 m3
222 SABTU 23-Apr-22 KU 8375 222 4,00 m3
223 SABTU 23-Apr-22 KU 8674 223 4,00 m3
224 SABTU 23-Apr-22 KT 8549 224 4,00 m3
225 SABTU 23-Apr-22 KU 8829 225 4,00 m3
226 SABTU 23-Apr-22 KU 8438 226 4,00 m3
227 SABTU 23-Apr-22 KT 8024 227 4,00 m3
228 SABTU 23-Apr-22 KU 8161 228 4,00 m3
229 SABTU 23-Apr-22 KU 8074 229 4,00 m3
230 SABTU 23-Apr-22 KU 8166 230 4,00 m3
231 SABTU 23-Apr-22 KU 8265 231 4,00 m3
232 SABTU 23-Apr-22 KU 8699 232 4,00 m3
233 SABTU 23-Apr-22 KT 8720 233 4,00 m3
234 SABTU 23-Apr-22 KU 8375 234 4,00 m3
235 SABTU 23-Apr-22 KU 9674 235 4,00 m3
236 SABTU 23-Apr-22 KT 8549 236 4,00 m3
237 SABTU 23-Apr-22 KU 8829 237 4,00 m3
238 SABTU 23-Apr-22 KU 8438 238 4,00 m3
239 SABTU 23-Apr-22 KT 8024 239 4,00 m3
240 SABTU 23-Apr-22 KU 8161 240 4,00 m3
241 SABTU 23-Apr-22 KU 8074 241 4,00 m3
242 SABTU 23-Apr-22 KU 8166 242 4,00 m3
243 SABTU 23-Apr-22 KU 8265 243 4,00 m3
244 SABTU 23-Apr-22 KU 8699 244 4,00 m3
245 SABTU 23-Apr-22 KT 8720 245 4,00 m3
246 SABTU 23-Apr-22 KU 8375 246 4,00 m3
247 SABTU 23-Apr-22 KU 9674 247 4,00 m3
248 SABTU 23-Apr-22 KU 8829 248 4,00 m3
249 SABTU 23-Apr-22 KU 8438 249 4,00 m3
250 SABTU 23-Apr-22 KT 8024 250 4,00 m3
251 SABTU 23-Apr-22 KU 8161 251 4,00 m3
252 SABTU 23-Apr-22 KU 8674 252 4,00 m3
253 SABTU 23-Apr-22 KU 8166 253 4,00 m3

Page 4 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
254 SABTU 23-Apr-22 KU 8265 254 4,00 m3
255 SABTU 23-Apr-22 KU 8699 255 4,00 m3
256 SABTU 23-Apr-22 KT 8720 256 4,00 m3
257 SABTU 23-Apr-22 KU 8375 257 4,00 m3
258 SABTU 23-Apr-22 KU 9674 258 4,00 m3
259 SABTU 23-Apr-22 KU 8829 259 4,00 m3
260 KAMIS 28-Apr-22 KU 8351 260 4,00 m3
261 KAMIS 28-Apr-22 KU 8088 261 4,00 m3
262 KAMIS 28-Apr-22 KT 8150 262 4,00 m3
263 KAMIS 28-Apr-22 KU 8958 263 4,00 m3
264 KAMIS 28-Apr-22 KU 8074 264 4,00 m3
265 KAMIS 28-Apr-22 KU 8860 265 4,00 m3
266 KAMIS 28-Apr-22 KU 8699 266 4,00 m3
267 KAMIS 28-Apr-22 KU 8265 267 4,00 m3
268 KAMIS 28-Apr-22 KU 8699 268 4,00 m3
269 KAMIS 28-Apr-22 KU 8088 269 4,00 m3
270 KAMIS 28-Apr-22 KU 8958 270 4,00 m3
271 KAMIS 28-Apr-22 KU 8314 271 4,00 m3
272 KAMIS 28-Apr-22 KU 8547 272 4,00 m3
273 KAMIS 28-Apr-22 KT 8024 273 4,00 m3
274 KAMIS 28-Apr-22 KT 8270 274 4,00 m3
275 KAMIS 28-Apr-22 KU 8265 275 4,00 m3
276 KAMIS 28-Apr-22 KT 8279 276 4,00 m3
277 KAMIS 28-Apr-22 KT 8720 277 4,00 m3
278 KAMIS 28-Apr-22 KU 8161 278 4,00 m3
279 KAMIS 28-Apr-22 KU 8265 279 4,00 m3
280 KAMIS 28-Apr-22 KT 8279 280 4,00 m3
281 KAMIS 28-Apr-22 KU 8351 281 4,00 m3
282 KAMIS 28-Apr-22 KU 8958 282 4,00 m3
283 KAMIS 28-Apr-22 KT 8150 283 4,00 m3
284 KAMIS 28-Apr-22 KU 8074 284 4,00 m3
285 KAMIS 28-Apr-22 KU 9305 285 4,00 m3
286 KAMIS 28-Apr-22 KU 8860 286 4,00 m3
287 KAMIS 28-Apr-22 KU 8166 287 4,00 m3
288 KAMIS 28-Apr-22 KU 8375 288 4,00 m3
289 KAMIS 28-Apr-22 KU 8509 289 4,00 m3
290 KAMIS 28-Apr-22 KU 8314 290 4,00 m3
291 KAMIS 28-Apr-22 KU 8699 291 4,00 m3
292 KAMIS 28-Apr-22 KU 9674 292 4,00 m3
293 KAMIS 28-Apr-22 KU 8438 293 4,00 m3
294 KAMIS 28-Apr-22 KT 4145 294 4,00 m3
295 KAMIS 28-Apr-22 KU 8088 295 4,00 m3
296 KAMIS 28-Apr-22 KU 8829 296 4,00 m3
297 KAMIS 28-Apr-22 KT 8720 297 4,00 m3
298 KAMIS 28-Apr-22 KU 8161 298 4,00 m3
299 KAMIS 28-Apr-22 KT 8024 299 4,00 m3
300 KAMIS 28-Apr-22 KU 8265 300 4,00 m3
301 KAMIS 28-Apr-22 KT 8279 301 4,00 m3
302 KAMIS 28-Apr-22 KT 8150 302 4,00 m3
303 KAMIS 28-Apr-22 KU 8958 303 4,00 m3
304 KAMIS 28-Apr-22 KU 8351 304 4,00 m3
305 KAMIS 28-Apr-22 KU 8074 305 4,00 m3
306 KAMIS 28-Apr-22 KU 9305 306 4,00 m3
307 KAMIS 28-Apr-22 KU 8860 307 4,00 m3
308 KAMIS 28-Apr-22 KU 8166 308 4,00 m3
309 KAMIS 28-Apr-22 KU 8375 309 4,00 m3
310 KAMIS 28-Apr-22 KU 8134 310 4,00 m3
311 KAMIS 28-Apr-22 KU 8699 311 4,00 m3
312 KAMIS 28-Apr-22 KU 9674 312 4,00 m3
313 KAMIS 28-Apr-22 KU 8438 313 4,00 m3
314 KAMIS 28-Apr-22 KT 8145 314 4,00 m3
315 KAMIS 28-Apr-22 KU 8829 315 4,00 m3
316 KAMIS 28-Apr-22 KT 8720 316 4,00 m3
317 KAMIS 28-Apr-22 KU 8161 317 4,00 m3

Page 5 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
318 KAMIS 28-Apr-22 KT 8024 318 4,00 m3
319 KAMIS 28-Apr-22 KU 8265 319 4,00 m3
320 KAMIS 28-Apr-22 KT 8279 320 4,00 m3
321 SABTU 07-Mei-22 KU 8074 328 4,00 m3
322 SABTU 07-Mei-22 KU 8072 329 4,00 m3
323 SABTU 07-Mei-22 KU 8375 330 4,00 m3
324 SABTU 07-Mei-22 KU 8549 331 4,00 m3
325 SABTU 07-Mei-22 KU 8375 332 4,00 m3
326 SABTU 07-Mei-22 KU 8024 333 4,00 m3
327 SABTU 07-Mei-22 KU 9305 334 4,00 m3
328 SABTU 07-Mei-22 KU 8265 335 4,00 m3
329 SABTU 07-Mei-22 KU 8074 336 4,00 m3
330 SABTU 07-Mei-22 KU 8549 337 4,00 m3
331 SABTU 07-Mei-22 KU 8375 338 4,00 m3
332 SABTU 07-Mei-22 KU 8024 339 4,00 m3
333 SABTU 07-Mei-22 KU 8547 340 4,00 m3
334 SABTU 07-Mei-22 KU 8540 341 4,00 m3
335 SABTU 07-Mei-22 KU 8265 342 4,00 m3
336 SABTU 07-Mei-22 KU 8074 343 4,00 m3
337 SABTU 07-Mei-22 KU 8549 344 4,00 m3
338 SABTU 07-Mei-22 KU 8166 345 4,00 m3
339 SABTU 07-Mei-22 KU 8699 346 4,00 m3
340 SABTU 07-Mei-22 KU 8375 347 4,00 m3
341 SABTU 07-Mei-22 KU 8438 348 4,00 m3
342 SABTU 07-Mei-22 KU 8547 349 4,00 m3
343 SABTU 07-Mei-22 KU 8161 351 4,00 m3
344 SABTU 07-Mei-22 KU 8509 352 4,00 m3
345 SABTU 07-Mei-22 KT 8549 353 4,00 m3
346 SABTU 07-Mei-22 KU 8860 354 4,00 m3
347 SABTU 07-Mei-22 KU 8166 355 4,00 m3
348 SABTU 07-Mei-22 KT 8279 356 4,00 m3
349 SABTU 07-Mei-22 KU 8829 357 4,00 m3
350 SABTU 07-Mei-22 KU 9674 358 4,00 m3
351 SABTU 07-Mei-22 KT 8150 359 4,00 m3
352 SABTU 07-Mei-22 KU 8699 360 4,00 m3
353 SABTU 07-Mei-22 KU 8438 361 4,00 m3
354 SABTU 07-Mei-22 KU 8375 362 4,00 m3
355 SABTU 07-Mei-22 KT 8024 363 4,00 m3
356 SABTU 07-Mei-22 KU 9305 364 4,00 m3
357 SABTU 07-Mei-22 KU 8265 365 4,00 m3
358 SABTU 07-Mei-22 KT 8720 366 4,00 m3
359 SABTU 07-Mei-22 KU 8074 367 4,00 m3
360 SABTU 07-Mei-22 KT 8786 368 4,00 m3
361 SABTU 07-Mei-22 KU 8161 369 4,00 m3
362 SABTU 07-Mei-22 KU 8505 370 4,00 m3
363 SABTU 07-Mei-22 KT 8549 371 4,00 m3
364 SABTU 07-Mei-22 KU 8860 372 4,00 m3
365 SABTU 07-Mei-22 KU 8166 373 4,00 m3
366 SABTU 07-Mei-22 KT 8279 374 4,00 m3
367 SABTU 07-Mei-22 KU 8829 375 4,00 m3
368 SABTU 07-Mei-22 KU 9674 376 4,00 m3
369 SABTU 07-Mei-22 KU 8699 377 4,00 m3
370 SABTU 07-Mei-22 KT 8150 378 4,00 m3
371 SABTU 07-Mei-22 KU 8375 379 4,00 m3
372 SABTU 07-Mei-22 KU 9305 380 4,00 m3
373 SABTU 07-Mei-22 KT 8024 381 4,00 m3
374 SABTU 07-Mei-22 KU 8265 382 4,00 m3
375 SABTU 07-Mei-22 KU 8438 401 4,00 m3
376 SABTU 07-Mei-22 KU 8375 402 4,00 m3
377 SABTU 07-Mei-22 KU 8074 403 4,00 m3
378 SABTU 07-Mei-22 KU 9305 404 4,00 m3
379 SABTU 07-Mei-22 KU 8265 405 4,00 m3
380 SABTU 07-Mei-22 KU 8699 406 4,00 m3
381 SABTU 07-Mei-22 KU 8166 407 4,00 m3

Page 6 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
382 SABTU 07-Mei-22 KU 8024 408 4,00 m3
383 SABTU 07-Mei-22 KU 8547 409 4,00 m3
384 SABTU 07-Mei-22 KU 8438 410 4,00 m3
385 SABTU 07-Mei-22 KU 8375 411 4,00 m3
386 SABTU 07-Mei-22 KU 8074 412 4,00 m3
387 SABTU 07-Mei-22 KU 8265 413 4,00 m3
388 SABTU 07-Mei-22 KU 9305 414 4,00 m3
389 SABTU 07-Mei-22 KU 8699 415 4,00 m3
390 SABTU 07-Mei-22 KU 8720 416 4,00 m3
391 SABTU 07-Mei-22 KU 8166 417 4,00 m3
392 SABTU 07-Mei-22 KU 8024 418 4,00 m3
393 SABTU 07-Mei-22 KU 8438 420 4,00 m3
394 SABTU 07-Mei-22 KU 8375 421 4,00 m3
395 SABTU 07-Mei-22 KU 8547 422 4,00 m3
396 SABTU 07-Mei-22 KU 8074 423 4,00 m3
397 SABTU 07-Mei-22 KU 8265 424 4,00 m3
398 SABTU 07-Mei-22 KU 8699 425 4,00 m3
399 SABTU 07-Mei-22 KU 8720 426 4,00 m3
400 SABTU 07-Mei-22 KU 8166 427 4,00 m3
401 SABTU 07-Mei-22 KU 9305 428 4,00 m3
402 SABTU 07-Mei-22 KU 8024 429 4,00 m3
403 SABTU 07-Mei-22 KU 8438 430 4,00 m3
404 SABTU 07-Mei-22 KU 8375 431 4,00 m3
405 SABTU 07-Mei-22 KU 8074 432 4,00 m3
406 SABTU 07-Mei-22 KU 8265 433 4,00 m3
407 SABTU 07-Mei-22 KU 8547 434 4,00 m3
408 SABTU 07-Mei-22 KU 8699 435 4,00 m3
409 SABTU 07-Mei-22 KU 8720 436 4,00 m3
410 SABTU 07-Mei-22 KU 8166 437 4,00 m3
411 SABTU 07-Mei-22 KU 9305 438 4,00 m3
412 SABTU 07-Mei-22 KU 8150 439 4,00 m3
413 SABTU 07-Mei-22 KU 9674 440 4,00 m3
414 SABTU 07-Mei-22 KU 8024 441 4,00 m3
415 SABTU 07-Mei-22 KU 8438 442 4,00 m3
416 SABTU 07-Mei-22 KU 8375 443 4,00 m3
417 SABTU 07-Mei-22 KU 8074 444 4,00 m3
418 SABTU 07-Mei-22 KU 8161 445 4,00 m3
419 SABTU 07-Mei-22 KU 8509 446 4,00 m3
420 SABTU 07-Mei-22 KU 8265 447 4,00 m3
421 SABTU 07-Mei-22 KU 8547 448 4,00 m3
422 SABTU 07-Mei-22 KU 8699 449 4,00 m3
423 SABTU 07-Mei-22 KU 8720 450 4,00 m3
424 SABTU 07-Mei-22 KU 8166 451 4,00 m3
425 SABTU 07-Mei-22 KU 9305 452 4,00 m3
426 SABTU 07-Mei-22 KU 8150 453 4,00 m3
427 SABTU 07-Mei-22 KU 8786 454 4,00 m3
428 SABTU 07-Mei-22 KU 8279 455 4,00 m3
429 SABTU 07-Mei-22 KU 9674 456 4,00 m3
430 SABTU 07-Mei-22 KU 8024 457 4,00 m3
431 SABTU 07-Mei-22 KU 8438 458 4,00 m3
432 SABTU 07-Mei-22 KU 8161 459 4,00 m3
433 SABTU 07-Mei-22 KU 8509 460 4,00 m3
434 SABTU 07-Mei-22 KU 8265 461 4,00 m3
435 SABTU 07-Mei-22 KU 8074 462 4,00 m3
436 SABTU 07-Mei-22 KU 8699 463 4,00 m3
437 SABTU 07-Mei-22 KT 8720 464 4,00 m3
438 SABTU 07-Mei-22 KT 8786 465 4,00 m3
439 SABTU 07-Mei-22 KU 8161 466 4,00 m3
440 SABTU 07-Mei-22 KU 8509 467 4,00 m3
441 SABTU 07-Mei-22 KT 8549 468 4,00 m3
442 SABTU 07-Mei-22 KU 8860 469 4,00 m3
443 SABTU 07-Mei-22 KU 8166 470 4,00 m3
444 SABTU 07-Mei-22 KT 8279 471 4,00 m3
445 SABTU 07-Mei-22 KU 8829 472 4,00 m3

Page 7 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
446 SABTU 07-Mei-22 KU 9674 473 4,00 m3
447 SABTU 07-Mei-22 KT 8150 474 4,00 m3
448 SABTU 07-Mei-22 KU 8436 475 4,00 m3
449 SABTU 07-Mei-22 KU 8375 476 4,00 m3
450 SABTU 07-Mei-22 KT 8024 477 4,00 m3
451 SABTU 07-Mei-22 KU 9305 478 4,00 m3
452 SABTU 07-Mei-22 KU 8265 479 4,00 m3
453 SABTU 07-Mei-22 KU 8074 480 4,00 m3
454 SABTU 07-Mei-22 KU 8720 481 4,00 m3
455 SABTU 07-Mei-22 KT 8786 482 4,00 m3
456 SABTU 07-Mei-22 KU 8161 483 4,00 m3
457 SABTU 07-Mei-22 KU 8509 484 4,00 m3
458 SABTU 07-Mei-22 KT 8549 485 4,00 m3
459 SABTU 07-Mei-22 KU 8860 486 4,00 m3
460 SABTU 07-Mei-22 KU 8166 487 4,00 m3
461 SABTU 07-Mei-22 KT 8279 488 4,00 m3
462 SABTU 07-Mei-22 KU 8829 489 4,00 m3
463 SABTU 07-Mei-22 KU 9674 490 4,00 m3
464 SABTU 07-Mei-22 KT 8150 491 4,00 m3
465 SABTU 07-Mei-22 KU 8699 492 4,00 m3
466 SABTU 07-Mei-22 KU 8438 493 4,00 m3
467 SABTU 07-Mei-22 KU 8375 494 4,00 m3
468 SABTU 07-Mei-22 KT 8024 495 4,00 m3
469 SABTU 07-Mei-22 KU 9305 496 4,00 m3
470 SABTU 07-Mei-22 KU 8265 497 4,00 m3
471 SABTU 07-Mei-22 KU 8074 498 4,00 m3
472 SABTU 07-Mei-22 KT 8720 499 4,00 m3
473 SABTU 07-Mei-22 KT 8786 500 4,00 m3
474 SABTU 07-Mei-22 KU 8024 551 4,00 m3
475 SABTU 07-Mei-22 KU 9305 552 4,00 m3
476 SABTU 07-Mei-22 KU 8074 553 4,00 m3
477 SABTU 07-Mei-22 KU 8549 554 4,00 m3
478 SABTU 07-Mei-22 KU 8166 555 4,00 m3
479 SABTU 07-Mei-22 KU 8375 556 4,00 m3
480 SABTU 07-Mei-22 KU 8438 557 4,00 m3
481 SABTU 07-Mei-22 KU 8074 558 4,00 m3
482 SABTU 07-Mei-22 KU 8265 559 4,00 m3
483 SABTU 07-Mei-22 KU 9305 560 4,00 m3
484 SABTU 07-Mei-22 KU 8699 561 4,00 m3
485 SABTU 07-Mei-22 KU 8166 562 4,00 m3
486 SABTU 07-Mei-22 KU 8024 563 4,00 m3
487 SABTU 07-Mei-22 KU 8547 564 4,00 m3
488 SABTU 07-Mei-22 KU 8505 565 4,00 m3
489 MINGGU 08-Mei-22 KU 9305 383 4,00 m3
490 MINGGU 08-Mei-22 KU 8161 384 4,00 m3
491 MINGGU 08-Mei-22 KU 8265 385 4,00 m3
492 MINGGU 08-Mei-22 KT 8024 386 4,00 m3
493 MINGGU 08-Mei-22 KU 8547 387 4,00 m3
494 MINGGU 08-Mei-22 KU 8829 388 4,00 m3
495 MINGGU 08-Mei-22 KT 8279 389 4,00 m3
496 MINGGU 08-Mei-22 KU 8509 390 4,00 m3
497 MINGGU 08-Mei-22 KU 9674 391 4,00 m3
498 MINGGU 08-Mei-22 KU 9305 392 4,00 m3
499 MINGGU 08-Mei-22 KT 8150 393 4,00 m3
500 MINGGU 08-Mei-22 KT 8279 394 4,00 m3
501 MINGGU 08-Mei-22 KU 8829 395 4,00 m3
502 MINGGU 08-Mei-22 KU 8074 396 4,00 m3
503 MINGGU 08-Mei-22 KU 8509 397 4,00 m3
504 MINGGU 08-Mei-22 KT 8024 398 4,00 m3
505 MINGGU 08-Mei-22 KU 8438 399 4,00 m3
506 MINGGU 08-Mei-22 KT 8720 400 4,00 m3
507 MINGGU 08-Mei-22 KT 8150 501 4,00 m3
508 MINGGU 08-Mei-22 KT 8279 502 4,00 m3
509 MINGGU 08-Mei-22 KU 8166 503 4,00 m3

Page 8 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
510 MINGGU 08-Mei-22 KU 8860 504 4,00 m3
511 MINGGU 08-Mei-22 KT 8786 505 4,00 m3
512 MINGGU 08-Mei-22 KU 8829 506 4,00 m3
513 MINGGU 08-Mei-22 KU 8265 507 4,00 m3
514 MINGGU 08-Mei-22 KU 8074 508 4,00 m3
515 MINGGU 08-Mei-22 KU 8509 509 4,00 m3
516 MINGGU 08-Mei-22 KU 8375 510 4,00 m3
517 MINGGU 08-Mei-22 KT 8781 511 4,00 m3
518 MINGGU 08-Mei-22 KU 8438 512 4,00 m3
519 MINGGU 08-Mei-22 KT 8024 513 4,00 m3
520 MINGGU 08-Mei-22 KU 8314 514 4,00 m3
521 MINGGU 08-Mei-22 KT 8720 515 4,00 m3
522 MINGGU 08-Mei-22 KU 8161 516 4,00 m3
523 MINGGU 08-Mei-22 KT 8150 517 4,00 m3
524 MINGGU 08-Mei-22 KT 8279 518 4,00 m3
525 MINGGU 08-Mei-22 KU 8166 519 4,00 m3
526 MINGGU 08-Mei-22 KU 8860 520 4,00 m3
527 MINGGU 08-Mei-22 KT 8786 521 4,00 m3
528 MINGGU 08-Mei-22 KU 8829 522 4,00 m3
529 MINGGU 08-Mei-22 KU 8265 523 4,00 m3
530 MINGGU 08-Mei-22 KU 8074 524 4,00 m3
531 MINGGU 08-Mei-22 KU 8509 525 4,00 m3
532 MINGGU 08-Mei-22 KU 8375 526 4,00 m3
533 MINGGU 08-Mei-22 KT 8781 527 4,00 m3
534 MINGGU 08-Mei-22 KU 8438 528 4,00 m3
535 MINGGU 08-Mei-22 KT 8720 529 4,00 m3
536 MINGGU 08-Mei-22 KT 8145 530 4,00 m3
537 MINGGU 08-Mei-22 KU 9674 531 4,00 m3
538 MINGGU 08-Mei-22 KU 8547 532 4,00 m3
539 MINGGU 08-Mei-22 KU 8314 533 4,00 m3
540 MINGGU 08-Mei-22 KT 8024 534 4,00 m3
541 MINGGU 08-Mei-22 KU 8161 535 4,00 m3
542 MINGGU 08-Mei-22 KT 8150 536 4,00 m3
543 MINGGU 08-Mei-22 KT 8279 537 4,00 m3
544 MINGGU 08-Mei-22 KU 8166 538 4,00 m3
545 MINGGU 08-Mei-22 KU 8860 539 4,00 m3
546 MINGGU 08-Mei-22 KU 8829 540 4,00 m3
547 MINGGU 08-Mei-22 KU 8265 541 4,00 m3
548 MINGGU 08-Mei-22 KT 8786 542 4,00 m3
549 MINGGU 08-Mei-22 KU 8375 543 4,00 m3
550 MINGGU 08-Mei-22 KT 8781 544 4,00 m3
551 MINGGU 08-Mei-22 KU 8509 545 4,00 m3
552 MINGGU 08-Mei-22 KU 8438 546 4,00 m3
553 MINGGU 08-Mei-22 KT 8720 547 4,00 m3
554 MINGGU 08-Mei-22 KT 8145 548 4,00 m3
555 MINGGU 08-Mei-22 KA 9674 549 4,00 m3
556 MINGGU 08-Mei-22 KU 9305 550 4,00 m3
557 MINGGU 08-Mei-22 KU 8547 566 4,00 m3
558 MINGGU 08-Mei-22 KU 8074 567 4,00 m3
559 MINGGU 08-Mei-22 KU 8313 568 4,00 m3
560 MINGGU 08-Mei-22 KT 8024 569 4,00 m3
561 MINGGU 08-Mei-22 KU 8161 570 4,00 m3
562 MINGGU 08-Mei-22 KT 8150 571 4,00 m3
563 MINGGU 08-Mei-22 KT 8279 572 4,00 m3
564 MINGGU 08-Mei-22 KU 8166 573 4,00 m3
565 MINGGU 08-Mei-22 KU 8860 574 4,00 m3
566 MINGGU 08-Mei-22 KU 8829 575 4,00 m3
567 MINGGU 08-Mei-22 KU 8265 576 4,00 m3
568 MINGGU 08-Mei-22 KY 8375 577 4,00 m3
569 MINGGU 08-Mei-22 KT 8786 578 4,00 m3
570 MINGGU 08-Mei-22 KT 8781 579 4,00 m3
571 MINGGU 08-Mei-22 KU 8509 580 4,00 m3
572 MINGGU 08-Mei-22 KU 8438 581 4,00 m3
573 MINGGU 08-Mei-22 KT 8720 582 4,00 m3

Page 9 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
574 MINGGU 08-Mei-22 KT 8145 583 4,00 m3
575 MINGGU 08-Mei-22 KU 9674 584 4,00 m3
576 MINGGU 08-Mei-22 KU 9305 585 4,00 m3
577 MINGGU 08-Mei-22 KU 8074 586 4,00 m3
578 MINGGU 08-Mei-22 KU 8161 587 4,00 m3
579 MINGGU 08-Mei-22 KU 8547 588 4,00 m3
580 MINGGU 08-Mei-22 KT 8279 589 4,00 m3
581 MINGGU 08-Mei-22 KT 8024 590 4,00 m3
582 MINGGU 08-Mei-22 KU 8829 591 4,00 m3
583 MINGGU 08-Mei-22 KU 8265 592 4,00 m3
584 MINGGU 08-Mei-22 KU 8375 593 4,00 m3
585 MINGGU 08-Mei-22 KT 8150 594 4,00 m3
586 MINGGU 08-Mei-22 KU 8509 595 4,00 m3
587 MINGGU 08-Mei-22 KU 8438 596 4,00 m3
588 MINGGU 08-Mei-22 KU 8720 597 4,00 m3
589 MINGGU 08-Mei-22 KT 8145 598 4,00 m3
590 MINGGU 08-Mei-22 KU 9674 599 4,00 m3
591 MINGGU 08-Mei-22 KU 8166 600 4,00 m3
592 MINGGU 08-Mei-22 KU 8314 601 4,00 m3
593 MINGGU 08-Mei-22 KU 8074 602 4,00 m3
594 MINGGU 08-Mei-22 KU 8161 603 4,00 m3
595 MINGGU 08-Mei-22 KU 8547 604 4,00 m3
596 MINGGU 08-Mei-22 KT 8150 605 4,00 m3
597 MINGGU 08-Mei-22 KU 8860 606 4,00 m3
598 MINGGU 08-Mei-22 KU 8305 607 4,00 m3
599 MINGGU 08-Mei-22 KT 8279 608 4,00 m3
600 MINGGU 08-Mei-22 KT 8024 609 4,00 m3
601 MINGGU 08-Mei-22 KU 8829 610 4,00 m3
602 MINGGU 08-Mei-22 KU 8265 611 4,00 m3
603 MINGGU 08-Mei-22 KU 8375 612 4,00 m3
604 MINGGU 08-Mei-22 KU 8509 613 4,00 m3
605 MINGGU 08-Mei-22 KU 8088 614 4,00 m3
606 MINGGU 08-Mei-22 KU 8438 615 4,00 m3
607 MINGGU 08-Mei-22 KT 8720 616 4,00 m3
608 MINGGU 08-Mei-22 KT 8145 617 4,00 m3
609 MINGGU 08-Mei-22 KU 9674 618 4,00 m3
610 MINGGU 08-Mei-22 KU 8166 619 4,00 m3
611 MINGGU 08-Mei-22 KU 8547 620 4,00 m3
612 MINGGU 08-Mei-22 KU 8161 621 4,00 m3
613 MINGGU 08-Mei-22 KT 8150 622 4,00 m3
614 MINGGU 08-Mei-22 KU 8860 623 4,00 m3
615 MINGGU 08-Mei-22 KT 8279 624 4,00 m3
616 MINGGU 08-Mei-22 KT 8024 625 4,00 m3
617 MINGGU 08-Mei-22 KU 8829 626 4,00 m3
618 MINGGU 08-Mei-22 KU 8265 627 4,00 m3
619 MINGGU 08-Mei-22 KU 8375 628 4,00 m3
620 MINGGU 08-Mei-22 KU 8509 629 4,00 m3
621 MINGGU 08-Mei-22 KU 8088 630 4,00 m3
622 MINGGU 08-Mei-22 KU 8438 631 4,00 m3
623 MINGGU 08-Mei-22 KT 8720 632 4,00 m3
624 MINGGU 08-Mei-22 KT 8786 633 4,00 m3
625 MINGGU 08-Mei-22 KT 8150 634 4,00 m3
626 MINGGU 08-Mei-22 KU 8161 635 4,00 m3
627 MINGGU 08-Mei-22 KU 8088 636 4,00 m3
628 MINGGU 08-Mei-22 KT 8024 637 4,00 m3
629 MINGGU 08-Mei-22 KU 8829 638 4,00 m3
630 MINGGU 08-Mei-22 KU 8265 639 4,00 m3
631 MINGGU 08-Mei-22 KU 8166 640 4,00 m3
632 MINGGU 08-Mei-22 KT 8279 641 4,00 m3
633 MINGGU 08-Mei-22 KU 8438 642 4,00 m3
634 MINGGU 08-Mei-22 KU 8438 643 4,00 m3
635 MINGGU 08-Mei-22 KU 9674 644 4,00 m3
636 MINGGU 08-Mei-22 KU 8509 645 4,00 m3
637 MINGGU 08-Mei-22 KU 9305 646 4,00 m3

Page 10 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
638 MINGGU 08-Mei-22 KU 8375 647 4,00 m3
639 MINGGU 08-Mei-22 KU 8547 648 4,00 m3
640 MINGGU 08-Mei-22 KU 8074 649 4,00 m3
641 MINGGU 08-Mei-22 KU 8860 650 4,00 m3
642 MINGGU 08-Mei-22 KT 8150 651 4,00 m3
643 MINGGU 08-Mei-22 KT 8720 652 4,00 m3
644 MINGGU 08-Mei-22 KT 8786 653 4,00 m3
645 MINGGU 08-Mei-22 KU 8161 654 4,00 m3
646 MINGGU 08-Mei-22 KU 8088 655 4,00 m3
647 MINGGU 08-Mei-22 KT 8024 656 4,00 m3
648 MINGGU 08-Mei-22 KU 8829 657 4,00 m3
649 MINGGU 08-Mei-22 KU 8265 658 4,00 m3
650 MINGGU 08-Mei-22 KU 8166 659 4,00 m3
651 MINGGU 08-Mei-22 KT 8279 660 4,00 m3
652 MINGGU 08-Mei-22 KU 9674 661 4,00 m3
653 MINGGU 08-Mei-22 KU 85 09 662 4,00 m3
654 MINGGU 08-Mei-22 KU 9305 663 4,00 m3
655 MINGGU 08-Mei-22 KU 8375 664 4,00 m3
656 MINGGU 08-Mei-22 KU 8547 665 4,00 m3
657 MINGGU 08-Mei-22 KU 8860 666 4,00 m3
658 MINGGU 08-Mei-22 KU 8074 667 4,00 m3
659 MINGGU 08-Mei-22 KT 8150 668 4,00 m3
660 MINGGU 08-Mei-22 KT 8720 669 4,00 m3
661 MINGGU 08-Mei-22 KT 8786 670 4,00 m3
662 MINGGU 08-Mei-22 KU 8161 671 4,00 m3
663 MINGGU 08-Mei-22 KU 8088 672 4,00 m3
664 MINGGU 08-Mei-22 KT 8024 673 4,00 m3
665 MINGGU 08-Mei-22 KU 8829 674 4,00 m3
666 MINGGU 08-Mei-22 KU 8265 675 4,00 m3
667 MINGGU 08-Mei-22 KU 8166 676 4,00 m3
668 MINGGU 08-Mei-22 KU 8438 677 4,00 m3
669 MINGGU 08-Mei-22 KU 9674 678 4,00 m3
670 MINGGU 08-Mei-22 KU 8509 679 4,00 m3
671 MINGGU 08-Mei-22 KU 9305 680 4,00 m3
672 MINGGU 08-Mei-22 KU 8375 681 4,00 m3
673 MINGGU 08-Mei-22 KU 8547 682 4,00 m3
674 MINGGU 08-Mei-22 KU 8074 683 4,00 m3
675 MINGGU 08-Mei-22 KU 8860 684 4,00 m3
676 MINGGU 08-Mei-22 KT 8720 685 4,00 m3
677 MINGGU 08-Mei-22 KU 8161 686 4,00 m3
678 MINGGU 08-Mei-22 KT 8786 687 4,00 m3
679 MINGGU 08-Mei-22 KU 8088 688 4,00 m3
680 MINGGU 08-Mei-22 KT 8024 689 4,00 m3
681 MINGGU 08-Mei-22 KU 8829 690 4,00 m3
682 MINGGU 08-Mei-22 KU 8265 691 4,00 m3
683 MINGGU 08-Mei-22 KU 8166 692 4,00 m3
684 MINGGU 08-Mei-22 KU 8438 693 4,00 m3
685 MINGGU 08-Mei-22 KU 8509 694 4,00 m3
686 MINGGU 08-Mei-22 KU 9305 695 4,00 m3
687 MINGGU 08-Mei-22 KU 8375 696 4,00 m3
688 MINGGU 08-Mei-22 KU 8547 697 4,00 m3
689 JUM'AT 13-Mei-22 KU 8161 698 4,00 m3
690 JUM'AT 13-Mei-22 KU 8958 699 4,00 m3
691 JUM'AT 13-Mei-22 KU 9674 700 4,00 m3
692 JUM'AT 13-Mei-22 KU 8549 701 4,00 m3
693 JUM'AT 13-Mei-22 KU 8547 702 4,00 m3
694 JUM'AT 13-Mei-22 KU 8375 703 4,00 m3
695 JUM'AT 13-Mei-22 KU 8265 704 4,00 m3
696 JUM'AT 13-Mei-22 KU 8166 705 4,00 m3
697 JUM'AT 13-Mei-22 KU 8074 706 4,00 m3
698 JUM'AT 13-Mei-22 KT 8024 707 4,00 m3
699 JUM'AT 13-Mei-22 KU 8438 708 m3
700 JUM'AT 13-Mei-22 KU 8958 709 4,00 m3
701 JUM'AT 13-Mei-22 KU 8161 710 4,00 m3

Page 11 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
702 JUM'AT 13-Mei-22 KU 9674 711 4,00 m3
703 JUM'AT 13-Mei-22 KT 8549 712 4,00 m3
704 JUM'AT 13-Mei-22 KU 8375 713 4,00 m3
705 JUM'AT 13-Mei-22 KU 8547 714 4,00 m3
706 JUM'AT 13-Mei-22 KU 8509 715 4,00 m3
707 JUM'AT 13-Mei-22 KU 8166 716 4,00 m3
708 JUM'AT 13-Mei-22 KU 8265 717 4,00 m3
709 JUM'AT 13-Mei-22 KU 8074 718 4,00 m3
710 JUM'AT 13-Mei-22 KU 8024 719 4,00 m3
711 JUM'AT 13-Mei-22 KU 8438 720 4,00 m3
712 JUM'AT 13-Mei-22 KU 8958 721 4,00 m3
713 JUM'AT 13-Mei-22 KU 8161 722 4,00 m3
714 JUM'AT 13-Mei-22 KT 8145 723 4,00 m3
715 JUM'AT 13-Mei-22 KU 9674 724 4,00 m3
716 JUM'AT 13-Mei-22 KT 8549 725 4,00 m3
717 JUM'AT 13-Mei-22 KU 8375 726 4,00 m3
718 JUM'AT 13-Mei-22 KU 8542 727 4,00 m3
719 JUM'AT 13-Mei-22 KU 8509 728 4,00 m3
720 JUM'AT 13-Mei-22 KU 8166 729 4,00 m3
721 JUM'AT 13-Mei-22 KU 8074 730 4,00 m3
722 JUM'AT 13-Mei-22 KU 8265 731 4,00 m3
723 JUM'AT 13-Mei-22 KT 8024 732 4,00 m3
724 JUM'AT 13-Mei-22 KT 8720 733 4,00 m3
725 JUM'AT 13-Mei-22 KU 8438 734 4,00 m3
726 JUM'AT 13-Mei-22 KU 8958 735 4,00 m3
727 JUM'AT 13-Mei-22 KT 8145 736 4,00 m3
728 JUM'AT 13-Mei-22 KU 8161 737 4,00 m3
729 JUM'AT 13-Mei-22 KU 9674 738 4,00 m3
730 JUM'AT 13-Mei-22 KU 8375 739 4,00 m3
731 JUM'AT 13-Mei-22 KU 8509 740 4,00 m3
732 JUM'AT 13-Mei-22 KU 8166 741 4,00 m3
733 JUM'AT 13-Mei-22 KU 8074 742 4,00 m3
734 JUM'AT 13-Mei-22 KU 8547 743 4,00 m3
735 JUM'AT 13-Mei-22 KU 8265 744 4,00 m3
736 JUM'AT 13-Mei-22 KT 8024 745 4,00 m3
737 JUM'AT 13-Mei-22 KU 8438 746 4,00 m3
738 JUM'AT 13-Mei-22 KT 8720 747 4,00 m3
739 JUM'AT 13-Mei-22 KU 8958 748 4,00 m3
740 JUM'AT 13-Mei-22 KT 8145 749 4,00 m3
741 JUM'AT 13-Mei-22 KU 8161 750 4,00 m3
742 JUM'AT 13-Mei-22 KU 9674 751 4,00 m3
743 JUM'AT 13-Mei-22 KU 8375 752 4,00 m3
744 JUM'AT 13-Mei-22 KU 8509 753 4,00 m3
745 JUM'AT 13-Mei-22 KU 8166 754 4,00 m3
746 JUM'AT 13-Mei-22 KU 8074 755 4,00 m3
747 JUM'AT 13-Mei-22 KU 8547 756 4,00 m3
748 JUM'AT 13-Mei-22 KU 8265 757 4,00 m3
749 JUM'AT 13-Mei-22 KU 8438 758 4,00 m3
750 JUM'AT 13-Mei-22 KT 8024 759 4,00 m3
751 JUM'AT 13-Mei-22 KU 8958 760 4,00 m3
752 JUM'AT 13-Mei-22 KT 8720 761 4,00 m3
753 JUM'AT 13-Mei-22 KT 8145 762 4,00 m3
754 JUM'AT 13-Mei-22 KU 8161 763 4,00 m3
755 JUM'AT 13-Mei-22 KU 9674 764 4,00 m3
756 JUM'AT 13-Mei-22 KU 8375 765 4,00 m3
757 JUM'AT 13-Mei-22 KU 8509 766 4,00 m3
758 JUM'AT 13-Mei-22 KU 8166 767 4,00 m3
759 JUM'AT 13-Mei-22 KU 8074 768 4,00 m3
760 JUM'AT 13-Mei-22 KU 8074 769 4,00 m3
761 JUM'AT 13-Mei-22 KU 8547 770 4,00 m3
762 JUM'AT 13-Mei-22 KU 8265 771 4,00 m3
763 JUM'AT 13-Mei-22 KU 8438 772 4,00 m3
764 JUM'AT 13-Mei-22 KU 8958 773 4,00 m3
765 JUM'AT 13-Mei-22 KT 8145 774 4,00 m3

Page 12 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
766 JUM'AT 13-Mei-22 KU 8509 775 4,00 m3
767 JUM'AT 13-Mei-22 KT 8024 776 4,00 m3
768 JUM'AT 13-Mei-22 KT 8720 777 4,00 m3
769 JUM'AT 13-Mei-22 KU 8161 778 4,00 m3
770 JUM'AT 13-Mei-22 KU 8438 779 4,00 m3
771 JUM'AT 13-Mei-22 KU 8375 780 4,00 m3
772 JUM'AT 13-Mei-22 KT 8150 781 4,00 m3
773 JUM'AT 13-Mei-22 KU 8265 782 4,00 m3
774 JUM'AT 13-Mei-22 KT 8024 783 4,00 m3
775 JUM'AT 13-Mei-22 KU 8166 784 4,00 m3
776 JUM'AT 13-Mei-22 KU 9674 785 4,00 m3
777 JUM'AT 13-Mei-22 KU 9305 786 4,00 m3
778 JUM'AT 13-Mei-22 KU 8806 787 4,00 m3
779 JUM'AT 13-Mei-22 KU 8699 788 4,00 m3
780 JUM'AT 13-Mei-22 KU 8088 789 4,00 m3
781 JUM'AT 13-Mei-22 KU 8958 790 4,00 m3
782 JUM'AT 13-Mei-22 KU 8547 791 4,00 m3
783 JUM'AT 13-Mei-22 KT 8020 792 4,00 m3
784 JUM'AT 13-Mei-22 KT 8786 793 4,00 m3
785 JUM'AT 13-Mei-22 KU 8088 794 4,00 m3
786 JUM'AT 13-Mei-22 KU 8549 795 4,00 m3
787 JUM'AT 13-Mei-22 KT 8145 796 4,00 m3
788 JUM'AT 13-Mei-22 KU 8161 797 4,00 m3
789 JUM'AT 13-Mei-22 KU 8438 798 4,00 m3
790 JUM'AT 13-Mei-22 KU 8074 799 4,00 m3
791 JUM'AT 13-Mei-22 KU 8375 800 4,00 m3
792 JUM'AT 13-Mei-22 KU 8150 801 4,00 m3
793 JUM'AT 13-Mei-22 KU 8265 802 4,00 m3
794 JUM'AT 13-Mei-22 KT 8024 803 4,00 m3
795 JUM'AT 13-Mei-22 KU 9674 804 4,00 m3
796 JUM'AT 13-Mei-22 KU 8509 805 4,00 m3
797 JUM'AT 13-Mei-22 KU 8166 806 4,00 m3
798 JUM'AT 13-Mei-22 KU 9305 807 4,00 m3
799 JUM'AT 13-Mei-22 KU 8008 808 4,00 m3
800 JUM'AT 13-Mei-22 KT 8720 809 4,00 m3
801 JUM'AT 13-Mei-22 KU 8860 810 4,00 m3
802 JUM'AT 13-Mei-22 KU 8699 811 4,00 m3
803 JUM'AT 13-Mei-22 KU 8958 812 4,00 m3
804 JUM'AT 13-Mei-22 KU 8542 813 4,00 m3
805 JUM'AT 13-Mei-22 KT 8786 814 4,00 m3
806 JUM'AT 13-Mei-22 KT 8279 815 4,00 m3
807 JUM'AT 13-Mei-22 KT 8549 816 4,00 m3
808 JUM'AT 13-Mei-22 KT 8145 817 4,00 m3
809 JUM'AT 13-Mei-22 KU 8161 818 4,00 m3
810 JUM'AT 13-Mei-22 KU 8438 819 4,00 m3
811 JUM'AT 13-Mei-22 KU 8074 820 4,00 m3
812 JUM'AT 13-Mei-22 KU 8375 821 4,00 m3
813 JUM'AT 13-Mei-22 KT 8150 822 4,00 m3
814 JUM'AT 13-Mei-22 KU 8265 823 4,00 m3
815 JUM'AT 13-Mei-22 KT 8024 824 4,00 m3
816 JUM'AT 13-Mei-22 KU 9674 825 2,90 m3
817 JUM'AT 13-Mei-22 KU 8609 826 3,00 m3
818 JUM'AT 13-Mei-22 KU 8166 827 2,90 m3
819 JUM'AT 13-Mei-22 KU 9305 828 3,40 m3
820 JUM'AT 13-Mei-22 KU 8088 829 4,00 m3
821 JUM'AT 13-Mei-22 KT 8720 830 3,30 m3
822 JUM'AT 13-Mei-22 KU 8699 831 4,00 m3
823 JUM'AT 13-Mei-22 KU 8958 832 3,40 m3
824 JUM'AT 13-Mei-22 KU 8547 833 3,80 m3
825 JUM'AT 13-Mei-22 KT 8486 834 3,80 m3
826 JUM'AT 13-Mei-22 KT 8279 835 2,45 m3
827 JUM'AT 13-Mei-22 KU 8060 836 4,20 m3
828 JUM'AT 13-Mei-22 KT 8549 837 3,97 m3
829 JUM'AT 13-Mei-22 KT 8145 838 4,00 m3

Page 13 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
830 JUM'AT 13-Mei-22 KU 8161 839 4,00 m3
831 JUM'AT 13-Mei-22 KU 8438 840 3,87 m3
832 JUM'AT 13-Mei-22 KU 8074 841 4,00 m3
833 JUM'AT 13-Mei-22 KU 8375 842 4,00 m3
834 JUM'AT 13-Mei-22 KT 8150 843 4,00 m3
835 SABTU 14-Mei-22 KU 8161 844 4,00 m3
836 SABTU 14-Mei-22 KU 8829 845 4,00 m3
837 SABTU 14-Mei-22 KT 8024 846 4,00 m3
838 SABTU 14-Mei-22 KU 8438 847 4,00 m3
839 SABTU 14-Mei-22 KT 8154 848 4,00 m3
840 SABTU 14-Mei-22 KU 8265 849 4,00 m3
841 SABTU 14-Mei-22 KU 8958 850 4,00 m3
842 SABTU 14-Mei-22 KT 8720 851 4,00 m3
843 SABTU 14-Mei-22 KU 9674 852 4,00 m3
844 SABTU 14-Mei-22 KU 8161 853 4,00 m3
845 SABTU 14-Mei-22 KU 8829 854 4,00 m3
846 SABTU 14-Mei-22 KU 8438 855 4,00 m3
847 SABTU 14-Mei-22 KT 8024 856 4,00 m3
848 SABTU 14-Mei-22 KT 8145 857 4,00 m3
849 SABTU 14-Mei-22 KU 8265 858 4,00 m3
850 SABTU 14-Mei-22 KU 8958 859 4,00 m3
851 SABTU 14-Mei-22 KT 8720 860 4,00 m3
852 SABTU 14-Mei-22 KU 9674 861 4,00 m3
853 SABTU 14-Mei-22 KU 9674 862 4,00 m3
854 SABTU 14-Mei-22 KU 8161 863 4,00 m3
855 SABTU 14-Mei-22 KU 8829 864 4,00 m3
856 SABTU 14-Mei-22 KU 8074 865 4,00 m3
857 SABTU 14-Mei-22 KU 8375 866 4,00 m3
858 SABTU 14-Mei-22 KU 8166 867 4,00 m3
859 SABTU 14-Mei-22 KT 8024 868 4,00 m3
860 SABTU 14-Mei-22 KT 8145 869 4,00 m3
861 SABTU 14-Mei-22 KU 8265 870 4,00 m3
862 SABTU 14-Mei-22 KU 8438 871 4,00 m3
863 SABTU 14-Mei-22 KU 8958 872 4,00 m3
864 SABTU 14-Mei-22 KT 8720 873 4,00 m3
865 SABTU 14-Mei-22 KU 8161 874 4,00 m3
866 SABTU 14-Mei-22 KU 8547 875 4,00 m3
867 SABTU 14-Mei-22 KU 8829 876 4,00 m3
868 SABTU 14-Mei-22 KU 8074 877 4,00 m3
869 SABTU 14-Mei-22 KU 8375 878 4,00 m3
870 SABTU 14-Mei-22 KU 8166 879 4,00 m3
871 SABTU 14-Mei-22 KT 8024 880 4,00 m3
872 SABTU 14-Mei-22 KT 8145 881 4,00 m3
873 SABTU 14-Mei-22 KU 8438 882 4,00 m3
874 SABTU 14-Mei-22 KU 8265 883 4,00 m3
875 SABTU 14-Mei-22 KU 8958 884 4,00 m3
876 SABTU 14-Mei-22 KT 8720 885 4,00 m3
877 SABTU 14-Mei-22 KU 9674 886 4,00 m3
878 SABTU 14-Mei-22 KU 8161 887 4,00 m3
879 SABTU 14-Mei-22 KT 8024 889 4,00 m3
880 SABTU 14-Mei-22 KU 8438 890 4,00 m3
881 MINGGU 15-Mei-22 KT 8150 891 4,00 m3
882 MINGGU 15-Mei-22 KT 8549 892 4,00 m3
883 MINGGU 15-Mei-22 KU 8509 893 4,00 m3
884 MINGGU 15-Mei-22 KU 8265 894 4,00 m3
885 MINGGU 15-Mei-22 KT 8024 895 4,00 m3
886 MINGGU 15-Mei-22 KU 9674 896 4,00 m3
887 MINGGU 15-Mei-22 KU 8375 897 4,00 m3
888 MINGGU 15-Mei-22 KU 8161 898 4,00 m3
889 MINGGU 15-Mei-22 KU 8166 899 4,00 m3
890 MINGGU 15-Mei-22 KU 8547 900 4,00 m3
891 MINGGU 15-Mei-22 KU 8074 901 4,00 m3
892 MINGGU 15-Mei-22 KU 8438 902 4,00 m3
893 MINGGU 15-Mei-22 KU 8829 903 4,00 m3

Page 14 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
894 MINGGU 15-Mei-22 KU 8314 904 4,00 m3
895 MINGGU 15-Mei-22 KT 8150 905 4,00 m3
896 MINGGU 15-Mei-22 KT 8549 906 4,00 m3
897 MINGGU 15-Mei-22 KU 8509 907 4,00 m3
898 MINGGU 15-Mei-22 KU 8265 908 4,00 m3
899 MINGGU 15-Mei-22 KU 9305 909 4,00 m3
900 MINGGU 15-Mei-22 KT 8024 910 4,00 m3
901 MINGGU 15-Mei-22 KU 9674 911 4,00 m3
902 MINGGU 15-Mei-22 KU 8375 912 4,00 m3
903 MINGGU 15-Mei-22 KU 8166 913 4,00 m3
904 MINGGU 15-Mei-22 KU 8161 914 4,00 m3
905 MINGGU 15-Mei-22 KU 8547 915 4,00 m3
906 MINGGU 15-Mei-22 KU 8074 916 4,00 m3
907 MINGGU 15-Mei-22 KT 8720 917 4,00 m3
908 MINGGU 15-Mei-22 KU 8438 918 4,00 m3
909 MINGGU 15-Mei-22 KU 8829 919 4,00 m3
910 MINGGU 15-Mei-22 KU 8314 920 4,00 m3
911 MINGGU 15-Mei-22 KU 8958 921 4,00 m3
912 MINGGU 15-Mei-22 KU 8549 922 4,00 m3
913 MINGGU 15-Mei-22 KT 8786 923 4,00 m3
914 MINGGU 15-Mei-22 KT 8150 924 4,00 m3
915 MINGGU 15-Mei-22 KU 8509 925 4,00 m3
916 MINGGU 15-Mei-22 KU 8699 926 4,00 m3
917 MINGGU 15-Mei-22 KU 8265 927 4,00 m3
918 MINGGU 15-Mei-22 KU 8860 928 4,00 m3
919 MINGGU 15-Mei-22 KU 9305 929 4,00 m3
920 MINGGU 15-Mei-22 KT 8024 930 4,00 m3
921 MINGGU 15-Mei-22 KU 9674 931 4,00 m3
922 MINGGU 15-Mei-22 KU 8375 932 4,00 m3
923 MINGGU 15-Mei-22 KU 8166 933 4,00 m3
924 MINGGU 15-Mei-22 KU 8161 934 4,00 m3
925 MINGGU 15-Mei-22 KU 8074 935 4,00 m3
926 MINGGU 15-Mei-22 KT 8145 936 4,00 m3
927 MINGGU 15-Mei-22 KT 8720 937 4,00 m3
928 MINGGU 15-Mei-22 KU 8438 938 4,00 m3
929 MINGGU 15-Mei-22 KU 8829 939 4,00 m3
930 MINGGU 15-Mei-22 KU 8958 940 4,00 m3
931 MINGGU 15-Mei-22 KT 8786 941 4,00 m3
932 MINGGU 15-Mei-22 KT 8150 942 4,00 m3
933 MINGGU 15-Mei-22 KU 8509 943 4,00 m3
934 MINGGU 15-Mei-22 KU 8699 944 4,00 m3
935 MINGGU 15-Mei-22 KU 8265 945 4,00 m3
936 MINGGU 15-Mei-22 KU 8305 946 4,00 m3
937 MINGGU 15-Mei-22 KT 8024 947 4,00 m3
938 MINGGU 15-Mei-22 KU 9674 948 4,00 m3
939 MINGGU 15-Mei-22 KU 8375 949 4,00 m3
940 MINGGU 15-Mei-22 KU 8166 950 4,00 m3
941 MINGGU 15-Mei-22 KU 8161 951 4,00 m3
942 MINGGU 15-Mei-22 KU 8074 952 4,00 m3
943 MINGGU 15-Mei-22 KT 8145 953 4,00 m3
944 MINGGU 15-Mei-22 KT 8720 954 4,00 m3
945 MINGGU 15-Mei-22 KU 8438 955 4,00 m3
946 MINGGU 15-Mei-22 KU 8829 956 4,00 m3
947 MINGGU 15-Mei-22 KU 8958 957 4,00 m3
948 MINGGU 15-Mei-22 KT 8786 958 4,00 m3
949 MINGGU 15-Mei-22 KT 8150 959 4,00 m3
950 MINGGU 15-Mei-22 KU 8509 960 4,00 m3
951 MINGGU 15-Mei-22 KU 8699 961 4,00 m3
952 MINGGU 15-Mei-22 KU 8265 962 4,00 m3
953 MINGGU 15-Mei-22 KT 8024 963 4,00 m3
954 MINGGU 15-Mei-22 KU 9674 964 4,00 m3
955 MINGGU 15-Mei-22 KU 8166 965 4,00 m3
956 MINGGU 15-Mei-22 KU 8161 966 4,00 m3
957 MINGGU 15-Mei-22 KU 8074 967 4,00 m3

Page 15 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
958 MINGGU 15-Mei-22 KT 8145 968 4,00 m3
959 MINGGU 15-Mei-22 KT 8720 969 4,00 m3
960 MINGGU 15-Mei-22 KU 8438 970 4,00 m3
961 MINGGU 15-Mei-22 KU 8161 971 4,00 m3
962 MINGGU 15-Mei-22 KT 8786 972 4,00 m3
963 MINGGU 15-Mei-22 KU 8509 973 4,00 m3
964 MINGGU 15-Mei-22 KU 8438 974 4,00 m3
965 MINGGU 15-Mei-22 KU 8860 975 4,00 m3
966 MINGGU 15-Mei-22 KU 8829 976 4,00 m3
967 MINGGU 15-Mei-22 KU 8699 977 4,00 m3
968 MINGGU 15-Mei-22 KT 8150 978 4,00 m3
969 MINGGU 15-Mei-22 KT 8145 979 4,00 m3
970 MINGGU 15-Mei-22 KT 8720 980 4,00 m3
971 MINGGU 15-Mei-22 KU 8958 981 4,00 m3
972 MINGGU 15-Mei-22 KU 8074 982 4,00 m3
973 MINGGU 15-Mei-22 KU 8166 983 4,00 m3
974 MINGGU 15-Mei-22 KU 9305 984 4,00 m3
975 MINGGU 15-Mei-22 KT 8024 985 4,00 m3
976 MINGGU 15-Mei-22 KU 8314 986 4,00 m3
977 MINGGU 15-Mei-22 KU 9674 987 4,00 m3
978 MINGGU 15-Mei-22 KU 8265 988 4,00 m3
979 MINGGU 15-Mei-22 KT 8786 989 4,00 m3
980 MINGGU 15-Mei-22 KT 8509 990 4,00 m3
981 MINGGU 15-Mei-22 KU 8438 991 4,00 m3
982 MINGGU 15-Mei-22 KU 8860 992 4,00 m3
983 MINGGU 15-Mei-22 KU 8161 993 4,00 m3
984 MINGGU 15-Mei-22 KU 8829 994 4,00 m3
985 MINGGU 15-Mei-22 KU 8699 995 4,00 m3
986 MINGGU 15-Mei-22 KT 8150 996 4,00 m3
987 MINGGU 15-Mei-22 KT 8145 997 4,00 m3
988 MINGGU 15-Mei-22 KT 8720 998 4,00 m3
989 MINGGU 15-Mei-22 KU 8958 999 4,00 m3
990 MINGGU 15-Mei-22 KU 8166 1000 4,00 m3
991 JUM'AT 03-Jun-22 KU 8161 1001 4,00 m3
992 JUM'AT 03-Jun-22 KU 8509 1002 4,00 m3
993 JUM'AT 03-Jun-22 KU 8699 1003 4,00 m3
994 JUM'AT 03-Jun-22 KT 8549 1004 4,00 m3
995 JUM'AT 03-Jun-22 KU 8860 1005 4,00 m3
996 JUM'AT 03-Jun-22 KT 8720 1006 4,00 m3
997 JUM'AT 03-Jun-22 KU 8375 1007 4,00 m3
998 JUM'AT 03-Jun-22 KU 8438 1008 4,00 m3
999 JUM'AT 03-Jun-22 KU 8547 1009 4,00 m3
1000 JUM'AT 03-Jun-22 KU 8074 1010 4,00 m3
1001 JUM'AT 03-Jun-22 KT 8145 1011 4,00 m3
1002 JUM'AT 03-Jun-22 KT 8786 1012 4,00 m3
1003 JUM'AT 03-Jun-22 KU 9674 1013 4,00 m3
1004 JUM'AT 03-Jun-22 KT 8279 1014 4,00 m3
1005 JUM'AT 03-Jun-22 KU 8161 1015 4,00 m3
1006 JUM'AT 03-Jun-22 KU 8509 1016 4,00 m3
1007 JUM'AT 03-Jun-22 KU 8699 1017 4,00 m3
1008 JUM'AT 03-Jun-22 KT 8549 1018 4,00 m3
1009 JUM'AT 03-Jun-22 KT 8860 1019 4,00 m3
1010 JUM'AT 03-Jun-22 KT 8720 1020 4,00 m3
1011 JUM'AT 03-Jun-22 KT 8375 1021 4,00 m3
1012 JUM'AT 03-Jun-22 KU 8438 1022 4,00 m3
1013 JUM'AT 03-Jun-22 KT 8024 1023 4,00 m3
1014 JUM'AT 03-Jun-22 KU 8074 1024 4,00 m3
1015 JUM'AT 03-Jun-22 KU 8166 1025 4,00 m3
1016 JUM'AT 03-Jun-22 KU 8314 1026 4,00 m3
1017 JUM'AT 03-Jun-22 KU 8547 1027 4,00 m3
1018 JUM'AT 03-Jun-22 KT 8786 1028 4,00 m3
1019 JUM'AT 03-Jun-22 KU 9674 1029 4,00 m3
1020 JUM'AT 03-Jun-22 KT 8279 1030 4,00 m3
1021 JUM'AT 03-Jun-22 KT 8145 1031 4,00 m3

Page 16 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
1022 JUM'AT 03-Jun-22 KU 8161 1032 4,00 m3
1023 JUM'AT 03-Jun-22 KU 8509 1033 4,00 m3
1024 JUM'AT 03-Jun-22 KU 8699 1034 4,00 m3
1025 JUM'AT 03-Jun-22 KU 8088 1035 4,00 m3
1026 JUM'AT 03-Jun-22 KT 8549 1036 4,00 m3
1027 JUM'AT 03-Jun-22 KU 8860 1037 4,00 m3
1028 JUM'AT 03-Jun-22 KT 8720 1038 4,00 m3
1029 JUM'AT 03-Jun-22 KU 8375 1039 4,00 m3
1030 JUM'AT 03-Jun-22 KU 8438 1040 4,00 m3
1031 JUM'AT 03-Jun-22 KT 8024 1041 4,00 m3
1032 JUM'AT 03-Jun-22 KU 8074 1042 4,00 m3
1033 JUM'AT 03-Jun-22 KU 8166 1043 4,00 m3
1034 JUM'AT 03-Jun-22 KU 8314 1044 4,00 m3
1035 JUM'AT 03-Jun-22 KU 8547 1045 4,00 m3
1036 JUM'AT 03-Jun-22 KT 8786 1046 4,00 m3
1037 JUM'AT 03-Jun-22 KU 9674 1047 4,00 m3
1038 JUM'AT 03-Jun-22 KT 8279 1048 4,00 m3
1039 JUM'AT 03-Jun-22 KT 8145 1049 4,00 m3
1040 JUM'AT 03-Jun-22 KU 8088 1050 4,00 m3
1041 JUM'AT 03-Jun-22 KU 8161 1051 4,00 m3
1042 JUM'AT 03-Jun-22 KU 8509 1052 4,00 m3
1043 JUM'AT 03-Jun-22 KU 8699 1053 4,00 m3
1044 JUM'AT 03-Jun-22 KT 8549 1054 4,00 m3
1045 JUM'AT 03-Jun-22 KU 8860 1055 4,00 m3
1046 JUM'AT 03-Jun-22 KT 8720 1056 4,00 m3
1047 JUM'AT 03-Jun-22 KU 8375 1057 4,00 m3
1048 JUM'AT 03-Jun-22 KU 8438 1058 4,00 m3
1049 JUM'AT 03-Jun-22 KT 8024 1059 4,00 m3
1050 JUM'AT 03-Jun-22 KU 8074 1060 4,00 m3
1051 JUM'AT 03-Jun-22 KU 8166 1061 4,00 m3
1052 JUM'AT 03-Jun-22 KU 8314 1062 4,00 m3
1053 JUM'AT 03-Jun-22 KU 8547 1063 4,00 m3
1054 JUM'AT 03-Jun-22 KT 8786 1064 4,00 m3
1055 JUM'AT 03-Jun-22 KU 9674 1065 4,00 m3
1056 JUM'AT 03-Jun-22 KT 8145 1066 4,00 m3
1057 JUM'AT 03-Jun-22 KU 8161 1067 4,00 m3
1058 JUM'AT 03-Jun-22 KU 8509 1068 4,00 m3
1059 JUM'AT 03-Jun-22 KU 8699 1069 4,00 m3
1060 JUM'AT 03-Jun-22 KU 8088 1070 4,00 m3
1061 JUM'AT 03-Jun-22 KT 8279 1071 4,00 m3
1062 JUM'AT 03-Jun-22 KU 8860 1072 4,00 m3
1063 JUM'AT 03-Jun-22 KU 8375 1073 4,00 m3
1064 JUM'AT 03-Jun-22 KU 8438 1074 4,00 m3
1065 JUM'AT 03-Jun-22 KT 8720 1075 4,00 m3
1066 JUM'AT 03-Jun-22 KT 8024 1076 4,00 m3
1067 JUM'AT 03-Jun-22 KU 8074 1077 4,00 m3
1068 JUM'AT 03-Jun-22 KU 8166 1078 4,00 m3
1069 JUM'AT 03-Jun-22 KU 8547 1079 4,00 m3
1070 JUM'AT 03-Jun-22 KT 8786 1080 4,00 m3
1071 JUM'AT 03-Jun-22 KU 8161 1081 4,00 m3
1072 JUM'AT 03-Jun-22 KU 9674 1082 4,00 m3
1073 JUM'AT 03-Jun-22 KU 8088 1083 4,00 m3
1074 JUM'AT 03-Jun-22 KU 8509 1084 4,00 m3
1075 JUM'AT 03-Jun-22 KT 8279 1085 4,00 m3
1076 JUM'AT 03-Jun-22 KU 8699 1086 4,00 m3
1077 JUM'AT 03-Jun-22 KU 8860 1087 4,00 m3
1078 JUM'AT 03-Jun-22 KU 8375 1088 4,00 m3
1079 JUM'AT 03-Jun-22 KU 8438 1089 4,00 m3
1080 JUM'AT 03-Jun-22 KT 8024 1090 4,00 m3
1081 JUM'AT 03-Jun-22 KU 8074 1091 4,00 m3
1082 JUM'AT 03-Jun-22 KU 8166 1092 4,00 m3
1083 JUM'AT 03-Jun-22 KT 8145 1093 4,00 m3
1084 JUM'AT 03-Jun-22 KU 9674 1094 4,00 m3
1085 JUM'AT 03-Jun-22 KU 8088 1095 4,00 m3

Page 17 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
1086 JUM'AT 03-Jun-22 KU 8509 1096 4,00 m3
1087 JUM'AT 03-Jun-22 KT 8720 1097 4,00 m3
1088 JUM'AT 03-Jun-22 KT 8786 1098 4,00 m3
1089 JUM'AT 03-Jun-22 KT 8279 1099 4,00 m3
1090 JUM'AT 03-Jun-22 KU 8699 1100 4,00 m3
1091 JUM'AT 03-Jun-22 KU 8166 1101 4,00 m3
1092 JUM'AT 03-Jun-22 KU 8438 1102 4,00 m3
1093 JUM'AT 03-Jun-22 KU 8074 1103 4,00 m3
1094 JUM'AT 03-Jun-22 KU 8161 1104 4,00 m3
1095 JUM'AT 03-Jun-22 KT 8720 1105 4,00 m3
1096 JUM'AT 03-Jun-22 KT 8145 1106 4,00 m3
1097 JUM'AT 03-Jun-22 KT 8279 1107 4,00 m3
1098 JUM'AT 03-Jun-22 KU 9674 1108 4,00 m3
1099 JUM'AT 03-Jun-22 KT 8786 1109 4,00 m3
1100 JUM'AT 03-Jun-22 KU 8699 1110 4,00 m3
1101 JUM'AT 03-Jun-22 KU 8509 1111 4,00 m3
1102 JUM'AT 03-Jun-22 KU 8088 1112 4,00 m3
1103 JUM'AT 03-Jun-22 KU 8860 1113 4,00 m3
1104 JUM'AT 03-Jun-22 KU 8375 1114 4,00 m3
1105 JUM'AT 03-Jun-22 KT 8549 1115 4,00 m3
1106 JUM'AT 03-Jun-22 KU 8166 1116 4,00 m3
1107 JUM'AT 03-Jun-22 KU 8438 1117 4,00 m3
1108 JUM'AT 03-Jun-22 KU 8074 1118 4,00 m3
1109 JUM'AT 03-Jun-22 KU 8161 1119 4,00 m3
1110 JUM'AT 03-Jun-22 KT 8720 1120 4,00 m3
1111 JUM'AT 03-Jun-22 KT 8145 1121 4,00 m3
1112 JUM'AT 03-Jun-22 KT 8279 1122 4,00 m3
1113 JUM'AT 03-Jun-22 KU 9674 1123 4,00 m3
1114 JUM'AT 03-Jun-22 KT 8786 1124 4,00 m3
1115 JUM'AT 03-Jun-22 KU 8699 1125 4,00 m3
1116 JUM'AT 03-Jun-22 KU 8509 1126 4,00 m3
1117 JUM'AT 03-Jun-22 KU 8375 1127 4,00 m3
1118 JUM'AT 03-Jun-22 KT 8549 1128 4,00 m3
1119 JUM'AT 03-Jun-22 KU 8166 1129 4,00 m3
1120 JUM'AT 03-Jun-22 KU 8438 1130 4,00 m3
1121 JUM'AT 03-Jun-22 KU 8088 1131 4,00 m3
1122 JUM'AT 03-Jun-22 KU 8074 1132 4,00 m3
1123 JUM'AT 03-Jun-22 KU 8161 1133 4,00 m3
1124 JUM'AT 03-Jun-22 KT 8720 1134 4,00 m3
1125 JUM'AT 03-Jun-22 KT 8145 1135 4,00 m3
1126 JUM'AT 03-Jun-22 KT 8279 1136 4,00 m3
1127 JUM'AT 03-Jun-22 KU 9674 1137 4,00 m3
1128 JUM'AT 03-Jun-22 KT 8786 1138 4,00 m3
1129 JUM'AT 03-Jun-22 KU 8699 1139 4,00 m3
1130 JUM'AT 03-Jun-22 KU 8509 1140 4,00 m3
1131 JUM'AT 03-Jun-22 KU 8375 1141 4,00 m3
1132 JUM'AT 03-Jun-22 KT 8549 1142 4,00 m3
1133 JUM'AT 03-Jun-22 KU 8166 1143 4,00 m3
1134 JUM'AT 03-Jun-22 KU 8088 1144 4,00 m3
1135 JUM'AT 03-Jun-22 KU 8438 1145 4,00 m3
1136 JUM'AT 03-Jun-22 KU 8074 1146 4,00 m3
1137 JUM'AT 03-Jun-22 KU 8161 1147 4,00 m3
1138 JUM'AT 03-Jun-22 KT 8720 1148 4,00 m3
1139 JUM'AT 03-Jun-22 KT 8145 1149 4,00 m3
1140 JUM'AT 03-Jun-22 KT 8279 1150 4,00 m3
1141 JUM'AT 03-Jun-22 KU 9674 1151 4,00 m3
1142 JUM'AT 03-Jun-22 KT 8786 1152 4,00 m3
1143 JUM'AT 03-Jun-22 KU 8699 1153 4,00 m3
1144 JUM'AT 03-Jun-22 KU 8509 1154 4,00 m3
1145 JUM'AT 03-Jun-22 KU 8375 1155 4,00 m3
1146 JUM'AT 03-Jun-22 KU 8166 1156 4,00 m3
1147 JUM'AT 03-Jun-22 KU 8088 1157 4,00 m3
1148 SABTU 04-Jun-22 KU 8547 1158 4,00 m3
1149 SABTU 04-Jun-22 KU 8314 1159 4,00 m3

Page 18 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
1150 SABTU 04-Jun-22 KT 8279 1160 4,00 m3
1151 SABTU 04-Jun-22 KU 8074 1161 4,00 m3
1152 SABTU 04-Jun-22 KU 9674 1162 4,00 m3
1153 SABTU 04-Jun-22 KU 8161 1163 4,00 m3
1154 SABTU 04-Jun-22 KU 8088 1164 4,00 m3
1155 SABTU 04-Jun-22 KU 8166 1165 4,00 m3
1156 SABTU 04-Jun-22 KU 8509 1166 4,00 m3
1157 SABTU 04-Jun-22 KU 8375 1167 4,00 m3
1158 SABTU 04-Jun-22 KU 8860 1168 4,00 m3
1159 SABTU 04-Jun-22 KU 8024 1169 4,00 m3
1160 SABTU 04-Jun-22 KU 8699 1170 4,00 m3
1161 SABTU 04-Jun-22 KT 8549 1171 4,00 m3
1162 SABTU 04-Jun-22 KU 8438 1172 4,00 m3
1163 SABTU 04-Jun-22 KT 8720 1173 4,00 m3
1164 SABTU 04-Jun-22 KT 8786 1174 4,00 m3
1165 SABTU 04-Jun-22 KU 8239 1175 4,00 m3
1166 SABTU 04-Jun-22 KU 8547 1176 4,00 m3
1167 SABTU 04-Jun-22 KT 8145 1177 4,00 m3
1168 SABTU 04-Jun-22 KU 8314 1178 4,00 m3
1169 SABTU 04-Jun-22 KT 8279 1179 4,00 m3
1170 SABTU 04-Jun-22 KU 8074 1180 4,00 m3
1171 SABTU 04-Jun-22 KU 8161 1181 4,00 m3
1172 SABTU 04-Jun-22 KU 9674 1182 4,00 m3
1173 SABTU 04-Jun-22 KU 8088 1183 4,00 m3
1174 SABTU 04-Jun-22 KU 8166 1184 4,00 m3
1175 SABTU 04-Jun-22 KU 8509 1185 4,00 m3
1176 SABTU 04-Jun-22 KU 8375 1186 4,00 m3
1177 SABTU 04-Jun-22 KU 8860 1187 4,00 m3
1178 SABTU 04-Jun-22 KT 8024 1188 4,00 m3
1179 SABTU 04-Jun-22 KU 8699 1189 4,00 m3
1180 SABTU 04-Jun-22 KT 8549 1190 4,00 m3
1181 SABTU 04-Jun-22 KT 8720 1191 4,00 m3
1182 SABTU 04-Jun-22 KU 8438 1192 4,00 m3
1183 SABTU 04-Jun-22 KT 8786 1193 4,00 m3
1184 SABTU 04-Jun-22 KU 8239 1194 4,00 m3
1185 SABTU 04-Jun-22 KU 8547 1195 4,00 m3
1186 SABTU 04-Jun-22 KT 8279 1196 4,00 m3
1187 SABTU 04-Jun-22 KU 8074 1197 4,00 m3
1188 SABTU 04-Jun-22 KU 8161 1198 4,00 m3
1189 SABTU 04-Jun-22 KU 9674 1199 4,00 m3
1190 SABTU 04-Jun-22 KU 8088 1200 4,00 m3
1191 SABTU 04-Jun-22 KU 8166 1201 4,00 m3
1192 SABTU 04-Jun-22 KU 8509 1202 4,00 m3
1193 SABTU 04-Jun-22 KU 8375 1203 4,00 m3
1194 SABTU 04-Jun-22 KU 8860 1204 4,00 m3
1195 SABTU 04-Jun-22 KT 8024 1205 4,00 m3
1196 SABTU 04-Jun-22 KT 8145 1206 4,00 m3
1197 SABTU 04-Jun-22 KT 8549 1207 4,00 m3
1198 SABTU 04-Jun-22 KU 8699 1208 4,00 m3
1199 SABTU 04-Jun-22 KU 8438 1209 4,00 m3
1200 SABTU 04-Jun-22 KT 8720 1210 4,00 m3
1201 SABTU 04-Jun-22 KT 8786 1211 4,00 m3
1202 SABTU 04-Jun-22 KU 8239 1212 4,00 m3
1203 SABTU 04-Jun-22 KU 8547 1213 4,00 m3
1204 SABTU 04-Jun-22 KT 8279 1214 4,00 m3
1205 SABTU 04-Jun-22 KU 8074 1215 4,00 m3
1206 SABTU 04-Jun-22 KU 8161 1216 4,00 m3
1207 SABTU 04-Jun-22 KU 9674 1217 4,00 m3
1208 SABTU 04-Jun-22 KU 8088 1218 4,00 m3
1209 SABTU 04-Jun-22 KU 8166 1219 4,00 m3
1210 SABTU 04-Jun-22 KU 8509 1220 4,00 m3
1211 SABTU 04-Jun-22 KU 8860 1221 4,00 m3
1212 SABTU 04-Jun-22 KT 8549 1222 4,00 m3
1213 SABTU 04-Jun-22 KT 8024 1223 4,00 m3

Page 19 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
1214 SABTU 04-Jun-22 KU 8699 1224 4,00 m3
1215 SABTU 04-Jun-22 KU 8438 1225 4,00 m3
1216 SABTU 04-Jun-22 KT 8720 1226 4,00 m3
1217 SABTU 04-Jun-22 KT 8786 1227 4,00 m3
1218 SABTU 04-Jun-22 KU 8547 1228 4,00 m3
1219 SABTU 04-Jun-22 KT 8279 1229 4,00 m3
1220 SABTU 04-Jun-22 KU 8314 1230 4,00 m3
1221 SABTU 04-Jun-22 KU 8239 1231 4,00 m3
1222 SABTU 04-Jun-22 KU 8074 1232 4,00 m3
1223 SABTU 04-Jun-22 KU 8161 1233 4,00 m3
1224 SABTU 04-Jun-22 KU 8088 1234 4,00 m3
1225 SABTU 04-Jun-22 KU 9674 1235 4,00 m3
1226 SABTU 04-Jun-22 KU 8166 1236 4,00 m3
1227 SABTU 04-Jun-22 KU 8509 1237 4,00 m3
1228 SABTU 04-Jun-22 KU 8860 1238 4,00 m3
1229 SABTU 04-Jun-22 KT 8549 1239 4,00 m3
1230 SABTU 04-Jun-22 KT 8024 1240 4,00 m3
1231 SABTU 04-Jun-22 KU 8699 1241 4,00 m3
1232 SABTU 04-Jun-22 KU 8438 1242 4,00 m3
1233 SABTU 04-Jun-22 KT 8720 1243 4,00 m3
1234 SABTU 04-Jun-22 KT 8786 1244 4,00 m3
1235 SABTU 04-Jun-22 KU 8547 1245 4,00 m3
1236 SABTU 04-Jun-22 KU 8314 1246 4,00 m3
1237 SABTU 04-Jun-22 KU 8088 1247 4,00 m3
1238 SABTU 04-Jun-22 KU 8166 1248 4,00 m3
1239 SABTU 04-Jun-22 KT 8549 1249 4,00 m3
1240 SABTU 04-Jun-22 KU 8438 1250 4,00 m3
1241 SABTU 04-Jun-22 KU 8860 1251 4,00 m3
1242 SABTU 04-Jun-22 KU 8161 1252 4,00 m3
1243 SABTU 04-Jun-22 KU 8074 1253 4,00 m3
1244 SABTU 04-Jun-22 KU 8375 1254 4,00 m3
1245 SABTU 04-Jun-22 KT 8279 1255 4,00 m3
1246 SABTU 04-Jun-22 KT 8720 1256 4,00 m3
1247 SABTU 04-Jun-22 KT 8145 1257 4,00 m3
1248 SABTU 04-Jun-22 KU 8239 1258 4,00 m3
1249 SABTU 04-Jun-22 KU 8958 1259 4,00 m3
1250 SABTU 04-Jun-22 KU 8509 1260 4,00 m3
1251 SABTU 04-Jun-22 KU 8699 1261 4,00 m3
1252 SABTU 04-Jun-22 KU 8547 1262 4,00 m3
1253 SABTU 04-Jun-22 KT 8024 1263 4,00 m3
1254 SABTU 04-Jun-22 KU 9674 1264 4,00 m3
1255 SABTU 04-Jun-22 KT 8786 1265 4,00 m3
1256 SABTU 04-Jun-22 KU 8088 1266 4,00 m3
1257 SABTU 04-Jun-22 KU 8314 1267 4,00 m3
1258 SABTU 04-Jun-22 KU 8166 1268 4,00 m3
1259 SABTU 04-Jun-22 KT 8549 1269 4,00 m3
1260 SABTU 04-Jun-22 KU 8438 1270 4,00 m3
1261 SABTU 04-Jun-22 KU 8860 1271 4,00 m3
1262 SABTU 04-Jun-22 KU 8161 1272 4,00 m3
1263 SABTU 04-Jun-22 KU 8375 1273 4,00 m3
1264 SABTU 04-Jun-22 KT 8279 1274 4,00 m3
1265 SABTU 04-Jun-22 KU 8074 1275 4,00 m3
1266 SABTU 04-Jun-22 KT 8720 1276 4,00 m3
1267 SABTU 04-Jun-22 KT 8145 1277 4,00 m3
1268 SABTU 04-Jun-22 KU 8958 1278 4,00 m3
1269 SABTU 04-Jun-22 KU 8239 1279 4,00 m3
1270 SABTU 04-Jun-22 KU 8509 1280 4,00 m3
1271 SABTU 04-Jun-22 KU 8699 1281 4,00 m3
1272 SABTU 04-Jun-22 KU 8547 1282 4,00 m3
1273 SABTU 04-Jun-22 KT 8024 1283 4,00 m3
1274 SABTU 04-Jun-22 KU 9674 1284 4,00 m3
1275 SABTU 04-Jun-22 KT 8786 1285 4,00 m3
1276 SABTU 04-Jun-22 KT 8314 1286 4,00 m3
1277 SABTU 04-Jun-22 KU 8088 1287 4,00 m3

Page 20 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
1278 SABTU 04-Jun-22 KU 8166 1288 4,00 m3
1279 SABTU 04-Jun-22 KU 8438 1289 4,00 m3
1280 SABTU 04-Jun-22 KU 8860 1290 4,00 m3
1281 SABTU 04-Jun-22 KU 8161 1291 4,00 m3
1282 SABTU 04-Jun-22 KU 8375 1292 4,00 m3
1283 SABTU 04-Jun-22 KU 8074 1293 4,00 m3
1284 SABTU 04-Jun-22 KT 8279 1294 4,00 m3
1285 SABTU 04-Jun-22 KT 8720 1295 4,00 m3
1286 SABTU 04-Jun-22 KT 8145 1296 4,00 m3
1287 SABTU 04-Jun-22 KU 8958 1297 4,00 m3
1288 SABTU 04-Jun-22 KU 8509 1298 4,00 m3
1289 SABTU 04-Jun-22 KU 8239 1299 4,00 m3
1290 SABTU 04-Jun-22 KU 8699 1300 4,00 m3
1291 SABTU 04-Jun-22 KU 8547 1301 4,00 m3
1292 SABTU 04-Jun-22 KT 8024 1302 4,00 m3
1293 SABTU 04-Jun-22 KU 9674 1303 4,00 m3
1294 SABTU 04-Jun-22 KT 8786 1304 4,00 m3
1295 SABTU 04-Jun-22 KU 8314 1305 4,00 m3
1296 SABTU 04-Jun-22 KU 8088 1306 4,00 m3
1297 SABTU 04-Jun-22 KU 8166 1307 4,00 m3
1298 SABTU 04-Jun-22 KU 8438 1308 4,00 m3
1299 SABTU 04-Jun-22 KU 8860 1309 4,00 m3
1300 SABTU 04-Jun-22 KU 8161 1310 4,00 m3
1301 SABTU 04-Jun-22 KU 8375 1311 4,00 m3
1302 SABTU 04-Jun-22 KU 8074 1312 4,00 m3
1303 SABTU 04-Jun-22 KT 8279 1313 4,00 m3
1304 SABTU 04-Jun-22 KT 8720 1314 4,00 m3
1305 SABTU 04-Jun-22 KU 8958 1315 4,00 m3
1306 SABTU 04-Jun-22 KU 8509 1316 4,00 m3
1307 SABTU 04-Jun-22 KU 8239 1317 4,00 m3
1308 SABTU 04-Jun-22 KT 8549 1318 4,00 m3
1309 SABTU 04-Jun-22 KU 8547 1319 4,00 m3
1310 SABTU 04-Jun-22 KU 9674 1320 4,00 m3
1311 SABTU 04-Jun-22 KT 8024 1321 4,00 m3
1312 SABTU 04-Jun-22 KT 8786 1322 4,00 m3
1313 SABTU 04-Jun-22 KU 8088 1323 4,00 m3
1314 SABTU 04-Jun-22 KU 8166 1324 4,00 m3
1315 SABTU 04-Jun-22 KU 8314 1325 4,00 m3
1316 SABTU 04-Jun-22 KU 8438 1326 4,00 m3
1317 SABTU 04-Jun-22 KU 8860 1327 4,00 m3
1318 SABTU 04-Jun-22 KU 8161 1328 4,00 m3
1319 SABTU 04-Jun-22 KU 8375 1329 4,00 m3
1320 SABTU 04-Jun-22 KU 8074 1330 4,00 m3
1321 SABTU 04-Jun-22 KU 8279 1331 4,00 m3
1322 SABTU 04-Jun-22 KT 8720 1332 4,00 m3
1323 SABTU 04-Jun-22 KU 8958 1333 4,00 m3
1324 SABTU 04-Jun-22 KU 8509 1334 4,00 m3
1325 SABTU 04-Jun-22 KU 8239 1335 4,00 m3
1326 SABTU 04-Jun-22 KU 8699 1336 4,00 m3
1327 SABTU 04-Jun-22 KU 8547 1337 4,00 m3
1328 SABTU 04-Jun-22 KU 9674 1338 4,00 m3
1329 SABTU 04-Jun-22 KT 8024 1339 4,00 m3
1330 SABTU 04-Jun-22 KT 8786 1340 4,00 m3
1331 SABTU 04-Jun-22 KU 8088 1341 4,00 m3
1332 SABTU 04-Jun-22 KU 8314 1342 4,00 m3
1333 SABTU 04-Jun-22 KU 8166 1343 4,00 m3
1334 SABTU 04-Jun-22 KU 8438 1344 4,00 m3
1335 SABTU 04-Jun-22 KU 8860 1345 4,00 m3
1336 SABTU 04-Jun-22 KT 8145 1346 4,00 m3
1337 SABTU 04-Jun-22 KU 8161 1347 4,00 m3
1338 SABTU 04-Jun-22 KU 8375 1348 4,00 m3
1339 SABTU 04-Jun-22 KU 8674 1349 4,00 m3
1340 SABTU 04-Jun-22 KT 8279 1350 4,00 m3
1341 SABTU 04-Jun-22 KT 8720 1351 4,00 m3

Page 21 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
1342 SABTU 04-Jun-22 KU 8958 1352 4,00 m3
1343 SABTU 04-Jun-22 KU 8509 1353 4,00 m3
1344 SABTU 04-Jun-22 KU 8239 1354 4,00 m3
1345 SABTU 04-Jun-22 KU 8699 1355 4,00 m3
1346 SABTU 04-Jun-22 KU 8547 1356 4,00 m3
1347 SABTU 04-Jun-22 KT 8279 1357 4,00 m3
1348 SABTU 04-Jun-22 KU 8161 1358 4,00 m3
1349 SABTU 04-Jun-22 KT 8145 1359 4,00 m3
1350 SABTU 04-Jun-22 KU 8088 1360 4,00 m3
1351 SABTU 04-Jun-22 KU 8074 1361 4,00 m3
1352 SABTU 04-Jun-22 KU 9674 1362 4,00 m3
1353 SABTU 04-Jun-22 KU 8958 1363 4,00 m3
1354 SABTU 04-Jun-22 KT 8720 1364 4,00 m3
1355 SABTU 04-Jun-22 KU 8166 1365 4,00 m3
1356 SABTU 04-Jun-22 KU 8547 1366 4,00 m3
1357 SABTU 04-Jun-22 KU 8375 1367 4,00 m3
1358 SABTU 04-Jun-22 KT 8024 1368 4,00 m3
1359 SABTU 04-Jun-22 KU 8438 1369 4,00 m3
1360 SABTU 04-Jun-22 KU 8699 1370 4,00 m3
1361 SABTU 04-Jun-22 KU 8239 1371 4,00 m3
1362 SABTU 04-Jun-22 KU 8509 1372 4,00 m3
1363 SABTU 04-Jun-22 KU 8786 1373 4,00 m3
1364 SABTU 04-Jun-22 KT 8279 1374 4,00 m3
1365 SABTU 04-Jun-22 KU 8161 1375 4,00 m3
1366 SABTU 04-Jun-22 KT 8145 1376 4,00 m3
1367 SABTU 04-Jun-22 KU 8088 1377 4,00 m3
1368 SABTU 04-Jun-22 KU 8074 1378 4,00 m3
1369 SABTU 04-Jun-22 KU 9674 1379 4,00 m3
1370 SABTU 04-Jun-22 KU 8958 1380 4,00 m3
1371 SABTU 04-Jun-22 KU 8166 1381 4,00 m3
1372 SABTU 04-Jun-22 KU 8547 1382 4,00 m3
1373 SABTU 04-Jun-22 KU 8375 1383 4,00 m3
1374 SABTU 04-Jun-22 KT 8024 1384 4,00 m3
1375 SABTU 04-Jun-22 KU 8438 1385 4,00 m3
1376 SABTU 04-Jun-22 KU 8699 1386 4,00 m3
1377 SABTU 04-Jun-22 KU 8239 1387 4,00 m3
1378 SABTU 04-Jun-22 KU 8509 1388 4,00 m3
1379 SABTU 04-Jun-22 KT 8786 1389 4,00 m3
1380 SABTU 04-Jun-22 KT 8279 1390 4,00 m3
1381 SABTU 04-Jun-22 KU 8161 1391 4,00 m3
1382 SABTU 04-Jun-22 KT 8145 1392 4,00 m3
1383 SABTU 04-Jun-22 KU 8088 1393 4,00 m3
1384 SABTU 04-Jun-22 KU 8074 1394 4,00 m3
1385 SABTU 04-Jun-22 KU 9674 1395 4,00 m3
1386 SABTU 04-Jun-22 KU 8958 1396 4,00 m3
1387 SABTU 04-Jun-22 KU 8166 1397 4,00 m3
1388 SABTU 04-Jun-22 KT 8720 1398 4,00 m3
1389 SABTU 04-Jun-22 KU 8547 1399 4,00 m3
1390 SABTU 04-Jun-22 KU 8375 1400 4,00 m3
1391 SABTU 04-Jun-22 KT 8024 1401 4,00 m3
1392 SABTU 04-Jun-22 KU 8438 1402 4,00 m3
1393 SABTU 04-Jun-22 KU 8699 1403 4,00 m3
1394 SABTU 04-Jun-22 KU 8239 1404 4,00 m3
1395 SABTU 04-Jun-22 KU 8509 1405 4,00 m3
1396 SABTU 04-Jun-22 KT 8786 1406 4,00 m3
1397 SABTU 04-Jun-22 KT 8279 1407 4,00 m3
1398 SABTU 04-Jun-22 KU 8161 1408 4,00 m3
1399 SABTU 04-Jun-22 KT 8145 1409 4,00 m3
1400 SABTU 04-Jun-22 KU 8088 1410 4,00 m3
1401 SABTU 04-Jun-22 KU 8074 1411 4,00 m3
1402 SABTU 04-Jun-22 KU 8958 1412 4,00 m3
1403 SABTU 04-Jun-22 KU 8166 1413 4,00 m3
1404 SABTU 04-Jun-22 KT 8720 1414 4,00 m3
1405 SABTU 04-Jun-22 KU 8375 1415 4,00 m3

Page 22 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
1406 SABTU 04-Jun-22 KT 8024 1416 4,00 m3
1407 SABTU 04-Jun-22 KU 8438 1417 4,00 m3
1408 SABTU 04-Jun-22 KU 8239 1418 4,00 m3
1409 SABTU 04-Jun-22 KU 8509 1419 4,00 m3
1410 SABTU 04-Jun-22 KT 8786 1420 4,00 m3
1411 SABTU 04-Jun-22 KT 8279 1421 4,00 m3
1412 SABTU 04-Jun-22 KU 8161 1422 4,00 m3
1413 SABTU 04-Jun-22 KT 8145 1423 4,00 m3
1414 SABTU 04-Jun-22 KU 8088 1424 4,00 m3
1415 SABTU 04-Jun-22 KU 8074 1425 4,00 m3
1416 SABTU 04-Jun-22 KU 8958 1426 4,00 m3
1417 SABTU 04-Jun-22 KU 8166 1427 4,00 m3
1418 SELASA 07-Jun-22 KU 8161 1428 4,00 m3
1419 SELASA 07-Jun-22 KU 8509 1429 4,00 m3
1420 SELASA 07-Jun-22 KU 8088 1430 4,00 m3
1421 SELASA 07-Jun-22 KU 8375 1431 4,00 m3
1422 SELASA 07-Jun-22 KT 8279 1432 4,00 m3
1423 SELASA 07-Jun-22 KU 8074 1433 4,00 m3
1424 SELASA 07-Jun-22 1434 4,00 m3
1425 SELASA 07-Jun-22 1435 4,00 m3
1426 SELASA 07-Jun-22 KU 8239 1436 4,00 m3
1427 SELASA 07-Jun-22 KU 8166 1437 4,00 m3
1428 SELASA 07-Jun-22 KT 8024 1438 4,00 m3
1429 SELASA 07-Jun-22 KU 8547 1439 4,00 m3
1430 SELASA 07-Jun-22 KU 8161 1440 4,00 m3
1431 SELASA 07-Jun-22 KU 9674 1441 4,00 m3
1432 SELASA 07-Jun-22 KU 8509 1442 4,00 m3
1433 SELASA 07-Jun-22 KU 8958 1443 4,00 m3
1434 SELASA 07-Jun-22 KU 8166 1444 4,00 m3
1435 SELASA 07-Jun-22 KT 8549 1445 4,00 m3
1436 SELASA 07-Jun-22 KT 8145 1446 4,00 m3
1437 SELASA 07-Jun-22 KU 8239 1447 4,00 m3
1438 SELASA 07-Jun-22 KU 8314 1448 4,00 m3
1439 SELASA 07-Jun-22 KT 8024 1449 4,00 m3
1440 SELASA 07-Jun-22 KU 8438 1450 4,00 m3
1441 SELASA 07-Jun-22 KU 9674 1451 4,00 m3
1442 SELASA 07-Jun-22 KU 8509 1452 4,00 m3
1443 SELASA 07-Jun-22 KU 8161 1453 4,00 m3
1444 SELASA 07-Jun-22 KU 8958 1454 4,00 m3
1445 SELASA 07-Jun-22 KU 8166 1455 4,00 m3
1446 SELASA 07-Jun-22 KT 8549 1456 4,00 m3
1447 SELASA 07-Jun-22 KT 8145 1457 4,00 m3
1448 SELASA 07-Jun-22 KU 8375 1458 4,00 m3
1449 SELASA 07-Jun-22 KU 8239 1459 4,00 m3
1450 SELASA 07-Jun-22 KT 8720 1460 4,00 m3
1451 SELASA 07-Jun-22 KU 8314 1461 4,00 m3
1452 SELASA 07-Jun-22 KT 8024 1462 4,00 m3
1453 SELASA 07-Jun-22 KU 8438 1463 4,00 m3
1454 SELASA 07-Jun-22 KU 9674 1464 4,00 m3
1455 SELASA 07-Jun-22 KU 8161 1465 4,00 m3
1456 SELASA 07-Jun-22 KU 8509 1466 4,00 m3
1457 SELASA 07-Jun-22 KU 8958 1467 4,00 m3
1458 SELASA 07-Jun-22 KU 8166 1468 4,00 m3
1459 SELASA 07-Jun-22 KT 8549 1469 4,00 m3
1460 SELASA 07-Jun-22 KU 8375 1470 4,00 m3
1461 SELASA 07-Jun-22 KU 8239 1471 4,00 m3
1462 SELASA 07-Jun-22 KT 8720 1472 4,00 m3
1463 SELASA 07-Jun-22 KU 8314 1473 4,00 m3
1464 SELASA 07-Jun-22 KT 8024 1474 4,00 m3
1465 SELASA 07-Jun-22 KU 8438 1475 4,00 m3
1466 SELASA 07-Jun-22 KU 9674 1476 4,00 m3
1467 SELASA 07-Jun-22 KU 8161 1477 4,00 m3
1468 SELASA 07-Jun-22 KU 8509 1478 4,00 m3
1469 SELASA 07-Jun-22 KU 8958 1479 4,00 m3

Page 23 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
1470 SELASA 07-Jun-22 KU 8166 1480 4,00 m3
1471 SELASA 07-Jun-22 KT 8549 1481 4,00 m3
1472 SELASA 07-Jun-22 KU 8375 1482 4,00 m3
1473 SELASA 07-Jun-22 KU 8239 1483 4,00 m3
1474 SELASA 07-Jun-22 KT 8720 1484 4,00 m3
1475 SELASA 07-Jun-22 KU 8314 1485 4,00 m3
1476 SELASA 07-Jun-22 KT 8024 1486 4,00 m3
1477 SELASA 07-Jun-22 KU 8438 1487 4,00 m3
1478 SELASA 07-Jun-22 KU 9674 1488 4,00 m3
1479 SELASA 07-Jun-22 KT 8279 1489 4,00 m3
1480 SELASA 07-Jun-22 KU 8161 1490 4,00 m3
1481 SELASA 07-Jun-22 KU 8509 1491 4,00 m3
1482 SELASA 07-Jun-22 KU 8958 1492 4,00 m3
1483 SELASA 07-Jun-22 KU 8166 1493 4,00 m3
1484 SELASA 07-Jun-22 KT 8549 1494 4,00 m3
1485 SELASA 07-Jun-22 KU 8375 1495 4,00 m3
1486 SELASA 07-Jun-22 KU 8239 1496 4,00 m3
1487 SELASA 07-Jun-22 KT 8720 1497 4,00 m3
1488 SELASA 07-Jun-22 KU 8314 1498 4,00 m3
1489 SELASA 07-Jun-22 KT 8024 1499 4,00 m3
1490 SELASA 07-Jun-22 KU 8438 1500 4,00 m3
1491 SELASA 07-Jun-22 KT 8279 1501 4,00 m3
1492 SELASA 07-Jun-22 KU 9674 1502 4,00 m3
1493 SELASA 07-Jun-22 KU 8161 1503 4,00 m3
1494 SELASA 07-Jun-22 KU 8509 1504 4,00 m3
1495 SELASA 07-Jun-22 KU 8958 1505 4,00 m3
1496 SELASA 07-Jun-22 KU 8166 1506 4,00 m3
1497 SELASA 07-Jun-22 KT 8549 1507 4,00 m3
1498 SELASA 07-Jun-22 KU 8375 1508 4,00 m3
1499 SELASA 07-Jun-22 KT 8720 1509 4,00 m3
1500 SELASA 07-Jun-22 KU 8239 1510 4,00 m3
1501 SELASA 07-Jun-22 KU 8314 1511 4,00 m3
1502 SELASA 07-Jun-22 KT 8024 1512 4,00 m3
1503 SELASA 07-Jun-22 KU 9674 1513 4,00 m3
1504 SELASA 07-Jun-22 KU 9674 1514 4,00 m3
1505 SELASA 07-Jun-22 KT 8279 1515 4,00 m3
1506 SELASA 07-Jun-22 KU 8161 1516 4,00 m3
1507 SELASA 07-Jun-22 KU 8509 1517 4,00 m3
1508 SELASA 07-Jun-22 KU 8166 1518 4,00 m3
1509 SELASA 07-Jun-22 KU 8958 1519 4,00 m3
1510 SELASA 07-Jun-22 KT 8549 1520 4,00 m3
1511 SELASA 07-Jun-22 KU 8375 1521 4,00 m3
1512 SELASA 07-Jun-22 KU 8239 1522 4,00 m3
1513 SELASA 07-Jun-22 KT 8720 1523 4,00 m3
1514 SELASA 07-Jun-22 KU 8314 1524 4,00 m3
1515 SELASA 07-Jun-22 KT 8024 1525 4,00 m3
1516 SELASA 07-Jun-22 KU 8438 1526 4,00 m3
1517 SELASA 07-Jun-22 KU 9674 1527 4,00 m3
1518 SELASA 07-Jun-22 KT 8279 1528 4,00 m3
1519 SELASA 07-Jun-22 KU 8161 1529 4,00 m3
1520 SELASA 07-Jun-22 KU 8509 1530 4,00 m3
1521 SELASA 07-Jun-22 KT 8786 1531 4,00 m3
1522 SELASA 07-Jun-22 KU 8088 1532 4,00 m3
1523 SELASA 07-Jun-22 KT 8166 1533 4,00 m3
1524 SELASA 07-Jun-22 KU 8699 1534 4,00 m3
1525 SELASA 07-Jun-22 KU 8958 1535 4,00 m3
1526 SELASA 07-Jun-22 KU 8375 1536 4,00 m3
1527 SELASA 07-Jun-22 KT 8549 1537 4,00 m3
1528 SELASA 07-Jun-22 KU 8074 1538 4,00 m3
1529 SELASA 07-Jun-22 KU 8239 1539 4,00 m3
1530 SELASA 07-Jun-22 KT 8720 1540 4,00 m3
1531 SELASA 07-Jun-22 KU 8438 1541 4,00 m3
1532 SELASA 07-Jun-22 KU 9674 1542 4,00 m3
1533 SELASA 07-Jun-22 KU 8161 1543 4,00 m3

Page 24 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
1534 SELASA 07-Jun-22 KT 8786 1544 4,00 m3
1535 SELASA 07-Jun-22 KT 8145 1545 4,00 m3
1536 SELASA 07-Jun-22 KU 8375 1546 4,00 m3
1537 SELASA 07-Jun-22 KT 8549 1547 4,00 m3
1538 SELASA 07-Jun-22 KU 8088 1548 4,00 m3
1539 SELASA 07-Jun-22 KU 8509 1549 4,00 m3
1540 SELASA 07-Jun-22 KU 8699 1550 4,00 m3
1541 SELASA 07-Jun-22 KT 8720 1551 4,00 m3
1542 SELASA 07-Jun-22 KU 8074 1552 4,00 m3
1543 SELASA 07-Jun-22 KT 8024 1553 4,00 m3
1544 SELASA 07-Jun-22 KU 8239 1554 4,00 m3
1545 SELASA 07-Jun-22 KU 8166 1555 4,00 m3
1546 SELASA 07-Jun-22 KU 8860 1556 4,00 m3
1547 SELASA 07-Jun-22 KT 8150 1557 4,00 m3
1548 SELASA 07-Jun-22 KT 8279 1558 4,00 m3
1549 SELASA 07-Jun-22 KU 8438 1559 4,00 m3
1550 SELASA 07-Jun-22 KU 9674 1560 4,00 m3
1551 SELASA 07-Jun-22 KU 8161 1561 4,00 m3
1552 SELASA 07-Jun-22 KT 8786 1562 4,00 m3
1553 SELASA 07-Jun-22 KT 8145 1563 4,00 m3
1554 SELASA 07-Jun-22 KU 8375 1564 4,00 m3
1555 SELASA 07-Jun-22 KT 8549 1565 4,00 m3
1556 SELASA 07-Jun-22 KU 8088 1566 4,00 m3
1557 SELASA 07-Jun-22 KU 8509 1567 4,00 m3
1558 SELASA 07-Jun-22 KT 8720 1568 4,00 m3
1559 SELASA 07-Jun-22 KU 8074 1569 4,00 m3
1560 SELASA 07-Jun-22 KT 8024 1570 4,00 m3
1561 SELASA 07-Jun-22 KU 8239 1571 4,00 m3
1562 SELASA 07-Jun-22 KT 8150 1572 4,00 m3
1563 SELASA 07-Jun-22 KU 8166 1573 4,00 m3
1564 SELASA 07-Jun-22 KU 8699 1574 4,00 m3
1565 SELASA 07-Jun-22 KU 8438 1575 4,00 m3
1566 SELASA 07-Jun-22 KT 8279 1576 4,00 m3
1567 SELASA 07-Jun-22 KU 8161 1577 4,00 m3
1568 SELASA 07-Jun-22 KT 8786 1578 4,00 m3
1569 SELASA 07-Jun-22 KT 8145 1579 4,00 m3
1570 SELASA 07-Jun-22 KU 8375 1580 4,00 m3
1571 SELASA 07-Jun-22 KT 8549 1581 4,00 m3
1572 SELASA 07-Jun-22 KU 8088 1582 4,00 m3
1573 SELASA 07-Jun-22 KU 8509 1583 4,00 m3
1574 SELASA 07-Jun-22 KT 8720 1584 4,00 m3
1575 SELASA 07-Jun-22 KU 8074 1585 4,00 m3
1576 SELASA 07-Jun-22 KT 8024 1586 4,00 m3
1577 SELASA 07-Jun-22 KU 8239 1587 4,00 m3
1578 SELASA 07-Jun-22 KT 8150 1588 4,00 m3
1579 SELASA 07-Jun-22 KU 8166 1589 4,00 m3
1580 SELASA 07-Jun-22 KU 8699 1590 4,00 m3
1581 SELASA 07-Jun-22 KU 8438 1591 4,00 m3
1582 SELASA 07-Jun-22 KT 8279 1592 4,00 m3
1583 SELASA 07-Jun-22 KU 8161 1593 4,00 m3
1584 SELASA 07-Jun-22 KT 8786 1594 4,00 m3
1585 SELASA 07-Jun-22 KU 8860 1595 4,00 m3
1586 SELASA 07-Jun-22 KT 8145 1596 4,00 m3
1587 SELASA 07-Jun-22 KU 8375 1597 4,00 m3
1588 SELASA 07-Jun-22 KT 8549 1598 4,00 m3
1589 SELASA 07-Jun-22 KU 8088 1599 4,00 m3
1590 SELASA 07-Jun-22 KU 8509 1600 4,00 m3
1591 SELASA 07-Jun-22 KT 8720 1601 4,00 m3
1592 SELASA 07-Jun-22 KU 8074 1602 4,00 m3
1593 SELASA 07-Jun-22 KT 8024 1603 4,00 m3
1594 SELASA 07-Jun-22 KU 8239 1604 4,00 m3
1595 SELASA 07-Jun-22 KU 8166 1605 4,00 m3
1596 SELASA 07-Jun-22 KU 8699 1606 4,00 m3
1597 SELASA 07-Jun-22 KU 8438 1607 4,00 m3

Page 25 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
1598 SELASA 07-Jun-22 KU 8161 1608 4,00 m3
1599 SELASA 07-Jun-22 KT 8786 1609 4,00 m3
1600 SELASA 07-Jun-22 KT 8145 1610 4,00 m3
1601 SELASA 07-Jun-22 KU 8375 1611 4,00 m3
1602 SELASA 07-Jun-22 KT 8549 1612 4,00 m3
1603 SELASA 07-Jun-22 KU 8088 1613 4,00 m3
1604 SELASA 07-Jun-22 KU 8509 1614 4,00 m3
RABU 08-Jun-22 KU 9674 1615 4,00 m3
RABU 08-Jun-22 KT 8279 1616 4,00 m3
RABU 08-Jun-22 KU 8375 1617 4,00 m3
RABU 08-Jun-22 KT 8720 1618 4,00 m3
RABU 08-Jun-22 KT 8024 1619 4,00 m3
RABU 08-Jun-22 KU 8509 1620 4,00 m3
RABU 08-Jun-22 KU 8161 1621 4,00 m3
RABU 08-Jun-22 KT 8549 1622 4,00 m3
RABU 08-Jun-22 KU 8166 1623 4,00 m3
RABU 08-Jun-22 KU 8239 1624 4,00 m3
RABU 08-Jun-22 KU 8145 1625 4,00 m3
RABU 08-Jun-22 KU 8958 1626 4,00 m3
RABU 08-Jun-22 KU 9674 1627 4,00 m3
RABU 08-Jun-22 KT 8279 1628 4,00 m3
RABU 08-Jun-22 KU 8375 1629 4,00 m3
RABU 08-Jun-22 KU 8509 1630 4,00 m3
RABU 08-Jun-22 KU 8161 1631 4,00 m3
RABU 08-Jun-22 KU 8166 1632 4,00 m3
RABU 08-Jun-22 KU 8314 1633 4,00 m3
RABU 08-Jun-22 KU 8239 1634 4,00 m3
RABU 08-Jun-22 KU 8145 1635 4,00 m3
RABU 08-Jun-22 KT 8279 1636 4,00 m3
RABU 08-Jun-22 KU 9674 1637 4,00 m3
RABU 08-Jun-22 KU 8375 1638 4,00 m3
RABU 08-Jun-22 KU 8509 1639 4,00 m3
RABU 08-Jun-22 KU 8161 1640 4,00 m3
RABU 08-Jun-22 KU 8166 1641 4,00 m3
RABU 08-Jun-22 KU 8314 1642 4,00 m3
RABU 08-Jun-22 KU 8239 1643 4,00 m3
RABU 08-Jun-22 KT 8145 1644 4,00 m3
RABU 08-Jun-22 KU 9674 1645 4,00 m3
RABU 08-Jun-22 KT 8279 1646 4,00 m3
RABU 08-Jun-22 KU 8375 1647 4,00 m3
RABU 08-Jun-22 KU 8166 1648 4,00 m3
RABU 08-Jun-22 KT 8720 1649 4,00 m3
RABU 08-Jun-22 KU 8161 1650 4,00 m3
RABU 08-Jun-22 KU 8314 1651 4,00 m3
RABU 08-Jun-22 KU 8239 1652 4,00 m3
RABU 08-Jun-22 KT 8145 1653 4,00 m3
RABU 08-Jun-22 KU 8509 1654 4,00 m3
RABU 08-Jun-22 KU 9674 1655 4,00 m3
RABU 08-Jun-22 KT 8279 1656 4,00 m3
RABU 08-Jun-22 KU 8375 1657 4,00 m3
RABU 08-Jun-22 KU 8166 1658 4,00 m3
RABU 08-Jun-22 KU 8161 1659 4,00 m3
RABU 08-Jun-22 KT 8720 1660 4,00 m3
RABU 08-Jun-22 KU 8239 1661 4,00 m3
RABU 08-Jun-22 KT 8145 1662 4,00 m3
RABU 08-Jun-22 KT 8279 1663 4,00 m3
RABU 08-Jun-22 KU 8166 1664 4,00 m3
RABU 08-Jun-22 KU 8375 1665 4,00 m3
RABU 08-Jun-22 KU 9674 1666 4,00 m3
RABU 08-Jun-22 KU 8161 1667 4,00 m3
RABU 08-Jun-22 KT 8720 1668 4,00 m3
RABU 08-Jun-22 KU 8509 1669 4,00 m3
RABU 08-Jun-22 KU 8314 1670 4,00 m3
RABU 08-Jun-22 KU 8161 1671 4,00 m3

Page 26 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
RABU 08-Jun-22 KU 8509 1672 4,00 m3
RABU 08-Jun-22 KU 9674 1673 4,00 m3
RABU 08-Jun-22 KU 8239 1674 4,00 m3
RABU 08-Jun-22 KT 8279 1675 4,00 m3
RABU 08-Jun-22 KU 8375 1676 4,00 m3
RABU 08-Jun-22 KU 8166 1677 4,00 m3
RABU 08-Jun-22 KU 8314 1678 4,00 m3
RABU 08-Jun-22 KT 8720 1679 4,00 m3
RABU 08-Jun-22 KT 8786 1680 4,00 m3
RABU 08-Jun-22 KU 8509 1681 4,00 m3
RABU 08-Jun-22 KU 8161 1682 4,00 m3
RABU 08-Jun-22 KU 9674 1683 4,00 m3
RABU 08-Jun-22 KT 8145 1684 4,00 m3
RABU 08-Jun-22 KT 8279 1685 4,00 m3
RABU 08-Jun-22 KU 8239 1686 4,00 m3
RABU 08-Jun-22 KU 8375 1687 4,00 m3
RABU 08-Jun-22 KT 8720 1688 4,00 m3
RABU 08-Jun-22 KU 8166 1689 4,00 m3
RABU 08-Jun-22 KU 8314 1690 4,00 m3
RABU 08-Jun-22 KT 8786 1691 4,00 m3
RABU 08-Jun-22 KU 8509 1692 4,00 m3
RABU 08-Jun-22 KU 8161 1693 4,00 m3
RABU 08-Jun-22 KT 8279 1694 4,00 m3
RABU 08-Jun-22 KU 9674 1695 4,00 m3
RABU 08-Jun-22 KT 8145 1696 4,00 m3
RABU 08-Jun-22 KU 8239 1697 4,00 m3
RABU 08-Jun-22 KU 8375 1698 4,00 m3
RABU 08-Jun-22 KU 8166 1699 4,00 m3
RABU 08-Jun-22 KU 8161 1700 4,00 m3
RABU 08-Jun-22 KT 8279 1701 4,00 m3
RABU 08-Jun-22 KU 9674 1702 4,00 m3
RABU 08-Jun-22 KT 8145 1703 4,00 m3
RABU 08-Jun-22 KU 8239 1704 4,00 m3
RABU 08-Jun-22 KU 8375 1705 4,00 m3
RABU 08-Jun-22 KU 8166 1706 4,00 m3
RABU 08-Jun-22 KT 8720 1707 4,00 m3
RABU 08-Jun-22 KU 8314 1708 4,00 m3
RABU 08-Jun-22 KU 8509 1709 4,00 m3
RABU 08-Jun-22 KT 8279 1710 4,00 m3
RABU 08-Jun-22 KU 8161 1711 4,00 m3
RABU 08-Jun-22 KT 8145 1712 4,00 m3
RABU 08-Jun-22 KU 9674 1713 4,00 m3
RABU 08-Jun-22 KU 8239 1714 4,00 m3
RABU 08-Jun-22 KU 8375 1715 4,00 m3
RABU 08-Jun-22 KU 8166 1716 4,00 m3
RABU 08-Jun-22 KT 8720 1717 4,00 m3
RABU 08-Jun-22 KU 8314 1718 4,00 m3
RABU 08-Jun-22 KU 8509 1719 4,00 m3
RABU 08-Jun-22 KT 8279 1720 4,00 m3
RABU 08-Jun-22 KU 8161 1721 4,00 m3
RABU 08-Jun-22 KU 9674 1722 4,00 m3
RABU 08-Jun-22 KU 8239 1723 4,00 m3
RABU 08-Jun-22 KU 8375 1724 4,00 m3
RABU 08-Jun-22 KU 8166 1725 4,00 m3
RABU 08-Jun-22 KT 8720 1726 4,00 m3
RABU 08-Jun-22 KU 8314 1727 4,00 m3
RABU 08-Jun-22 KU 8509 1728 4,00 m3
RABU 08-Jun-22 KU 8161 1729 4,00 m3
RABU 08-Jun-22 KT 8279 1730 4,00 m3
RABU 08-Jun-22 KU 8239 1731 4,00 m3
RABU 08-Jun-22 KU 8375 1732 4,00 m3
RABU 08-Jun-22 KU 8166 1733 4,00 m3
RABU 08-Jun-22 KU 9674 1734 4,00 m3
RABU 08-Jun-22 KT 8720 1735 4,00 m3

Page 27 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
RABU 08-Jun-22 KU 8314 1736 4,00 m3
RABU 08-Jun-22 KU 8509 1737 4,00 m3
RABU 08-Jun-22 KT 8279 1738 4,00 m3
RABU 08-Jun-22 KU 8161 1739 4,00 m3
RABU 08-Jun-22 KU 8239 1740 4,00 m3
RABU 08-Jun-22 KU 8375 1741 4,00 m3
RABU 08-Jun-22 KT 8145 1742 4,00 m3
RABU 08-Jun-22 KU 8166 1743 4,00 m3
RABU 08-Jun-22 KT 8024 1744 4,00 m3
RABU 08-Jun-22 KU 8699 1745 4,00 m3
RABU 08-Jun-22 KU 9674 1746 4,00 m3
RABU 08-Jun-22 KU 8314 1747 4,00 m3
RABU 08-Jun-22 KU 8509 1748 4,00 m3
RABU 08-Jun-22 KT 8720 1749 4,00 m3
RABU 08-Jun-22 KT 8279 1750 4,00 m3
RABU 08-Jun-22 KU 8161 1751 4,00 m3
RABU 08-Jun-22 KU 8239 1752 4,00 m3
RABU 08-Jun-22 KT 8145 1753 4,00 m3
RABU 08-Jun-22 KU 8166 1754 4,00 m3
RABU 08-Jun-22 KU 8438 1755 4,00 m3
RABU 08-Jun-22 KT 8549 1756 4,00 m3
RABU 08-Jun-22 KU 8375 1757 4,00 m3
RABU 08-Jun-22 KU 8239 1758 4,00 m3
RABU 08-Jun-22 KT 8720 1759 4,00 m3
RABU 08-Jun-22 KU 8699 1760 4,00 m3
RABU 08-Jun-22 KT 8145 1761 4,00 m3
RABU 08-Jun-22 KT 8279 1762 4,00 m3
RABU 08-Jun-22 KU 8161 1763 4,00 m3
RABU 08-Jun-22 KU 8074 1764 4,00 m3
RABU 08-Jun-22 KU 8088 1765 4,00 m3
RABU 08-Jun-22 KU 8509 1766 4,00 m3
RABU 08-Jun-22 KT 8786 1767 4,00 m3
RABU 08-Jun-22 KU 8166 1768 4,00 m3
RABU 08-Jun-22 KU 9674 1769 4,00 m3
RABU 08-Jun-22 KT 8024 1770 4,00 m3
RABU 08-Jun-22 KU 8509 1771 4,00 m3
RABU 08-Jun-22 KT 8786 1772 4,00 m3
RABU 08-Jun-22 KU 8166 1773 4,00 m3
RABU 08-Jun-22 KT 8024 1774 4,00 m3
RABU 08-Jun-22 KU 8438 1775 4,00 m3
RABU 08-Jun-22 1776 4,00 m3
RABU 08-Jun-22 KU 8375 1777 4,00 m3
RABU 08-Jun-22 KU 8238 1778 4,00 m3
RABU 08-Jun-22 KT 8145 1779 4,00 m3
RABU 08-Jun-22 KU 8161 1780 4,00 m3
RABU 08-Jun-22 KU 8509 1781 4,00 m3
RABU 08-Jun-22 KT8786 1782 4,00 m3
RABU 08-Jun-22 KU 8186 1783 4,00 m3
RABU 08-Jun-22 KT 8024 1784 4,00 m3
RABU 08-Jun-22 KU 8438 1785 4,00 m3
RABU 08-Jun-22 KT 8024 1786 4,00 m3
RABU 08-Jun-22 KU 8375 1787 4,00 m3
RABU 08-Jun-22 KU 8238 1788 4,00 m3
RABU 08-Jun-22 KT 8145 1789 4,00 m3
RABU 08-Jun-22 KU 8161 1790 4,00 m3
RABU 08-Jun-22 KU 8075 1791 4,00 m3
RABU 08-Jun-22 KU 8088 1792 4,00 m3
RABU 08-Jun-22 KU 8509 1793 4,00 m3
RABU 08-Jun-22 KT 8786 1794 4,00 m3
RABU 08-Jun-22 KU 8166 1795 4,00 m3
RABU 08-Jun-22 KT 8024 1796 4,00 m3
RABU 08-Jun-22 KU 8438 1797 4,00 m3
RABU 08-Jun-22 KT 8549 1798 4,00 m3
RABU 08-Jun-22 KU 8375 1799 4,00 m3

Page 28 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
RABU 08-Jun-22 KU 8239 1800 4,00 m3
RABU 08-Jun-22 KT 8145 1801 4,00 m3
RABU 08-Jun-22 KU 8074 1802 4,00 m3
RABU 08-Jun-22 KU 8161 1803 4,00 m3
RABU 08-Jun-22 KU 8088 1804 4,00 m3
KAMIS 09-Jun-22 KU 8314 1805 4,00 m3
KAMIS 09-Jun-22 KU 9674 1806 4,00 m3
KAMIS 09-Jun-22 KT 8549 1807 4,00 m3
KAMIS 09-Jun-22 KT 8279 1808 4,00 m3
KAMIS 09-Jun-22 KU 8161 1809 4,00 m3
KAMIS 09-Jun-22 KU 8166 1810 4,00 m3
KAMIS 09-Jun-22 KU 8088 1811 4,00 m3
KAMIS 09-Jun-22 KU 8509 1812 4,00 m3
KAMIS 09-Jun-22 KT 8024 1813 4,00 m3
KAMIS 09-Jun-22 KT 8720 1814 4,00 m3
KAMIS 09-Jun-22 KU 8239 1815 4,00 m3
KAMIS 09-Jun-22 KU 8699 1816 4,00 m3
KAMIS 09-Jun-22 KU 8375 1817 4,00 m3
KAMIS 09-Jun-22 KU 8958 1818 4,00 m3
KAMIS 09-Jun-22 KU 8438 1819 4,00 m3
KAMIS 09-Jun-22 KU 8314 1820 4,00 m3
KAMIS 09-Jun-22 KU 9674 1821 4,00 m3
KAMIS 09-Jun-22 KT 8279 1822 4,00 m3
KAMIS 09-Jun-22 KT 8549 1823 4,00 m3
KAMIS 09-Jun-22 KU 8161 1824 4,00 m3
KAMIS 09-Jun-22 KU 8088 1825 4,00 m3
KAMIS 09-Jun-22 KU 8509 1826 4,00 m3
KAMIS 09-Jun-22 KU 8166 1827 4,00 m3
KAMIS 09-Jun-22 KT 8024 1828 4,00 m3
KAMIS 09-Jun-22 KT 8720 1829 4,00 m3
KAMIS 09-Jun-22 KU 8699 1830 4,00 m3
KAMIS 09-Jun-22 KU 8239 1831 4,00 m3
KAMIS 09-Jun-22 KU 8958 1832 4,00 m3
KAMIS 09-Jun-22 KU 8438 1833 4,00 m3
KAMIS 09-Jun-22 KU 8314 1834 4,00 m3
KAMIS 09-Jun-22 KU 9674 1835 4,00 m3
KAMIS 09-Jun-22 KU 8375 1836 4,00 m3
KAMIS 09-Jun-22 KT 8549 1837 4,00 m3
KAMIS 09-Jun-22 KT 8145 1838 4,00 m3
KAMIS 09-Jun-22 KU 8279 1839 4,00 m3
KAMIS 09-Jun-22 KU 8088 1840 4,00 m3
KAMIS 09-Jun-22 KU 8161 1841 4,00 m3
KAMIS 09-Jun-22 KU 8509 1842 4,00 m3
KAMIS 09-Jun-22 KU 8166 1843 4,00 m3
KAMIS 09-Jun-22 KT 8720 1844 4,00 m3
KAMIS 09-Jun-22 KT 8024 1845 4,00 m3
KAMIS 09-Jun-22 KU 8375 1846 4,00 m3
KAMIS 09-Jun-22 KU 8239 1847 4,00 m3
KAMIS 09-Jun-22 KU 8699 1848 4,00 m3
KAMIS 09-Jun-22 KU 9674 1849 4,00 m3
KAMIS 09-Jun-22 KU 8438 1850 4,00 m3
KAMIS 09-Jun-22 KT 8145 1851 4,00 m3
KAMIS 09-Jun-22 KU 8314 1852 4,00 m3
KAMIS 09-Jun-22 KT 8279 1853 4,00 m3
KAMIS 09-Jun-22 KT 8549 1854 4,00 m3
KAMIS 09-Jun-22 KU 8161 1855 4,00 m3
KAMIS 09-Jun-22 KU 8088 1856 4,00 m3
KAMIS 09-Jun-22 KU 8509 1857 4,00 m3
KAMIS 09-Jun-22 KU 8958 1858 4,00 m3
KAMIS 09-Jun-22 KT 8720 1859 4,00 m3
KAMIS 09-Jun-22 KT 8024 1860 4,00 m3
KAMIS 09-Jun-22 KU 8375 1861 4,00 m3
KAMIS 09-Jun-22 KU 8699 1862 4,00 m3
KAMIS 09-Jun-22 KU 9674 1863 4,00 m3

Page 29 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
KAMIS 09-Jun-22 KU 8239 1864 4,00 m3
KAMIS 09-Jun-22 KU 8438 1865 4,00 m3
KAMIS 09-Jun-22 KT 8145 1866 4,00 m3
KAMIS 09-Jun-22 KU 8314 1867 4,00 m3
KAMIS 09-Jun-22 KT 8279 1868 4,00 m3
KAMIS 09-Jun-22 KT 8549 1869 4,00 m3
KAMIS 09-Jun-22 KU 8166 1870 4,00 m3
KAMIS 09-Jun-22 KU 8161 1871 4,00 m3
KAMIS 09-Jun-22 KU 8509 1872 4,00 m3
KAMIS 09-Jun-22 KU 8958 1873 4,00 m3
KAMIS 09-Jun-22 KU 8088 1874 4,00 m3
KAMIS 09-Jun-22 KT 8720 1875 4,00 m3
KAMIS 09-Jun-22 KT 8024 1876 4,00 m3
KAMIS 09-Jun-22 KU 8375 1877 4,00 m3
KAMIS 09-Jun-22 KU 8699 1878 4,00 m3
KAMIS 09-Jun-22 KU 8438 1879 4,00 m3
KAMIS 09-Jun-22 KT 8279 1880 4,00 m3
KAMIS 09-Jun-22 KU 8161 1881 4,00 m3
KAMIS 09-Jun-22 KU 8375 1882 4,00 m3
KAMIS 09-Jun-22 KT 8549 1883 4,00 m3
KAMIS 09-Jun-22 KT 8145 1884 4,00 m3
KAMIS 09-Jun-22 KU 8239 1885 4,00 m3
KAMIS 09-Jun-22 KU 8958 1886 4,00 m3
KAMIS 09-Jun-22 KU 8314 1887 4,00 m3
KAMIS 09-Jun-22 KU 8088 1888 4,00 m3
KAMIS 09-Jun-22 KU 8166 1889 4,00 m3
KAMIS 09-Jun-22 KU 8509 1890 4,00 m3
KAMIS 09-Jun-22 KT 8720 1891 4,00 m3
KAMIS 09-Jun-22 KU 9674 1892 4,00 m3
KAMIS 09-Jun-22 KT 8024 1893 4,00 m3
KAMIS 09-Jun-22 KU 8699 1894 4,00 m3
KAMIS 09-Jun-22 KU 8438 1895 4,00 m3
KAMIS 09-Jun-22 KT 8279 1896 4,00 m3
KAMIS 09-Jun-22 KU 8161 1897 4,00 m3
KAMIS 09-Jun-22 KU 8375 1898 4,00 m3
KAMIS 09-Jun-22 KT 8549 1899 4,00 m3
KAMIS 09-Jun-22 KT 8145 1900 4,00 m3
KAMIS 09-Jun-22 KU 8239 1901 4,00 m3
KAMIS 09-Jun-22 KU 8958 1902 4,00 m3
KAMIS 09-Jun-22 KU 8314 1903 4,00 m3
KAMIS 09-Jun-22 KU 8088 1904 4,00 m3
KAMIS 09-Jun-22 KU 8166 1905 4,00 m3
KAMIS 09-Jun-22 KU 8509 1906 4,00 m3
KAMIS 09-Jun-22 KU 9674 1907 4,00 m3
KAMIS 09-Jun-22 KT 8024 1908 4,00 m3
KAMIS 09-Jun-22 KU 8438 1909 4,00 m3
KAMIS 09-Jun-22 KU 8699 1910 4,00 m3
KAMIS 09-Jun-22 KT 8279 1911 4,00 m3
KAMIS 09-Jun-22 KU 8161 1912 4,00 m3
KAMIS 09-Jun-22 KU 8375 1913 4,00 m3
KAMIS 09-Jun-22 KT 8549 1914 4,00 m3
KAMIS 09-Jun-22 KU 8239 1915 4,00 m3
KAMIS 09-Jun-22 KT 8145 1916 4,00 m3
KAMIS 09-Jun-22 KU 8958 1917 4,00 m3
KAMIS 09-Jun-22 KU 8314 1918 4,00 m3
KAMIS 09-Jun-22 KU 8166 1919 4,00 m3
KAMIS 09-Jun-22 KU 8509 1920 4,00 m3
KAMIS 09-Jun-22 KU 9674 1921 4,00 m3
KAMIS 09-Jun-22 KU 8438 1922 4,00 m3
KAMIS 09-Jun-22 KT 8279 1923 4,00 m3
KAMIS 09-Jun-22 KU 8161 1924 4,00 m3
KAMIS 09-Jun-22 KU 8699 1925 4,00 m3
KAMIS 09-Jun-22 KT 8549 1926 4,00 m3
KAMIS 09-Jun-22 KU 8239 1927 4,00 m3

Page 30 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
KAMIS 09-Jun-22 KU 8958 1928 4,00 m3
KAMIS 09-Jun-22 KU 8166 1929 4,00 m3
KAMIS 09-Jun-22 KU 8509 1930 4,00 m3
KAMIS 09-Jun-22 KU 9674 1931 4,00 m3
KAMIS 09-Jun-22 KU 8438 1932 4,00 m3
KAMIS 09-Jun-22 KT 8279 1933 4,00 m3
KAMIS 09-Jun-22 KU 8161 1934 4,00 m3
KAMIS 09-Jun-22 KT 8549 1935 4,00 m3
KAMIS 09-Jun-22 KU 8239 1936 4,00 m3
KAMIS 09-Jun-22 KU 8375 1937 4,00 m3
KAMIS 09-Jun-22 KU 8699 1938 4,00 m3
KAMIS 09-Jun-22 KU 8958 1939 4,00 m3
KAMIS 09-Jun-22 KU 8166 1940 4,00 m3
KAMIS 09-Jun-22 KU 8509 1941 4,00 m3
KAMIS 09-Jun-22 KU 9674 1942 4,00 m3
KAMIS 09-Jun-22 KU 8438 1943 4,00 m3
KAMIS 09-Jun-22 KT 8279 1944 4,00 m3
KAMIS 09-Jun-22 KU 8161 1945 4,00 m3
KAMIS 09-Jun-22 KT 8024 1946 4,00 m3
KAMIS 09-Jun-22 KT 8549 1947 4,00 m3
KAMIS 09-Jun-22 KU 8239 1948 4,00 m3
KAMIS 09-Jun-22 KU 9674 1949 4,00 m3
KAMIS 09-Jun-22 KU 8375 1950 4,00 m3
KAMIS 09-Jun-22 KU 8699 1951 4,00 m3
KAMIS 09-Jun-22 KU 8958 1952 4,00 m3
KAMIS 09-Jun-22 KU 8166 1953 4,00 m3
KAMIS 09-Jun-22 KU 8509 1954 4,00 m3
KAMIS 09-Jun-22 KU 8438 1955 4,00 m3
KAMIS 09-Jun-22 KT 8279 1956 4,00 m3
KAMIS 09-Jun-22 KU 8161 1957 4,00 m3
KAMIS 09-Jun-22 KT 8024 1958 4,00 m3
KAMIS 09-Jun-22 KT 8549 1959 4,00 m3
JUMAT 10-Jun-22 1960 4,00 m3
JUMAT 10-Jun-22 KU 8161 1961 4,00 m3
JUMAT 10-Jun-22 KU 8239 1962 4,00 m3
JUMAT 10-Jun-22 KU 8699 1963 4,00 m3
JUMAT 10-Jun-22 KU 8375 1964 4,00 m3
JUMAT 10-Jun-22 KT 8024 1965 4,00 m3
JUMAT 10-Jun-22 KT 8549 1966 4,00 m3
JUMAT 10-Jun-22 KT 8279 1967 4,00 m3
JUMAT 10-Jun-22 KT 8145 1968 4,00 m3
JUMAT 10-Jun-22 KT 8720 1969 4,00 m3
JUMAT 10-Jun-22 KU 8161 1970 4,00 m3
JUMAT 10-Jun-22 KU 8438 1971 4,00 m3
JUMAT 10-Jun-22 KU 8239 1972 4,00 m3
JUMAT 10-Jun-22 KU 8699 1973 4,00 m3
JUMAT 10-Jun-22 KU 8375 1974 4,00 m3
JUMAT 10-Jun-22 KT 8145 1975 4,00 m3
JUMAT 10-Jun-22 KT 8549 1976 4,00 m3
JUMAT 10-Jun-22 KT 8279 1977 4,00 m3
JUMAT 10-Jun-22 KT 8720 1978 4,00 m3
JUMAT 10-Jun-22 KT 8024 1979 4,00 m3
JUMAT 10-Jun-22 KU 8166 1980 4,00 m3
JUMAT 10-Jun-22 KU 8509 1981 4,00 m3
JUMAT 10-Jun-22 KT 8786 1982 4,00 m3
JUMAT 10-Jun-22 KU 8161 1983 4,00 m3
JUMAT 10-Jun-22 KU 8438 1984 4,00 m3
JUMAT 10-Jun-22 KU 8239 1985 4,00 m3
JUMAT 10-Jun-22 KT 8145 1986 4,00 m3
JUMAT 10-Jun-22 KT 8549 1987 4,00 m3
JUMAT 10-Jun-22 KU 8699 1988 4,00 m3
JUMAT 10-Jun-22 KT 8720 1989 4,00 m3
JUMAT 10-Jun-22 KT 8024 1990 4,00 m3
JUMAT 10-Jun-22 KU 8166 1991 4,00 m3

Page 31 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
JUMAT 10-Jun-22 KU 8509 1992 4,00 m3
JUMAT 10-Jun-22 KT 8786 1993 4,00 m3
JUMAT 10-Jun-22 KU 8161 1994 4,00 m3
JUMAT 10-Jun-22 KU 8438 1995 4,00 m3
JUMAT 10-Jun-22 KU 8239 1996 4,00 m3
JUMAT 10-Jun-22 KT 8145 1997 4,00 m3
JUMAT 10-Jun-22 KT 8024 1998 4,00 m3
JUMAT 10-Jun-22 KT 8720 1999 4,00 m3
JUMAT 10-Jun-22 KU 8509 2000 4,00 m3
JUMAT 10-Jun-22 KU 8166 2001 4,00 m3
JUMAT 10-Jun-22 KT 8786 2002 4,00 m3
JUMAT 10-Jun-22 KU 8161 2003 4,00 m3
JUMAT 10-Jun-22 KU 8438 2004 4,00 m3
JUMAT 10-Jun-22 KU 8239 2005 4,00 m3
JUMAT 10-Jun-22 KT 8145 2006 4,00 m3
SABTU 11-Jun-22 KU 8699 2007 4,00 m3
SABTU 11-Jun-22 KT 8549 2008 4,00 m3
SABTU 11-Jun-22 KU 8161 2009 4,00 m3
SABTU 11-Jun-22 KU 8509 2010 4,00 m3
SABTU 11-Jun-22 KT 8279 2011 4,00 m3
SABTU 11-Jun-22 KT 8720 2012 4,00 m3
SABTU 11-Jun-22 KU 8547 2013 4,00 m3
SABTU 11-Jun-22 KU 8166 2014 4,00 m3
SABTU 11-Jun-22 KU 8958 2015 4,00 m3
SABTU 11-Jun-22 KT 8024 2016 4,00 m3
SABTU 11-Jun-22 KU 8239 2017 4,00 m3
SABTU 11-Jun-22 KT 8145 2018 4,00 m3
SABTU 11-Jun-22 KU 8375 2019 4,00 m3
SABTU 11-Jun-22 KU 8699 2020 4,00 m3
SABTU 11-Jun-22 KU 8438 2021 4,00 m3
SABTU 11-Jun-22 KT 8549 2022 4,00 m3
SABTU 11-Jun-22 KU 8161 2023 4,00 m3
SABTU 11-Jun-22 KU 8509 2024 4,00 m3
SABTU 11-Jun-22 KU 8279 2025 4,00 m3
SABTU 11-Jun-22 KT 8720 2026 4,00 m3
SABTU 11-Jun-22 KU 8547 2027 4,00 m3
SABTU 11-Jun-22 KU 8166 2028 4,00 m3
SABTU 11-Jun-22 KU 8958 2029 4,00 m3
SABTU 11-Jun-22 KU 8239 2030 4,00 m3
SABTU 11-Jun-22 KU 8375 2031 4,00 m3
SABTU 11-Jun-22 KU 8438 2032 4,00 m3
SABTU 11-Jun-22 KU 8699 2033 4,00 m3
SABTU 11-Jun-22 KT 8549 2034 4,00 m3
SABTU 11-Jun-22 KU 8161 2035 4,00 m3
SABTU 11-Jun-22 KU 8509 2036 4,00 m3
SABTU 11-Jun-22 KU 8279 2037 4,00 m3
SABTU 11-Jun-22 KT 8024 2038 4,00 m3
SABTU 11-Jun-22 KT 8720 2039 4,00 m3
SABTU 11-Jun-22 KU 8166 2040 4,00 m3
SABTU 11-Jun-22 KU 8547 2041 4,00 m3
SABTU 11-Jun-22 KU 8958 2042 4,00 m3
SABTU 11-Jun-22 KU 8239 2043 4,00 m3
SABTU 11-Jun-22 KU 8375 2044 4,00 m3
SABTU 11-Jun-22 KU 8438 2045 4,00 m3
SABTU 11-Jun-22 KT 8549 2046 4,00 m3
SABTU 11-Jun-22 KT 8145 2047 4,00 m3
SABTU 11-Jun-22 KU 8699 2048 4,00 m3
SABTU 11-Jun-22 KU 8161 2049 4,00 m3
SABTU 11-Jun-22 KU 8509 2050 4,00 m3
SABTU 11-Jun-22 KT 8279 2051 4,00 m3
SABTU 11-Jun-22 KT 8024 2052 4,00 m3
SABTU 11-Jun-22 KT 8720 2053 4,00 m3
SABTU 11-Jun-22 KU 8547 2054 4,00 m3
SABTU 11-Jun-22 KU 8166 2055 4,00 m3

Page 32 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
SABTU 11-Jun-22 KU 8958 2056 4,00 m3
SABTU 11-Jun-22 KU 8239 2057 4,00 m3
SABTU 11-Jun-22 KU 8375 2058 4,00 m3
SABTU 11-Jun-22 KU 8438 2059 4,00 m3
SABTU 11-Jun-22 KT 8549 2060 4,00 m3
SABTU 11-Jun-22 KT 8145 2061 4,00 m3
SABTU 11-Jun-22 KU 8699 2062 4,00 m3
SABTU 11-Jun-22 KU 8161 2063 4,00 m3
SABTU 11-Jun-22 KU 8279 2064 4,00 m3
SABTU 11-Jun-22 KT 8024 2065 4,00 m3
SABTU 11-Jun-22 KT 8720 2066 4,00 m3
SABTU 11-Jun-22 KU 8547 2067 4,00 m3
SABTU 11-Jun-22 KU 8166 2068 4,00 m3
SABTU 11-Jun-22 KU 8958 2069 4,00 m3
SABTU 11-Jun-22 KU 8239 2070 4,00 m3
SABTU 11-Jun-22 KU 8509 2071 4,00 m3
SABTU 11-Jun-22 KU 8375 2072 4,00 m3
SABTU 11-Jun-22 KU 8438 2073 4,00 m3
SABTU 11-Jun-22 KT 8549 2074 4,00 m3
SABTU 11-Jun-22 KT 8145 2075 4,00 m3
SABTU 11-Jun-22 KU 8699 2076 4,00 m3
SABTU 11-Jun-22 KU 8161 2077 4,00 m3
SABTU 11-Jun-22 KT 8279 2078 4,00 m3
SABTU 11-Jun-22 KT 8024 2079 4,00 m3
SABTU 11-Jun-22 KT 8720 2080 4,00 m3
SABTU 11-Jun-22 KU 8166 2081 4,00 m3
SABTU 11-Jun-22 KU 8958 2082 4,00 m3
SABTU 11-Jun-22 KU 8438 2083 4,00 m3
SABTU 11-Jun-22 KU 8375 2084 4,00 m3
MINGGU 12-Jun-22 KT 8549 2085 4,00 m3
MINGGU 12-Jun-22 KU 8699 2086 4,00 m3
MINGGU 12-Jun-22 KU 8161 2087 4,00 m3
MINGGU 12-Jun-22 KU 9674 2088 4,00 m3
MINGGU 12-Jun-22 KU 8074 2089 4,00 m3
MINGGU 12-Jun-22 KT 8024 2090 4,00 m3
MINGGU 12-Jun-22 KU 8239 2091 4,00 m3
MINGGU 12-Jun-22 KT 8720 2092 4,00 m3
MINGGU 12-Jun-22 KU 8375 2093 4,00 m3
MINGGU 12-Jun-22 KU 8166 2094 4,00 m3
MINGGU 12-Jun-22 KT 8145 2095 4,00 m3
MINGGU 12-Jun-22 KU 8438 2096 4,00 m3
MINGGU 12-Jun-22 KU 8786 2097 4,00 m3
MINGGU 12-Jun-22 KU 9305 2098 4,00 m3
MINGGU 12-Jun-22 KT 8545 2099 4,00 m3
MINGGU 12-Jun-22 KU 8161 2100 4,00 m3
MINGGU 12-Jun-22 KU 9674 2101 4,00 m3
MINGGU 12-Jun-22 KU 8074 2102 4,00 m3
MINGGU 12-Jun-22 KT 8024 2103 4,00 m3
MINGGU 12-Jun-22 KU 8239 2104 4,00 m3
MINGGU 12-Jun-22 KT 8720 2105 4,00 m3
MINGGU 12-Jun-22 KU 8166 2106 4,00 m3
MINGGU 12-Jun-22 KU 8375 2107 4,00 m3
MINGGU 12-Jun-22 KT 8145 2108 4,00 m3
MINGGU 12-Jun-22 KU 8438 2109 4,00 m3
MINGGU 12-Jun-22 KT 8786 2110 4,00 m3
MINGGU 12-Jun-22 KU 9305 2111 4,00 m3
MINGGU 12-Jun-22 KT 8549 2112 4,00 m3
MINGGU 12-Jun-22 KU 8161 2113 4,00 m3
MINGGU 12-Jun-22 KU 8074 2114 4,00 m3
MINGGU 12-Jun-22 KT 8024 2115 4,00 m3
MINGGU 12-Jun-22 KU 8239 2116 4,00 m3
MINGGU 12-Jun-22 KU 8375 2117 4,00 m3
MINGGU 12-Jun-22 KU 8166 2118 4,00 m3
MINGGU 12-Jun-22 KT 8145 2119 4,00 m3

Page 33 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
MINGGU 12-Jun-22 KU 8438 2120 4,00 m3
MINGGU 12-Jun-22 KT 8786 2121 4,00 m3
MINGGU 12-Jun-22 KU 9305 2122 4,00 m3
MINGGU 12-Jun-22 KT 8549 2123 4,00 m3
SELASA 14-Jun-22 KU 8166 2124 4,00 m3
SELASA 14-Jun-22 KT 8549 2125 4,00 m3
SELASA 14-Jun-22 KU 8547 2126 4,00 m3
SELASA 14-Jun-22 KT 8024 2127 4,00 m3
SELASA 14-Jun-22 KU 9674 2128 4,00 m3
SELASA 14-Jun-22 KU 8509 2129 4,00 m3
SELASA 14-Jun-22 KU 8161 2130 4,00 m3
SELASA 14-Jun-22 KU 8239 2131 4,00 m3
SELASA 14-Jun-22 KU 8166 2132 4,00 m3
SELASA 14-Jun-22 KT 8279 2133 4,00 m3
SELASA 14-Jun-22 KU 8265 2134 4,00 m3
SELASA 14-Jun-22 KT 8549 2135 4,00 m3
SELASA 14-Jun-22 KU 8547 2136 4,00 m3
SELASA 14-Jun-22 KU 8958 2137 4,00 m3
SELASA 14-Jun-22 KT 8024 2138 4,00 m3
SELASA 14-Jun-22 KU 9674 2139 4,00 m3
SELASA 14-Jun-22 KU 8438 2140 4,00 m3
SELASA 14-Jun-22 KU 8345 2141 4,00 m3
SELASA 14-Jun-22 KU 8161 2142 4,00 m3
SELASA 14-Jun-22 KU 8509 2143 4,00 m3
SELASA 14-Jun-22 KU 8239 2144 4,00 m3
SELASA 14-Jun-22 KU 8166 2145 4,00 m3
SELASA 14-Jun-22 KT 8549 2146 4,00 m3
SELASA 14-Jun-22 KU 8265 2147 4,00 m3
SELASA 14-Jun-22 KU 8958 2148 4,00 m3
SELASA 14-Jun-22 KT 8024 2149 4,00 m3
SELASA 14-Jun-22 KU 9674 2150 4,00 m3
SELASA 14-Jun-22 KU 8439 2151 4,00 m3
SELASA 14-Jun-22 KU 8375 2152 4,00 m3
SELASA 14-Jun-22 KU 8279 2153 4,00 m3
SELASA 14-Jun-22 KU 8547 2154 4,00 m3
SELASA 14-Jun-22 KU 8509 2155 4,00 m3
SELASA 14-Jun-22 KU 8161 2156 4,00 m3
SELASA 14-Jun-22 KU 8239 2157 4,00 m3
SELASA 14-Jun-22 KU 8166 2158 4,00 m3
SELASA 14-Jun-22 KT 8549 2159 4,00 m3
SELASA 14-Jun-22 KU 8265 2160 4,00 m3
SELASA 14-Jun-22 KU 8958 2161 4,00 m3
SELASA 14-Jun-22 KU 8438 2162 4,00 m3
SELASA 14-Jun-22 KU 8375 2163 4,00 m3
SELASA 14-Jun-22 KT 8720 2164 4,00 m3
SELASA 14-Jun-22 KT 8279 2165 4,00 m3
SELASA 14-Jun-22 KU 8547 2166 4,00 m3
SELASA 14-Jun-22 KU 8509 2167 4,00 m3
SELASA 14-Jun-22 KU 8161 2168 4,00 m3
SELASA 14-Jun-22 KU 8239 2169 4,00 m3
SELASA 14-Jun-22 KU 8166 2170 4,00 m3
SELASA 14-Jun-22 KT 8549 2171 4,00 m3
SELASA 14-Jun-22 KU 8265 2172 4,00 m3
SELASA 14-Jun-22 KU 8958 2173 4,00 m3
SELASA 14-Jun-22 KU 8438 2174 4,00 m3
SELASA 14-Jun-22 KU 8375 2175 4,00 m3
SELASA 14-Jun-22 KT 8279 2176 4,00 m3
SELASA 14-Jun-22 KU 8509 2177 4,00 m3
SELASA 14-Jun-22 0 2178 4,00 m3
SELASA 14-Jun-22 KU 8161 2179 4,00 m3
SELASA 14-Jun-22 KT 8720 2180 4,00 m3
SELASA 14-Jun-22 KU 8509 2181 4,00 m3
SELASA 14-Jun-22 KT 8279 2182 4,00 m3
SELASA 14-Jun-22 KU 9674 2183 4,00 m3

Page 34 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
SELASA 14-Jun-22 KU 8375 2184 4,00 m3
SELASA 14-Jun-22 KU 8265 2185 4,00 m3
SELASA 14-Jun-22 KU 8438 2186 4,00 m3
SELASA 14-Jun-22 KU 8166 2187 4,00 m3
SELASA 14-Jun-22 KU 9305 2188 4,00 m3
SELASA 14-Jun-22 KT 8549 2189 4,00 m3
SELASA 14-Jun-22 KT 8786 2190 4,00 m3
SELASA 14-Jun-22 KU 8161 2191 4,00 m3
SELASA 14-Jun-22 KT 8720 2192 4,00 m3
SELASA 14-Jun-22 KU 8509 2193 4,00 m3
SELASA 14-Jun-22 KT 8279 2194 4,00 m3
SELASA 14-Jun-22 KU 9674 2195 4,00 m3
SELASA 14-Jun-22 KU 8375 2196 4,00 m3
SELASA 14-Jun-22 KU 8438 2197 4,00 m3
SELASA 14-Jun-22 KU 8265 2198 4,00 m3
SELASA 14-Jun-22 KU 8166 2199 4,00 m3
SELASA 14-Jun-22 KU 9305 2200 4,00 m3
SELASA 14-Jun-22 KU 8074 2201 4,00 m3
SELASA 14-Jun-22 KT 8549 2202 4,00 m3
SELASA 14-Jun-22 KT 8786 2203 4,00 m3
SELASA 14-Jun-22 KU 8161 2204 4,00 m3
SELASA 14-Jun-22 KU 8509 2205 4,00 m3
SELASA 14-Jun-22 KU 8375 2206 4,00 m3
SELASA 14-Jun-22 KU 8438 2207 4,00 m3
SELASA 14-Jun-22 KU 8265 2208 4,00 m3
SELASA 14-Jun-22 KU 8166 2209 4,00 m3
SELASA 14-Jun-22 KU 9305 2210 4,00 m3
SELASA 14-Jun-22 KU 8074 2211 4,00 m3
SELASA 14-Jun-22 KT 8549 2212 4,00 m3
SELASA 14-Jun-22 KT 8786 2213 4,00 m3
SELASA 14-Jun-22 KT 8720 2214 4,00 m3
SELASA 14-Jun-22 KU 8161 2215 4,00 m3
SELASA 14-Jun-22 KU 8509 2216 4,00 m3
SELASA 14-Jun-22 KU 8375 2217 4,00 m3
SELASA 14-Jun-22 KU 8265 2218 4,00 m3
SELASA 14-Jun-22 KU 8166 2219 4,00 m3
SELASA 14-Jun-22 KU 9305 2220 4,00 m3
SELASA 14-Jun-22 KU 8074 2221 4,00 m3
SELASA 14-Jun-22 KT 8549 2222 4,00 m3
SELASA 14-Jun-22 KT 8786 2223 4,00 m3
14-Jul-22 KT 8150 2224 4,00 m3
14-Jul-22 KT 8549 2225 4,00 m3
14-Jul-22 KT 8279 2226 4,00 m3
14-Jul-22 KT 8375 2227 4,00 m3
14-Jul-22 KU 8074 2228 4,00 m3
14-Jul-22 KU 8438 2229 4,00 m3
14-Jul-22 KU 8088 2230 4,00 m3
14-Jul-22 KT 8024 2231 4,00 m3
14-Jul-22 KU 8166 2232 4,00 m3
14-Jul-22 KU 9674 2233 4,00 m3
14-Jul-22 KT 8150 2234 4,00 m3
14-Jul-22 KT 8279 2235 4,00 m3
14-Jul-22 KT 8549 2236 4,00 m3
14-Jul-22 KU 8375 2237 4,00 m3
14-Jul-22 KU 8161 2238 4,00 m3
14-Jul-22 KU 8074 2239 4,00 m3
14-Jul-22 KU 9305 2240 4,00 m3
14-Jul-22 KU 8088 2241 4,00 m3
14-Jul-22 KU 8166 2242 4,00 m3
14-Jul-22 KU 8265 2243 4,00 m3
14-Jul-22 KU 8862 2244 4,00 m3
14-Jul-22 KU 9674 2245 4,00 m3
14-Jul-22 KU 8438 2246 4,00 m3
14-Jul-22 KT 8150 2247 4,00 m3

Page 35 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
14-Jul-22 KT 8024 2248 4,00 m3
14-Jul-22 KT 8549 2249 4,00 m3
14-Jul-22 KT 8786 2250 4,00 m3
14-Jul-22 KU 8509 2251 4,00 m3
14-Jul-22 KU 8375 2252 4,00 m3
14-Jul-22 KT 8279 2253 4,00 m3
14-Jul-22 KU 8699 2254 4,00 m3
14-Jul-22 KU 8161 2255 4,00 m3
14-Jul-22 KU 8074 2256 4,00 m3
14-Jul-22 KU 9305 2257 4,00 m3
14-Jul-22 KU 8161 2258 4,00 m3
14-Jul-22 KU 8088 2259 4,00 m3
14-Jul-22 KU 8265 2260 4,00 m3
14-Jul-22 KU 8860 2261 4,00 m3
14-Jul-22 KU 9674 2262 4,00 m3
14-Jul-22 KU 8438 2263 4,00 m3
14-Jul-22 KT 8024 2264 4,00 m3
14-Jul-22 KT 8150 2265 4,00 m3
14-Jul-22 KT 8549 2266 4,00 m3
14-Jul-22 KT 8786 2267 4,00 m3
14-Jul-22 KU 8265 2268 4,00 m3
14-Jul-22 KT 8279 2269 4,00 m3
14-Jul-22 KU 8375 2270 4,00 m3
14-Jul-22 KU 8699 2271 4,00 m3
14-Jul-22 KU 8509 2272 4,00 m3
14-Jul-22 KU 8161 2273 4,00 m3
14-Jul-22 KU 9305 2274 4,00 m3
14-Jul-22 KU 8166 2275 4,00 m3
14-Jul-22 KU 8074 2276 4,00 m3
14-Jul-22 KU 8088 2277 4,00 m3
14-Jul-22 KU 8860 2278 4,00 m3
14-Jul-22 KU 8438 2279 4,00 m3
14-Jul-22 KU 9674 2280 4,00 m3
14-Jul-22 KT8024 2281 4,00 m3
14-Jul-22 KT 8150 2282 4,00 m3
14-Jul-22 KT 8549 2283 4,00 m3
14-Jul-22 KU 8239 2284 4,00 m3
14-Jul-22 KT 8279 2285 4,00 m3
14-Jul-22 KU 8375 2286 4,00 m3
14-Jul-22 KU 8699 2287 4,00 m3
14-Jul-22 KU 8509 2288 4,00 m3
14-Jul-22 KU 8161 2289 4,00 m3
14-Jul-22 KU 8074 2290 4,00 m3
14-Jul-22 KU 8166 2291 4,00 m3
14-Jul-22 KU 9305 2292 4,00 m3
14-Jul-22 KU 8088 2293 4,00 m3
14-Jul-22 KU 8265 2294 4,00 m3
14-Jul-22 KU 8860 2295 4,00 m3
14-Jul-22 KT 8786 2296 4,00 m3
14-Jul-22 KU 8438 2297 4,00 m3
14-Jul-22 KU9674 2298 4,00 m3
14-Jul-22 KT 8150 2299 4,00 m3
14-Jul-22 KT 8549 2300 4,00 m3
14-Jul-22 KT 8024 2301 4,00 m3
14-Jul-22 KT 8279 2302 4,00 m3
14-Jul-22 KU 8699 2303 4,00 m3
14-Jul-22 KU 8239 2304 4,00 m3
14-Jul-22 KU 8375 2305 4,00 m3
14-Jul-22 KU 8509 2306 4,00 m3
16-Jul-22 KT 8549 2307 4,00 m3
16-Jul-22 KU 8375 2308 4,00 m3
16-Jul-22 KU 9674 2309 4,00 m3
16-Jul-22 KT 8279 2310 4,00 m3
16-Jul-22 KU 8074 2311 4,00 m3

Page 36 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
16-Jul-22 KT 8150 2312 4,00 m3
16-Jul-22 KT 8024 2313 4,00 m3
16-Jul-22 KU 8161 2314 4,00 m3
16-Jul-22 KU 8166 2315 4,00 m3
16-Jul-22 KU 8509 2316 4,00 m3
16-Jul-22 KU 8239 2317 4,00 m3
16-Jul-22 KU 8265 2318 4,00 m3
16-Jul-22 KU 8854 2319 4,00 m3
16-Jul-22 KU 8699 2320 4,00 m3
16-Jul-22 KU 8314 2321 4,00 m3
16-Jul-22 KT 8549 2322 4,00 m3
16-Jul-22 KU 8438 2323 4,00 m3
16-Jul-22 KU 8375 2324 4,00 m3
16-Jul-22 KT 8279 2325 4,00 m3
16-Jul-22 KU 8720 2326 4,00 m3
16-Jul-22 KT 8786 2327 4,00 m3
16-Jul-22 KU 8074 2328 4,00 m3
16-Jul-22 KT 8150 2329 4,00 m3
16-Jul-22 KU 8161 2330 4,00 m3
16-Jul-22 KT 8024 2331 4,00 m3
16-Jul-22 KU 8166 2332 4,00 m3
16-Jul-22 KU 85-09 2333 4,00 m3
16-Jul-22 KU 8239 2334 4,00 m3
16-Jul-22 KU 8854 2335 4,00 m3
16-Jul-22 KU 8265 2336 4,00 m3
16-Jul-22 KU 8314 2337 4,00 m3
16-Jul-22 KU 8699 2338 4,00 m3
16-Jul-22 KT 8549 2339 4,00 m3
16-Jul-22 KU 8438 2340 4,00 m3
16-Jul-22 KU 8375 2341 4,00 m3
16-Jul-22 KT 8279 2342 4,00 m3
16-Jul-22 KT 8720 2343 4,00 m3
16-Jul-22 KU 8074 2344 4,00 m3
16-Jul-22 KT 8549 2345 4,00 m3
16-Jul-22 KU 8161 2346 4,00 m3
16-Jul-22 KT 8024 2347 4,00 m3
16-Jul-22 KU 8166 2348 4,00 m3
16-Jul-22 KU 8854 2349 4,00 m3
16-Jul-22 KU 8509 2350 4,00 m3
16-Jul-22 KU 8265 2351 4,00 m3
16-Jul-22 KU 8314 2352 4,00 m3
16-Jul-22 KT 8786 2353 4,00 m3
16-Jul-22 KT 8549 2354 4,00 m3
16-Jul-22 KT 8279 2355 4,00 m3
16-Jul-22 KU 8438 2356 4,00 m3
16-Jul-22 KU 8375 2357 4,00 m3
16-Jul-22 KT 8720 2358 4,00 m3
16-Jul-22 KU 8699 2359 4,00 m3
17-Jul-22 KU 8150 2360 4,00 m3
17-Jul-22 KT 8279 2361 4,00 m3
17-Jul-22 KT 8024 2362 4,00 m3
17-Jul-22 KU 8166 2363 4,00 m3
17-Jul-22 KU 8074 2364 4,00 m3
17-Jul-22 KU 8161 2365 4,00 m3
17-Jul-22 KU 8088 2366 3,70 m3
17-Jul-22 KU 8509 2367 4,30 m3
17-Jul-22 KU 8265 2368 4,00 m3
17-Jul-22 KU 8854 2369 4,00 m3
17-Jul-22 KT 8720 2370 4,00 m3
17-Jul-22 KU 8375 2371 4,80 m3
17-Jul-22 KU 9674 2372 4,00 m3
17-Jul-22 KT 8786 2373 4,00 m3
17-Jul-22 KU 8699 2374 4,00 m3
17-Jul-22 KU 8438 2375 4,00 m3

Page 37 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
17-Jul-22 KT 8549 2376 4,00 m3
17-Jul-22 KU 8239 2377 4,00 m3
17-Jul-22 KT 8150 2378 4,00 m3
17-Jul-22 KU 8860 2379 4,00 m3
17-Jul-22 KT 8279 2380 4,00 m3
17-Jul-22 KT 8024 2381 4,00 m3
17-Jul-22 KU 8166 2382 4,00 m3
17-Jul-22 KU 8074 2383 4,00 m3
17-Jul-22 KU 8161 2384 4,00 m3
17-Jul-22 KU 8088 2385 4,00 m3
17-Jul-22 KU 8509 2386 4,00 m3
17-Jul-22 KU 8161 2387 4,00 m3
17-Jul-22 KT 8279 2388 4,00 m3
17-Jul-22 KU 8088 2389 4,00 m3
17-Jul-22 KU 8699 2390 4,00 m3
17-Jul-22 KU 8265 2391 4,00 m3
17-Jul-22 KU 9674 2392 4,00 m3
17-Jul-22 KT 8024 2393 4,00 m3
17-Jul-22 KU 8074 2394 4,00 m3
17-Jul-22 KU 8375 2395 4,00 m3
17-Jul-22 KU 8166 2396 4,00 m3
17-Jul-22 KT 8145 2397 4,00 m3
17-Jul-22 KT 8549 2398 4,00 m3
17-Jul-22 KT 8279 2399 4,00 m3
17-Jul-22 KU 8161 2400 4,00 m3
17-Jul-22 KU 8088 2401 4,00 m3
17-Jul-22 KU 8699 2402 4,00 m3
17-Jul-22 KU 8974 2403 4,00 m3
17-Jul-22 KU 8265 2404 4,00 m3
17-Jul-22 KT 8024 2405 4,00 m3
17-Jul-22 KU 8375 2406 4,00 m3
17-Jul-22 KU 8074 2407 4,00 m3
17-Jul-22 KU 8166 2408 4,00 m3
17-Jul-22 KT 8145 2409 4,00 m3
17-Jul-22 KT 8549 2410 4,00 m3
17-Jul-22 KT 8279 2411 4,00 m3
17-Jul-22 KU 8161 2412 4,00 m3
17-Jul-22 KU 9674 2413 4,00 m3
17-Jul-22 KU 8699 2414 4,00 m3
17-Jul-22 KU 8375 2415 4,00 m3
17-Jul-22 KU 8279 2416 4,00 m3
17-Jul-22 KU 8265 2417 4,00 m3
17-Jul-22 KT 8145 2418 4,00 m3
17-Jul-22 KU 8166 2419 4,00 m3
17-Jul-22 KT 8720 2420 4,00 m3
17-Jul-22 KY 8786 2421 4,00 m3
17-Jul-22 KT 8024 2422 4,00 m3
17-Jul-22 KU 8074 2423 4,00 m3
17-Jul-22 KU 8161 2424 4,00 m3
17-Jul-22 KU 9674 2425 4,00 m3
17-Jul-22 KU 8699 2426 4,00 m3
17-Jul-22 KU 8375 2427 4,00 m3
17-Jul-22 KT 8279 2428 4,00 m3
17-Jul-22 KT 8145 2429 4,00 m3
17-Jul-22 KU 8265 2430 4,00 m3
17-Jul-22 KT 8720 2431 4,00 m3
17-Jul-22 KU 8166 2432 4,00 m3
17-Jul-22 KT 8786 2433 4,00 m3
17-Jul-22 KT 8024 2434 4,00 m3
17-Jul-22 KU 8074 2435 4,00 m3
17-Jul-22 KU 8161 2436 4,00 m3
17-Jul-22 KU 9674 2437 4,00 m3
17-Jul-22 KU 8699 2438 4,00 m3
17-Jul-22 KU 8375 2439 4,00 m3

Page 38 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
17-Jul-22 KT 8279 2440 4,00 m3
17-Jul-22 KT 8145 2441 4,00 m3
17-Jul-22 KU 8265 2442 4,00 m3
17-Jul-22 KT 8720 2443 4,00 m3
17-Jul-22 KU 8166 2444 4,00 m3
17-Jul-22 KU 8786 2445 4,00 m3
17-Jul-22 KT 8024 2446 4,00 m3
17-Jul-22 KU 8074 2447 4,00 m3
17-Jul-22 KU 8161 2448 4,00 m3
17-Jul-22 KU 9674 2449 4,00 m3
17-Jul-22 KU 8699 2450 4,00 m3
17-Jul-22 KU 8375 2451 4,00 m3
17-Jul-22 KT 8279 2452 4,00 m3
17-Jul-22 KT 8145 2453 4,00 m3
17-Jul-22 KU 8265 2454 4,00 m3
17-Jul-22 KT 8720 2455 4,00 m3
17-Jul-22 KU 8166 2456 4,00 m3
17-Jul-22 KT 8786 2457 4,00 m3
17-Jul-22 KT 8024 2458 4,00 m3
17-Jul-22 KU 8074 2459 4,00 m3
17-Jul-22 KU 8161 2460 4,00 m3
17-Jul-22 KU 9674 2461 4,00 m3
17-Jul-22 KU 8375 2462 4,00 m3
17-Jul-22 KT 8279 2463 4,00 m3
17-Jul-22 KT 8145 2464 4,00 m3
17-Jul-22 KU 8265 2465 4,00 m3
17-Jul-22 KT 8720 2466 4,00 m3
17-Jul-22 KT 8786 2467 4,00 m3
20-Jul-22 KU 8166 2468 4,00 m3
20-Jul-22 KU 8549 2469 4,00 m3
20-Jul-22 KU 8375 2470 4,00 m3
20-Jul-22 KU 8699\ 2471 4,00 m3
20-Jul-22 KU 8860 2472 4,00 m3
20-Jul-22 KU 8509 2473 4,00 m3
20-Jul-22 KU 8166 2474 4,00 m3
20-Jul-22 KU 8509 2475 4,00 m3
20-Jul-22 KT 8270 2476 4,00 m3
20-Jul-22 KU 8375 2477 4,00 m3
20-Jul-22 KU 8547 2478 4,00 m3
20-Jul-22 KT 8549 2479 4,00 m3
20-Jul-22 KU 8499 2480 4,00 m3
20-Jul-22 KU 8088 2481 4,00 m3
20-Jul-22 KU 8860 2482 4,00 m3
20-Jul-22 KU 8351 2483 4,00 m3
20-Jul-22 KU 8161 2484 4,00 m3
20-Jul-22 KU 8438 2485 4,00 m3
20-Jul-22 KU 8024 2486 4,00 m3
20-Jul-22 KU 8509 2487 4,00 m3
20-Jul-22 KU 8314 2488 4,00 m3
20-Jul-22 KU 8265 2489 4,00 m3
20-Jul-22 KU 8239 2490 4,00 m3
20-Jul-22 KU 9674 2491 4,00 m3
20-Jul-22 KU 8074 2492 4,00 m3
20-Jul-22 KU 8166 2493 4,00 m3
20-Jul-22 KU 9305 2494 4,00 m3
20-Jul-22 KU 8375 2495 4,00 m3
20-Jul-22 KU 8699 2496 4,00 m3
20-Jul-22 KU 8547 2497 4,00 m3
20-Jul-22 KT 8549 2498 4,00 m3
20-Jul-22 KU 8860 2499 4,00 m3
20-Jul-22 KU 8438 2500 4,00 m3
20-Jul-22 KU 8351 2501 4,00 m3
20-Jul-22 KU 8161 2502 4,00 m3
20-Jul-22 KU 9674 2503 4,00 m3

Page 39 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
20-Jul-22 KT 8024 2504 4,00 m3
20-Jul-22 KU 8239 2505 4,00 m3
20-Jul-22 KU 8074 2506 4,00 m3
20-Jul-22 KT 8270 2507 4,00 m3
20-Jul-22 KU 8088 2508 4,00 m3
20-Jul-22 KU 8509 2509 4,00 m3
20-Jul-22 KU 8314 2510 4,00 m3
20-Jul-22 KT 8786 2511 4,00 m3
20-Jul-22 KU 8265 2512 4,00 m3
20-Jul-22 KU 8166 2513 4,00 m3
20-Jul-22 KU 8375 2514 4,00 m3
20-Jul-22 KU 8547 2515 4,00 m3
20-Jul-22 KT 8549 2516 4,00 m3
20-Jul-22 KU 8860 2517 4,00 m3
20-Jul-22 KU 8438 2518 4,00 m3
20-Jul-22 KU 9305 2519 4,00 m3
20-Jul-22 KU 8161 2520 4,00 m3
20-Jul-22 KU 8699 2521 4,00 m3
20-Jul-22 KT 8024 2522 4,00 m3
20-Jul-22 KU 9674 2523 4,00 m3
20-Jul-22 KU 8239 2524 4,00 m3
20-Jul-22 KU 8074 2525 4,00 m3
20-Jul-22 KT 8270 2526 4,00 m3
20-Jul-22 KU 8088 2527 4,00 m3
20-Jul-22 KU 8509 2528 4,00 m3
20-Jul-22 KT 8786 2529 4,00 m3
20-Jul-22 KU 8265 2530 4,00 m3
20-Jul-22 KU 8166 2531 4,00 m3
20-Jul-22 KU 8375 2532 4,00 m3
20-Jul-22 KU 8547 2533 4,00 m3
20-Jul-22 KU 8549 2534 4,00 m3
20-Jul-22 KU 8438 2535 4,00 m3
20-Jul-22 KU 9305 2536 4,00 m3
20-Jul-22 KU 8161 2537 4,00 m3
20-Jul-22 KU 9674 2538 4,00 m3
20-Jul-22 KT 8024 2539 4,00 m3
20-Jul-22 KU 8239 2540 4,00 m3
20-Jul-22 KU 8699 2541 4,00 m3
20-Jul-22 KU 8375 2542 4,00 m3
20-Jul-22 KU 8549 2543 4,00 m3
20-Jul-22 KU 8088 2544 4,00 m3
20-Jul-22 KU 9674 2545 4,00 m3
20-Jul-22 KU 8074 2546 4,00 m3
20-Jul-22 KU 8265 2547 4,00 m3
20-Jul-22 KU 8509 2548 4,00 m3
20-Jul-22 KT 8786 2549 4,00 m3
20-Jul-22 KU 8438 2550 4,00 m3
20-Jul-22 KT 8786 2551 4,00 m3
20-Jul-22 KU 8239 2552 4,00 m3
20-Jul-22 KU 8699 2553 4,00 m3
20-Jul-22 KU 8547 2554 4,00 m3
20-Jul-22 KU 8161 2555 4,00 m3
20-Jul-22 KT 8549 2556 4,00 m3
20-Jul-22 KU 8375 2557 4,00 m3
20-Jul-22 KU 8088 2558 4,00 m3
20-Jul-22 KU 8074 2559 4,00 m3
20-Jul-22 KU 8509 2560 4,00 m3
20-Jul-22 KU 8265 2561 4,00 m3
20-Jul-22 KU 8438 2562 4,00 m3
20-Jul-22 KU 8239 2563 4,00 m3
20-Jul-22 KU 8699 2564 4,00 m3
20-Jul-22 KU 8547 2565 4,00 m3
20-Jul-22 KU 8161 2566 4,00 m3
20-Jul-22 KU 8375 2567 4,00 m3

Page 40 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
20-Jul-22 KT 8549 2568 4,00 m3
20-Jul-22 KU 8088 2569 4,00 m3
20-Jul-22 KU 8509 2570 4,00 m3
20-Jul-22 KU 8074 2571 4,00 m3
20-Jul-22 KU 8265 2572 4,00 m3
20-Jul-22 KU 8438 2573 4,00 m3
20-Jul-22 KT 8786 2574 4,00 m3
20-Jul-22 KU 8239 2575 4,00 m3
20-Jul-22 KU 8161 2576 4,00 m3
20-Jul-22 KU 8375 2577 4,00 m3
20-Jul-22 KU 8088 2578 4,00 m3
20-Jul-22 KU 8509 2579 4,00 m3
20-Jul-22 KU 8074 2580 4,00 m3
20-Jul-22 KU 8265 2581 4,00 m3
20-Jul-22 KT 8786 2582 4,00 m3
20-Jul-22 KU 8239 2583 4,00 m3
20-Jul-22 KU 8161 2584 4,00 m3
20-Jul-22 KU 8375 2585 4,00 m3
20-Jul-22 KU 8088 2586 4,00 m3
20-Jul-22 KU 8509 2587 4,00 m3
20-Jul-22 KT 8786 2588 4,00 m3
20-Jul-22 KU 8239 2589 4,00 m3
21-Jul-22 KU 8375 2590 4,00 m3
21-Jul-22 KU 8265 2591 4,00 m3
21-Jul-22 KT 8549 2592 4,00 m3
21-Jul-22 KU 8161 2593 4,00 m3
21-Jul-22 KU 8699 2594 4,00 m3
21-Jul-22 KU 9305 2595 4,00 m3
21-Jul-22 KU 8860 2596 4,00 m3
21-Jul-22 KU 8509 2597 4,00 m3
21-Jul-22 KT 8786 2598 4,00 m3
21-Jul-22 KU 8375 2599 4,00 m3
21-Jul-22 KU 8438 2600 4,00 m3
21-Jul-22 KT 82 79 2601 4,00 m3
21-Jul-22 KU 8161 2602 4,00 m3
21-Jul-22 KT 8549 2603 4,00 m3
21-Jul-22 KU 8166 2604 4,00 m3
21-Jul-22 KU 8074 2605 4,00 m3
21-Jul-22 KU 9305 2606 4,00 m3
21-Jul-22 KU 8699 2607 4,00 m3
21-Jul-22 KU 8239 2608 4,00 m3
21-Jul-22 KU 8860 2609 4,00 m3
21-Jul-22 KU 8509 2610 4,00 m3
21-Jul-22 KT 8786 2611 4,00 m3
21-Jul-22 KT 8024 2612 4,00 m3
21-Jul-22 KU 8438 2613 4,00 m3
21-Jul-22 KU 8375 2614 4,00 m3
21-Jul-22 KT 8279 2615 4,00 m3
21-Jul-22 KU 8161 2616 4,00 m3
21-Jul-22 KT 8549 2617 4,00 m3
21-Jul-22 KU 8166 2618 4,00 m3
21-Jul-22 KU 9305 2619 4,00 m3
21-Jul-22 KU 8547 2620 4,00 m3
21-Jul-22 KU 8265 2621 4,00 m3
21-Jul-22 KU 8074 2622 4,00 m3
21-Jul-22 KU 8699 2623 4,00 m3
21-Jul-22 KU 9674 2624 4,00 m3
21-Jul-22 KU 8239 2625 4,00 m3
21-Jul-22 KU 8860 2626 4,00 m3
21-Jul-22 KU 8509 2627 4,00 m3
21-Jul-22 KU 8786 2628 4,00 m3
21-Jul-22 KU 8438 2629 4,00 m3
21-Jul-22 KU 8375 2630 4,00 m3
21-Jul-22 KT 8279 2631 4,00 m3

Page 41 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
21-Jul-22 KU 8161 2632 4,00 m3
21-Jul-22 KU 8314 2633 4,00 m3
21-Jul-22 KT 8549 2634 4,00 m3
21-Jul-22 KU 8166 2635 4,00 m3
21-Jul-22 KU 8547 2636 4,00 m3
21-Jul-22 KT 8024 2637 4,00 m3
21-Jul-22 KU 8265 2638 4,00 m3
21-Jul-22 2639
21-Jul-22 KU 8074 2640 4,00 m3
21-Jul-22 KU 8509 2641 4,00 m3
21-Jul-22 KU 8438 2642 4,00 m3
21-Jul-22 KU 8699 2643 4,00 m3
21-Jul-22 KT 8549 2644 4,00 m3
21-Jul-22 KT 8375 2645 4,00 m3
21-Jul-22 KT 8699 2646 4,00 m3
21-Jul-22 KU 8547 2647 4,00 m3
21-Jul-22 KU 8166 2648 4,00 m3
21-Jul-22 KU 9305 2649 4,00 m3
21-Jul-22 KT 8549 2650 4,00 m3
21-Jul-22 KU 8375 2651 4,00 m3
21-Jul-22 KU 8699 2652 4,00 m3
21-Jul-22 KU 8547 2653 4,00 m3
21-Jul-22 KU 9305 2654 4,00 m3
21-Jul-22 KU 8166 2655 4,00 m3
21-Jul-22 KT 8549 2656 4,00 m3
21-Jul-22 KU 8547 2657 4,00 m3
21-Jul-22 KT 8786 2658 4,00 m3
21-Jul-22 KU 8699 2659 4,00 m3
21-Jul-22 KU 8547 2660 4,00 m3
21-Jul-22 KU 9305 2661 4,00 m3
21-Jul-22 KU 8166 2662 4,00 m3
21-Jul-22 KT 8549 2663 4,00 m3
21-Jul-22 KU 8509 2664 4,00 m3
21-Jul-22 KU 8375 2665 4,00 m3
21-Jul-22 KU 8351 2666 4,00 m3
21-Jul-22 KU 8166 2667 4,00 m3
21-Jul-22 KU 8699 2668 4,00 m3
21-Jul-22 KT 8549 2669 4,00 m3
21-Jul-22 KU 8509 2670 4,00 m3
21-Jul-22 KU 8375 2671 4,00 m3
21-Jul-22 KU 8351 2672 4,00 m3
21-Jul-22 KU 9305 2673 4,00 m3
21-Jul-22 KT 8786 2674 4,00 m3
21-Jul-22 KU 8166 2675 4,00 m3
21-Jul-22 KU 8088 2676 4,00 m3
21-Jul-22 KT 8549 2677 4,00 m3
21-Jul-22 KU 8699 2678 4,00 m3
21-Jul-22 KU 8509 2679 4,00 m3
21-Jul-22 KU 8375 2680 4,00 m3
21-Jul-22 KU 8351 2681 4,00 m3
21-Jul-22 KU 9305 2682 4,00 m3
21-Jul-22 KU 8166 2683 4,00 m3
21-Jul-22 KU 8088 2684 4,00 m3
21-Jul-22 KU 8699 2685 4,00 m3
21-Jul-22 KT 8549 2686 4,00 m3
21-Jul-22 KU 8509 2687 4,00 m3
21-Jul-22 KU 8375 2688 4,00 m3
21-Jul-22 KU 9305 2689 4,00 m3
21-Jul-22 KT 8549 2690 4,00 m3
21-Jul-22 KU 8509 2691 4,00 m3
21-Jul-22 KU 8699 2692 4,00 m3
21-Jul-22 KU 8375 2693 4,00 m3
21-Jul-22 KU 8088 2694 4,00 m3
21-Jul-22 KU 8166 2695 4,00 m3

Page 42 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
21-Jul-22 KT 8786 2696 4,00 m3
21-Jul-22 KT 8549 2697 4,00 m3
21-Jul-22 KU 9305 2698 4,00 m3
21-Jul-22 KU 8509 2699 4,00 m3
21-Jul-22 KU 8438 2700 4,00 m3
21-Jul-22 KU 8699 2701 4,00 m3
21-Jul-22 KU 9674 2702 4,00 m3
21-Jul-22 KU 8375 2703 4,00 m3
21-Jul-22 KU 8088 2704 4,00 m3
21-Jul-22 KU 8161 2705 4,00 m3
21-Jul-22 KU 8265 2706 4,00 m3
21-Jul-22 KU 8166 2707 4,00 m3
21-Jul-22 KT 8786 2708 4,00 m3
21-Jul-22 KT 8549 2709 4,00 m3
21-Jul-22 KU 8509 2710 4,00 m3
21-Jul-22 KU 9305 2711 4,00 m3
21-Jul-22 KU 8438 2712 4,00 m3
21-Jul-22 KU 8699 2713 4,00 m3
21-Jul-22 KT 8024 2714 4,00 m3
21-Jul-22 KU 8375 2715 4,00 m3
21-Jul-22 KU 8088 2716 4,00 m3
21-Jul-22 KU 8161 2717 4,00 m3
21-Jul-22 KU 8265 2718 4,00 m3
21-Jul-22 KU 8166 2719 4,00 m3
21-Jul-22 KU 8074 2720 4,00 m3
21-Jul-22 KT 8786 2721 4,00 m3
21-Jul-22 KT 8549 2722 4,00 m3
21-Jul-22 KU 8509 2723 4,00 m3
21-Jul-22 KU 9305 2724 4,00 m3
21-Jul-22 KU 8438 2725 4,00 m3
21-Jul-22 KU 8699 2726 4,00 m3
21-Jul-22 KT 8024 2727 4,00 m3
21-Jul-22 KU 8375 2728 4,00 m3
21-Jul-22 KU 8088 2729 4,00 m3
21-Jul-22 KU 8161 2730 4,00 m3
21-Jul-22 KU 8265 2731 4,00 m3
21-Jul-22 KU 8074 2732 4,00 m3
21-Jul-22 KT 8786 2733 4,00 m3
21-Jul-22 KU 8509 2734 4,00 m3
21-Jul-22 KU 8088 2735 4,00 m3
21-Jul-22 KU 8161 2736 4,00 m3
21-Jul-22 KU 8074 2737 4,00 m3
22-Jul-22 KU 8438 2738 4,00 m3
22-Jul-22 KU 8509 2739 4,00 m3
22-Jul-22 KU 8375 2740 4,00 m3
22-Jul-22 KU 8549 2741 4,00 m3
22-Jul-22 KU 8161 2742 4,00 m3
22-Jul-22 KU 8699 2743 4,00 m3
22-Jul-22 KU 8166 2744 4,00 m3
22-Jul-22 KU 8265 2745 4,00 m3
22-Jul-22 KU 9674 2746 4,00 m3
22-Jul-22 KU 8239 2747 4,00 m3
22-Jul-22 KU 8509 2748 4,00 m3
22-Jul-22 KT 8024 2749 4,00 m3
22-Jul-22 KU 8438 2750 4,00 m3
22-Jul-22 KU 8375 2751 4,00 m3
22-Jul-22 KU 8549 2752 4,00 m3
22-Jul-22 KU 8161 2753 4,00 m3
22-Jul-22 KU 8265 2754 4,00 m3
22-Jul-22 KU 8166 2755 4,00 m3
22-Jul-22 KU 8699 2756 4,00 m3
22-Jul-22 KU 9674 2757 4,00 m3
22-Jul-22 KU 8509 2758 4,00 m3
22-Jul-22 KT 8024 2759 4,00 m3

Page 43 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
22-Jul-22 KU 8438 2760 4,00 m3
22-Jul-22 KU 8375 2761 4,00 m3
22-Jul-22 KU 8549 2762 4,00 m3
22-Jul-22 KU 8161 2763 4,00 m3
22-Jul-22 KU 8265 2764 4,00 m3
22-Jul-22 KU 8161 2765 4,00 m3
22-Jul-22 KU 9674 2766 4,00 m3
22-Jul-22 KU 8509 2767 4,00 m3
22-Jul-22 KT 8024 2768 4,00 m3
22-Jul-22 KU 8438 2769 4,00 m3
22-Jul-22 KU 8699 2770 4,00 m3
22-Jul-22 KU 8375 2771 4,00 m3
22-Jul-22 KU 8074 2772 4,00 m3
22-Jul-22 KU 8549 2773 4,00 m3
22-Jul-22 KU 8161 2774 4,00 m3
22-Jul-22 KU 8265 2775 4,00 m3
22-Jul-22 KU 8161 2776 4,00 m3
22-Jul-22 KU 8786 2777 4,00 m3
22-Jul-22 KU 9674 2778 4,00 m3
22-Jul-22 KU 8088 2779 4,00 m3
22-Jul-22 KU 8509 2780 4,00 m3
22-Jul-22 KU 8024 2781 4,00 m3
22-Jul-22 KU 8438 2782 4,00 m3
22-Jul-22 KU 8699 2783 4,00 m3
22-Jul-22 KU 8375 2784 4,00 m3
22-Jul-22 KU 8074 2785 4,00 m3
22-Jul-22 KU 8549 2786 4,00 m3
22-Jul-22 KU 8161 2787 4,00 m3
22-Jul-22 KU 8166 2788 4,00 m3
22-Jul-22 KT 8786 2789 4,00 m3
22-Jul-22 KU 9674 2790 4,00 m3
22-Jul-22 KU 8088 2791 4,00 m3
22-Jul-22 KU 8509 2792 4,00 m3
22-Jul-22 KT 8024 2793 4,00 m3
22-Jul-22 KU 8438 2794 4,00 m3
22-Jul-22 KU 8699 2795 4,00 m3
22-Jul-22 KU 8375 2796 4,00 m3
22-Jul-22 KU 8074 2797 4,00 m3
22-Jul-22 KU 8161 2798 4,00 m3
22-Jul-22 KU 8549 2799 4,00 m3
22-Jul-22 KU 8438 2800 4,00 m3
22-Jul-22 KT 8024 2801 4,00 m3
22-Jul-22 KU 8375 2802 4,00 m3
22-Jul-22 KT 8150 2803 4,00 m3
22-Jul-22 KU 9674 2804 4,00 m3
22-Jul-22 KU 8074 2805 4,00 m3
22-Jul-22 KU 8509 2806 4,00 m3
22-Jul-22 KU 8166 2807 4,00 m3
22-Jul-22 KU 8239 2808 4,00 m3
22-Jul-22 KU 8786 2809 4,00 m3
22-Jul-22 KU 8088 2810 4,00 m3
22-Jul-22 KU 8699 2811 4,00 m3
22-Jul-22 KU 8549 2812 4,00 m3
22-Jul-22 KU 8161 2813 4,00 m3
22-Jul-22 KT 8161 2814 4,00 m3
22-Jul-22 KU 8854 2815 4,00 m3
22-Jul-22 KU 8438 2816 4,00 m3
22-Jul-22 KU 8375 2817 4,00 m3
22-Jul-22 KT 8150 2818 4,00 m3
22-Jul-22 KT 8024 2819 4,00 m3
22-Jul-22 KU 9674 2820 4,00 m3
22-Jul-22 KU 8074 2821 4,00 m3
22-Jul-22 KU 8509 2822 4,00 m3
22-Jul-22 KU 8239 2823 4,00 m3

Page 44 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
22-Jul-22 KU 8166 2824 4,00 m3
22-Jul-22 KT 8786 2825 4,00 m3
22-Jul-22 KU 8088 2826 4,00 m3
22-Jul-22 KU 8549 2827 4,00 m3
22-Jul-22 KU 8161 2828 4,00 m3
22-Jul-22 KU 8854 2829 4,00 m3
22-Jul-22 KU 8438 2830 4,00 m3
22-Jul-22 KU 8375 2831 4,00 m3
22-Jul-22 KT 8150 2832 4,00 m3
22-Jul-22 KU 9674 2833 4,00 m3
22-Jul-22 KU 8074 2834 4,00 m3
22-Jul-22 KU 8509 2835 4,00 m3
22-Jul-22 KU 8239 2836 4,00 m3
22-Jul-22 KU 8166 2837 4,00 m3
22-Jul-22 KU 8375 2838 4,00 m3
22-Jul-22 KU 8088 2839 4,00 m3
22-Jul-22 KT 8786 2840 4,00 m3
22-Jul-22 KT 8549 2841 4,00 m3
22-Jul-22 KU 8161 2842 4,00 m3
22-Jul-22 KU 8854 2843 4,00 m3
22-Jul-22 KU 8438 2844 4,00 m3
22-Jul-22 KU 9674 2845 4,00 m3
22-Jul-22 KU 8074 2846 4,00 m3
22-Jul-22 KU 8509 2847 4,00 m3
22-Jul-22 KU 8166 2848 4,00 m3
22-Jul-22 KU 8088 2849 4,00 m3
22-Jul-22 KT 8786 2850 4,00 m3
22-Jul-22 KU 8239 2851 4,00 m3
22-Jul-22 KU 8161 2852 4,00 m3
22-Jul-22 KU 8854 2853 4,00 m3
22-Jul-22 KU 8074 2854 4,00 m3
22-Jul-22 KU 8509 2855 4,00 m3
22-Jul-22 KT8786 2856 4,00 m3
23-Jul-22 KU 8509 2857 4,00 m3
23-Jul-22 KU 8161 2858 4,00 m3
23-Jul-22 KU 8375 2859 4,00 m3
23-Jul-22 KU 8438 2860 4,00 m3
23-Jul-22 KU 9674 2861 4,00 m3
23-Jul-22 KT 8549 2862 4,00 m3
23-Jul-22 KU 8699 2863 4,00 m3
23-Jul-22 KU 8239 2864 3,00 m3
23-Jul-22 KU 9305 2865 4,00 m3
23-Jul-22 KU 8166 2866 3,00 m3
23-Jul-22 KU 8509 2867 3,00 m3
23-Jul-22 KT 8024 2868 3,00 m3
23-Jul-22 KU 8161 2869 3,00 m3
23-Jul-22 KU 8375 2870 3,00 m3
23-Jul-22 KU 8438 2871 4,00 m3
23-Jul-22 KU 9674 2872 4,00 m3
23-Jul-22 KT 8549 2873 4,00 m3
23-Jul-22 KU 8699 2874 4,00 m3
23-Jul-22 KU 8239 2875 4,00 m3
23-Jul-22 KU 9305 2876 4,00 m3
23-Jul-22 KU 8166 2877 4,00 m3
23-Jul-22 KU 8509 2878 4,00 m3
23-Jul-22 KT 8024 2879 4,00 m3
23-Jul-22 KU 8161 2880 4,00 m3
23-Jul-22 KU 8375 2881 4,00 m3
23-Jul-22 KU 9674 2882 4,00 m3
23-Jul-22 KU 8438 2883 4,00 m3
23-Jul-22 KT 8549 2884 4,00 m3
23-Jul-22 KU 8699 2885 4,00 m3
23-Jul-22 KU 9305 2886 4,00 m3
23-Jul-22 KU 8509 2887 4,00 m3

Page 45 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
23-Jul-22 KT 8024 2888 4,00 m3
23-Jul-22 KU 8161 2889 4,00 m3
23-Jul-22 KU 8375 2890 4,00 m3
23-Jul-22 KU 8166 2891 4,00 m3
23-Jul-22 KU 8239 2892 4,00 m3
23-Jul-22 KT 8549 2893 4,00 m3
23-Jul-22 KU 8438 2894 4,00 m3
23-Jul-22 KU 8699 2895 4,00 m3
23-Jul-22 KU 9305 2896 4,00 m3
23-Jul-22 KU 8509 2897 4,00 m3
23-Jul-22 KU 8161 2898 4,00 m3
23-Jul-22 KU 8166 2899 4,00 m3
23-Jul-22 KU 8375 2900 4,00 m3
23-Jul-22 KU 9674 2901 4,00 m3
23-Jul-22 KT 8024 2902 4,00 m3
23-Jul-22 KU 8438 2903 4,00 m3
23-Jul-22 KU 8161 2904 4,00 m3
23-Jul-22 KU 8239 2905 4,00 m3
23-Jul-22 KU 8375 2906 4,00 m3
23-Jul-22 KU 9305 2907 4,00 m3
23-Jul-22 KU 8166 2908 4,00 m3
23-Jul-22 KU 9674 2909 4,00 m3
23-Jul-22 KU 8689 2910 4,00 m3
23-Jul-22 KT 8549 2911 4,00 m3
23-Jul-22 KU 8509 2912 4,00 m3
23-Jul-22 KU 8438 2913 4,00 m3
23-Jul-22 KU 8161 2914 4,00 m3
23-Jul-22 KT 8024 2915 4,00 m3
23-Jul-22 KU 8375 2916 4,00 m3
23-Jul-22 KU 8239 2917 4,00 m3
23-Jul-22 KU 9305 2918 4,00 m3
23-Jul-22 KU 8166 2919 4,00 m3
23-Jul-22 KU 8699 2920 4,00 m3
23-Jul-22 KU 9674 2921 4,00 m3
23-Jul-22 KT 8549 2922 4,00 m3
23-Jul-22 KU 8509 2923 4,00 m3
23-Jul-22 KU 8438 2924 4,00 m3
23-Jul-22 KU 8074 2925 4,00 m3
23-Jul-22 KU 8161 2926 4,00 m3
23-Jul-22 KT 8786 2927 4,00 m3
23-Jul-22 KU 8375 2928 4,00 m3
23-Jul-22 KT 8024 2929 4,00 m3
23-Jul-22 KU 8239 2930 4,00 m3
23-Jul-22 KU 8166 2931 4,00 m3
23-Jul-22 KU 9305 2932 4,00 m3
23-Jul-22 KU 9674 2933 4,00 m3
23-Jul-22 KU 8099 2934 4,00 m3
23-Jul-22 KT 8549 2935 4,00 m3
23-Jul-22 KU 8438 2936 4,00 m3
23-Jul-22 KU 8509 2937 4,00 m3
23-Jul-22 KU 8860 2938 4,00 m3
23-Jul-22 KU 8074 2939 4,00 m3
23-Jul-22 KU 8161 2940 4,00 m3
23-Jul-22 KT 8786 2941 4,00 m3
23-Jul-22 KU 8375 2942 4,00 m3
23-Jul-22 KT 8024 2943 4,00 m3
23-Jul-22 KU 8239 2944 4,00 m3
23-Jul-22 KU 9674 2945 4,00 m3
23-Jul-22 KT 8549 2946 4,00 m3
23-Jul-22 KU 8166 2947 4,00 m3
23-Jul-22 KU 9305 2948 4,00 m3
23-Jul-22 KU 8509 2949 4,00 m3
23-Jul-22 KU 8438 2950 4,00 m3
23-Jul-22 KU 8860 2951 4,00 m3

Page 46 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
23-Jul-22 KU 8074 2952 4,00 m3
23-Jul-22 KU 8161 2953 4,00 m3
23-Jul-22 KT 8786 2954 4,00 m3
23-Jul-22 KU 8375 2955 4,00 m3
23-Jul-22 KT 8024 2956 4,00 m3
23-Jul-22 KU 8239 2957 4,00 m3
23-Jul-22 KT 8549 2958 4,00 m3
23-Jul-22 KU 8166 2959 4,00 m3
23-Jul-22 KU 9674 2960 4,00 m3
23-Jul-22 KU 9305 2961 4,00 m3
23-Jul-22 KU 8509 2962 4,00 m3
23-Jul-22 KU 8438 2963 4,00 m3
23-Jul-22 KU 8166 2964 4,00 m3
23-Jul-22 KU 8549 2965 4,00 m3
23-Jul-22 KU 8834 2966 4,00 m3
23-Jul-22 KU 9674 2967 4,00 m3
23-Jul-22 KU 8074 2968 4,00 m3
23-Jul-22 KT 8279 2969 4,00 m3
23-Jul-22 KU 8375 2970 4,00 m3
23-Jul-22 KU 8509 2971 4,00 m3
23-Jul-22 KU 8088 2972 4,00 m3
23-Jul-22 KT 8024 2973 4,00 m3
23-Jul-22 KT 8786 2974 4,00 m3
23-Jul-22 KU 8438 2975 4,00 m3
23-Jul-22 KU 8166 2976 4,00 m3
23-Jul-22 KU 8239 2977 4,00 m3
23-Jul-22 KU 8161 2978 4,00 m3
23-Jul-22 KT 8549 2979 4,00 m3
23-Jul-22 KU 8854 2980 4,00 m3
KU 9674 2981 4,00 m3
KU 8074 2982 4,00 m3
KT 8279 2983 4,00 m3
KU 8375 2984 4,00 m3
KU 8509 2985 4,00 m3
KU 8088 2986 4,00 m3
KT 8024 2987 4,00 m3
KT 8786 2988 4,00 m3
KU 8166 2989 4,00 m3
KU 8438 2990 4,00 m3
KU 8239 2991 4,00 m3
KU 8161 2992 4,00 m3
KT 8549 2993 4,00 m3
KU 8854 2994 4,00 m3
KU 9674 2995 4,00 m3
KU 8074 2996 4,00 m3
KT 8279 2997 4,00 m3
KU 8375 2998 4,00 m3
KU 8509 2999 4,00 m3
KU 8088 3000 4,00 m3
KT 8024 3001 4,00 m3
KT 8786 3002 4,00 m3
KU 8438 3003 4,00 m3
KU 8166 3004 4,00 m3
KU 8239 3005 4,00 m3
KU 8161 3006 4,00 m3
KT 8549 3007 4,00 m3
KU 8854 3008 4,00 m3
KU 8074 3009 4,00 m3
KT 8279 3010 4,00 m3
KU 8375 3011 4,00 m3
KU 8509 3012 4,00 m3
KU 8088 3013 4,00 m3
KT 8024 3015 4,00 m3
KT 8786 3016 4,00 m3

Page 47 of 48
MONITORING MOS (MATERIAL ON SITE) - DETAIL
BAHAN/PERALATAN MASUK LOKASI
TANAH TIMBUNAN
SUPPLIER : PT. SAKINAH JAYA ABADI
PEKERJAAN : PEKERJAAN PEMBANGUNAN FASILITAS PELABUHAN LAUT BUNYU
LOKASI : PULAU BUNYU KALIMANTAN UTARA
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2022

No. Polisi No. Nama


No. Hari Tanggal Jam Keterangan
Kendaraan Surat Jalan Sopir/Supir Volume Sat.
KU 8438 3017 4,00 m3
KU 8166 3018 4,00 m3
KU 8161 3019 4,00 m3
KT 8549 3020 4,00 m3
KU 8854 3021 4,00 m3
KU 8074 3022 4,00 m3
KT 8279 3023 4,00 m3
KU 8239 3024 4,00 m3
KU 8375 3025 4,00 m3
KU 8509 3026 4,00 m3
KU 8088 3027 4,00 m3
KT 8024 3028 4,00 m3
KT 8786 3029 4,00 m3
KU 8161 3030 4,00 m3
KU 8166 3031 4,00 m3
KU 8438 3032 4,00 m3
KT 8549 3033 4,00 m3
KU 8854 3034 4,00 m3
KU 8239 3035 4,00 m3

Jumlah 12067,79 m3

Catatan : Monitoring Oleh,


1 Yang Disebut Material Disini Mencakup Bahan & Peralatan
2 Monitoring MOS - Detail ini dibuat per jenis material (bahan/peralatan)

(MANJIJIRANG)
PIC (Personal In Charge)

Page 48 of 48