Professional Documents
Culture Documents
https://www.emerald.com/insight/0969-9988.htm
1. Introduction
The construction industry contributes positively to the growth of the socio-economic
development of a nation, especially in developing countries. Generally, a project is considered
successful if it is completed within a stated cost or budget, used according to the target date,
and there is a high level of satisfaction concerning the project outcome among the project
participants. However, one of the main problems hampering the successful completion of
most projects in the construction industry is cost overruns that directly affect the progress of
the task, sometimes leading to the abandonment of projects. According to Flyvbjerg (2009),
the average cost overrun for large-scale infrastructure projects ranges from 20.4% to 44.7%;
and nine out of 10 projects have cost overruns worldwide. The literature review shows that
most developing countries suffer from everyday causes of delay and cost overrun because of
economic difficulties, which usually lead to tight financial in construction projects in these
countries.
Engineering, Construction and
Iran is a developing country, and the construction industry is one of its critical economic Architectural Management
sectors. So, it has a significant portion in the formation of the capital city acting as an Vol. 30 No. 7, 2023
pp. 2739-2766
economic stimulus due to its numerous connections with different economic sectors. Iran’s © Emerald Publishing Limited
0969-9988
Central Bank announced that 4.7% of GDP is related to the construction sector in 2020, and DOI 10.1108/ECAM-05-2021-0445
ECAM the share of this part of the entire country’s budget has been increased from 17.5% in 2003 to
30,7 32% in 2016.
Although in Iran, a lot of money has been spent on construction, the industry faces many
challenges, such as delays in on-time completion of the project and expenditure exceeding the
budget. Construction (especially building) projects have problems with construction techniques
and management as well as limitations of funds and time. Indeed, the critical feature of
developing decision support systems specifically designed to facilitate the decision-making
2740 process in the Iranian construction sector has not received sufficient attention (Samarghandi
et al., 2016). According to the results of recent studies (i.e. Dabirian et al., 2020; Balali et al., 2020),
projects’ execution and deliverable performance in Iran decreased dramatically because of the
projects’ poor time and cost performance. Based on a study conducted by Heravi and
Mohammadian (2017), 24% of the projects in Iran have encountered more than 25% of cost
overruns and delays. Also, in a similar study, Samarghandi et al. (2016) interpreted that the
average delay per year in the Iranian construction projects is 5.9 months, and the overall cost
overrun is 15.4%. So, the results of the previous studies show that cost overrun in the
construction industry is one of the problems that many contributors face in Iran.
Among the studies conducted in Iran, to rank the causes of cost overrun in the
construction industry, we found five surveys, three of which have focused on the specific
types of construction buildings (Balali et al., 2020: mega-hospital construction projects,
Mirzaei Matin, 2016: water construction projects, Derakhshanalavijeh and Teixeira, 2017:
Gas-Oil construction industry). Two other studies have been published in Persian. Amini et al.
(2021) investigated the causes of cost overrun only in one of the cities of Iran (Mashhad), and
Dabirian et al. (2020) ranked the causes of cost overrun with a small sample size (36 experts).
Therefore, there is still a need to investigate the issue of cost overrun in Iranian construction
projects in a larger-scale study. To this end, the present paper aims to identify and rank the
leading causes of cost overrun in building construction projects in Iran with a broader
study scale.
Given that no study comprehensively discussed the causes of cost overrun in Asian
countries, the current study intends to clear up the missing gaps of the proposed literature.
In addition, it aids the project managers in developing a comprehensive list of potential
causes that shall be managed to avoid the consequences of cost overruns. Indeed,
understanding common causes among these countries, despite economic, political, and
social differences, could be helpful in future research. The framework of this study is
shown in Figure 1.
Unfortunately, the construction industry operators in Iran have limited resources for
addressing so many contributors to the cost overruns. Due to its strategic importance to the
construction operators, it is essential to identify the fewest number of factors having the most
outstanding contribution to the cost overruns. This knowledge can help the industry
operators focus their efforts and available resources on addressing the most influential
contributor for maximum results, which is, in turn, the study’s primary objective. Also, a
comparison of the results of this paper with those of similar studies conducted in Iran can help
different parties to understand the critical causes of cost overruns for reducing their impacts
on project performance. Furthermore, the identification and ranking of such factors can assist
owners, contractors, and the project management team in the following:
(1) Preparing a more realistic and accurate project cost and schedule.
(2) Completing the project on time with the projected budget.
(3) Taking the necessary steps and actions in advance to avoid cost overrun.
(4) Giving more attention to the most crucial factors.
Causes of cost
overruns
2741
Figure 1.
Study framework
2. Literature review
2.1 Definition of cost overrun
There are various definitions of cost overrun across the world. For example, Enrica et al.
(2021) described project cost overrun as the difference between the final actual cost of a
construction project at completion and the contract amount agreed by and between the
owner and the contractor during the signing of the contract. Flyvbjerg et al. (2002)
interpreted cost overrun as the difference between forecasted and actual construction costs.
The difference may be measured in absolute or relative terms. In complete terms, cost
overrun is calculated as the actual minus estimated cost. In relative terms, overrun is
measured as (1) actual cost in percent of estimated cost or (2) the ratio of actual divided by
estimated cost. Size, frequency, and distribution of cost overrun should all be measured as
part of measuring cost overrun for a specific investment type (Flyvbjerg et al., 2018). The
budget at the decision to build is used as the reference for determining the overrun that may
be incurred, and actual construction costs are defined as accounted construction costs at the
time of project completion.
Cost overrun is also called cost acceleration, cost increment, cost increase, cost escalation,
or budget overrun.
ECAM 2.2 Effects of cost overrun
30,7 In many countries, attempts have been made to assess the scale of cost overruns in
construction projects. Some studies identified the most critical factors causing cost overrun in
several countries and various project types. In contrast, other studies discussed the influence
of these factors on the success and failure of construction projects.
The World Bank has announced that 30–40% of construction projects face cost overruns
globally (Balali et al., 2020). The study of Prajapati et al. study (2016) was an assessment of the
2742 causes and effects of cost overrun on construction projects in India. The study found that cost
overruns ranged between zero and 120% of contract amounts. Shehu et al. (2014) found that
more than half of Malaysian construction projects (55%) experienced cost overruns, and
public sector projects performed better than private sector projects. Senouci et al. (2016), in
their study on the increase of term and cost in 122 construction contracts in Qatar, showed
that 54% had their prices increased and 72% of their deadlines increased. According to
Samarghandi et al. (2016), the average delay per year in the Iranian construction projects is
5.9 months (one can expect 11.8 months of delay if the original project duration is 24 months),
and the overall cost overrun is 15.4%. The findings of some studies on construction cost
overruns are shown in Table 1 below.
The data in the table shows that the amount of cost overrun varies according to the location.
Only by comparing ten studies, a range of 4.5–214% increase in construction costs is observed.
2.3 Factors influencing the cost overrun during the construction stages
The body of knowledge has attracted myriads of studies on cost overrun. The majority of
which have reported the causes of cost overrun in different construction project types in
various regions and countries.
Ahady et al. (2017) investigated the cost overrun problems for building construction
projects in Afghanistan. For this purpose, a quantitative survey was performed among
clients, contractors, and consultants representatives involved in building construction
projects in Afghanistan. They found that the crucial sources for cost overruns are market
inflation, corruption, shortage of supply of construction material required, and fluctuations in
the cost of building. Abusafiya and Suliman (2017) identified the major causes of cost overrun
in the Bahrain construction sector. A list of the causes was collected through an extensive
literature review, historical construction projects records, and expert opinions—a
questionnaire survey conducted with representatives from local contracting, consulting,
and client firms. The results showed that frequent design changes, mistakes during
construction, and schedule delays were considered the most important causes of cost overrun.
Ramabhadran (2018) investigated the various factors influencing cost overrun and the Causes of cost
mitigation measures in the UAE construction industry. The most critical causes of cost overruns
overrun are poor productivity, insufficient early planning, delayed completion, and lack of
skilled resources and motivation. He found that the most effective mitigation measures for
cost overrun are detailed estimation, brainstorming sessions for cost control, procurement
planning, mobilizing resources at the right time, and training of workers. In a similar study
conducted in the UAE, Johnson and Babu (2018) used a concurrent mixed-methods approach,
a questionnaire, and an interview with UAE construction professionals, to analyze the 2743
significant causes of time and cost performance. They stated that the top five causes of cost
overrun are design variation, poor cost estimation, delay in client’s decision making, financial
constraints of the client, and inappropriate procurement method.
Rezaei and Jalal (2018) carried out a study to determine the causes of delay and cost-overrun
in the construction industry of Northern Iraq. Sixty-one delay factors and forty-two cost
overrun factors were considered in this study. The three major causes of delays were found as
security measures, the high number of sub-contracts by the same contractor, and poor labor
productivity. Similarly, three major factors causing cost overrun were scarce labor and skill
availability, inappropriate contractor policies, and domination of the construction industry by
foreign firms and aids. Bekr (2015) identified the causes of cost overrun in construction projects
in Jordan. A comprehensive literature review was made to carry out the study. A questionnaire
survey was conducted to find the causes of cost overrun related to client, consultant,
contractor, financial management, resources, and external factors. He found that the most
important causes were: Schedule delay, frequent design changes, additional works, mistakes
in design, inadequate planning and scheduling, and inflation/prices fluctuation.
Among the studies conducted in Iran, Derakhshanalavijeh and Teixeira (2017) evaluated the
relative importance of the significant factors contributing to the Gas-Oil construction industry
of Iran. Their findings revealed that the leading causes of cost overrun include inaccurate cost
estimations, improper planning, frequent design changes, inadequate labor, and inflation of
prices. Balali et al. (2020) ranked cost overrun factors in mega-hospital construction projects of
Iran. The results illustrated that rework, not allocating sufficient budget from the government
during the project and lack of supervisors’ technical knowledge were the most crucial factors in
contractors, employers, and consultant groups, respectively. Mirzai Matin (2016) identified the
practical factors for cost overrun and time delay in water construction projects in Iran. The
results showed that the top issues in cost overrun were: bureaucracy in bidding method,
inflation, governments economic condition, not enough survey and information before design,
difficulties in owners’ monthly payment, and instability of the material prices. Dabirian et al.
(2020) stated that lack of cash flow, lack of technical and specialized personnel, and the reworks
are the most affecting factors on the cost overrun in Iran. In a similar study, Amini et al. (2021)
found that causative factors of cost overrun in construction projects in Iran are poor project
management, improper planning, inflation, and mistakes during construction.
Based on an intensive literature review, the top ten rankings of building construction cost
overrun factors in various Asian countries are summarized in Table A1. This table shows 59
leading causes of cost overrun according to 38 articles conducted in 13 Asian countries,
including Iran, Turkey, Malaysia, Pakistan, India, Bahrain, Jordan, Iraq, Afghanistan,
Vietnam, UAE, Saudi Arabia, and Palestine. Figure 2 shows how many papers were selected
to review from 2011 to 2021.
3. Research methodology
For achieving the aim of the research, the work has been divided into two stages. In the first
iteration, an intensive literature review was conducted based on more than 800 different
sources. In this regard, a wide variety of journals was considered. Some of the papers were
found through resources given by the database, e.g. Scopus and Web of Science. We extended
ECAM our search to the reference lists provided in the previous search results and Google Scholar. In
30,7 the same vein, the most relevant sources were selected using the keywords “construction
projects OR construction industry” AND “cost overrun”.
Since Iran is a developing country in Asia, our review is limited to the studies
investigating the causes of cost overrun in building construction projects in an Asian
country. In recent years, the political and economic conditions of many Asian countries,
including Iran, Afghanistan, Saudi Arabia, Iraq, Turkey, etc., have been changing
2744 significantly. All the studies on the cost overruns of construction projects in Iran have
been conducted during the last ten years, and it shows that this issue has been considered an
essential issue. Indeed, the recent economic problems in Iran, such as inflation, exchange rate
fluctuations, intense price fluctuations, etc., have seriously affected the construction industry
and construction costs. So, the results of studies conducted in the last decade have been
considered and reviewed to analyze the current situation better. One of the objectives of this
study is to compare the results of these studies with each other. To develop a better
comparison and the possibility of presenting a new ranking under the ranking of each study,
we excluded the studies in which there was no ranking of the cost overrun factors or those in
which less than ten causative factors were identified. While extracting the cost overrun factor
in each study, we avoided repetitions in listing the causes. For instance, “delay in preliminary
handing over of project”, “delay in delivery of construction documents”, “delay in delivery of
work by subcontractors”, etc. were merged and expressed as “delay in planned activity”.
Also, similar factors were used to reflect the same meaning between one study and another.
For example, factors such as “fluctuation in money exchange”, “economic instability”,
“inflation”, etc., will be considered in the category “poor economic conditions”.
To identify the “top ten causative cost overrun factors” in the Asian countries, we
considered the frequency of different factors in the selected studies. Based on the actual
ranking, we calculated the new scale. The calculation of the overall ranking index (ORI) for
the selected factors is based on this equation (Zidane and Anderson, 2018):
10
1 X 10 X Ni
ORI ¼ 3 ðNi Þ 3 (1)
F i¼1 i¼1
i
where ORI: is the overall ranking index; F: is the number of studies (which is equal to 38 in this
study); the number i is the actual ranking (from 1 to 10 since all the rankings are about the top
ten); Ni represents the frequency of each rank in one row.
This study prepared a list of factors affecting the cost overrun in construction projects
through a literature review. The list was then revised through face-to-face interviews with six
university professors who had extensive experience in executing construction projects. In
addition, the experts checked the face and content validity of the instrument and the accuracy
of translation from English to Persian.
In the next stage, a quantitative survey was designed to acquire information from
individuals regarding the importance of identified factors with the Iranian construction
12
10
8
6 11
4
Figure 2. 2 4 4 5
List of paper’s year 3 3 3 2
0 1 1 1
published
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
industry. The impact of each factor on cost performance was measured on an ordinal five- Causes of cost
point Likert scale (where 1 very low, 2 low, 3 medium, 4 high, 5 very high impacts), similar to overruns
what is used by Enshassi’s et al. (2009). According to Ubani et al. (2015), the following
statistical equation was used to calculate the sample size.
z2 3 p 3 ð1 pÞ
n¼ (2)
d2
2745
where n 5 Sample size; Z is the statistical value for the confidence level used, 1.96 for 95%
confidence level; P indicates the value of the population proportion estimated and d denotes
the sampling error of the point estimate. Since the value of P is unknown, Sincich et al. (2002)
suggested a conservative value of 0.50 be used so that a sample size that is, at least as large as
required, be obtained.
To achieve predictably, representative, and robust quantitative data, the questionnaires
were distributed randomly among three groups of clients (active members in Association of
Mass Housing Builders), contractors (working in different contracting companies), and
consultants (architects and civil engineers with the first- and second-grade work permits of
the construction engineering organization) in Tehran and Mashhad as two metropolises of
Iran. The survey was done online through the Porsline website (a Persian professional
networking site). Before distributing the questionnaires, a pilot study was conducted on 15
respondents who met the inclusion criteria, such as being involved in high-rise construction
projects and having at least ten years of experience. Five professional engineers and ten
construction managers participated in the pilot study to evaluate the instrument’s reliability.
Two statistical methods were used to analyze data collected from the questionnaires: the
reliability test using Cronbach’s alpha coefficient and the relative importance index (RII) to
measure the level of importance of factors indicated by respondents.
0.9 ≤ α Excellent
0.8 ≤ α < 0.9 Good
0.7 ≤ α < 0.8 Acceptable
0.6 ≤ α < 0.7 Questionable
0.5 ≤ α < 0.6 Poor Table 2.
α < 0.5 Unacceptable Criteria for assessing
Source(s): George (2011) reliability
ECAM 3.2 Relative Importance Index (RII)
30,7 The RII was calculated using the following formula to analyze the returned questionnaires. It is a
known practice among scholars to use RII to identify factors influencing cost overrun (i.e.
Durdyev et al., 2012; Kamaruddeen et al., 2020). The value of RII ranges from 0 to 1 where the
highest value indicates the high significance of the item as a cause of cost overrun in construction
projects. The RII for each component was calculated according to Eq. 4 (Enshassi et al., 2009).
P5
2746 Wi $Xi
RII ¼ i¼1 (4)
A3N
W 5 Weight given to each factor by the respondents, ranging from 1 to 5
(1) Frequency of ith response given for each cause
(2) A 5 Highest weight (i.e. 5 in this case)
(3) N 5 Total number of respondents
Table 3. (continued )
Factors of cost Factors of cost
Causes of cost
No overrun References No overrun References overruns
19 Additional works Dabirian et al. (2020), 41 Land acquisition Subramani et al. (2014),
Derakhshanalavijeh and problems Memon et al. (2019)
Teixeira (2017), Nazeer
and Uddin Shah (2020),
Allahaim and Liu (2015), 2749
Wanjari and Dobariya
(2016)
20 Change of project Derakhshanalavijeh and 42 Owner Amini et al. (2021),
scope Teixeira (2017), Akhund interference/Lack Johnson and Babu (2018),
et al. (2019), Allahaim and of client’s Sohu et al. (2020), Memon
Liu (2015), Kamaruddeen experience et al. (2020)
et al. (2020), Balali et al.
(2020)
21 Poor financial Derakhshanalavijeh and 43 Complexity of Rezaei and Jalal (2018),
control on site Teixeira (2017), Memon construction Keng et al. (2018)
et al. (2019), Rezaei and works
Jalal (2018), Nazeer and
Uddin Shah (2020),
Kamaruddeen et al. (2020)
22 Changes in client Amini et al. (2021),
requirements Kamaruddeen et al.
(2020), Akhund et al.
(2019), Jadhav et al.
(2020), Gupta and Kumar
(2020)
Source(s): Authors (2021) Table 3.
10%
5 years and less
14%
41% 6-10 years
2754
Table 6.
ECAM
of cost overrun
Mitigation measures
for significant causes
Causes Mitigation measures
1st problem: Poor site - Focus on new methods and techniques such as value management and risk management (Ramabhadran, 2018)
management and - Improve managerial skills by conducting continuous training programs (Mahamid, 2014)
supervision - Employ integrated monitoring system (Ullah et al., 2018)
2nd: problem: - Use the computerized latest planning and monitoring techniques (Ramabhadran, 2018)
Improper planning and - Schedule the project considering the seasonal weather and special times such as Ramadan (Ramabhadran, 2018)
scheduling - Allocate sufficient time for planning (Mahamid, 2014)
- Consider true constraints of market and logistics during planning (Ullah et al., 2018)
3rd problem: - Conduct continuous updating on material prices (Mahamid, 2014)
Fluctuations in the - Acquiring Bulk of materials (Ullah et al., 2018)
cost of materials - Establish an effective contract system with raw material suppliers (Ullah et al., 2018)
- Utilize local materials as much as possible (Ullah et al., 2018)
4th problem: Lack of - Acquire project professionals with similar project experience (Ramabhadran, 2018)
experience of
contractors
5th problem: Poor - Use expert opinion and advice for estimating inflation rates (Derakhshanalavijeh and Teixeira, 2017)
economic condition - Expedite orders of long delivery items to reduce the impact of inflation (Derakhshanalavijeh and Teixeira, 2017)
(currency, inflation) - Hedge exchange rates by use of money transfer tools (Ramabhadran, 2018)
rate) - Obtain guarantees of exchange rates and convertibility (Ramabhadran, 2018)
6th problem: Rework/ - Employ experienced and qualified technical staff (Derakhshanalavijeh and Teixeira, 2017)
mistakes during - Train fresh staff to increase their technical knowledge (Derakhshanalavijeh and Teixeira, 2017)
construction - Plan quality management (Ramabhadran, 2018)
- Proper understanding of site drawings and specifications (Ullah et al., 2018)
- Employ a proper mentoring system (Ullah et al., 2018)
7th problem: Delay in - Review and approve design documents, shop drawings, and time schedules by consultants (Bekr, 2015)
planned activity - Plan the proper sequence for all construction activities (Keng et al., 2018)
- Arrange regular meetings (Ullah et al., 2018)
8th problem: - Select qualified cost estimators (Derakhshanalavijeh and Teixeira, 2017)
Inaccurate project cost - Regular training for cost estimators through meetings (Derakhshanalavijeh and Teixeiram, 2017; Asrilhant et al., 2004)
estimation - Use of models for relationships among project construction time, project cumulative sales, and cost (Derakhshanalavijeh and Teixeiram, 2017; Chen, 2011)
- Employ integrated software for estimation (Ramabhadran, 2018)
- Ensure a clear understanding of the scope and sufficient time to cross-check the estimate (Ramabhadran, 2018)
- Improve the accuracy of cost estimating by direct market price inquiry (Keng et al., 2018)
(continued )
Causes Mitigation measures
2755
Table 6.
ECAM Survey results (based on Previous study results in Asian countries
30,7 Rank questionnaire survey) RII (based on 38 studies) ORI
1 Poor site management and 0/893 Fluctuations in the cost of materials 6/977
supervision
2 Improper planning and scheduling 0/869 Improper planning and scheduling 3/977
3 Fluctuations in the cost of materials 0/861 Poor site management and supervision 3/76
2756 4 Lack of experience of contractors 0/844 Delay in planned activity 2/337
5 Poor economic condition (currency, 0/838 Poor economic condition (currency, inflation 2/027
inflation rate) rate)
6 Rework/mistakes during 0/831 Lack of communication between parties 2/00
construction
7 Delay in planned activity 0/822 Shortage of labour and technical personnel 1/906
8 Inaccurate project cost estimation 0/819 Inaccurate project cost estimation 1/757
Table 7.
Comparison of Survey 9 Lack of communication between 0/812 Frequent design changes 1/698
Results and Literature parties
Review of causes of 10 Frequent design changes 0/809 Rework/mistakes during construction 1/424
cost overrun Source(s): Authors (2021)
Iran and the wars, civil unrest, and political conditions in Afghanistan and Palestine have
been the reasons for economic instability and construction cost overruns. On the contrary, the
economic situation ranked as an insignificant factor for Malaysia, and the UAE, which
reflects relative stability in the currency exchange in these countries.
Table 6 shows that inaccurate cost estimation is the next significant factor of cost overrun
in the previous studies. Derakhshanalavijeh and Teixeira (2017) concluded that inaccurate
cost estimation was the most severe cause of cost overrun in the gas-oil industry of Iran. Also,
the comparison shows that in most research conducted in Pakistan, this factor was ranked as
one of the top ten causative factors.
Shortage of labor and technical personnel was identified as another factor influencing cost
overrun among the previous studies. This factor has been considered the main reason for
overruns in construction costs in Iraq. This country depends on foreign labor, so a shortage of
labor occurs at specific periods during the year that are reflected in the delays in
subcontractor works. Also, training methods and not using up-to-date new procedures and
techniques are another reason for this country’s inadequate labor/skill availability.
Frequent design changes have affected the construction costs in Iran and some other
Asian countries, including Malaysia (Keng et al., 2018), UAE (Johnson and Babu, 2018), and
Bahrain (Abusafiya and Suliman, 2017). Less involvement of the owners in the early phases of
the projects, design mistakes, and lack of clearly defined project objectives and scope were
mainly the causes of frequent change orders in construction projects in these countries. Other
causes of cost overrun were ranked for Asian countries, and most of them are related to the
lack of technology, management, skills, and competencies of project participants.
5. Conclusions
This study was conducted in three parts, and the results are presented separately. In the first
part, through a comprehensive literature review, recent studies on cost overruns in
construction projects in Asian countries were reviewed. The output of this investigation was
a list of 59 common causes of cost overruns in the construction industry, and the authors
provided a new ranking based on the frequency of each factor in a total of 38 studies (see
Table A1). This investigation revealed that “materials cost fluctuations, improper planning
and scheduling, and poor site management and supervision” are the top three causes of cost
overrun in Asian countries.
In the second part, 43 causative factors of construction cost overrun were analyzed with Causes of cost
experienced personnel involved in the Iranian construction industry to validate the contents overruns
of addressing the issue of construction cost overrun in Iran. Approximately half of the
respondents stated that construction projects in Iran face a cost overrun of more than 25%.
Also, the survey shows that the leading causes of cost overrun in the Iranian construction
projects are “poor site management and supervision, improper planning and scheduling,
materials cost fluctuations, lack of contractors’ experience, poor economic condition, rework,
delay in planned activities, inaccurate cost estimation, lack of communication between 2757
parties, and frequent design changes.”
In the final part, a comparative study was conducted to match the top ten causative factors
of cost overrun in Iran with other Asian countries, including Turkey, Malaysia, Pakistan,
India, Bahrain, Iraq, Afghanistan, Vietnam, UAE, Jordan, Saudi Arabia, and Palestine. The
comparison demonstrates that Iran’s main factors causing cost overrun agree with the
countries mentioned above, except for some individual cases. The summary of the results is
shown in Figure 4.
The findings of this study indicate that:
(1) Approximately 50% of respondents stated that construction projects in Iran face a
cost overrun of more than 25%.
(2) According to the survey result, cost overrun is considered a significant problem in the
Iranian construction industry.
(3) The main problems identified in past research in Iran, such as poor economic
condition, improper planning and scheduling, inaccurate project cost estimation, and
rework, still have remained the chief obstacles in the path of increasing productivity.
(4) Material price fluctuation has been recognized as one of the leading causes of cost
overrun in Asian countries.
(5) In some Asian countries with specific geopolitical situations such as Afghanistan,
Pakistan, Palestine, and Iraq, economic instability, variation in the exchange rate, and
fluctuations in the cost of materials have led to cost overrun in construction projects.
It should be noted that “corruption” is one of the causes of cost overrun cited only in
the study conducted in Afghanistan.
(6) Rework, frequent changes in design, project scope, and requirements are the leading
causes of cost overrun in Jordan and Bahrain.
(7) Improper planning and poor management and supervision in Iran, Malaysia, UAE,
India, Vietnam, and Turkey have been cited as one of the main reasons for the cost
overrun.
(8) In the Persian Gulf countries such as Iran, Saudi Arabia, and the UAE, changes in oil
prices affect fluctuations in the price of raw materials and thus the deviation of
construction project costs.
(9) In the UAE, as an immigrant country, the lack of experienced local specialists has led
to a low productivity level of labor and improper management and supervision of
projects.
Based on the ranking of the main factors behind cost overrun in producing buildings, for
effective and efficient cost control of construction projects, the authors recommend that the
project management section should be especially considered and modified. Also, the planning
in different stages, material management, resource planning and management, and proper
ECAM
30,7
2758
Figure 4.
Summary of research
results
financial management should be emphasized. In addition, all stakeholders should work Causes of cost
together to achieve successful projects within the stipulated budget and exceed the overruns
anticipated quality standard. In the meantime, the scholars can concentrate on more specific
and detailed studies on the causes of cost overrun and its effects on the Iranian construction
industry.
In conclusion, the current study results can be considered valuable for international
academics and researchers since it identifies the most significant causes of cost overrun and
provide adequate knowledge about the common causes of cost overrun and its impact on the 2759
Iranian construction industry. It also fills the gap in the current body of knowledge in
construction project cost overrun in general and with specific regard to the construction
industry of Iran.
References
Abusafiya, H.A.M. and Suliman, S.M.A. (2017), “Causes and effects of cost overrun on construction
project in Bahrain: part I (ranking of cost overrun factors and risk mapping)”, Modern Applied
Science, Vol. 11 No. 7, p. 20, doi: 10.5539/mas.v11n7p20.
Ahady, S., Gupta, S. and Malik, R.K. (2017), “A study of the causes of cost overrun in construction
industry in Afghanistan”, International Journal of Engineering Development and Research,
Vol. 5 No. 3, pp. 978-985.
Akhund, M.A., Raza Khoso, A., Shahzaib Khan, J., Usama Imad, H. and Muhammad Memon, K. (2019),
“Prompting cost overrun factors during PCP in construction projects”, Indian Journal of Science
and Technology, Vol. 12 No. 4, pp. 1-7, doi: 10.17485/ijst/2019/v12i4/140936.
Akram, M., Ali, T., Memon, N.A. and Khahro, Sh. H. (2017), “Causal attributes of cost overrun in
construction projects of Pakistan”, International Journal of Civil Engineering and Technology
(IJCIET), Vol. 8 No. 6, pp. 477-483.
Al-Hazim, N., Salem, Z.A. and Ahmad, H. (2017), “Delay and cost overrun in infrastructure projects in
Jordan”, Procedia Engineering, Vol. 182, pp. 18-24, doi: 10.1016/j.proeng.2017.03.105.
Alaryan, A., Elbeltagi, E., Elshahat, A. and Dawood, M. (2014), “Causes and effects of change orders
on construction projects in Kuwait”, Journal of Engineering Research and Applications, Vol. 4
No. 2, pp. 01-08.
Alhajri, A.R. and Alshibani, A. (2018), “Critical factors behind construction delay in petrochemical
projects in Saudi Arabia”, Energies, Vol. 11, p. 1652, doi: 10.3390/en11071652.
ECAM Alhammadi, A.S.A.M. and Memon, A.H. (2020), “Ranking of the factors causing cost overrun in
infrastructural projects of UAE”, International Journal of Sustainable Construction Engineering
30,7 and Technology, Vol. 11 No. 2, pp. 204-211, doi: 10.30880/ijscet.2020.11.02.025.
Aljohani, A., Ahiaga-Dagbui, D. and Moore, D. (2017), “Construction projects cost overrun: what does the
literature tell us?”, International Journal of Innovation, Management and Technology, Vol. 8 No. 2.
Allahaim, F.S. and Liu, L. (2015), “Causes of cost overruns on infrastructure projects in Saudi Arabia”,
International Journal of Collaborative Enterprise, Vol. 5 Nos 1/2, p. 32, doi: 10.1504/IJCENT.2015.
2760 073176.
Amini, Sh., Rezvani, A. and Tabasi, M. (2021), “Identification and ranking significant factors causing
cost overrun in the design and construction process of buildings using the BWM method (Case
study: city of Mashhad)”, Urban Management Studies, Vol. 12 No. 44, pp. 67-83, (Persian).
Armesh, H., Salarzehi, H. and Mohammad, N. (2010), “Causes of inflation in the Iranian economy”,
International Review of Business Research Papers, Vol. 6 No. 3, pp. 30-44.
Asrilhant, B., Meadows, M. and Dyson, R.G. (2004), “Exploring decision support and strategic project
management in the oil and gas sector”, European Management Journal, Vol. 22 No. 1, pp. 63-73,
doi: 10.1016/j.emj.2003.11.017.
Balaji, H.V. and Venugopal, P. (2020), “Impact of cost overrun factors in constructing apartments in
Tamil Nadu”, International Journal of Innovative Technology and Exploring Engineering, Vol. 9
No. 3, pp. 456-459, doi: 10.35940/ijitee.C8092.019320.
Balali, A., Moehler, R.C. and Valipour, A. (2020), “Ranking cost overrun factors in the mega hospital
construction projects using Delphi-SWARA method: an Iranian case study”, International
Journal of Construction Management. doi: 10.1080/15623599.2020.1811465.
Bekr, Gh. A. (2015), “Identifying factors leading to cost overrun in construction projects in Jordan”,
Journal of Construction Engineering, Technology and Management, Vol. 5 No. 3, pp. 25-33.
Bentil, E., Nana-Addy, E., Asare, E.K. and Fokuo-Kusi, A. (2017), “The level of existence and impact of
cost and time overruns of building construction projects in Ghana”, Civil and Environmental
Research, Vol. 9 No. 1, pp. 36-46.
Chen, H.L. (2011), “An empirical examination of project contractors’ supply-chain cash flow
performance and owners’ payment patterns”, International Journal of Project Management,
Vol. 29 No. 5, pp. 604-614, doi: 10.1016/j.ijproman.2010.04.001.
Chinda, T. (2020), “Factors affecting construction costs in Thailand: a structural equation modelling
approach”, International Journal of Construction Supply Chain Management, Vol. 10 No. 3,
pp. 115-140, doi: 10.14424/ijcscm100320-115-140.
Cronbach, L.J. (1951), “Coefficient alpha and the internal structure of tests”, Psychometrika, Vol. 16,
pp. 297-334.
Dabirian, Sh., Khanzadi, M. and Abdollahi, M. (2020), “Investigation of the most important factors
affecting cost overruns in construction projects using Hybrid system dynamic and Dematel
method”, Sharif Journal of Civil Engineering, Vol. 36.2 No. 3.1, No. 3, pp. 13-28, (Persian), doi: 10.
24200/J30.2019.51915.2448.
Derakhshanalavijeh, R. and Teixeira, J.M.C. (2017), “Cost overrun in construction projects in
developing countries, Gas-Oil industry of Iran as a case study”, Journal of Civil Engineering and
Management, Vol. 23 No. 1, pp. 125-136, doi: 10.3846/13923730.2014.992467.
Durdyev, S. (2021), “Review of construction journals on causes of project cost overruns”, Engineering,
Construction and Architectural Management, Vol. 28 No. 4, pp. 1241-1260, doi: 10.1108/ECAM-
02-2020-0137.
Durdyev, S., Ismail, S. and Bakar, N.A. (2012), “Factors causing cost overruns in construction of
residential project: case study of Turkey”, International Journal of Science and Management,
Vol. 1 No. 1, pp. 3-12.
Enrica, M., Purba, H.H. and Purba, A. (2021), “Risks leading to cost overrun in construction projects: a Causes of cost
systematic literature review”, Advance Researches in Civil Engineering, Vol. 3 No. 1, pp. 43-60,
doi: 10.30469/ARCE.2021.130147. overruns
Enshassi, A., Sherif, M. and Saleh, A. (2009), “Factors affecting the performance of construction
projects in the Gaza strip”, Journal of Civil Engineering and Management, Vol. 15 No. 3,
pp. 269-280, doi: 10.3846/1392-3730.
Flyvbjerg, B. (2009), “Survival of the unfit test: why the worst infrastructure gets built and what we
can do about it”, Oxford Review of Economic Policy, Vol. 25 No. 3, pp. 344-367. 2761
Flyvbjerg, B., Ansar, A., Budzier, A., Buhl, S., Cantarelli, Ch., Garbuio, M., Glenting, C., Holm, M.S.,
Lovallo, D., Lunn, D., Molin, E., Rønnest, A., Stewart, A. and Wee, B.V. (2018), “Five things you
should know about cost overrun”, Transportation Research Part A: Policy and Practice,
Vol. 118, pp. 174-190, doi: 10.1016/j.tra.2018.07.013.
Flyvbjerg, B., Holm, M.S. and Buhl, S. (2002), “Underestimating costs in public works projects: error or
lie?”, Journal of the American Planning Association, Vol. 68 No. 3, pp. 279-295.
George, D. (2011), SPSS for Windows Step by Step: A Simple Study Guide and Reference, 17.0 Update,
Pearson Education India, 10/e.
Gupta, C. and Kumar, C. (2020), “Study of factors causing cost and time overrun in construction projects”,
International Journal of Engineering Research and Technology, Vol. 9 No. 10, pp. 202-206.
Heravi, G. and Mohammadian, M. (2017), “Cost overruns and delay in municipal construction projects
in developing countries”, AUT Journal of Civil Engineering, Vol. 1 No. 1, pp. 31-38, doi: 10.22060/
ceej.2017.12189.5163.
neda, K. and Porras, H. (2020), “Cost overrun causative factors in road
Herrera, R., Sanchez, O., Casta~
infrastructure projects: a frequency and importance analysis”, Applied Sciences, Vol. 10, p. 5506,
doi: 10.3390/app10165506.
Hwang, B., Xianbo, Z. and Khang, J.G. (2014), “Investigating the client-related rework in building
projects: the case of Singapore”, International Journal of Project Management, Vol. 32 No. 4,
pp. 698-708, doi: 10.1016/j.ijproman.2013.08.009.
Idrees, Sh. and Shafiq, M.T. (2021), “Factors for time and cost overrun in public projects”, Journal of
Engineering, Project, and Production Management, Vol. 11 No. 3, pp. 243-254, doi: 10.2478/
jeppm-2021-0023.
Jadhav, D., Konnur, B.A. and Patil, S. (2020), “Analysis of factors causing cost overruns in residential
building construction projects”, International Journal of Research in Engineering, Science and
Management, Vol. 3 No. 7, pp. 308-311.
Johnson, R.M. and Babu, R.I.I. (2018), “Time and cost overruns in the UAE construction industry: a
critical analysis”, International Journal of Construction Management, Vol. 0 No. 0, pp. 1-10, doi:
10.1080/15623599.2018.1484864.
Kadiri, D.S. and Onabanjo, B.O. (2017), “Cost and time overruns in building projects procured using
traditional contracts in Nigeria”, Journal of Sustainable Development, Vol. 10 No. 5, doi: 10.5539/
jsd.v10n5p234.
Kakitahi, J.M., Henry, M.A., Anne, L. and Simon, J.M. (2016), “Impact of construction-related rework on
selected Ugandan public projects”, Journal of Engineering, Design and Technology, Vol. 14 No. 2,
pp. 238-251, doi: 10.1108/jedt-02-2014-0006.
Kamaruddeen, A.M., Sung, Ch. F. and Wahi, W. (2020), “A study on factors causing cost overrun of
construction projects in sarawak, Malaysia”, Civil Engineering and Architecture, Vol. 8 No. 3,
pp. 191-199. doi: 10.13189/cea.2020.080301.
Keng, T. Ch., Mansor, N. and Ching, Y.K. (2018), “An exploration of cost overrun in building
construction projects”, Global Business and Management Research: An International Journal,
Vol. 10 No. 3, pp. 638-646.
Mahamid, I. (2011), “Cost overrun causes in infrastructure projects, consultants perspective”, 2nd
International Conference on Construction and Project Management, Vol. 15, IPEDR.
ECAM Mahamid, I. (2014), “Contractors’ perception of risk factors affecting cost overrun in building projects
in Palestine”, IES Journal Part A: Civil and Structural Engineering, Vol. 7 No. 1, pp. 38-50, doi:
30,7 10.1080/19373260.2013.854180.
Mahamid, I. and Dmaidi, N. (2013), “Risks leading to cost overrun in building construction from
consultants’ perspective”, Organization, Technology and Management in Construction. An
International Journal, Vol. 5 No. 2, p. 862, doi: 10.5592/otmcj.2013.2.5.
Memon, A.H., Rahman, I.A. and Azis, A.A.A. (2011), “Preliminary study on causative factors leading
2762 to construction cost overrun”, International Journal of Sustainable Construction Engineering and
Technology, Vol. 2 No. 1, June, pp. 57-71.
Memon, A.H., Rahman, I.A., Abdullah, M.R. and Abdu Azis, A.A. (2014), “Factors affecting
construction cost performance in project management projects: case of MARA large projects”,
International Journal of Civil Engineering and Built Environment, Vol. 1 No. 1, pp. 30-35.
Memon, A.Q., Memon, A.H., Soomro, M.A. and Rahman, I.A. (2019), “Common factors affecting time
and cost performance of construction projects in Pakistan”, Pakistan Journal of Science, Vol. 71
No. 4 Suppl, pp. 64-68.
Memon, A.Q., Memon, A.H. and Soomro, M.A. (2020), “Contractor’s Perception on Factors causing cost
overrun in construction works of Pakistan”, International Journal of Sustainable Construction
Engineering and Technology, Vol. 11 No. 3, pp. 84-92, doi: 10.30880/ijscet.2020.11.03.009.
Mirzai Matin, D. (2016), “Identifying the effective factors for cost overrun and time delay in water
construction projects”, Engineering, Technology and Applied Science Research, Vol. 6 No. 4, pp.
1062-1066.
Naveenkumar, G.V. and Prabhu, V. (2016), “Factors influencing time and cost overruns in construction
projects”, International Journal of Innovative Research in Science Engineering And Technology,
Vol. 5 No. 4, pp. 6468-6473.
Nazeer, T. and Uddin Shah, S.N. (2020), “An observational examination on components affecting cost
overwhelm on construction projects – a case from Karachi, Pakistan”, Indus Journal of
Management Sciences, Vol. 01 No. 02, pp. 1-12.
Palaneeswaran, E. (2006), “Reducing rework to enhance project performance levels”, Proceedings of
the One day Seminar on: Recent Developments in Project Management in Hong Kong, (12
May 2006).
Patil, Y.K. and Bhangale, P.P. (2016), “Investigation of factors influencing cost overrun in high-rise
building constructions”, International Journal of Latest Trends in Engineering and Technology,
Vol. 6 No. 3, p. 336.
Prajapati, S.K., Gupta, R. and Pandey, M. (2016), “Causes and effects of cost overrun on construction
projects in Madhya Pradesh”, International Journal of Engineering Development and Research,
Vol. 4 No. 2, pp. 1346-1350.
Rahman, I.A., Memon, A.H. and Abd Karim, A.T. (2013), “Significant factors causing cost overruns in
large construction projects in Malaysia”, Journal of Applied Sciences, Vol. 13 No. 2, pp. 286-293,
doi: 10.3923/jas.2013.286.293.
Ramabhadran, M. (2018), “An investigation into cost overrun in construction projects in United Arab
Emirates”, International Journal of Construction Engineering and Management, Vol. 7 No. 1,
pp. 1-21, doi: 10.5923/j.ijcem.20180701.01.
Rezaei, A. and Jalal, S. (2018), “Investigating the causes of delay and cost-overrun in construction
industry”, International Advanced Researches and Engineering Journal, Vol. 02 No. 02, pp. 075-079.
Samarghandi, H., Moosavi Tabatabaei, S.M., Taabayan, P., Mir Hashemi, A. and Willoughby, K. (2016),
“Studying the reasons for delay and cost overrun in construction projects: the case of Iran”, Journal
of Construction in Developing Countries, Vol. 21 No. 1, pp. 51-84, doi: 10.21315/jcdc2016.21.1.4.
Senouci, A., Ismail, A. and Eldin, N. (2016), “Time delay and cost overrun in Qatari public construction
projects”, Procedia Engineering, Vol. 164, pp. 368-375, doi: 10.1016/j.proeng.2016.11.632.
Shanmugapriya, S. and Subramanian, K. (2013), “Investigation of significant factors influencing time Causes of cost
and cost overruns in Indian construction projects”, International Journal of Emerging
Technology and Advanced Engineering, Vol. 3 No. 10, pp. 734-740. overruns
Shehu, Z., Endut, I.R., Akintoye, A. and Holt, G.D. (2014), “Cost overrun in the Malaysian construction
industry projects: a deeper insight”, International Journal of Project Management, Vol. 32 No. 8,
pp. 1471-1480, doi: 10.1016/j.ijproman.2014.04.004.
Sincich, T., Levine, D. and Stephan, D. (2002), Practical Statistics by Example using Microsoft Excel and
Minitab, 2nd ed., Prentice Hall, Upper Saddle River. 2763
Sohu, S., Ansari, A.A. and Jhatial, A.A. (2020), “Most common factors causing cost overrun with its
mitigation measure for Pakistan construction industry”, International Journal of Sustainable
Construction Engineering and Technology, Vol. 11 No. 2, pp. 256-261, doi: 10.30880/ijscet.2020.
11.02.032.
Subramani, T., Sruthi, P.S. and Kavitha, M. (2014), “Causes of cost overrun in construction”, IOSR
Journal of Engineering (IOSRJEN), Vol. 4 No. 6, pp. 1-7.
Tejale, D.S. and Khandekar, S.D. (2015), “Analysis of construction project cost overrun by statistical
method”, International Journal of Advance Research in Computer Science and Management
Studies, Vol. 3 No. 5, pp. 349-355.
Ubani, E.C., Okorocha, K.A. and Emeribe, S.C. (2015), “Analysis of factors influencing time and cost
overruns on construction projects in south eastern Nigeria”, International Journal of
Management Sciences and Business Research, Vol. 2 No. 2.
Ullah, K., Abdullah, A.H., Nagapan, S., Sohu, S. and Khan, M.S. (2018), “Measures to mitigate causative
factors of budget overrun in Malaysian building projects”, International Journal of Integrated
Engineering, Vol. 10, pp. 66-71, doi: 10.30880/IJIE.2018.10.09.032.
Vu, Th.Q., Pham, C.Ph., Nguyen, Th.A., Nguyen, Ph.Th., Phan, Ph.Th. and Nguyen, Q.L. (2020),
“Factors influencing cost overruns in construction projects of international contractors in
Vietnam”, Journal of Asian Finance, Economics and Business, Vol. 07 No. 09, pp. 389-400.
Wanjari, P.S. and Dobariya, G. (2016), “Identifying factors causing cost overrun of the construction
projects in India”, Sadhana, Vol. 41 No. 6, June, pp. 679-693, doi: 10.1007/s12046-016-0498-3.
Yang, J.B., Chu, M.Y. and Huang, K.M. (2013), “An empirical study of schedule delay causes based on
Taiwan’s litigation cases”, Project Management Journal, Vol. 44 No. 3, pp. 21-31.
Yap, J.B.H. and Skitmore, M. (2017), “Investigating design changes in Malaysian building projects”,
Architectural Engineering and Design Management, Vol. 14 No. 3, pp. 218-238, doi: 10.1080/
17452007.2017.1384714.
Zidane, Y.J.-T. and Andersen, B. (2018), “The top 10 universal delay factors in construction projects”,
International Journal of Managing Projects in Business, Vol. 11 No. 2, doi: 10.1108/IJMPB-05-
2017-0052.
Corresponding author
Alireza Rezvani can be contacted at: Rezvani0112@mshdiau.ac.ir
30,7
2764
ECAM
Table A1.
literature review
overrun in construction
projects identified from
Common factors of cost
Iran
Iraq
UAE
India
Jordan
Appendix
Turkey
Bahrain
Pakistan
Vietnam
Palestine
Malaysia
Saudi Arabia
Afghanistan
Causes of Cost Overrun
ORI
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
(continued )
Payments delay 7 4 5 6 8 8 8 6 2 0/427
(continued )
overruns
Causes of cost
2765
Table A1.
30,7
2766
ECAM
Table A1.
Project complexity/ 9 5 0/016
Note(s): 1, Balali et al ., 2020; 2, Dabirian et al ., 2020; 3, Derakhshanalavijeh and Teixeira, 2017; 4, Amini et al ., 2021; 5, Mirzai Matin, 2016; 6, Ahady et al ., 2017;
7. Johnson and Babu, 2018; 8, Alhammadi and Memon, 2020; 9, Ramabhadran, 2018; 10, Abusafiya and Suliman, 2017; 11, Memon et al ., 2020; 12, Memon et al .,
2019; 13, Akhund et al ., 2019; 14, Sohu et al ., 2020; 15, Nazeer and Uddin Shah, 2020; 16, Akram et al ., 2017; 17, Rezaei and Jalal, 2018; 18, Bekr, 2015;
19, Allahaim and Liu, 2015; 20, Kamaruddeen et al ., 2020; 21, Memon et al ., 2011; 22, Memon et al ., 2014; 23, Rahman et al ., 2013; 24, Ullah et al ., 2018;
25, Keng et al ., 2018; 26, Vu et al ., 2020; 27, Durdyev et al ., 2012; 28, Mahamid, 2014; 29, Mahamid and Dmaidi, 2013; 30, Naveenkumar and Prabhu, 2016;
31, Patil and Bhangale, 2016; 32, Subramani et al ., 2014; 33, Shanmugapriya and Subramanian, 2013; 34, Tejale and Khandekar, 2015; 35, Wanjari and Dobariya, 2016;
36, Balaji and Venugopal, 2020; 37, Gupta and Kumar, 2020; 38, Jadhav et al ., 2020
Source(s): Authors, (2021)