Professional Documents
Culture Documents
Abstract - IEC 61850 standards edition 2 has been released interoperability functions among IEDs, in order to achieve
for a few years, and many countries started investigating the high system stability and selectivity.
and implementing IEC 61850. Thailand is one of the leading
countries in IEC 61850 implementation among Asian power II. IEC61850 APPLICATION IN MEA
utilities, especially Metropolitan Electricity Authority
(MEA), who initiated the distribution substation renovation There are several typical IEC 61850 GOOSE
projects with IEC 61850 in Bangkok since 2012 for more
applications adopted in MEA, listed as follows and this
than 100 substations.
JHM Electric Solutions and OMICRON has been deeply section shares the background information about the
involved the MEA’s substations renovation projects for two design and functions:
years as the substation commissioning service provider, for Coupler Throw Over Scheme (CTO)
more than 60 substations in Bangkok area. This paper is to Line Throw Over Scheme (LTO)
share our experiences in the commissioning and Bus Throw Over Scheme (BTO)
maintenance process in MEA’s IEC 61850 systems.
The existing IEC 61850 implementation is focus on
Circuit Breaker Failure Scheme
Manufacturing Message Specification (MMS) and Generic Interlocking
Object Oriented System Event (GOOSE) applications.
GOOSE is adopted in the circuit breaker failure (50BF) A. Coupler Throw Over Scheme (CTO)
function, as well as some other interoperability functions
among IEDs, in order to achieve the high system stability This scheme is to ensure continuous power supply to
and selectivity. the transformer when one of the incoming feeders failed.
This paper shares the examples of some identified issues
during the commissioning stages and the corresponding
solutions. We also provide our recommendation on the
commissioning process improvement, which can be
considered as useful input for future implementations in
Thailand and other Asian countries.
I. INTRODUCTION
example, from previous process, when re-transfer is On High Voltage Side: Three GOOSEs are designed
started, the circuit breaker “A” will be closed first and for sending to the other for tripping on each IEDs. We call
then open breaker “C” after breaker “A” is completely GOOSE A, GOOSE B and GOOSE AB. And also on
closed. transformer feeder there is the other GOOSE which is sent
Step 3: There are also GOOSE5, GOOSE6, GOOSE7 for tripping to the medium side.
from IED4, IED5 and IED6 send to IED3 for blocking the
operation of CTO in case Circuit Breaker Failure operated
or transformer protection operated.
Authorized licensed use limited to: King Mongkuts Institute of Technology Ladkrabang provided 229
by UniNet. Downloaded on March 06,2024 at 08:30:36 UTC from IEEE Xplore. Restrictions apply.
Proceedings of the 2019 IEEE PES GTD Asia
incoming feeder and bus section feeder will receive these The effect of the operation time in the logic of relays
GOOSEs and make decision to release trip command. also causes and adds the delay time of GOOSE
application
GOOSE Send and Receive should do mapping by
looking up the name or sequence of the member in
the dataset
Can we add some signals in the dataset for testing the
worst case of system traffic? The idea is to start
changing a member in all GOOSEs at the same time.
How important is testing and capturing the GOOSE
during commissioning?
How to replace the new relay of different model or
different manufacturer? In other words, the
Fig. 6. Breaker Failure Scheme on Medium Voltage Side
procedure what we have to do.
MMS Application for 50BF Is there a limitation to the number of subscribers for
Report Service one GOOSE?
To MMI for alarm message, status and analog MMS Application
value The member in the dataset of report should use the
To CCU1 for alarm message, status and analog standard logical node, better than use the logic to
value send to SCADA (Main) generate signal GGIO
To CCU2 for alarm message, status and analog How to check or verify report application?
value send to SCADA (Backup) Network Topology
The limitation of IED in one loop of IED on Ethernet
Control Service switch
Close/Open Circuit Breaker Communication port of IED should be considered
Close/Open Disconnecting Switch Others
On/Off Recloser Function What if we have the problem to manage the files or
On/Off Earth Fault Protection lose it?
Raise/Lower Transformer Tap Position
On/Off Fan Control A. GOOSE absent: How to monitor these GOOSEs after
the system is put into service?
Authorized licensed use limited to: King Mongkuts Institute of Technology Ladkrabang provided 230
by UniNet. Downloaded on March 06,2024 at 08:30:36 UTC from IEEE Xplore. Restrictions apply.
Proceedings of the 2019 IEEE PES GTD Asia
Visualization on IEC 61850 Configurations time in the special logic of relays. It is delayed because
Another challenge about GOOSE application is how we have added some logic in the IED before sending
to understand which IED sends GOOSE and which IED GOOSE or after receiving GOOSE. Some relays separate
receives GOOSE. So, the standard format should be the operation of logic inside into different categories,
created for this purpose to understand about GOOSE namely fast operation, medium operation and slow
‘connection’. Such information of GOOSE sending or operation. Therefore, when we use the logic together with
receiving in each IED will be used in the future to verify GOOSE for special application, we need to check also the
when the IED is changed or is under preventive GOOSE delay properly. Fig.11. illustrates an example of
maintenance. Some examples below illustrate different the special logics designed for GOOSE send and receive.
approaches on the GOOSE sending and receiving
visualizations.
Fig. 8. Example1 GOOSE sending / receiving Fig. 11. Example the logic for GOOSE sending / receiving
Authorized licensed use limited to: King Mongkuts Institute of Technology Ladkrabang provided 231
by UniNet. Downloaded on March 06,2024 at 08:30:36 UTC from IEEE Xplore. Restrictions apply.
Proceedings of the 2019 IEEE PES GTD Asia
Fig. 17. Testing the GOOSE which send out from IED
Fig. 14. The idea using GOOSE to generate the package at the same time
E. Importance of Capturing GOOSE during Fig. 18. Testing the action of IED when receive GOOSE from outside
Commissioning
In the past, during commissioning, what we needed to F. How to replace a new relay of a different model or
do was to verify that all functions operated and worked manufacturer?
correctly according to the design. The output contact, That what we have to do and what we have to
binary input were configured to complete the function. consider in the procedure has to be considered by the user
Now, in case the IED is replaced by the new one or under when replacing the existing one.
the preventive maintenance again, we can retest it with GOOSE Receiving
the configured output contact and binary input. GOOSE Sending
The question is with GOOSE application. There is no Report
more binary contact and binary input. How can it be Other?
tested? Thus, it would be better to record all the GOOSE
in the testing file and re-test it with the same file. In case the same model of IED and the same firmware
version is used, this is quite easy. We just connect the
wiring the same as before and then download the previous
relay setting and IEC configuration file. After that we can
re-test it with the same file that we use during
commissioning.
However, in case we use a relay of different model or
of a different manufacturer, it is more complicated. The
new GOOSE and new report will be generated to work
together with the existing system. In order to ensure that
all new GOOSE and new report are working correctly,
Fig. 15. Test template for testing GOOSE sending / receiving testing is required. However, in this situation we have to
test it in a larger scale because many IEDs which are
related to this new one should be tested.
Authorized licensed use limited to: King Mongkuts Institute of Technology Ladkrabang provided 232
by UniNet. Downloaded on March 06,2024 at 08:30:36 UTC from IEEE Xplore. Restrictions apply.
Proceedings of the 2019 IEEE PES GTD Asia
Fig. 22. The network topology what we change by using two loops
IV. CONCLUSION
VI. REFERENCES
Authorized licensed use limited to: King Mongkuts Institute of Technology Ladkrabang provided 233
by UniNet. Downloaded on March 06,2024 at 08:30:36 UTC from IEEE Xplore. Restrictions apply.
Proceedings of the 2019 IEEE PES GTD Asia
Authorized licensed use limited to: King Mongkuts Institute of Technology Ladkrabang provided 234
by UniNet. Downloaded on March 06,2024 at 08:30:36 UTC from IEEE Xplore. Restrictions apply.