You are on page 1of 11

Articles

Weng Yuen Kam* DOI: 10.1002/suco.201100044


Stefano Pampanin

The seismic performance of RC buildings in the


22 February 2011 Christchurch earthquake
The 22 February 2011 Mw 6.2 Christchurch (Lyttelton) earthquake RC construction and design practice in New Zealand
was a particularly severe test for both modern seismically de- is similar to that in many other parts of the world. There-
signed and existing non-ductile reinforced concrete (RC) build- fore, some of the lessons learnt are directly relevant to the
ings. Some 16.2 % of 833 buildings with RC systems within the international community for further research, improve-
Christchurch central business district (CBD) were severely dam- ments to current seismic code design and performance cri-
aged. There were 182 fatalities, 135 of which were the unfortu- teria, and beg the implementation of most recent and most
nate consequences of the complete collapse of two medium-rise advanced technology.
RC buildings. As with the post-Northridge 1994 earthquake, the
design performance of ”modern” structures is being scrutinized – 2 Canterbury and Christchurch Earthquakes, 2010–11
with the inevitable question: is ”life safety” but irreparable dam- 2.1 The 4 September 2010 Mw 7.1 Darfield (Canterbury)
age still a valid performance target? This brief paper presents a
earthquake
summary of RC building damage from a broad performance-
based earthquake engineering perspective. Several preliminary
The 22 February 2011 earthquake was an “aftershock” of
lessons, not all of them surprising, and the issues that have
the sequence of earthquakes triggered by the Mw 7.1
arisen will be discussed using case study buildings, with sugges-
Darfield (Canterbury) earthquake of 4 September 2010.
tions for urgently needed research areas.
The 4 September 2010 Mw 7.1 Darfield earthquake, with
Keywords: Christchurch 2011 earthquake, reinforced concrete, seismic an epicentre approx. 35 km from the Christchurch CBD,
performance, earthquake reconnaissance, performance-based earthquake
engineering, field damage, New Zealand
generated peak ground accelerations (PGA) of up to
0.2–0.3 g in the CBD area. This main shock resulted in
widespread liquefaction and damage to land, residential
1 Introduction buildings and infrastructure in the Canterbury region [2].
Preliminary research has indicated that the associat-
The 22 February 2011 Mw 6.2 Christchurch (Lyttelton) ed seismic demand was deemed to correspond to the ap-
earthquake represents one of the most severe tests of proximate 400–500-year return period motions of the New
“modern” and older non-ductile RC structures in a devel- Zealand loading standards, NZS1170:5 [3] for structures
oped nation with a strong seismic engineering back- with periods of 0.3–1.0 s [4]. However, a reconnaissance
ground. Some 16.2 % of 833 buildings with reinforced report on the seismic performance of the RC buildings in
concrete (RC) systems within the Christchurch central the 4 September event [5] has indicated low to moderate
business district (CBD) were severely damaged. There levels of damage for pre-1970s “brittle” RC buildings,
were 182 fatalities, 135 of these due to the complete col- somehow contradicting the expected level of damage
lapse of two medium-rise RC buildings. given the magnitude of the earthquake and the recorded
This brief overview paper discusses some preliminary level of PGA.
lessons learnt from the observed seismic performance of Prior to the 22 February 2011 earthquake, it had
RC buildings in the 22 February 2011 earthquake. The been demonstrated via a series of numerical non-linear
background to New Zealand RC seismic design and the time history analyses and experimental shaking table tests
seismic shaking of the Christchurch 2010–11 earthquakes that the characteristics of the ground motions (recorded
are also briefly discussed. A full damage report on the seis- signal itself) in the CBD after the 4 September event might
mic performance of RC buildings in the CBD will be avail- have not be as demanding as compatibility with the design
able in the near future in [1]. spectra (itself an approximate approach) would suggest
[6].

* Corresponding author: kam.wengyuen@beca.com, 2.2 Seismicity of the 22 February 2011 earthquake


weng.kam@canterbury.ac.nz
The epicentre of the 22 February 2011 Mw 6.2 Christ-
Submitted for review: 18 September 2011
Revised: 18 September 2011 church earthquake was approx. 10 km south-east of the
Accepted for publication: 21 September 2011 Christchurch CBD at a shallow depth of 5 km. The maxi-

© 2011 Ernst & Sohn Verlag für Architektur und technische Wissenschaften GmbH & Co. KG, Berlin · Structural Concrete 12 (2011), No. 4 223
W. Y. Kam/St. Pampanin · The seismic performance of RC buildings in the 22 February 2011 Christchurch earthquake

Fig. 1. Fault rupture length and aftershock sequence for the 4 September 2010, 22 February 2011 and 13 June 2011 events (source: GNS Science)

Fig. 2. Peak ground accelerations recorded during the 22 February 2011 Christchurch aftershock (source: EQC-GNS Geonet)

mum felt intensity was MMI IX and the maximum PGA in the CBD. Fig. 2 shows a comparison of PGAs (horizon-
recorded was 0.4–0.7g in the Christchurch CBD. Fig. 1 tal and vertical) recorded by the GeoNet seismic monitor-
shows the fault rupture associated with the 4 September ing network in the Christchurch CBD. A wide range of
and 22 February events and associated aftershocks as (medium to very high) horizontal accelerations was
recorded until 29 August 2011. recorded, with peaks exceeding 1.6g at Heathcote Valley
A rich set of strong ground motion records were cap- and between 0.4 and 0.7 g at the CBD recording stations.
tured in these earthquakes by the EQC-GNS GeoNet seis- A significant peculiarity of the 22 February earthquake
mic hazard monitoring network, which has more than 50 was the very high vertical acceleration, in the range of
seismic instrumentation stations within 100 km of 1.8–2.2 g on the hills, which were among the highest ever
Christchurch CBD and four permanent recording stations recorded worldwide [7]. In the CBD, the highest value of

224 Structural Concrete 12 (2011), No. 4


W. Y. Kam/St. Pampanin · The seismic performance of RC buildings in the 22 February 2011 Christchurch earthquake

N N
1.8 EQ3:REHS 1.8 EQ3:REHS
EQ3:REHS Secondary horizontal direction
Principal direction
Spectra Acceleration / S a (g ms-2) .

Spectra Acceleration / S a (g ms-2) .


(S88E)
1.6 EQ1:CBGS
1.6
NZS1170:5 (2004) EQ1:CBGS
1.4 EQ4:CCCC (N89W)
1.4 2500−year motion
EQ4:CCCC (S01W)
Mean of 4 EQ4:CCCC EQ4:CCCC
1.2 CBD records EQ2:CHHC
1.2 EQ2:CHHC
EQ3:REHS (N02E)
1.0 EQ1:CBGS 1.0 Mean of 4
(NS64E) CBD records
0.8 EQ2:CHHC (S89W)
0.8
NZS1170:5 (2004) EQ2:CHHC (N01W)
0.6 2500−year motion 0.6
NZS1170:5 (2004) 500−year motion
0.4 0.4
0.2 NZS1170:5 (2004) 0.2 EQ1:CBGS (N26W)
500−year motion
0.0 0.0
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
a) Period (sec) b) Period (sec)

Fig. 3. 22 February 2011 Mw 6.2 earthquake: elastic acceleration response spectra (5 % damped) in the Christchurch CBD after the 22 February event and
the NZS1170:2004 design spectra (solid red line) for Christchurch (soil class D, R = 20 km): a) principal horizontal direction (generally east-west component),
b) secondary horizontal direction (generally north-south component) [12]

peak ground vertical acceleration recorded was between hazard model do not (yet) consider any near-fault effects
0.5 and 0.8 g. for Christchurch CBD as there was no known active fault
Comparison of the recorded ground motions with within 20 km of Christchurch CBD. The amplification of
the probabilistic hazard model and various ground mo- spectra acceleration in the 0.5–1.5 s period range and the
tion attenuation models has highlighted the peculiarity of shift of the peak spectra acceleration “plateau” is typically
the extremely high shaking of the 22 February event [8]. observed in ground motion records with forward directiv-
Preliminary seismological investigation indicates the com- ity effects [10], [11]. In addition, the soft-soil site amplifica-
plex seismic wave interaction in the deep alluvial soils un- tion observed in the response spectra is also significantly
derlying Christchurch (“basin effect”), the shallowness of higher than typical measurements for similar geological
the rupture and the directivity effects from the oblique-re- sites, which indicates that further urgent research is re-
verse fault rupture mechanism resulting in severe ground quired to quantify such site effects.
shaking within the Christchurch CBD [9]. The 5 %-damped elastic displacement response spec-
tra for the four CBD recording stations are plotted in
2.3 Response spectra of 22 February 2011 Mw 6.2 Fig. 4. In all period ranges, both the principal and sec-
Christchurch earthquake ondary directions of horizontal shakings were higher than
the 500-year design displacement spectra [3].
The elastic acceleration response spectra (5 % damped) of In the principal direction, there are significant dis-
the 22 February earthquake, from the four recorded placement demands at 1.0–1.8 s and 2.9–3.8 s. This sug-
ground motions from the Christchurch CBD, are com- gests RC buildings of 5–10 storeys and 15–20 storeys re-
pared with the site seismic design coefficient in Fig. 3. The spectively would experience significant displacement
NZS1170:5 [3] 500-year and 2500-year design spectra for demands and thus possibly significant damage. The prin-
the Christchurch site (Z/PGA = 0.22g), distance R = cipal direction motion exceeded the NZS1170:2004 spec-
20 km and soil class D (consistent with the four recording tra corresponding to a 2500-year return period event (con-
sites) are also plotted in Fig. 3. sidered the Maximum Credible Event, MCE) at these two
In general, it can be noted that the seismic shaking in “amplification lumps” period ranges.
the Christchurch CBD significantly exceeded the 500-year A more thorough discussion of the response spectra
motion design spectra, which is the design level in New of the 22 February 2011 earthquake in comparison with
Zealand for new buildings. The principal direction of the 4 September 2010 and 26 December 2010 earthquakes
shaking was of the predominantly east-west component. is given in [12].
The east-west components were approx. 15–30 % higher in
the periods ranging from 0 to 2.4 s, except for the period 3 RC buildings in Christchurch
range 0.35–0.6 s, where the north-south components were 3.1 Development of New Zealand seismic design
stronger. of RC buildings
The east-west components matched or exceeded the
New Zealand loading standard NZS1170:2004 [3] 2500- The first national building by-law, the 1935 Model Build-
year motion in the period range 0.5–1.75 s (approx. 5- to ing By-Law NZS95:1935 [13], was published by the New
20-storey RC buildings). Zealand Standards (NZS) in the wake of the Napier
It should be noted that the existing NZS1170.5:2004 Hawke’s Bay 1931 Mw 7.9 earthquake, which resulted in
design spectra and the underlying probabilistic seismic 256 fatalities. Unreinforced masonry buildings were dis-

Structural Concrete 12 (2011), No. 4 225


W. Y. Kam/St. Pampanin · The seismic performance of RC buildings in the 22 February 2011 Christchurch earthquake

N
N Mean of 4 EQ3:REHS
1200 EQ3:REHS CBD records
900
EQ3:REHS Secondary horizontal direction

Spectra Dispacelemt / S d (mm) .


Spectral Displacement / S d (mm) .

(S88E) 800 EQ1:CBGS NZS1170:5 (2004)


1000 EQ1:CBGS EQ3:REHS
2500−year motion
NZS1170:5 700 (N02E)
EQ4:CCCC
EQ4:CCCC (2004) 2500− EQ2:CHHC
800 EQ2:CHHC
EQ1:CBGS (NS64E) year motion 600
500 EQ4:CCCC (S01W)
600 EQ2:CHHC (S89W)
400 Mean of 4
CBD records
400 300 EQ2:CHHC
(N01W)
NZS1170:5 (2004)
500−year motion
200 EQ1:CBGS
200 EQ4:CCCC (N26W)
NZS1170:5 (2004)
(N89W) Principal direction 100 500−year motion
0 0
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
a) Period (sec) b) Period (sec)

Fig. 4. 22 February 2011 Mw 6.2 earthquake: 5 %-damped elastic displacement response spectra of four Christchurch CBD records and the NZS1170:2004
design spectra (solid red line) for Christchurch (soil class D, R = 20 km): a) principal horizontal direction (generally east-west component), b) secondary hor-
izontal direction (generally north-south component) [12]

couraged and masonry walls were required to be tied to Park and Paulay outlined many concepts of modern seis-
the floor diaphragms. mic RC design and detailing, including a rigorous design
The 1955 revision of the NZS Standard Model Build- procedure for RC frames using the capacity design philos-
ing By-Law (NZS95:1955) introduced an inverted triangu- ophy and quantification of the ductility capacity of RC
lar distribution of horizontal load with seismic coefficients beam, column, wall and joint elements.
of 0.12 g and 0 at the top and bottom of the structure re- The introduction of the NZS4203:1976 loading stan-
spectively. Explicit definitions of deformed and plain dards [23] represented a quantum change in the seismic
round bars were given, but limited bond advantage of de- load requirements. NZS4203:1976 quantified the soil am-
formed reinforcement was accounted for. The provision plification factors, with higher seismic coefficients speci-
for shear resistance of concrete elements was tightened fied for softer soils. The ultimate strength design approach
and the requirement of 135° anchorage for links was in- was codified as the preferred design method. Concurrent-
cluded. ly, the 1982 edition of the NZS3101 concrete design stan-
The NZS1900:1964 code [14], [15] was a significant dard [24] was developed and written. NZS3101:1982 in-
evolution from its predecessors. Three seismic zones with cluded now well-accepted concepts of ductile RC detailing
the maximum seismic coefficient ranging from 8 % (zone and capacity design philosophy.
C) to 12 % (zone A) were introduced to achieve a better NZS3101 was reviewed and updated in 1995 [25] and
representation of the regional seismicity of New Zealand. 2006 [26] to reflect the further knowledge gained from
The magnitude of seismic force was formed as a function research and the lessons learnt from the Loma Prieta,
of a building’s natural period. The concept of structural Northridge and Kobe earthquakes. NZS3101:1995 in-
ductility was introduced with the stated assumption of creased the requirements for minimum seating lengths for
5–10 % of damping for structural ductility of 4 for RC precast floor elements and ties between precast walls and
structures. However, no provision for ductile RC detailing floors. The column transverse reinforcement requirement
or modern capacity design considerations was included. was increased, whereas the shear reinforcement required
In the late 1960s, following the 1966 SEAOC recom- in the joint cores of ductile frames was lowered in
mendations [16] and the 1971 ACI-318 code [17], practising NZS3101:1995.
engineers in New Zealand began to develop “ductile” rein- The achievable material strain on assumed ductile
forced concrete design and detailing. J. P. Hollings intro- detailing was quantified in the 2006 revision of the
duced a step-by-step design procedure to achieve beam- NZS3101. The overstrength from slab and diaphragm con-
hinging inelastic mechanism in RC frames under seismic tributions to the beam flexural capacity was refined. Spe-
loading, which pre-dated the concept of capacity design, cific clauses relating to beam elongation and precast floor
in 1969 [18]. The 1970 Ministry of Work’s Code of Prac- detailing were also incorporated in NZS3101:2006, includ-
tice for Design of Public Buildings [19], [20] adopted many ing disallowing the use of cold-worked brittle wire mesh as
ductile detailing recommendations, including a recom- diaphragm ties into seismic elements [27]. The use of joint-
mendation for beam-column joint reinforcement. ed ductile connections (post-tensioned/rocking dissipa-
The provisional NZS3101 code, published in 1972 tive) systems has been introduced (NZS3101:2006 Appen-
[21], also adopted many parts of the 1971 ACI-318 code dix B) along with the possibility (for these special
[17] and some of the recommendations were from the structures) of designing according to a displacement-based
draft version of ref [22]. In their seminal publication [22], approach.

226 Structural Concrete 12 (2011), No. 4


W. Y. Kam/St. Pampanin · The seismic performance of RC buildings in the 22 February 2011 Christchurch earthquake

Pre-1970s RC Frame Green 1980s RC Frame Green 1990s-2010s RC Frame Unknown Age RC Frame
Yellow Green Green
Yellow 9; 18;
29; Red Yellow Yellow
Red 20; 20% 14%
25% Red Red
50; 29% 28; 26; 75;
43% 42% 56% 34; 59%
11; 27%
37; 20; 24%
32% 29%

Pre-1970s RC Wall Green 1980s RC Wall Green 1990s-2010s RC Wall Unknown Age RC Wall
Green Green
4; Yellow 2; Yellow Yellow Yellow
15% 11% Red 8; 4;
Red Red Red
24%
11; 6; 11; 29% 14; 8;
41% 32% 57% 50% 47%
12;
44% 6; 5;
21% 29%

Fig. 5. RC (wall and frame systems) building stock “damage tagging” data and distribution in terms of construction year in Christchurch CBD based on 12
June 2011 CCC Building Safety Evaluation (BSE) statistics

3.2 Damage statistics for RC buildings in Christchurch placements, beam elongation effects (section 4.5) and col-
lapse of precast staircases (section 4.6) resulted in exces-
Christchurch CBD consists of predominantly commercial sively expensive repairs and consequently the need for the
and light industrial buildings (58 %) but also a significant demolition of a number of these buildings.
number of residential buildings (42 %). The majority (ap- Whereas for the more recent RC buildings (built
prox. 81 %) of the buildings are of one and two storeys. since 1990, particularly RC-wall and high-rise buildings,
There are 127 buildings with at least six storeys, with the some unexpected performance such as significant lique-
tallest building being 22 storeys (86 m). Based on the faction-induced differential settlement (section 4.7) and
12 June 2011 CCC Building Safety Evaluation (BSE) statis- poor performance of “ductile” shear walls (section 4.3) was
tics, there are at least 3000 buildings within the observed.
Christchurch CBD. Fig. 5 presents the summary of build-
ing damage and building type/age statistics for RC build- 4 Preliminary lessons and damage observed
ings within the Christchurch CBD.
Pre-1970s RC buildings generally performed poorly, Some of the unexpected performance and preliminary
with about 60 % of these buildings being given yellow or lessons from the observed damage to RC buildings in this
red placards to indicate restricted or unsafe buildings. As severe earthquake event are discussed below. Many com-
part of this class of buildings, those relying upon RC walls plex issues and surprising (and unsurprising) lessons were
as the primary lateral-resisting system generally showed learned and these issues will be briefly highlighted for fur-
some higher level of structural redundancy such that se- ther research.
vere damage (e.g. section 4.2) did not lead to collapse of Detailed discussion of the observed damage pattern
the buildings. Pre-1970s buildings with a significant RC and damage statistics for RC buildings during the 22 Feb-
frames gravity and lateral system are observed to be more ruary Christchurch earthquake is presented elsewhere
susceptible to damage leading to structural instability (and [1], [28], [30]. Several preliminary observations and likely
likely collapse). changes to design practice have also been summarized
A construction boom in the 1980s led to a large num- by the New Zealand Structural Engineering Society
ber of medium- to high-rise RC buildings in Christchurch [31].
CBD, with precast concrete ductile perimeter frame sys-
tems being widely used. Fig. 6 illustrates some of the no- 4.1 Capacity design and ductile-response RC buildings
table RC medium- to high-rise structures in Christchurch
CBD. Some of these high-rise buildings were previously re- Many RC buildings were moderately and severely dam-
ported to be damaged during the 4 September 2010 aged in the 22 February 2011 earthquake. A large majority
Darfield earthquake [5], [29]. of the RC buildings, particularly those with capacity-de-
After the 22 February 2011 earthquake, a large num- sign consideration, performed as expected of them in a se-
ber of these 1980s RC buildings performed as expected of vere earthquake, with formation of plastic hinges in the
them in a severe earthquake, with formation of plastic beams, coupling beams and at bases of walls and columns
hinges in the beams (section 4.1). However, unexpected is- (see Fig. 7a and 7b). Nevertheless, in many cases, the
sues such as brittle failure of cold-worked mesh required buildings are considered too expensive to be repaired. In
for diaphragm action (section 4.5), excessive residual dis- addition, there are also no New Zealand guidelines for the

Structural Concrete 12 (2011), No. 4 227


W. Y. Kam/St. Pampanin · The seismic performance of RC buildings in the 22 February 2011 Christchurch earthquake

Fig. 6. Notable medium- and high-rise buildings in Christchurch CBD in 1978 and 1990 [28] (photo sketch courtesy of CCC)

a) b) c)

d) e) f)

Fig. 7. Ductile-response RC systems: a) coupling beams of 1960s coupled-walls building; b) beam plastic hinges on 1980s perimeter RC frames building;
c) ductile behaviour of 1980s RC walls building and d–f) “low-damage” PRESSS post-tensioned frames building built in 2010

assessment and estimation of the residual ductility of plas- In recent years, the emerging damage-resisting solu-
tic hinges. This makes it difficult to design the repairs as tions for precast concrete structures, typically referred to
well as estimate the building capacity and safety under se- as PRESSS technology, have been successfully introduced,
vere aftershocks. further refined, developed, codified [26], [32] and imple-

228 Structural Concrete 12 (2011), No. 4


W. Y. Kam/St. Pampanin · The seismic performance of RC buildings in the 22 February 2011 Christchurch earthquake

mented in practice in New Zealand. This approach relies nisms such as beam lap-splice/shear, column shear, beam-
on jointed ductile connections as an alternative to the column joint shear and/or wall shear failures (e.g. Fig. 8).
more traditional monolithic emulative of cast-in-place so- Unfortunately, pre-1970s “non-ductile” RC buildings can
lutions [33]. respond with a binary “on – safe, off – collapse” mecha-
New Zealand South Island’s first PRESSS building, nism, as observed in several partially or totally collapsed
completed in 2010, is a three/four storey (plus basement buildings in Christchurch, e.g. the Pyne Gould Corp.
parking) concrete building with post-tensioned coupled building (Fig. 9). For pre-1970s buildings with significant
walls in one direction and post-tensioned frames in the redundancy and regular plan form and height, generally
other. The hospital building sustained the very severe satisfactory behaviour was observed. The detailed analysis
(and beyond design level) sequence of earthquake from 4 of brittle and inelastic-response RC buildings remains a
September, through 22 February and 13 June, with no evi- challenging task, pre- and post-earthquake.
dent structural damage [34]. Given the suddenly appreci-
ated importance of damage-control design and also the ac- 4.3 Ductile shear walls detailing and design
tually proven cost-efficiency of such systems, it does not
come as a surprise that such technology in precast con- Prior to the NZS3101:1982 standard, walls were not de-
crete is likely to be one of the milestones in the post-earth- tailed for ductility, thus resulting in inadequate horizontal
quake reconstruction of the city. and vertical reinforcement, particularly at critical regions
in the walls. In particular, the older walls generally have
4.2 Pre-1970s buildings brittle response no reinforcement to prevent brittle confinement or buck-
ling failure. Fig. 8c and 8d illustrate the typical wall dam-
For the older RC frame buildings, the observed perfor- age observed for pre-1970s designs.
mance was generally poor and the observed inelastic dam- Perhaps due to the apparent increase in sophistica-
age pattern was typically characterized by brittle mecha- tion in design and structural analysis in recent years, a

a) b) c) d)

Fig. 8. Pre-1970s RC buildings brittle failure mechanism: a) near collapse of a frame/wall building with beam-column joint failure, b) short column shear and
beam-column shear damage, c) lightly reinforced 1950 RC wall compression failure, d) shear/axial failure of composite RC wall/steel columns system

Fig. 9. The collapsed Pyne Gould Corp. 1950s core wall/frames building

Structural Concrete 12 (2011), No. 4 229


W. Y. Kam/St. Pampanin · The seismic performance of RC buildings in the 22 February 2011 Christchurch earthquake

a) b) c)

Fig. 10. Post-1970s RC structural wall buildings collapse/damage patterns: a) nine-storey residential apartment block built in 2000–10 with severe shear fail-
ure of the long slender wall (photo courtesy of Ken Elwood), b) 14-storey residential apartment block built in 2007 with buckling of the boundary reinforce-
ment, c) seven-storey 1980s office block with significant compression failure of V-shaped RC shear wall

large percentage of the recently constructed RC walls con- 22 February 2011 earthquake could have also amplified
sists of thin slender walls with a minimum level of rein- the compression force demand on RC walls with already
forcement and a higher level of axial load ratio. RC walls non-negligible axial load. The lack of a distributed crack-
designed for limited or nominal ductility in accordance ing pattern in the plastic hinge zone of the RC walls is also
with NZS3101:2006 [26], with limited boundary zone con- an unexpected observation that requires further research.
finement reinforcement, e.g. Fig.10b, have been observed
to fail in brittle shear-compression or premature reinforc- 4.4 Plan and vertical irregularity
ing tensile/compressive fracture, leading to irreparable
buildings. In general, buildings with significant plan and/or vertical
The high number of severely damaged reasonably irregularity were found to perform very poorly. For exam-
new RC wall buildings (see Fig. 10a to 10c) has indicated ple, RC walls that discontinued above the basement level
that the current design for slender RC walls with inade- were observed to induce severe damage in the transfer
quate confinement steel at the non-boundary zone (possi- slabs and basement columns and walls. Plan irregularity
bly in the core region, too), and with inter-panel grouted as a consequence of inelastic behaviour of perimeter later-
lap-splice, is inadequate. In addition, many reinforced con- al-resisting systems (walls or frames) leading to inelastic
crete walls suffered premature compression failure (e.g. torsion amplification was another problem commonly ob-
Fig. 7c and Fig. 10c), particularly for L-, T- and V-shaped served. Further discussion of the observed damage due to
walls. The effects of the high vertical acceleration of the plan and vertical irregularity is presented in [1], [30].

Fig. 11. Extensive damage to floor diaphragm and loss of floor support due to the beam elongation effects of concrete frame inelastic response

230 Structural Concrete 12 (2011), No. 4


W. Y. Kam/St. Pampanin · The seismic performance of RC buildings in the 22 February 2011 Christchurch earthquake

4.5 Displacement incompatibility, brittle diaphragm been designed for (even when compatible with the code
reinforcement and beam elongation requirements at the time) was typically inadequate to sus-
tain the very high seismic demand. Considering that stair-
Displacement incompatibility of lateral load-resisting sys- cases represent a critical means of escape in buildings, it is
tems and the “gravity” elements such as floors and transfer clear that a major reconsideration of the design philoso-
beams have been recognized as a critical structural weak- phy of staircases in multi-storey buildings (RC or other-
ness in recent research [27]. In particular, the adverse wise) will be needed. An interim approach to the assess-
elongation effect of expected ductile plastic behaviour of ment and retrofitting of existing stairs has been developed
lateral systems (e.g. RC frames) on the structural integrity by an Engineering Advisory Group to the Department of
of the diaphragm of the precast flooring elements is well Building and Housing [37]. Further description of the ap-
documented [35], [36]. proach to staircase design in New Zealand is given in [37],
Fig. 11 illustrates an extreme example in which ex- [12].
tensive floor diaphragm damage and loss of precast floor-
ing unit support occurred due to the beam elongation 4.7 Liquefaction, lateral spreading and building foundation
effect. The use of cold-formed brittle wire mesh for the damage
diaphragm shear transfer has resulted in uncertainty over
the remaining structural life of the diaphragm. Severe widespread liquefaction and lateral spreading were
Whereas Fig. 11 represents an extreme example of observed in Christchurch and surrounding suburbs in the
brittle diaphragm behaviour, there are many buildings with 4 September 2010 Mw 7.1 Darfield earthquake as well as
minor to moderate cracking in the slabs-to-lateral system the 22 February 2011 Mw 6.2 Christchurch earthquake.
(beams or walls). It was found that even for residual crack However, limited or partial liquefaction manifestation was
widths < 1 mm, the cold-worked mesh across the floor slab observed within the Christchurch CBD in the 4 Septem-
topping (which is meant to act as the seismic diaphragm ber event, whereas severe liquefaction was observed in
shear transfer) could be fractured. The uncertainty of the parts of the Christchurch CBD in the 22 February earth-
residual diaphragm capacity and the difficulty of assessing quake.
the remaining strain life of the “brittle” mesh indicate that Liquefaction land damage induced differential settle-
buildings relying on cold-formed mesh for the diaphragm ment of buildings, resulting in foundation damage and
action may require urgent remedial retrofits. building permanent tilting [38]. There is clear evidence of
building damage/tilting as a consequence of liquefaction-
4.6 Precast staircases in multi-storey buildings induced settlements and ground movement as shown in
Fig. 13. Variable soil profiles underneath these buildings
Severe damage and collapse of precast staircases have with varying foundation designs are some of the complex-
been observed in many instances in the 22 February 2011 ities, resulting in mixed (good and bad) performance of
earthquake. In many buildings, staircases exhibited signifi- various CBD buildings within the same segments of lique-
cant damage in buildings where the inter-storey move- faction-damaged streets.
ments of the staircases were restrained. Complete or par- Preliminary observations indicate buildings with pile
tial internal precast concrete staircases collapses have foundations generally exhibit less differential settlement
been reported for four multi-storey high-rise buildings (e.g. and liquefaction-induced tilt [38]. High-rise multi-storey
Fig. 12a). Minor to moderate levels of staircase move- buildings on shallow foundations with significant liquefi-
ment/damage (e.g. Fig. 12b and 12c) were observed in able soil depth generally exhibit substantial settlement
many other medium- to high-rise buildings. and liquefaction-induced tilt. The soil-foundation-struc-
The staircase damage observed in multi-storey build- ture interaction is a very complicated subject that remains
ings indicates that the deformation allowance they had in the forefront of earthquake engineering research.

a) b) c)

Fig. 12. Precast concrete staircases in multi-storey buildings: a) collapse, b) top landing damage, and c) bottom landing damage

Structural Concrete 12 (2011), No. 4 231


W. Y. Kam/St. Pampanin · The seismic performance of RC buildings in the 22 February 2011 Christchurch earthquake

a) b) c)

Fig. 13. Liquefaction-induced differential settlement resulting in significant tilting of medium- to high-rise buildings with various foundation and soil details:
a) four-storey with shallow foundation, b) six-storey with shallow foundation, c) two high-rise buildings with substantial differential settlement and tilting

5 Conclusions concrete technology capable of giving society what it


naturally believes was already an ”earthquake-proof”
This paper has presented a brief summary and overview of building.
preliminary lessons learnt from our observations of the seis-
mic performance of RC buildings in the 22 February 2011 Acknowledgements
Christchurch earthquake. Due to the concise nature of the
paper, it is impossible to discuss all relevant aspects in de- Special thanks go to the numerous professional structural
tail. Readers are encouraged to read more detailed recon- engineers, Urban Search & Rescue Teams and New
naissance reports presented elsewhere [1], [9], [30], [31]. Zealand Civil Defence who assisted in various forms dur-
At the time of writing, the Canterbury Earthquakes ing the critical emergency period of these earthquakes.
Royal Commission and various investigations into the Any conclusions and inappropriate mistakes in reporting
seismic performance of severely damaged and collapsed made in this contribution are nevertheless to be consid-
RC buildings are ongoing. This paper has therefore re- ered entirely those of the authors.
frained from any discussion of the buildings that form part The assistance and data provided by Christchurch
of this current investigation. Readers are encouraged to City Council, Dr. Ken Elwood and Dr. Umut Akguzel are
read the outcomes of the inquiry at the Royal Commission gratefully acknowledged. Thanks are also given to the
website [39]. FRST Retrofit project postgraduate students (Sahin
The unique and unprecedented series of severe Tasligedik and Patricio Quintana-Gallo) for their contri-
earthquake events in Christchurch and the substantial butions in the field data collection.
damage observed to “modern” and “well”-designed rein-
forced concrete buildings (in addition to the expected References
damage to and collapse of unreinforced masonry build- 1. Pampanin, S., Kam, W. Y., Akguzel, U., Tasligedik, A. S.,
ings and older ”non-ductile” RC buildings) has prompted Quintana-Gallo, P.: Report on the observed earthquake
the consideration that current performance criteria adopt- damage of reinforced concrete buildings in the Christchurch
CBD on the 22 February 2011 Earthquake (not yet for public
ed for both new building and older building stock might
release). University of Canterbury, Christchurch, NZ, 2011.
not be adequate, certainly not in fulfilling the expectations
2. Wood, P., Robins, P., Hare, J.: Preliminary observations of
of modern society. the 2010 Darfield (Canterbury) earthquakes: An introduc-
Although it has to be recognized that the 22 Febru- tion. Bull. of New Zealand Soc. of Earthquake Eng., 43 (4),
ary Christchurch earthquake caused particularly high seis- 2010. pp. i–iv.
mic shaking well beyond the current code design levels 3. NZS1170: NZS 1170.5:2004 Structural design actions. Part
and that the event was caused by an unknown blind fault, 5: Earthquake actions – New Zealand, Standards New
the devastating reality of the facts is that the bar should Zealand, Wellington, NZ, 2004.
undoubtedly be raised (at international level). 4. Cousins, J., McVerry, G. H.: Overview of strong motion data
Such a step-up can be achieved not only by obvious- from the Darfield earthquake. Bull. of New Zealand Soc. of
ly increasing the seismic coefficients or hazard levels, but Earthquake Eng., 43 (4), 2010, pp. 222–227.
5. Kam, W. Y., Pampanin, S., Dhakal, R. P., Gavin, H., Roeder,
– and probably just as importantly – by:
C. W.: Seismic performance of reinforced concrete buildings
– increasing the performance requirements (e.g. moving
in the September 2010 Darfield (Canterbury) earthquakes.
towards a low-damage or damage-control approach even Bull. of New Zealand Soc. of Earthquake Eng., 43 (4), 2010,
under design-level or MCE-level earthquakes) for both pp. 340–350.
new and, to a lesser extent, existing structures, and 6. Pampanin, S., Kam, W. Y., Tasligedik, A. S., Quintana-Gallo,
– favouring the implementation, and continuing the re- P., Akguzel, U.: Considerations on the seismic performance
search and development, of higher seismic-performance of pre-1970s RC buildings in the Christchurch CBD during

232 Structural Concrete 12 (2011), No. 4


W. Y. Kam/St. Pampanin · The seismic performance of RC buildings in the 22 February 2011 Christchurch earthquake

the 4th Sept 2010 Canterbury earthquake: was that really a 30. Kam, W. Y., Pampanin, S., Elwood, K.: Seismic performance
big one? Proc., 9th Pacific Conf. on Earthquake Eng. of reinforced concrete buildings in the 22 February 2011
7. Berrill, J.: Some Aspects of the M6.3 February 22nd Earth- Christchurch (Lyttelton) earthquake. Bull. of New Zealand
quake. The Press, Christchurch, 2011. Soc. of Earthquake Eng., 44, 2011 (in press).
8. Fry, B., Benites, R., Reyners, M., Holden, C., Kaiser, A., Ban- 31. SESOC: Preliminary observations from Christchurch earth-
nister, S., Gerstenberger, M. C., WIlliams, C., Ristau, J., Bea- quakes., Structural Engineering Society New Zealand
van, J.: Extremely strong shaking in the New Zealand earth- (SESOC), Auckland, NZ, 2011.
quakes of 2010 and 2011. Trans. of American Geophysical 32. NZCS: PRESSS Design Handbook, New Zealand Concrete
Union, 2011 (submitted). Society (NZCS), (Ed S. Pampanin), Auckland, New Zealand,
9. GNS: Canterbury earthquakes sequence and implications 2010.
for seismic design levels. A submission to the Canterbury 33. fib: Seismic design of precast concrete building structures,
Earthquakes Royal Commission., Geological Nuclear Sci- fib Bulletin no. 27, Intl. Fed. for Struct. Concrete (fib), Lau-
ence (GNS), Lower Hutt, New Zealand, 2011. sanne, Switzerland, 2003.
10. Somerville, P.: Magnitude scaling of the near-fault rupture di- 34. Pampanin, S., Kam, W. Y., Haverland, G., Gardiner, S.: Seis-
rectivity pulse. Physics of the Earth and Planetary Interiors, mic Performance of a Post-Tensioned Precast Concrete
137 (1), 2003, pp. 201–212. Building (PRESSS Technology) during the 22nd Feb 2011
11. Somerville, P.: Engineering characterization of near fault Christchurch Earthquake: Reality Check meets Community
ground motions. Proc., NZSEE 2005 Conf., NZSEE. Expectations. Proc., NZ Concrete Industry Conference 2011,
12. Kam, W. Y., Pampanin, S.: General performance of buildings New Zealand Concrete Society (NZCS).
in Christchurch CBD: A contextual report prepared for DBH 35. Fenwick, R., Bull, D. K., Gardiner, D.: Assessment of hollow-
Expert Panel. , University of Canterbury, Christchurch, New core floors for seismic performance. Research report 2010-
Zealand, 2011. 02. Dept. of Civil and Natural Resources Eng., Uni. of Can-
13. NZS95:1935: New Zealand Standard model buildings by- terbury, Christchurch, NZ, 2010.
laws, New Zealand Standards Inst., Wellington, NZ, 1935. 36. Matthews, J., Bull, D. K., Mander, J. B.: Hollowcore floor
14. NZS1900.8-64: NZS1900 – Model building bylaw: Chapter slab performance following a severe earthquake. Proc., Con-
8: Basic Design Loads and Commentary. Standards Assoc. crete Structures in Seismic Region: fib 2003 Symposium.
of New Zealand, Wellington, NZ, 1964. 37. Bull, D. K.: Stairs and Access Ramps between Floors in Mul-
15. NZS1900.9-64: NZS1900 – Model building bylaw: Chapter ti-storey Buildings. A report of the Canterbury Earthquakes
9.3: Design and construction – Concrete, Standards Assoc. Royal Commission. Holmes Consulting Group, Christ-
of New Zealand, Wellington, NZ, 1964. church, N.Z., 8, 2011.
16. SEAOC: Recommended lateral force requirements, Structur- 38. Giorgini, S., Taylor, M., Cubrinovski, M., Pampanin, S.: Pre-
al Engineers Association of California (SEAOC), Sacramen- liminary observations of multi-storey RC building founda-
to, CA, 1966. tion performance in Christchurch following the 22nd Febru-
17. ACI318-71: Building code requirements for reinforced concrete ary 2011 Earthquake. Proc., NZ Concrete Industry
(ACI318-71), American Concrete Inst. (ACI), Detroit, MI, 1971. Conference 2011, New Zealand Concrete Society (NZCS).
18. Hollings, J. P.: Reinforced concrete seismic design. Bull. of New 39. Royal Commission: Canterbury Earthquakes Royal Commis-
Zealand Soc. of Earthquake Eng., 2 (3), 1969, pp. 217–250. sions. Technical Reports. http://canterbury.royalcommis-
19. Megget, L. M.: From brittle to ductile: 75 years of seismic de- sion.govt.nz/. (1 Sept 2011).
sign in New Zealand. Proc., NZSEE 2006 Conf., NZSEE, 15.
20. MOW-NZ: PW81/10/1: Code of Practice, Design of Public
Buildings, Office of Chief Structural Engineer, Ministry of
Works, Wellington, NZ, 1970.
21. NZS3101:1970P: Code of practice for the design of concrete
structures NZS 3101:1970 (Provisional), Standards Assoc. of
New Zealand, Wellington, NZ, 1970.
22. Park, R., Paulay, T.: Reinforced concrete structures, John Wi-
ley & Sons, New York, 1975.
23. NZS4203:1976: Code of practice for general structural de-
sign and design loading for buildings. NZS 4203:1976, Stan-
dards Assoc. of New Zealand, Wellington, NZ, 1976. Weng Yuen Kam
24. NZS3101:1982: Code of practice for the design of concrete Beca Carter Hollings & Ferner Ltd, Auckland, New Zealand
structures NZS 3101:1982, Standards Assoc. of New Formerly Research Associate Department of Civil & Natural Resources
Zealand, Wellington, NZ, 1982. Engineering, University of Canterbury, Christchurch, New Zealand
Email: kam.wengyuen@beca.com
25. NZS3101:1995: NZS 3101:1995 Concrete structures stan-
dard, Standards New Zealand, Wellington, NZ, 1995.
26. NZS3101:2006: NZS 3101:2006 Concrete structures stan-
dard, Standards New Zealand, Wellington, NZ, 2006.
27. NZS3101:1995: Amendments No. 3 to 1995 Standard
(NZS3101), Standards New Zealand, Wellington, NZ, 2004.
28. Pampanin, S., Kam, W. Y.: Seismic performance of rein-
forced concrete buildings during the 22nd February 2011
Christchurch earthquakes. Seminar notes for NZCS-
NZSEE-SESOC NZTDS Building Performance in the Feb-
ruary 2011 Christchurch Earthquake Seminar. New Zealand Stefano Pampanin
Concrete Society (NZCS), Auckland, N.Z., 130, 2011. Chair of the Structures/Geotechnical Cluster, Associate Professor (Reader)
29. Galloway, B., Hare, J., Bull, D. K.: Performance of multi- Department of Civil & Natural Resources Engineering, University
storey reinforced concrete buildings in the Darfield earth- of Canterbury, Private Bag 4800, Christchurch 81240, New Zealand
quake. Proc., 9th Pacific Conf. on Earthquake Eng., 11. Email: stefano.pampanin@canterbury.ac.nz

Structural Concrete 12 (2011), No. 4 233

You might also like