Professional Documents
Culture Documents
4, NOVEMBER 2011
Abstract—This paper presents a model for active distribution Active distribution networks need to employ modern elec-
systems expansion planning based on genetic algorithms, where tronic devices and communication technologies, leading to
distributed generation (DG) integration is considered together what is being currently called smartgrids. The smart devices
with conventional alternatives for expansion, such as rewiring,
network reconfiguration, installation of new protection devices, added to the network enable larger controllability of the system
etc. The novel approach of planning DG integration together with during disturbances or generation unavailability, such as to
network expansion is a requirement for the modern active distri- restore supply-demand balance through demand side manage-
bution network. However, the uncertainties related to DG power ment schemes. In ADN, the distribution system operator (DSO)
generation and load response growth must be taken into account in can interact with DG and control the production of active and
order to plan a safe system at a minimum cost. Thus, two different
methodologies for uncertainties incorporation through the use reactive power. In addition, load response programs are being
of multiple scenarios analysis are proposed and compared. The stimulated as a way to provide electrical capacity during crit-
multiple objectives optimization algorithm applied in the model ical demand periods. In load response programs, the enrolled
takes into account the costs of reliability, losses, power imported customers receive a payment for the capacity that is actually
from transmission, and network investments. provided during curtailment events. Therefore, the economical
Index Terms—Active distribution network, distributed genera- benefits may induce the customers to adhere to load response
tion, expansion planning, genetic algorithms, load response, uncer- and use private small capacity source to supply their load. All
tainty representation. these characteristics add an enormous amount of uncertainty
on the demand to be considered for system planning.
For all these reasons, active distribution networks need flex-
I. INTRODUCTION ible and intelligent planning methodologies in order to properly
exploit the integration of DG and load response, while still satis-
fying quality and reliability constraints. Uncertainties represen-
ISTRIBUTION systems are facing the challenge of
D evolving from passive networks with unidirectional flow
supplied by the transmission grid to active distribution networks
tation for generation and load is a must for these methodologies
in order to plan a safe and reliable system.
The problem of the expansion planning of distribution net-
(ADN) with the integration of distributed generation (DG) [1]. works consists in determining the place and the capacity of re-
Distribution network becomes active when DG is incorporated inforcement installation, based on the demand and the region ge-
to the system leading to bidirectional power flows. Many of ographical, political, and economical data. Expansion planning
these DG units are based on renewable energy sources, like seeks to define the capacity of the reinforcements and where
wind power, solar photovoltaic, biogas, fuel cells, etc., in order they should be installed to meet forecasted demand with min-
to meet the environmental constraints established by the Kyoto imal cost and acceptable quality standards. Conventional alter-
Protocol and other government initiatives. Although promising natives for expansion are rewiring, network reconfiguration by
an improvement on the power supply reliability and a reduction closing normally opened switches (NO) for load transfer, instal-
on greenhouse gas emission, the implementation of active lation of new NO switches, capacity expansion or construction
distribution networks imposes a large number of technical and of new substations, installation of new feeders, etc. For active
regulatory issues that need to be carefully evaluated. Dispersed distribution networks, the installation of DG units or the pur-
generation availability, mainly those based on renewable energy chase of energy from DG enterprises can also be considered to
sources, has a high degree of uncertainty due to intermittency meet the growing demand.
of primary energy sources and to flexible operation policies. Planning depends on two basic parameters: technical con-
straints (equipment capacity, voltage drop, radial structure of the
Manuscript received July 11, 2010; revised January 03, 2011; accepted Feb- network, reliability indices, etc.) and the optimization of eco-
ruary 18, 2011. Date of publication April 07, 2011; date of current version Oc-
tober 21, 2011. Paper no. TPWRS-00551-2010.
nomical targets such as minimization of investment and oper-
V. F. Martins is with EPE—Brazilian Energy Research Company, Rio de ating costs, minimization of energy imported from transmission,
Janeiro 20050-002, Brazil (e-mail: vinicius.martins@epe.gov.br). energy loss and reliability costs, etc.
C. L. T. Borges is with the Department of Electrical Engineering, Federal Despite the evolution of traditional optimization algorithms,
University of Rio de Janeiro, Rio de Janeiro 21941-972, Brazil (e-mail:
carmen@nacad.ufrj.br). they still face problems dealing with the inherent characteristics
Digital Object Identifier 10.1109/TPWRS.2011.2122347 of combinatory explosion of the distribution network expansion
0885-8950/$26.00 © 2011 IEEE
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
MARTINS AND BORGES: ACTIVE DISTRIBUTION NETWORK INTEGRATED PLANNING 2165
(4)
where
TABLE VI
CONSIDERED SCENARIOS
TABLE VII
REWIRED LINES, INSTALLED SWITCHES, AND NEW TOPOLOGY
FOR EACH SCENARIO—METHODOLOGY I
A. Methodology I
The proposals for reinforcements and system configuration
changes for each scenario obtained by Methodology I are pre-
sented in Tables VII and VIII, where P.L. is the Penetration
Level (%) of DG relative to the load of each scenario.
Annualized cost values are shown in Table IX and reliability
indices and the lowest voltage value for each scenario are shown
Fig. 4. Test system. in Table X. In this paper, all costs are expressed in R$, SAIDI in
hours/consumer, and SAIFI in occurrences/consumer. Scenario
0 corresponds to the planning horizon without any expansion
TABLE V
COSTS OF LOSSES AND REINFORCEMENTS
investment considering all possible scenarios and their proba-
bility of occurrence.
The option of installing switches is the same for all the an-
alyzed scenarios. Two possibilities of rewiring were obtained;
the difference between them is the rewiring or not of line (20).
Table XI presents a percent comparison of costs, lowest
voltage value, and reliability indices between the configura-
tions obtained for each scenario and the original configuration
of the planning horizon (Scenario 0).
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
MARTINS AND BORGES: ACTIVE DISTRIBUTION NETWORK INTEGRATED PLANNING 2169
TABLE XIII
DISTRIBUTED GENERATION—METHODOLOGY I—PHASE II
TABLE IX
ANNUALIZED COSTS FOR EACH SCENARIO—METHODOLOGY I
TABLE XIV
ANNUALIZED COSTS AND RELIABILITY INDICES—METHODOLOGY I—PHASE II
TABLE XV
TABLE X REDUCTION RELATIVE TO SCENARIO 0—METHODOLOGY I—PHASE II
RELIABILITY INDICES AND LOWEST VOLTAGE VALUE
FOR EACH SCENARIO—METHODOLOGY I
B. Methodology II
The proposals for reinforcements and system configuration
changes are presented in Tables XVI and XVII, and annual-
Applying Phase II of Methodology I, to determine a unique ized costs, SAIDI, SAIFI, and lowest voltage value are shown
expansion solution considering all analyzed scenarios and their in Table XVIII.
probabilities of occurrence, the proposals of reinforcement and Table XIX presents a comparison between the results ob-
system configuration changes obtained are shown in Tables XII tained and the original configuration of Scenario 0. An annual
and XIII. Annualized cost values, SAIDI, SAIFI, and the lowest reduction of R$512 316 or approximately 28.27% of total costs
voltage value are shown in Table XIV. is observed.
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
2170 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 26, NO. 4, NOVEMBER 2011
TABLE XVII
DISTRIBUTED GENERATION—METHODOLOGY II
TABLE XXI
CONDITION OF THE PLANNING HORIZON BEFORE
EXPANSION—NEW SCENARIOS
TABLE XVIII
ANNUALIZED COSTS AND RELIABILITY INDICES—METHODOLOGY II
TABLE XXII
REWIRED LINES, INSTALLED SWITCHES, AND NEW
TOPOLOGY—NEW SCENARIOS—METHODOLOGY I
TABLE XIX
REDUCTION RELATIVE TO SCENARIO 0—METHODOLOGY II
TABLE XXIII
DISTRIBUTED GENERATION—NEW SCENARIOS—METHODOLOGY I
The solution found using Methodology II is better than the
solution obtained by Methodology I in relation to cost and re-
liability indices. In fact, the solution obtained by Methodology
II coincides with the solution of scenario 2 of Methodology I,
which is indeed the scenario with the lowest total cost. This good
behavior is explained because all the scenarios are analyzed si-
multaneously in Methodology II while in Methodology I, each
scenario is analyzed individually and only during the second
phase the best expansion alternative is obtained through a de-
cision-making process. However, Methodology I offers a set of
possible solutions and not just one as with Methodology II, al- The proposals for reinforcements and system configuration
lowing the planner to have more flexibility to decide. changes for each scenario analyzed, obtained by Methodology
I, are presented in Tables XXII and XXIII.
C. Changes in Scenarios The solution obtained in Phase II of Methodology I, consid-
The system behavior was observed under more pessimistic ering the nine scenarios, is the same shown in Table XII for
factors of load and generation uncertainties as well as under rewiring and switches. However, it is not indicated any dis-
new probabilities of occurrence of each scenario as shown in tributed generation installation. This result demonstrates the in-
Table XX. These scenarios consider a larger uncertainty around fluence of the generation uncertainty factor when obtaining the
the forecasted load (until 60%) and the possibility of much lower best solution. In this study, pessimistic generation availabili-
energy availability from DG (until 20%). ties were considered, which caused the non-installation of dis-
Annualized costs, reliability indices, and lowest voltage value tributed generation, because the benefits brought by DG are
relative to the original configuration of the planning horizon are small although their costs are constant, depending only on the
presented in Table XXI considering the new scenarios. installed capacities. Since there is no power generation at DG
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
MARTINS AND BORGES: ACTIVE DISTRIBUTION NETWORK INTEGRATED PLANNING 2171
TABLE XXIV
ANNUALIZED COSTS AND RELIABILITY INDICES—NEW
SCENARIOS—METHODOLOGY I—FASE II
TABLE XXV
ANNUALIZED COSTS AND RELIABILITY INDICES—NEW
SCENARIOS—METHODOLOGY II
be added to attend the load. A cost increase of R$254 702 or [2] R. I. J. Rosado and B. J. L. Agustin, “Genetic algorithm applied to the
approximately 19.53% is observed due to the necessity of a design of large power distribution systems,” IEEE Trans. Power Syst.,
vol. 13, no. 2, pp. 696–703, May 1997.
system load increase of 15.22%. [3] V. Miranda and M. A. C. C. Matos, “Distribution system planning with
fuzzy models and techniques,” in Proc. CIRED, Brighton, U.K., 1989,
vol. 6, pp. 472–476.
V. CONCLUSION [4] N. Kagan and R. N. Adams, “Electrical power distribution systems
planning using fuzzy mathematical programming,” Elect. Power En-
Uncertainties on the power generated by distributed gen- ergy Syst., vol. 16, no. 3, pp. 191–196, 1994.
[5] V. Calderaro, V. Galdi, and A. Picolo, “Distribution planning by ge-
eration units and the variation of demand are inherent to the netic algorithm with renewable energy units,” in Proc. Bulk Power Sys-
problem of active distribution networks expansion planning. tems Dynamics and Control, Italy, 2004, vol. 1, pp. 375–380.
Two methodologies were proposed for representing uncer- [6] G. Celli et al., “A multiobjective evolutionary algorithm for the sizing
and sitting of distributed generation,” IEEE Trans. Power Syst., vol. 20,
tainties. Methodology I considered the individual analysis of no. 2, pp. 750–757, May 2005.
each scenario, and an expansion alternative for each scenario [7] K. H. Kim et al., “Dispersed generator placement using fuzzy-GA in
was determined in a first phase. In a second phase, a deci- distribution systems,” in Proc. IEEE Power Eng. Soc. Summer Meeting,
2002, vol. 13, pp. 1148–1153.
sion-making process was applied aiming at obtaining a unique [8] G. Carpinelli et al., “Distributed generation siting and sizing under un-
solution considering the solutions obtained in the first phase certainty,” IEEE Trans. Power Syst., vol. 20, no. 2, pp. 750–757, May
as well as the probabilities of occurrence of each scenario 2001.
[9] V. F. Martins, “Heuristic algorithm dedicated to reconfiguration of dis-
considered. In Methodology II, the scenarios were analyzed tribution networks,” (in Portuguese) M.Sc. thesis, Federal Univ. Juiz de
simultaneously together with their probabilities of occurrence, Fora, Juiz de Fora, Brazil, 2003.
directly obtaining a unique solution. [10] C. L. T. Borges and D. M. Falcao, “Optimal distributed generation al-
location for reliability, losses, and voltage improvement,” Int. J. Elect.
The obtained results indicate that most of the times, the so- Power Energy Syst., vol. 28, no. 6, pp. 413–420, 2006.
lution obtained by Methodology II was better than the solution [11] A. P. Leite, C. L. T. Borges, and D. M. Falcao, “Probabilistic wind farms
obtained by Methodology I in terms of cost and reliability. This generation model for reliability studies applied to Brazilian sites,” IEEE
Trans. Power Syst., vol. 21, no. 4, pp. 1493–1501, Nov. 2006.
can be explained because in Methodology II, all the scenarios [12] M. Baran and F. Wu, “Network reconfiguration in distribution systems
are analyzed simultaneously while in Methodology I, each sce- for loss reduction and load balancing,” IEEE Trans. Power Syst., vol.
nario is considered individually and only in a second phase, 4, no. 2, pp. 1401–1407, May 1989.
the best expansion alternative is obtained by a decision-making Vinicius F. Martins received the B.Sc. and M.Sc.
process. Nonetheless, Methodology I offers a set of solutions degrees from the Federal University of Juiz de Fora
and not just one, allowing the planner to have more flexibility (UFJF), Juiz de Fora, Brazil, in 2001 and 2003,
in choosing the best solution. The computer effort required is respectively, and the D.Sc. degree from the Federal
University of Rio de Janeiro (COPPE/UFRJ), Rio de
similar for both methdologies. Janeiro, Brazil, in 2009.
In a general manner, consideration of uncertainties during He has been an Energy Researcher at EPE-
Brazilian Energy Research Company since 2006.
the optimization process allows obtaining a solution more com- His general research interests are in the area of
mitted with reality, since several scenarios with their probabili- power system analysis, optimization, transmission,
ties of occurrence are analyzed. A realistic planning can provide and distribution systems planning.
a great improvement in terms of system efficiency as well as a
great reduction of costs. In modern active distribution networks,
an integrated planning facing all alternatives together with gen- Carmen L. T. Borges (S’97–M’99–SM’07) re-
eration and load uncertainties is an important requirement in ceived the B.Sc. degree from the Rio de Janeiro State
University (UERJ), Rio de Janeiro, Brazil, in 1984
order to mostly explore the benefits without extra investment and the M.Sc. and D.Sc. degrees from the Federal
costs or system risks. University of Rio de Janeiro (COPPE/UFRJ) in 1991
and 1998, respectively.
She has been a Professor of electrical engineering
REFERENCES at the Federal University of Rio de Janeiro since 1996.
Her general research interests are in the area of com-
[1] S. Chowdhury, S. P. Chowdhury, and P. Crossley, Microgrids and Ac- puter methods for power system analysis, optimiza-
tive Distribution Networks. London, U.K.: IET, 2009. tion, reliability, and high performance computing.
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.