You are on page 1of 9

2164 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 26, NO.

4, NOVEMBER 2011

Active Distribution Network Integrated


Planning Incorporating Distributed Generation
and Load Response Uncertainties
Vinicius F. Martins and Carmen L. T. Borges, Senior Member, IEEE

Abstract—This paper presents a model for active distribution Active distribution networks need to employ modern elec-
systems expansion planning based on genetic algorithms, where tronic devices and communication technologies, leading to
distributed generation (DG) integration is considered together what is being currently called smartgrids. The smart devices
with conventional alternatives for expansion, such as rewiring,
network reconfiguration, installation of new protection devices, added to the network enable larger controllability of the system
etc. The novel approach of planning DG integration together with during disturbances or generation unavailability, such as to
network expansion is a requirement for the modern active distri- restore supply-demand balance through demand side manage-
bution network. However, the uncertainties related to DG power ment schemes. In ADN, the distribution system operator (DSO)
generation and load response growth must be taken into account in can interact with DG and control the production of active and
order to plan a safe system at a minimum cost. Thus, two different
methodologies for uncertainties incorporation through the use reactive power. In addition, load response programs are being
of multiple scenarios analysis are proposed and compared. The stimulated as a way to provide electrical capacity during crit-
multiple objectives optimization algorithm applied in the model ical demand periods. In load response programs, the enrolled
takes into account the costs of reliability, losses, power imported customers receive a payment for the capacity that is actually
from transmission, and network investments. provided during curtailment events. Therefore, the economical
Index Terms—Active distribution network, distributed genera- benefits may induce the customers to adhere to load response
tion, expansion planning, genetic algorithms, load response, uncer- and use private small capacity source to supply their load. All
tainty representation. these characteristics add an enormous amount of uncertainty
on the demand to be considered for system planning.
For all these reasons, active distribution networks need flex-
I. INTRODUCTION ible and intelligent planning methodologies in order to properly
exploit the integration of DG and load response, while still satis-
fying quality and reliability constraints. Uncertainties represen-
ISTRIBUTION systems are facing the challenge of
D evolving from passive networks with unidirectional flow
supplied by the transmission grid to active distribution networks
tation for generation and load is a must for these methodologies
in order to plan a safe and reliable system.
The problem of the expansion planning of distribution net-
(ADN) with the integration of distributed generation (DG) [1]. works consists in determining the place and the capacity of re-
Distribution network becomes active when DG is incorporated inforcement installation, based on the demand and the region ge-
to the system leading to bidirectional power flows. Many of ographical, political, and economical data. Expansion planning
these DG units are based on renewable energy sources, like seeks to define the capacity of the reinforcements and where
wind power, solar photovoltaic, biogas, fuel cells, etc., in order they should be installed to meet forecasted demand with min-
to meet the environmental constraints established by the Kyoto imal cost and acceptable quality standards. Conventional alter-
Protocol and other government initiatives. Although promising natives for expansion are rewiring, network reconfiguration by
an improvement on the power supply reliability and a reduction closing normally opened switches (NO) for load transfer, instal-
on greenhouse gas emission, the implementation of active lation of new NO switches, capacity expansion or construction
distribution networks imposes a large number of technical and of new substations, installation of new feeders, etc. For active
regulatory issues that need to be carefully evaluated. Dispersed distribution networks, the installation of DG units or the pur-
generation availability, mainly those based on renewable energy chase of energy from DG enterprises can also be considered to
sources, has a high degree of uncertainty due to intermittency meet the growing demand.
of primary energy sources and to flexible operation policies. Planning depends on two basic parameters: technical con-
straints (equipment capacity, voltage drop, radial structure of the
Manuscript received July 11, 2010; revised January 03, 2011; accepted Feb- network, reliability indices, etc.) and the optimization of eco-
ruary 18, 2011. Date of publication April 07, 2011; date of current version Oc-
tober 21, 2011. Paper no. TPWRS-00551-2010.
nomical targets such as minimization of investment and oper-
V. F. Martins is with EPE—Brazilian Energy Research Company, Rio de ating costs, minimization of energy imported from transmission,
Janeiro 20050-002, Brazil (e-mail: vinicius.martins@epe.gov.br). energy loss and reliability costs, etc.
C. L. T. Borges is with the Department of Electrical Engineering, Federal Despite the evolution of traditional optimization algorithms,
University of Rio de Janeiro, Rio de Janeiro 21941-972, Brazil (e-mail:
carmen@nacad.ufrj.br). they still face problems dealing with the inherent characteristics
Digital Object Identifier 10.1109/TPWRS.2011.2122347 of combinatory explosion of the distribution network expansion
0885-8950/$26.00 © 2011 IEEE
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
MARTINS AND BORGES: ACTIVE DISTRIBUTION NETWORK INTEGRATED PLANNING 2165

planning problem, due to the large number of variables involved


in the process. On that sense, evolutionary algorithms, particu-
larly genetic algorithms (GA), have been applied in this area
during the last years. Some models have been proposed for the Fig. 1. Chromosome structure.
problem of distribution systems expansion planning showing
the advantages of GA utilization and allowing consideration of TABLE I
many aspects of the problem. DECODING—CHANGES IN NETWORK TOPOLOGY
The algorithms presented in [2] use GA as a technique to
solve the problem of static planning of distribution system ex-
pansion considering possible reinforcements or installation of
new feeders and substations. Fuzzy numbers are used in [3] to
consider uncertainties inherent to the expansion of distribution
networks. A proposal under the auspices of multiple objectives
and uncertainties is presented in [4] based on fuzzy numbers
and arithmetic operations. Based on multiple scenarios, an al- TABLE II
DECODING—DISTRIBUTED GENERATION
gorithm is suggested in [5] in order to determine which lines
should be inserted into the system to optimize voltage profile
considering the presence of distributed generation. Proposals
using GA aiming at determining the best localization and ca-
pacity of distributed generation units, considering uncertainties
by fuzzy logics or multiple scenarios, are presented in [6]–[8]. The genetic algorithm uses binary codification, where the
This paper presents a model for expansion planning of chromosome may be divided in four parts, as represented in
active distribution networks, based on genetic algorithms, Fig. 1.
where distributed generation integration is considered together The first part of the chromosome refers to the possibility of
with conventional alternatives for expansion, such as rewiring network topology changes through changes in the status of some
and installation of new feeders, network reconfiguration by switches already installed or through the installation of new
changing the status of switches, installation of new switches switches. In this case, three bits are used resulting in eight pos-
and protection devices, etc. Multiple objectives optimization is sibilities for each alternative as shown in Table I.
applied concerning reliability, energy losses, energy imported Closing a NO switch causes the formation of a loop, a fact
from transmission, and investment costs. Uncertainties on that is not desired in distribution networks. Consequently, an-
demand values and power supplied by distributed generation other normally closed (NC) switch of the same loop has to be
units are represented through the analysis of multiple scenarios opened to ensure maintenance of the radial structure. An algo-
using two different methodologies. The first methodology rithm of optimal reconfiguration, developed in [9], is used to ob-
considers individual analysis of each scenario while the second tain the new configuration of the network. Aiming at reducing
methodology analyzes all the scenarios simultaneously. Both the size of the chromosome, only the switch that must be opened
methodologies combine the multi-scenarios approach with is represented. Each chromosome represents a particular config-
GA as a way of introducing probabilistic assessment into the uration or network topology.
algorithm. Each optimal solution is weighted by the probability The analysis of radial structure is conducted either for NO
of occurrence of that specific scenario, or, in order words, the switches already installed in the network or for candidate
optimal solution is obtained considering the probability of switches. The change of network topology through changing
occurrence of the scenarios considered. the status of some already installed switches has only the cost
The novelty of the proposed model is the consideration of related to the maneuver of switch opening/closing .
DG integration together with conventional expansion alterna- However, the installation of a new NO switch presents the cost
tives, taking into consideration reliability, losses, and costs con- of the purchase of the equipment besides the cost of reconfigu-
straints. The “fit-and-forget strategy” of DG employment may ration when the new switch is closed and a switch that belongs
be changed by the application of the proposed model, since it to the same loop is opened .
incorporates integration of DG and load response at the expan- The second part of the chromosome refers to the possibility
sion planning phase. Moreover, due to the high degree of uncer- of installing DG units in certain buses of the system and their
tainties involved, the main focus of the paper is to propose two capacities (cost ). In this case, three bits are used for each
different approaches to incorporate generation and load uncer- candidate DG unit, generating a total of eight possibilities,
tainties in order to plan a safe, reliable, and economic system. including non-installation of the generating unit, as shown in
Table II.
II. EXPANSION PLANNING BASED ON GENETIC ALGORITHMS The third part of the chromosome refers to the possibility of
The model proposed to solve the problem of expansion plan- rewiring certain network lines (cost ). In this case, one bit is
ning of active distribution networks uses genetic algorithms for used, generating two possibilities for each alternative, as shown
multi-objective optimization considering uncertainties. The so- in Table III.
lution is a radial structure network that minimizes the adopted The fourth part of the chromosome refers to the connection
objective function. of new load points into the system (cost ). For each load
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
2166 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 26, NO. 4, NOVEMBER 2011

TABLE III the planning horizon, modified to incorporate the uncertainties


DECODING—REWIRING related to its stochastic nature and also to load response. The
different generation levels represent a combination of the
energy availability, dependent of the renewable source type,
together with the uncertainty around the actual integration of
DG in the planning horizon.
TABLE IV The choice of scenarios should consider aspects relevant to
GA PARAMETERS
the system under analysis. The developed methodologies allow
using a variable number of scenarios depending on the interest
of the planner. It is the planner who defines the amount of sce-
narios, the levels of load and generation, and the respective prob-
abilities to be considered in each one, based on his experience
and knowledge about the system and expansion alternatives.
The scenarios are defined independently of the methodology
and only after the scenarios have been defined are the proposed
methodologies applied.
point, two bits are used giving a total of four possible alterna-
tives of allocation. The best alternative for connection is deter- A. Methodology I
mined considering construction costs of the feeder to connect The first methodology proposed for uncertainty consideration
the new load point to the system, according to (1): during expansion planning of active distribution networks pro-
vides the planner an expansion alternative for each scenario an-
(1)
alyzed, thus allowing him to define what is the best expansion
where plan to be adopted by applying some decision-making process.
A probability of occurrence is assigned to each scenario ob-
cost of the connection of new load point to the tained through the combination of scenarios of generation and
system bus ; load.
cost per km of feeder construction to connect the A genetic algorithm is executed for each scenario considered
new load point to the distribution system, which aiming at obtaining the best expansion alternative, considering
varies with the type of wire; the uncertainty factors of load and generation for the respec-
distance in km between the new load point and the tive scenario. The calculation of the fitness function to deter-
point of the system where it will be connected. mine the best expansion alternative in each analyzed scenario is
The GA parameters adopted are shown in Table IV. The performed by evaluating (2), which is composed by: 1) annual-
values of the parameters were obtained after exhaustive tests, ized energy loss costs; 2) annualized expected value for non-dis-
varying them and comparing the performance of the algorithm tributed energy costs; 3) annualized costs of investments in dis-
in terms of quality of the solution and simulation time. tribution network reinforcement; and 4) annualized costs of en-
The value of losses and energy imported from transmission ergy imported from transmission, as follows:
system are calculated by a nonlinear power flow solved by the
Newton-Raphson method. (2)
The reliability indices (ECOST, SAIDI, and SAIFI) are calcu-
where
lated by an analytical method, as described in [10], which con-
siders all protection devices installed in the distribution network annualized energy loss costs;
as well as DG units. The power availability of DG units based on expected value of non-distributed energy costs;
intermittent energy sources, such as wind generation, are mod- annualized costs of system investments, calculated
eled as [11], where their stochastic behavior is represented by by as
a multiple state Markov model that combines the intermittent described below;
characteristics of the renewable energy source with the opera- annualized costs of energy imported from
tional information (failure and repair rates) of the generator. transmission system.
The constraints of active and reactive power balance, bus
III. UNCERTAINTIES TREATMENT voltage limits, power flow limits, and network radial structure
The active distribution network expansion planning is in- are also considered in the optimization process.
fluenced by several factors, among which are uncertainties of Fig. 2 presents the flowchart of Methodology I algorithm in
loads, power generated by distributed generation units, and order to incorporate the uncertainties to the expansion plan-
cost of the reinforcements to be implanted in the network. This ning problem of active distribution networks. This methodology
paper presents two methodologies based on the theory of mul- presents an expansion alternative for each scenario analyzed.
tiple scenarios to incorporate uncertainties relative to demand A second phase (Phase II) of Methodology I is characterized
and power supplied by DG. Each scenario is characterized by by the decision-making process that aims to obtain a unique so-
a combination of load demand and generation availability. The lution for the expansion planning considering the solution of all
different load levels represent the load growth forecasted for scenarios. The decision-making process developed was based
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
MARTINS AND BORGES: ACTIVE DISTRIBUTION NETWORK INTEGRATED PLANNING 2167

In Methodology II, GA is executed just once, considering all


possible scenarios and their probability of occurrence simul-
taneously. For each individual that attends the radial network
structure constraint, the power flow and ECOST are calculated
for each scenario aiming at determining its fitness value in each
scenario. In this way, the fitness of each individual is calculated
as a function of its fitness on multiple scenarios as shown in (4):

(4)

where

annualized energy loss costs of individual on


scenario ;
expected value of non-distributed energy costs of
individual on scenario ;
annualized costs of system investments of
individual on scenario ;
annualized costs of energy imported from
transmission of individual on scenario .
Fig. 2. Algorithm for uncertainties treatment—Methodology I. This process offers an expansion alternative which considers
all analyzed scenarios and their probability of occurrence. Fig. 3
shows the flowchart of Methodology II.
on [5] in which the final solution is determined taking into con-
sideration the solutions obtained in each scenario along with
IV. RESULTS
their probabilities of occurrence. The final solution is composed
by the alternatives that have the highest probability of occur- The test system used was extracted from [12] and has one sub-
rence, calculated by adding the probability of occurrence of station, 33 buses, 35 lines, 32 NC switches, three NO switches,
the scenarios in which that particular alternative was selected. voltage of 12.66 KV, and nominal load of 3715 MW and 2700
Therefore, it is noteworthy that the final solution obtained by the MVAr. Table V presents the costs related to losses and rein-
proposed decision-making process may be different from all the forcements obtained from published Brazilian figures (Brazil
solutions for each scenario analyzed individually. Real R$1.00 corresponds to approximately US$0.50). An av-
In order to calculate the value of each parcel of (2) for the erage cost was considered for DG units, regardless of its type
solution determined after the application of Phase II, (3) is used. and technology, although different costs may be used. Fig. 4
Therefore, the objective function parcel value is obtained by the shows a diagram of the system. The dotted lines represent NO
sum of the value of that parcel in each scenario, weighted by the switches while the dashed lines represent candidate places for
probability of occurrence of the respective scenario: new switches installation.
In order to ensure that the electric energy demand is met with
(3) quality and economy, within the planning horizon, several ex-
pansion alternatives are analyzed:
• network reconfiguration by changing the status of NO
where switches, installed in lines (34), (35), and (36);
• installation of new switches in lines (33) and (37);
value of the objective function ; • rewiring of lines (5), (6), (7), (16), (17), (20), (21), (22),
value of objective function in scenario ; (23), (24), (28), (29), (30), (31), and (32);
number of scenarios considered; • installation of DG units at buses (6), (7), (17), (21), (23),
probability of occurrence of scenario . (24), (29), (31), and (32). Units with capacity 30, 60, 90,
120, 150, 180, and 210 kW based on thermal and wind
generation are considered.
B. Methodology II Three load scenarios and three generation scenarios are con-
The second methodology proposed for uncertainty consider- sidered, totaling nine scenarios with different probabilities of
ation during expansion planning of active distribution networks, occurrence, as presented in Table VI, where
analyzes simultaneously all possible scenarios for each gener-
ation of the evolutive process. In this way, a unique solution is Factor used to obtain different load levels, as follows:
obtained at the end of the process and a decision process is not
needed.
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
2168 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 26, NO. 4, NOVEMBER 2011

TABLE VI
CONSIDERED SCENARIOS

TABLE VII
REWIRED LINES, INSTALLED SWITCHES, AND NEW TOPOLOGY
FOR EACH SCENARIO—METHODOLOGY I

Factor used to obtain different generation levels,


as follows:
Fig. 3. Algorithm for uncertainties treatment—Methodology II.

where is the load of bus considering scenario


is the nominal load of bus is the generation of bus
considering scenario , and is the nominal generation
of bus .
These scenarios represent the planner expectation about the
probable values of load and generation factors. It means that an
uncertainty of until 20% on load growth and an uncertainty of
until 40% reduction on energy availability from DG need to be
evaluated for expansion planning.

A. Methodology I
The proposals for reinforcements and system configuration
changes for each scenario obtained by Methodology I are pre-
sented in Tables VII and VIII, where P.L. is the Penetration
Level (%) of DG relative to the load of each scenario.
Annualized cost values are shown in Table IX and reliability
indices and the lowest voltage value for each scenario are shown
Fig. 4. Test system. in Table X. In this paper, all costs are expressed in R$, SAIDI in
hours/consumer, and SAIFI in occurrences/consumer. Scenario
0 corresponds to the planning horizon without any expansion
TABLE V
COSTS OF LOSSES AND REINFORCEMENTS
investment considering all possible scenarios and their proba-
bility of occurrence.
The option of installing switches is the same for all the an-
alyzed scenarios. Two possibilities of rewiring were obtained;
the difference between them is the rewiring or not of line (20).
Table XI presents a percent comparison of costs, lowest
voltage value, and reliability indices between the configura-
tions obtained for each scenario and the original configuration
of the planning horizon (Scenario 0).
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
MARTINS AND BORGES: ACTIVE DISTRIBUTION NETWORK INTEGRATED PLANNING 2169

TABLE VIII TABLE XII


DISTRIBUTED GENERATION FOR EACH SCENARIO—METHODOLOGY I REWIRED LINES, INSTALLED SWITCHES, AND NEW
TOPOLOGY—METHODOLOGY I—PHASE II

TABLE XIII
DISTRIBUTED GENERATION—METHODOLOGY I—PHASE II

TABLE IX
ANNUALIZED COSTS FOR EACH SCENARIO—METHODOLOGY I
TABLE XIV
ANNUALIZED COSTS AND RELIABILITY INDICES—METHODOLOGY I—PHASE II

TABLE XV
TABLE X REDUCTION RELATIVE TO SCENARIO 0—METHODOLOGY I—PHASE II
RELIABILITY INDICES AND LOWEST VOLTAGE VALUE
FOR EACH SCENARIO—METHODOLOGY I

Table XV shows a comparison between the results obtained in


Phase II and the original configuration of Scenario 0. An annual
TABLE XI reduction of R$508 275 or approximately 28.05% of total costs
PERCENT REDUCTION RELATIVE TO SCENARIO 0—METHODOLOGY I is observed.
Phase II provides the expansion solution that is committed
with all analyzed scenarios and respective probability of occur-
rence. However, it may obtain a final solution with total cost
higher than one or more of the individual scenarios. In this case,
for example, the final solution coincides with scenario 8, while
scenarios 2 and 4 have lower total costs. However, since the sce-
narios are uncertain, the decision-making process aims to cap-
ture the most probable optimum expansion alternatives selected
in the scenarios.

B. Methodology II
The proposals for reinforcements and system configuration
changes are presented in Tables XVI and XVII, and annual-
Applying Phase II of Methodology I, to determine a unique ized costs, SAIDI, SAIFI, and lowest voltage value are shown
expansion solution considering all analyzed scenarios and their in Table XVIII.
probabilities of occurrence, the proposals of reinforcement and Table XIX presents a comparison between the results ob-
system configuration changes obtained are shown in Tables XII tained and the original configuration of Scenario 0. An annual
and XIII. Annualized cost values, SAIDI, SAIFI, and the lowest reduction of R$512 316 or approximately 28.27% of total costs
voltage value are shown in Table XIV. is observed.
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
2170 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 26, NO. 4, NOVEMBER 2011

TABLE XVI TABLE XX


REWIRED LINES, INSTALLED SWITCHES, NEW SCENARIOS
AND NEW TOPOLOGY—METHODOLOGY II

TABLE XVII
DISTRIBUTED GENERATION—METHODOLOGY II

TABLE XXI
CONDITION OF THE PLANNING HORIZON BEFORE
EXPANSION—NEW SCENARIOS
TABLE XVIII
ANNUALIZED COSTS AND RELIABILITY INDICES—METHODOLOGY II

TABLE XXII
REWIRED LINES, INSTALLED SWITCHES, AND NEW
TOPOLOGY—NEW SCENARIOS—METHODOLOGY I
TABLE XIX
REDUCTION RELATIVE TO SCENARIO 0—METHODOLOGY II

TABLE XXIII
DISTRIBUTED GENERATION—NEW SCENARIOS—METHODOLOGY I
The solution found using Methodology II is better than the
solution obtained by Methodology I in relation to cost and re-
liability indices. In fact, the solution obtained by Methodology
II coincides with the solution of scenario 2 of Methodology I,
which is indeed the scenario with the lowest total cost. This good
behavior is explained because all the scenarios are analyzed si-
multaneously in Methodology II while in Methodology I, each
scenario is analyzed individually and only during the second
phase the best expansion alternative is obtained through a de-
cision-making process. However, Methodology I offers a set of
possible solutions and not just one as with Methodology II, al- The proposals for reinforcements and system configuration
lowing the planner to have more flexibility to decide. changes for each scenario analyzed, obtained by Methodology
I, are presented in Tables XXII and XXIII.
C. Changes in Scenarios The solution obtained in Phase II of Methodology I, consid-
The system behavior was observed under more pessimistic ering the nine scenarios, is the same shown in Table XII for
factors of load and generation uncertainties as well as under rewiring and switches. However, it is not indicated any dis-
new probabilities of occurrence of each scenario as shown in tributed generation installation. This result demonstrates the in-
Table XX. These scenarios consider a larger uncertainty around fluence of the generation uncertainty factor when obtaining the
the forecasted load (until 60%) and the possibility of much lower best solution. In this study, pessimistic generation availabili-
energy availability from DG (until 20%). ties were considered, which caused the non-installation of dis-
Annualized costs, reliability indices, and lowest voltage value tributed generation, because the benefits brought by DG are
relative to the original configuration of the planning horizon are small although their costs are constant, depending only on the
presented in Table XXI considering the new scenarios. installed capacities. Since there is no power generation at DG
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
MARTINS AND BORGES: ACTIVE DISTRIBUTION NETWORK INTEGRATED PLANNING 2171

TABLE XXIV
ANNUALIZED COSTS AND RELIABILITY INDICES—NEW
SCENARIOS—METHODOLOGY I—FASE II

TABLE XXV
ANNUALIZED COSTS AND RELIABILITY INDICES—NEW
SCENARIOS—METHODOLOGY II

Fig. 5. New load points connection.


units, the load is entirely attended by the energy imported from
the transmission network. Annualized costs, SAIDI, SAIFI, and TABLE XXVI
NEW LOAD POINTS AND POSSIBLE CONNECTION POINTS
lowest voltage value are shown in Table XXIV.
Methodology II obtained the same solution found for scenario
(7) of Methodology I, which is the installation of 180 kW of DG
in both buses (17) and (32). Table XXV shows the annualized
costs, reliability indices, and lowest voltage value obtained by
Methodology II. TABLE XXVII
As occurred in the previous case, the solution found using DISTRIBUTED GENERATION—NEW LOAD POINTS—METHODOLOGY I—PHASE
II
Methodology II is better than the solution obtained by Method-
ology I in relation to cost and reliability indices. On the other
hand, Methodology I has the advantage of providing a larger
portfolio of expansion options, since it obtains an optimal solu-
tion for each one. TABLE XXVIII
In a general manner, it can be concluded that the solution with CONNECTION POINTS OF NEW LOAD POINTS—METHODOLOGY I—PHASE II
relation to rewiring, installed switches, and topology do not or
slightly change when the scenarios are modified. The variation
of uncertainties factors for loads and DG and scenarios proba-
bilities is significant in determining the DG capacities to be in-
stalled in the system. When more pessimistic uncertainty factor TABLE XXIX
for generation are considered, there is a trend to reduce or even ANNUALIZED COSTS AND RELIABILITY INDICES—NEW LOAD
not install DG due to the fact that the benefits to the system are POINTS—METHODOLOGY I—PHASE II
reduced while the installation cost remains the same.

D. New Load Points


For this test, the necessity of attending three new load points
represented by buses (34), (35), and (36) is considered. They
can be connected to one of four possible connection points as
shown in Fig. 5 and detailed in Table XXVI.
Methodology I was applied in order to represent the uncer- and Table XXIX shows the solution costs and reliability indices.
tainties with the same scenarios and probabilities shown in
Table VI. The solution obtained in Phase II is the same shown The necessity of attending new load points did not cause
in Table XII for rewiring and switches. Results for distributed changes in relation to the solution obtained for rewiring,
generation are shown in Table XXVII, while Table XXVIII switches, and grid topology of Section IV-A. However, in
shows the connection points selected for the new load points relation to DG installation, 90 kW of extra generation has to
Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.
2172 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 26, NO. 4, NOVEMBER 2011

be added to attend the load. A cost increase of R$254 702 or [2] R. I. J. Rosado and B. J. L. Agustin, “Genetic algorithm applied to the
approximately 19.53% is observed due to the necessity of a design of large power distribution systems,” IEEE Trans. Power Syst.,
vol. 13, no. 2, pp. 696–703, May 1997.
system load increase of 15.22%. [3] V. Miranda and M. A. C. C. Matos, “Distribution system planning with
fuzzy models and techniques,” in Proc. CIRED, Brighton, U.K., 1989,
vol. 6, pp. 472–476.
V. CONCLUSION [4] N. Kagan and R. N. Adams, “Electrical power distribution systems
planning using fuzzy mathematical programming,” Elect. Power En-
Uncertainties on the power generated by distributed gen- ergy Syst., vol. 16, no. 3, pp. 191–196, 1994.
[5] V. Calderaro, V. Galdi, and A. Picolo, “Distribution planning by ge-
eration units and the variation of demand are inherent to the netic algorithm with renewable energy units,” in Proc. Bulk Power Sys-
problem of active distribution networks expansion planning. tems Dynamics and Control, Italy, 2004, vol. 1, pp. 375–380.
Two methodologies were proposed for representing uncer- [6] G. Celli et al., “A multiobjective evolutionary algorithm for the sizing
and sitting of distributed generation,” IEEE Trans. Power Syst., vol. 20,
tainties. Methodology I considered the individual analysis of no. 2, pp. 750–757, May 2005.
each scenario, and an expansion alternative for each scenario [7] K. H. Kim et al., “Dispersed generator placement using fuzzy-GA in
was determined in a first phase. In a second phase, a deci- distribution systems,” in Proc. IEEE Power Eng. Soc. Summer Meeting,
2002, vol. 13, pp. 1148–1153.
sion-making process was applied aiming at obtaining a unique [8] G. Carpinelli et al., “Distributed generation siting and sizing under un-
solution considering the solutions obtained in the first phase certainty,” IEEE Trans. Power Syst., vol. 20, no. 2, pp. 750–757, May
as well as the probabilities of occurrence of each scenario 2001.
[9] V. F. Martins, “Heuristic algorithm dedicated to reconfiguration of dis-
considered. In Methodology II, the scenarios were analyzed tribution networks,” (in Portuguese) M.Sc. thesis, Federal Univ. Juiz de
simultaneously together with their probabilities of occurrence, Fora, Juiz de Fora, Brazil, 2003.
directly obtaining a unique solution. [10] C. L. T. Borges and D. M. Falcao, “Optimal distributed generation al-
location for reliability, losses, and voltage improvement,” Int. J. Elect.
The obtained results indicate that most of the times, the so- Power Energy Syst., vol. 28, no. 6, pp. 413–420, 2006.
lution obtained by Methodology II was better than the solution [11] A. P. Leite, C. L. T. Borges, and D. M. Falcao, “Probabilistic wind farms
obtained by Methodology I in terms of cost and reliability. This generation model for reliability studies applied to Brazilian sites,” IEEE
Trans. Power Syst., vol. 21, no. 4, pp. 1493–1501, Nov. 2006.
can be explained because in Methodology II, all the scenarios [12] M. Baran and F. Wu, “Network reconfiguration in distribution systems
are analyzed simultaneously while in Methodology I, each sce- for loss reduction and load balancing,” IEEE Trans. Power Syst., vol.
nario is considered individually and only in a second phase, 4, no. 2, pp. 1401–1407, May 1989.
the best expansion alternative is obtained by a decision-making Vinicius F. Martins received the B.Sc. and M.Sc.
process. Nonetheless, Methodology I offers a set of solutions degrees from the Federal University of Juiz de Fora
and not just one, allowing the planner to have more flexibility (UFJF), Juiz de Fora, Brazil, in 2001 and 2003,
in choosing the best solution. The computer effort required is respectively, and the D.Sc. degree from the Federal
University of Rio de Janeiro (COPPE/UFRJ), Rio de
similar for both methdologies. Janeiro, Brazil, in 2009.
In a general manner, consideration of uncertainties during He has been an Energy Researcher at EPE-
Brazilian Energy Research Company since 2006.
the optimization process allows obtaining a solution more com- His general research interests are in the area of
mitted with reality, since several scenarios with their probabili- power system analysis, optimization, transmission,
ties of occurrence are analyzed. A realistic planning can provide and distribution systems planning.
a great improvement in terms of system efficiency as well as a
great reduction of costs. In modern active distribution networks,
an integrated planning facing all alternatives together with gen- Carmen L. T. Borges (S’97–M’99–SM’07) re-
eration and load uncertainties is an important requirement in ceived the B.Sc. degree from the Rio de Janeiro State
University (UERJ), Rio de Janeiro, Brazil, in 1984
order to mostly explore the benefits without extra investment and the M.Sc. and D.Sc. degrees from the Federal
costs or system risks. University of Rio de Janeiro (COPPE/UFRJ) in 1991
and 1998, respectively.
She has been a Professor of electrical engineering
REFERENCES at the Federal University of Rio de Janeiro since 1996.
Her general research interests are in the area of com-
[1] S. Chowdhury, S. P. Chowdhury, and P. Crossley, Microgrids and Ac- puter methods for power system analysis, optimiza-
tive Distribution Networks. London, U.K.: IET, 2009. tion, reliability, and high performance computing.

Authorized licensed use limited to: VIT University. Downloaded on June 27,2023 at 05:58:13 UTC from IEEE Xplore. Restrictions apply.

You might also like