This report has been prepared under the control of the Hoxana Consulting Engineers’ Quality
Management System.
Verification Capacity Name Signature Date
Document Control...............................................................................................................................i
Approvals............................................................................................................................................ii
Table of Contents................................................................................................................................i
List of Tables.......................................................................................................................................i
List of Figures......................................................................................................................................i
Abbreviations......................................................................................................................................ii
Project Synopsis................................................................................................................................iii
1. INTRODUCTION........................................................................................................................1
1.1 Terms of Reference.............................................................................................................1
1.2 Inception meeting................................................................................................................1
1.3 Purpose of the report...........................................................................................................1
1.4 Project Description...............................................................................................................1
2. PROJECT SCOPE......................................................................................................................3
3. WAY FORWARD........................................................................................................................4
List of Tables
List of Figures
i
Abbreviations
ii
Project Synopsis
Project Title: Construction of a pedestrian underpass between Station 8 and 10, Tembisa
LONGITUDE -26.017066
LATITUDE 28.212835
iii
iv
1. INTRODUCTION
The Transport and Fleet Management Department of the City of Ekurhuleni (COE) resolved to
appointed Hoxana Consulting Engineers (Pty) Ltd (HCE) on the 22 nd of September 2021 from their
Enterprise Project management Office (EPMO) database of professional service providers for the
implementation of Normal Services (limited to Stage 4: Documentation and Procurement to Stage
6: Close-out) in terms of the Engineering Council of South Africa (ECSA) Guideline Scope of
Services and Tariff of Fees (Government Gazette No 42391 - 01 April 2019 to 31 March 2020), to
conduct a design review, implement the construction of a pedestrian and a non-motorized
underpass in Tembisa.
An inception meeting was scheduled on site (Tembisa) for the 12th of November 2021. This also
served as an introductory meeting between the Consultant (HCE), the Client (CoE) and
the Passenger Rail Agency of South Africa (PRASA). The following items were discussed during
this meeting:
During this meeting PRASA representatives also indicated that they will provide the Consultant
with bracing details of the railway, foundation details of the electric poles along the railway, and
specifications on the earthworks and stones.
1
- Mr. B. Mudhawa (HCE, Resident Engineer)
- Mr. P. Ngombe (HCE, Resident Engineer)
All parties also agreed to have a fortnight technical meeting during which the Consultant will
present the final design review and methodology of the project implementation.
The objective of this Inception Report is to establish a clear project brief and develop a detailed
timetable for the implementation of the project. It specifies in detail the tasks of the Project and
identifies the various necessary work activities such as analysis, tests and other investigations that
are required for the successful implementation of the project. This Inception report also seeks to
confirm the scope of work to be carried out by Hoxana Consulting Engineers.
2
1.4 Project Description
The project forms part of the City of Ekurhuleni’s Integrate Rapid Public Transportation Network
(IRPTN) project currently under implementation. The scope of work involves the construction of 2
No. culverts under the existing railway line, parallel to the BRT Trunk route, to allow movements of
pedestrians and other forms of Non-Motorised Transport along Andrew Mapheto Drive in Tembisa.
The culverts are planned to be constructed next to the railway embankment and jacked into
position across the embankment, below the railway line, while the railway line remains operational.
3
2. PROJECT SCOPE
The scope of work proposed during the inception involves the following:
To undertake a detailed design review of the design drawings, methodology and Bill of
quantities obtained from the previous consultant, in order to assume liability,
To provide any information that might be deemed to be outstanding,
To provide a comprehensive drawing pack and detailed design report for construction
purposes,
To apply for wayleave authorization from railway authorities,
To prepare tender documents for procurement purposes,
To conduct contract administration and site supervision,
To prepare a close out report
The Instruction to Proceed with Works (Trans 10 08) states that these activities covers Stage 4:
Documentation and Procurement to Stage 6: Close-out) in terms of the Engineering Council of
South Africa (ECSA) Guideline Scope of Services and Tariff of Fees (Government Gazette No
42391 - 01 April 2019 to 31 March 2020)
The project is envisaged to have a maximum duration of 8 months lapsing by May 2022 duration
(including builder’s holidays) with the expected milestones for the various activities highlighted
below
4
Description Expected Date Actual Date
Activity
Site Cognizance
Submission of
scope
confirmation
Approval of
scope
Initial
Engagements
with Ward
Councilor
Engagements
with universal
Access
Design Review
Report
Finalization of
engagements
with PRASA
Necessary
approvals by
PRASA
Submission of
BOQ and Tender
Specifications
Appointment of a
contractor
Site Handover
5
Construction
begins
Project Close
Close-Out
Table 2.2: Proposed implementation plan for phase 1
3. WAY FORWARD
This Inception Report outlines the agreed Scope of work and marks the beginning of the preparation for the
critical design review report. City of Ekurhuleni will be required to issue an approval of the inception report. At
this stage, no Contractor has been appointed. Below is a table of all the contacts who will participate to in the
successful delivery of the project.